October 08, 2026
Between agility and predictability: hybrid roadmap in regulatory IT projects
Between Agility and Predictability: Hybrid Roadmap in Regulatory Projects of Tl
Julio Antonio Soares; Samira Sestari do Nascimento
DOI: 10.22167/2675-6528-202603091
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The Brazilian banking sector presented high regulatory complexity and growing dependence on digital solutions, generating tension between the predictability required by regulatory bodies and the flexibility needed for continuous improvement initiatives. This tension resulted in misalignments between business and technology areas, low planning predictability, and predominantly reactive prioritization. The objective was to develop and evaluate a hybrid “roadmap”, based on the Now-Next-Later model, to improve strategic alignment, communication, and demand prioritization in regulated IT projects within a Brazilian financial institution. The research, qualitative and applied in nature, followed the Design Science Research paradigm, with a single case study. Data collection occurred through Jira records, Microsoft Teams communications, and participant observation over three months. The artifact’s evaluation was performed qualitatively, by comparing evidence before and after its implementation, using thematic analysis and structured triangulation across three axes: information fragmentation, leadership visibility, and decision traceability. The results indicated that the “roadmap” reduced informational fragmentation, made the teams’ execution capacity more explicit, and amplified the visibility of governance instances. It was concluded that the artifact has the potential to balance regulatory predictability and operational flexibility, although its sustainability depends on the clear definition of maintenance roles and available technological support.
Keywords: Strategic alignment; Design Science Research; Portfolio management; Demand prioritization; Banking sector.
1. Introduction
The Brazilian banking sector is characterized by high organizational complexity, strongly influenced by regulatory requirements and continuous technological advancements. Added to this is the growing pressure for operational efficiency and digital innovation. The environment is regulated by the Central Bank of Brazil (BACEN), responsible for supervising and standardizing the national financial system, including critical systems such as Pix. In parallel, legislation such as the General Data Protection Law (LGPD) expands compliance and governance requirements for Information Technology (IT) projects. In this context, financial institutions need to conduct regulatory projects, with externally defined deadlines and scopes, and continuous innovation initiatives, which demand greater flexibility, simultaneously.
This combination generates a structural tension between predictability and flexibility. Regulatory projects require greater control, traceability, and adherence to legal deadlines. On the other hand, evolution and continuous improvement initiatives call for adaptability and adherence to agile approaches. Agile methods, although widely used in the development of digital solutions, may present limitations when applied without adaptations in regulated environments. On the other hand, traditional approaches, based on detailed planning, tend to respond poorly to technological dynamics and the uncertainties of non-regulatory projects.
As a result, many organizations have resorted to combinations of agile and predictive practices, configuring hybrid approaches. However, the unstructured application of these approaches leads to recurring difficulties throughout the project lifecycle. Problems appear especially in communication between areas and in the way demands are organized. This results in a lack of shared vision of initiatives, constant planning revisions, and reactive interventions as deadlines approach (Gonçalves et al., 2024).
This gap in the integration between planning, execution, and strategic alignment is consistent with contemporary project management guidelines. The PMBOK Guide (PMI, 2021) emphasizes the transition from management oriented by prescriptive processes to an approach based on principles and performance domains. Among these, the Stakeholder Performance Domain (engagement, alignment, and communication) and the Development Approach and Life Cycle Domain (adaptation between predictive, agile, and hybrid approaches) stand out. In this context, the concept of tailoring, which is the deliberate adaptation of management practices, methods, and artifacts to the specific characteristics of each initiative, gains relevance.
The adoption of hybrid approaches therefore requires instruments capable of supporting planning and communication across different time horizons. It is in this scenario that the roadmap proves useful for strategic planning and communication, especially in environments with multiple stakeholders and high complexity (Cagan, 2020). In practice, however, it is still difficult to structure systematized communication and prioritization mechanisms that can reconcile, in a balanced way, the predictability demands of regulatory projects and the flexibility needs of business initiatives.
This gap between practice and theory leads to the following research question: how to structure and apply a roadmap capable of improving strategic alignment, communication, and demand prioritization in regulated IT projects in a Brazilian financial institution? To answer this question, the present study aims to develop and evaluate a hybrid project management roadmap, based on the Now-Next-Later model, as an instrument to support strategic alignment, communication, and demand prioritization in Information Technology projects in the banking sector.
2. Material and Methods
The research, of an applied nature and qualitative approach, aimed to develop and evaluate a hybrid project management roadmap. Design Science Research (DSR) was adopted as the methodological strategy, aiming at the construction and evaluation of an artifact to solve organizational problems (Hevner et al., 2004). The study followed the six phases of the DSR cycle and used a single case study for the investigation (Yin, 2015).
The unit of analysis corresponded to the planning, prioritization, and communication processes in IT projects of a large financial institution in the Brazilian banking sector. Technology teams and business areas were considered subunits of analysis. The selected case represented an organizational environment with simultaneous regulatory projects and business initiatives, requiring high coordination and presenting regulatory constraints.
Data collection occurred over three months, a period that encompassed a complete cycle of an initiative, from planning to delivery. Data sources included records in the Jira demand management system, communications on the Microsoft Teams platform, and participant observation. The researcher acted as a participant observer, following routines and decision-making processes, while documentary sources allowed for the analysis of information recording and sharing.
To ensure validity and reliability, triangulation of different sources and collection methods was employed (Yin, 2015). The data were analyzed through thematic analysis (Braun; Clarke, 2006), organized into three axes: fragmentation of information and Knowledge Management, visibility and leadership performance, and traceability of decisions.
The thematic analysis process followed four operational steps: initial coding, grouping into descriptive categories, organization into thematic axes, and review with validation by triangulation. In DSR, thematic analysis identified problems in the diagnosis phase and verified changes in the aspects of integration, transparency, and consistency in the artifact evaluation phase.
The artifact evaluation was conducted qualitatively, comparing evidence before and after its implementation. The evaluation criteria were: reduction of informational fragmentation, increase in the traceability of prioritization decisions, and expansion of leadership visibility over the real state of initiatives. These criteria were applied from the triangulation of the three data sources.
The proposed artifact consisted of a structured roadmap model, aiming to promote a consolidated view of initiatives across business, technology, and leadership areas. The goal was to reduce information fragmentation throughout the project lifecycle, organizing the model into three temporal horizons: Now, Next, and Later.
The Now horizon gathered demands in execution or with immediate start (0-2 months), including detailed information such as title, priority, status, and alerts. The Next horizon contemplated initiatives planned for sequential development (2-4 months), generally in the “discovery” phase. The Later horizon grouped potential initiatives or those dependent on strategic decisions (above four months), incorporating additional dependency management information.
The differentiation of attributes by horizon sought to balance simplicity and utility, avoiding informational overload and ensuring visibility of strategic factors. Attributes such as Status, Alerts, and Status Summary were defined to reduce informational fragmentation and bring the formal record closer to the real state of initiatives. Priority and Strategic Impact were included to support decision traceability, while Dependencies and Responsible were incorporated to provide visibility into implicit factors. The model adopted status categories (‘backlog’, ‘discovery’, in progress, and completed), classifications for strategic impact (regulatory, revenue, customer experience, operational efficiency, or risk reduction), and priority (critical, high, medium, or low).
The artifact incorporated the synthetic visualization of the portfolio of demands, through indicators that evidenced the distribution of initiatives by priority level, the status in the workflow, and the presence of alerts. The definition of these indicators was guided by thematic data analysis, translating recurring patterns into managerial monitoring needs and operationalized from the defined attributes.
To ensure the artifact’s continued usefulness, periodic rituals for updating and reviewing the roadmap were defined, with the Now horizon reviewed weekly, the Next bi-weekly, and the Later monthly. Responsibility for maintaining the roadmap was assigned to the Product Owner, who acted to ensure its update, promote its use, and ensure the consistency of the recorded information.
3. Results and Discussion
The analysis of the collected data revealed recurring patterns in the investigated context, which were structured into three main analytical dimensions: strategic communication, demand prioritization, and governance. These dimensions, aligned with the thematic axes of the methodology, allowed for the diagnosis of existing challenges before the implementation of the artifact and, subsequently, the evaluation of changes resulting from its application. The findings are robust, supported by the triangulation of evidence from records in the demand management system (Jira), communications on messaging platforms (Microsoft Teams), and direct participant observation, ensuring an in-depth understanding of the phenomenon.
Initially, the pre-implementation scenario of the artifact was marked by significant informational fragmentation. It was observed that status updates in formal Jira records were often incomplete or discontinuous, not reflecting the actual state of initiatives. In parallel, crucial decisions regarding direction and prioritization were made in informal Teams channels, without proper recording in corporate systems. This practice resulted in a decentralized circulation of strategic information, generating different levels of understanding among stakeholders and compromising the unified view of the project portfolio.
Direct observation corroborated this fragmentation, evidencing divergent interpretations on the status of the same initiative in alignment meetings. The high quantity of simultaneous interactions made monitoring difficult, and initiatives without immediate problems received less attention, even with relevant medium-term risks or dependencies. Another critical aspect was the need for manual consolidation of information before executive meetings. Leadership frequently requested individual summaries, prepared in a decentralized manner, which, despite the availability of data in corporate tools, required significant compilation and interpretation effort, sometimes resulting in inconsistencies in the presented reports.
This panorama of deficient communication points to the absence of a single source of truth, a problem that the PMBOK Guide (PMI, 2021) highlights as a limitation to governance in complex environments. The lack of structured communication channels compromised the quality of decision-making at the organizational level, preventing a holistic and proactive view of the project portfolio. The difficulty in accessing consolidated and consistent information generated rework and delays, directly impacting operational efficiency and the institution’s ability to respond to market and regulatory demands.
On the axis of demand prioritization, the traceability of decisions was a constant challenge. The integrated analysis of meeting minutes, Jira records, and Teams interactions revealed a systematic divergence between formally documented priorities and those effectively executed by the teams. Informal interactions indicated frequent renegotiations and new interpretations without proper updating in formal records. This behavior was confirmed by direct observation, where the inclusion of new urgent demands, often motivated by regulatory deadlines or operational impediments, was not accompanied by an explicit review of existing priorities.
As a consequence, new initiatives were frequently incorporated into the portfolio without the formalization of decisions to postpone or cancel previous ones. This pattern resulted in a predominantly reactive prioritization process, with low traceability, where the demand for previously prioritized deliveries persisted even after informal redefinitions. This generated a significant misalignment between leadership expectations and the teams’ actual execution capacity. The absence of a consolidated portfolio view intensified disputes between regulatory projects, business improvements, and technological evolutions, without clear indicators relating the quantity of critical demands to execution capacity.
Decisions on prioritizing new critical demands were made without explicit articulation of their impacts on other initiatives, making it difficult to understand which ones would be affected, postponed, or rendered unfeasible. This finding corroborates the results of Gonçalves et al. (2024), who identified the absence of structured prioritization mechanisms as a critical factor for the loss of planning predictability in regulated environments. The lack of transparency and a formalized process for re-evaluating priorities contributed to team overload and inefficient resource allocation.
Governance, in turn, presented a predominantly reactive pattern of action by the leadership instances. The analysis of Jira records, combined with direct observations, indicated that ongoing initiatives without registered alerts received less attention. Leadership participation only increased in the face of critical signals, such as imminent risk of regulatory delay or relevant operational impediments. This reactive stance limited the capacity for preventive intervention, transforming risk management into a response to already manifested problems, rather than a proactive approach to mitigate them.
Discrepancies were identified between the formally registered information and that discussed through informal channels. In some cases, leadership was informed about the status of initiatives, but the available records did not offer sufficient detail for a proactive risk assessment. Interactions between teams on Teams showed that critical information, especially related to dependencies and impediments, was not always consolidated and communicated to decision-making instances in an accessible manner. This information asymmetry contributed to a more reactive approach, focused on resolving already manifested problems, rather than anticipatory management.
This reactive behavior of leadership can be associated with the perception that initiatives in the development phase are under control, which reduces continuous monitoring. Consequently, preventive action becomes limited, characterizing a pattern of reactive governance, as described in the literature by Hevner et al. (2004). The convergence of documentary and observational evidence indicated that this pattern was structural, reflecting a gap in the visibility and proactive engagement of governance instances regarding the project portfolio.
Given this scenario, the proposed artifact consists of a structured roadmap model, designed to promote a consolidated vision of initiatives across business, technology, and leadership areas, and to reduce information fragmentation throughout the project lifecycle. The model organizes demands into three distinct time horizons: Now, Next, and Later, allowing initiatives to be differentiated according to their degree of maturity and the complexity involved. This structure aims to balance the need for detailed information with practical utility for decision-making.
The Now horizon groups demands that are in execution or with immediate start, with development forecast in the short term, generally from zero to two months. This horizon includes detailed information essential for monitoring initiatives, such as title, priority, status summary, current status, alerts, strategic impact, and deadline. This level of detail is crucial for operational management and for the rapid identification of impediments, ensuring that teams have a clear view of the most urgent priorities and challenges.
The Next horizon concentrates planned demands to start after the completion of initiatives in development, covering the medium term, typically two to four months. Most of these initiatives are in the “discovery” phase, which involves gathering requirements and exploring solutions. This horizon allows for monitoring planning progress and identifying emerging risks or dependencies before they become critical, facilitating the preparation and allocation of future resources more efficiently and strategically.
The Later horizon, on the other hand, brings together potential initiatives or those dependent on strategic decisions, with execution planned for the long term, above four months. At this stage, in addition to the basic identification and prioritization fields, additional information related to the management of organizational dependencies and responsibilities is incorporated. This differentiation of attributes by horizon seeks to balance the simplicity and usefulness of information, avoiding overload in ongoing initiatives and ensuring visibility of the strategic factors that influence long-term demands.
The attributes defined for each initiative in the roadmap include: Title, a brief description for quick identification; Status, with categories such as “backlog”, “discovery”, “in progress”, and “completed”, indicating the maturity level; Strategic Impact, classifying the contribution to organizational objectives (regulatory, revenue, customer experience, operational efficiency, or risk reduction); Deadline, the expected completion date; Alerts, for risks or impediments; Status Summary, a synthesis of progress; Priority, classifying criticality (critical, high, medium, low); Dependencies, for external factors (especially on the Later horizon); and Owner, the individual responsible for monitoring the initiative’s evolution.
In addition to the initiative registration structure, the artifact incorporates synthetic visualizations of the demand portfolio, through indicators that highlight the distribution of initiatives by priority level, their status in the workflow, and the presence of alerts. For example, a graphical representation in pie chart format shows the proportion of open initiatives by priority level, indicating that 10% are critical, 40% are high priority, 35% are medium priority, and 15% are low priority. This visualization allows leadership to quickly identify concentrations of critical demands, bottlenecks, and risks that require intervention, supporting managerial decision-making.
Additionally, the artifact includes a specific dashboard for visualizing demands that have associated alerts, bringing together initiatives with risks, blockers, or dependencies that could compromise their progress or delivery timeline. This consolidation of information in a dedicated space enhances visibility into potential problems and facilitates the identification of priority or mitigation actions. Examples of alerts include “Risk of delay due to external API dependency” for the “MED Pix Implementation”, “Costs above the planned budget” for the “Cloud infrastructure migration”, and “Specialized resource unavailable” for the “Payment module refactoring”.
To ensure the artifact’s continued usefulness, periodic rituals for updating and reviewing the roadmap were defined, according to the different time horizons. The Now horizon is reviewed weekly, focusing on monitoring ongoing initiatives and identifying impediments. The Next horizon is reviewed bi-weekly, allowing for an assessment of the progress of initiatives in the “discovery” or refinement phase. The Later horizon, on the other hand, is reviewed monthly, focusing on the analysis of strategic opportunities and dependencies required for certain initiatives to advance in the planning.
To ensure the execution of these rituals and the continuous updating of information, the responsibility for maintaining the roadmap was assigned to the “Product Owner”, who acts as a link between the business and technology areas. This role not only ensures the artifact’s update but also promotes its use in monitoring routines, supports the prioritization of initiatives, and ensures the consistency of the recorded information, especially regarding status, priorities, risks, and dependencies. This maintenance process contributes to the roadmap being used as a dynamic instrument for strategic communication and organizational alignment, preventing the artifact from becoming merely a static planning record.
Starting from the initial scenario of information fragmentation, low traceability of decisions, and reactive governance, the application of the artifact allowed us to observe relevant changes in the organization and monitoring of portfolio initiatives. The results are supported by the convergence between records in the demand management system (Jira), communications on messaging platforms (Teams), and direct observation of the organizational context, ensuring analytical consistency to the findings and evidencing the effectiveness of the proposed roadmap.
Regarding the fragmentation of information and knowledge management, it was observed that, in contrast to the previous scenario, the roadmap began to be used as a central point of reference for portfolio visualization. The analysis of interactions in Teams showed a reduction in queries distributed across multiple tools and parallel channels, and the artifact started to guide discussions in alignment meetings. This usage contributed significantly to reducing the need for manual information consolidation and bringing formal records closer to the actual state of initiatives, promoting a single source of truth.
Regarding the traceability of decisions, the organization of initiatives across different time horizons made the teams’ execution capacity in prioritization processes more explicit. In one of the observed cases, the inclusion of a new demand was re-evaluated upon identifying, through the roadmap, that initiatives in the Now horizon presented risk alerts. This evidence indicates that the integrated visualization favored decisions based on the entire portfolio, unlike the previous pattern, characterized by reactive and poorly documented decisions, thus qualifying the decision-making process.
Regarding the visibility and performance of leadership, the roadmap contributed to reducing informational asymmetries between technical teams and decision-making instances. In one analyzed case, a regulatory demand considered to be in development was identified as not yet initiated when positioned on the Later horizon. This discrepancy, identified convergently from both sources, illustrates how the artifact can support more proactive action by governance instances by making the real state of initiatives explicit, allowing for earlier and more effective interventions.
The use of attributes such as alerts and dependencies reinforced this effect, as demands with impediments became more visibly highlighted in the tracking routines, increasing visibility of risks and facilitating their identification in meetings and interactions between areas. This greater transparency allowed leadership to act more preventively, directing resources and efforts to mitigate problems before they became critical, which represents an advance compared to the reactive governance standard initially observed.
The artifact’s replicability depends on some organizational conditions and variables. The existence of a clearly defined person responsible for maintaining the roadmap, such as the “Product Owner” in the studied case, proved critical to prevent the artifact from becoming a static record. The availability of pre-configured templates also proved important in reducing the teams’ initial resistance, especially in contexts with high operational demand, facilitating the adoption and standardization of the artifact’s use.
The choice of support tool, whether Jira, spreadsheets, or other platforms, needs to consider the organization’s capacity to keep fields updated continuously. Variables that can influence results in other contexts include the degree of formalization already existing in prioritization processes, the maturity of the area’s agile practices, the volume of parallel regulatory demands, and the level of leadership engagement in monitoring routines. In environments with low governance maturity or high turnover of responsible parties, the sustainability of the artifact tends to be more challenging, requiring greater effort in implementation and maintenance.
It is therefore recommended that the artifact be made available in a shared environment, with broad access to all involved areas, and that its maintenance be incorporated into monitoring routines, such as prioritization meetings and inter-area communications. These results reinforce the guidelines of the PMBOK (PMI, 2021) on the concept of “tailoring” and dialogue with the findings of Gonçalves et al. (2024) on the importance of formalized prioritization mechanisms in regulated environments of the Brazilian banking sector, highlighting the need to adapt management practices to the organizational reality.
In summary, the hybrid roadmap based on the Now-Next-Later model demonstrated significant potential to mitigate informational fragmentation, improve the traceability of prioritization decisions, and enhance leadership visibility over the project portfolio. By making priorities, dependencies, and alerts explicit, the artifact contributed to qualifying discussions and reducing the need for manual information consolidation, promoting a more effective balance between regulatory predictability and operational flexibility, essential for the banking environment.
4. Conclusion
The present study sought to develop and evaluate a hybrid roadmap, based on the Now-Next-Later model, as an instrument to support strategic alignment, communication, and prioritization of demands in Information Technology projects at a Brazilian financial institution. It was found that, before the implementation of the artifact, the context was marked by informational fragmentation, low traceability of prioritization decisions, and predominantly reactive governance. The application of the roadmap demonstrated that the artifact reduced the need for manual information consolidation, establishing a single source of truth for the project portfolio. It was observed that the organization of initiatives into distinct temporal horizons made the teams’ execution capacity more explicit, qualifying prioritization discussions. Additionally, the roadmap increased leadership visibility into the actual status of initiatives, allowing for more proactive action in managing risks and dependencies. This practical contribution lies in offering a structured mechanism that balances the predictability required by regulatory projects with the flexibility needed for continuous improvement initiatives in the banking sector.
However, the artifact’s replicability and sustainability depend on factors such as the clear definition of maintenance roles, the existence of associated governance rituals, and adequate technological support. The research, conducted in a single financial institution over a three-month observation period, limits the generalization of results and may not capture variations across different phases of the regulatory calendar or during periods of higher business volatility. It is suggested that future studies expand the application of the artifact to other regulated organizations or sectors, evaluating its adaptability and effectiveness in distinct contexts. It is also recommended to investigate the impact of different technological tools on the adoption and maintenance of the roadmap, as well as to develop quantitative metrics to assess its effects on planning predictability and organizational alignment.
Bibliographic References
Braun, V.; Clarke, V. 2006. Using thematic analysis in psychology. Qualitative Research in Psychology 3(2): 77-101.
Cagan, M. 2020. Inspirado: como criar produtos de tecnologia que os clientes amam. 2ed. Alta Books, Rio de Janeiro, RJ, Brasil.
Gonçalves, A.; Silveira, M.A.P. da; Marcolin, C.B.; Kubo, E.K. de M. 2024. Metodologias de projetos para atender exigências regulatórias: um estudo com gerentes de projeto do setor bancário nacional. Revista de Gestão e Projetos 15(3): 625-650. Disponível em: https://doi.org/10.5585/gep.v15i3.26590.
Hevner, A.R.; March, S.T.; Park, J.; Ram, S. 2004. Design science in information systems research. MIS Quarterly 28(1): 75-105. Disponível em: https://doi.org/10.2307/25148625.
Project Management Institute [PMI]. 2021. Guia PMBOK®: um guia para o conjunto de conhecimentos em gerenciamento de projetos. 7ed. Newtown Square, PA, EUA: Project Management Institute.
Yin, R.K. 2015. Estudo de caso: planejamento e métodos. 5ed. Porto Alegre, RS, Brasil: Bookman.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq