Systematization of lessons learned in projects: an action-research applied to the supply of electrical equipment
Ana Luiza da Costa Garcia; Tatiana Kimura Kodama
DOI: 10.22167/2675-6528-202600537
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The absence of structured routines for recording and sharing experiences in projects frequently contributes to the repetition of failures, generating delays and rework that impact efficiency and customer satisfaction. Faced with this problem, lessons learned presented themselves as a mitigation tool, although their implementation faced challenges. The study aimed to implement and evaluate a systematized lessons learned routine in the administration of customized product contracts, aiming to reduce rework and strengthen organizational knowledge retention. The research was characterized as exploratory, mixed (qualitative and quantitative), and was classified as action research, developed in stages of initial diagnosis, implementation with the 5W2H tool, obtaining results, and post-implementation. The results showed that failures were concentrated in the implementation phase and in commercial documents, mainly affecting the Sales and Contract Administration areas. After the intervention, a reduction in the failure occurrence rates was observed, with significant drops in issues such as cancellation curves and “Databook”, associated with systemic changes and changes in documentary templates. The findings indicated that the institutionalization of knowledge in shared repositories, combined with process standardization, mitigated information losses, promoted interdepartmental alignment, and increased project execution efficiency.
Keywords: Knowledge Management; Continuous Improvement; Process Standardization.
1. Introduction
Knowledge Management has been consolidated as a strategic differentiator in project management, especially in industrial environments. In these contexts, the recurrence of operational failures directly impacts efficiency and customer satisfaction (Schindler; Eppler, 2003). Large companies frequently face challenges such as process diversity across sectors, lack of document standardization, and failures in interdepartmental communication. The absence of a structured routine to record and reuse previous experiences contributes to the repetition of errors and rework (Ferenhof et al., 2013).
The systematization of lessons learned is recognized as an essential tool for the improvement of internal processes and the increase of maturity in project management (Kerzner, 2017; PMI, 2017). Furthermore, organizational culture directly influences the adoption and effectiveness of knowledge management practices. The sharing of experiences and the collective construction of solutions favor collaborative environments conducive to innovation. The use of practical project management tools can be a success factor for the consolidation of continuous improvement routines, and the proactive action of leadership is fundamental for team engagement and organizational learning (Rodrigues, 2018; Osobajo et al., 2025).
However, despite the growing recognition of the value of lessons learned in project management, aiming to avoid costs and save time, their implementation still faces significant obstacles. Many organizations, even aware of the need to record and share learnings, lack structured processes, adequate tools, standardization, or an organizational culture that favors this behavior (Osobajo et al., 2025). Frequently, lessons learned are conducted superficially and face resistance. The knowledge acquired in a project is often not properly documented or communicated for later use, resulting in “corporate amnesia” and contributing to increased costs, schedule delays, and considerable rework (Jugdev, 2012; Debs and Hubbard, 2023).
This scenario of difficulties aligns with the context of the company under study, a large organization located in Santa Catarina, operating in the supply of electrical panels for the industrial sector. A high recurrence of similar problems was identified among projects, such as failures in deadline communication, divergence of information in contractual documents, and ambiguities regarding scopes and responsibilities. The absence of a consolidated routine for collecting and reusing lessons learned resulted in rework, delays, and customer dissatisfaction, which could have been avoided based on previous project experiences.
Faced with this problem, this work sought to answer the research question: how can the systematization of lessons learned contribute to reducing recurring failures and strengthening organizational knowledge retention in electrical equipment supply projects? The relevance of the study lies in the need to mitigate the negative impacts of these failures, which compromise operational efficiency and customer satisfaction, and in the opportunity to transform tacit knowledge into an organizational asset, promoting continuous improvement and organizational learning.
Thus, the general objective was to implement and evaluate a systematized routine of lessons learned in the administration of customized product contracts, focusing on reducing rework and strengthening organizational knowledge retention. As a practical contribution, the study proposes and evaluates an intervention applicable to project management in an industrial environment, articulating knowledge management, process standardization, and organizational learning.
2. Material and Methods
The present research was characterized, in terms of objectives, as exploratory, seeking to provide greater familiarity with the studied theme, according to Gil (2002). In the context of this work, communication failures and knowledge loss in projects configured an unstructured scenario in the organization, justifying the exploratory nature of the study to deepen the understanding of the problem.
Regarding the nature of the data, a mixed approach was adopted, combining quantitative and qualitative techniques. The qualitative bias sought to understand individuals’ perspectives on their reality during project execution, while the quantitative focused on data collection and analysis to support the research, according to the principles of Sampieri et al. (2013).
Regarding the design, the study was classified as action research, which is distinguished by being conducted participatively to solve a real problem while generating scientific knowledge (Coughlan; Coghlan, 2002). Action research, according to Thiollent (2019), is applicable in organizations with hierarchical structures or groups with problematic relationships, aligning with the investigated scenario.
The study was conducted in a large company, located in the state of Santa Catarina, which operates in the supply of electrical panels for the industrial sector. The research was initiated from a real problem, given the need to systematize knowledge that emerged from operational difficulties experienced directly in the work environment, according to the approach of Mello et al. (2012).
The research conduction followed the cyclical logic of action research, composed of the phases of planning, implementation, observation, and reflection, adapted from the proposal by Coughlan and Coghlan (2002). This logic resembles the PDCA cycle (“Plan-Do-Check-Act”), reinforcing the idea of development through continuous cycles of planning, executing, evaluating, and acting (Mello et al., 2012).
For organization and presentation, the work was divided into four logical scenarios, which correspond to the eight main stages proposed by Coughlan and Coghlan (2002). The first scenario, named “Initial Scenario”, sought to identify the context and purpose of the study, responding to the premises of rationality for action and research.
In the data collection stage, an organizational diagnosis was carried out to identify the absence of consolidated lessons learned practices and the main recurring failure points in projects. This stage involved the analysis of past project documents and the holding of “brainstorm” sessions with project management team members, aiming to identify problems and difficulties in the processes.
The unit of analysis was composed of project transition documents, including Commercial Contracts, Technical Proposals, Sales Price Closing Spreadsheets, Sales Orders, and annexes such as “Order Form” and GFS, according to the specification of each project. Data extraction focused on information that parameterizes execution, such as technical scopes, delivery deadlines, expediting definitions, payment conditions, and shipping methods.
The initial survey comprised the documents of projects implemented in the five months immediately preceding the implementation of the lessons learned routine, specifically between June and October 2024. This temporal and documentary scope was selected because it represents the critical interface of responsibility transfer between the Sales and Execution areas, in addition to reflecting the average project lifecycle in the organization.
In the data return and analysis steps, the main improvement points identified were presented and, collaboratively, the failures were categorized according to the areas involved, the phase in which the improvement opportunity was identified, the documents impacted, and the frequency of occurrence. For the treatment and triage of failures, a Probability and Impact Matrix, adapted from the PMBOK (PMI, 2017), was constructed.
The probability of failure occurrence was assessed based on the number of occurrences, with frequency calculated by dividing the number of identified failure occurrences by the number of new projects implemented in the period. The impact was collectively assigned by representatives from the Sales, Contract Administration, PCP, Engineering, Logistics, and Billing areas, in three meetings held in November 2024.
The criteria for classifying the impact as ‘low’, ‘moderate’, or ‘high’ were based on the joint analysis of the project schedule delay potential, volume of rework hours, direct financial impact, risk of contractual misalignment, and impact on final customer satisfaction. The researcher acted as a facilitator to mitigate the bias inherent in her dual role. The risk classification was calculated by multiplying probability by impact.
The second stage, “Implementation”, began with the structuring of the lessons learned routine, corresponding to the Action Planning of the methodology. The 5W2H tool was used for the creation of action plans, which allows for the decomposition of complex processes and standardization of procedures, according to Lisbôa and Godoy (2012).
The defined actions included the creation of a recurring meeting and a digital repository. The recurring meeting aimed at the formal presentation and discussion of operational failures and lessons learned, with the participation of a multidisciplinary team from the Sales, Contract Administration, Production Planning and Control, Logistics, and Billing areas, in addition to superiors and senior management, in bi-weekly online meetings, lasting fifteen to thirty minutes.
The repository for consulting lessons learned consisted of the creation, parameterization, and availability of a centralized and standardized database on a cloud platform. The creation of the repository was the responsibility of the researcher, with access made available to all participating teams. The repository was categorized by impacted area, project phase, involved document, and error frequency, using keywords to facilitate the search, according to Greer (2008).
The implementation of both actions did not require direct financial contribution, as it utilized the existing IT infrastructure in the company. The real cost of the intervention was accounted for by the hours spent by the teams for preparation and execution of the meetings, as well as for the creation and maintenance of the repository. A brief training was conducted in the first meeting to guide the teams on the use of the repository.
In the third stage, “Obtained Results”, the effectiveness of applying the lessons learned methodology was evaluated by comparing the failure occurrence rate in two five-month periods: before and after the topic was presented to the teams. The indicator of drop or increase in occurrences in percentage points (PP) was calculated by the equation PP = (NOA / NPA × 100) – (NOP / NPP × 100), where NOA and NOP represent the number of occurrences before and after, and NPA and NPP the number of new projects before and after, respectively.
The indicator’s evaluation was normalized by the quantity of sales orders deployed. Furthermore, attendance rates at each meeting were assessed, seeking to ensure the participation of relevant teams and leadership. The fourth stage, “Post-implementation”, involved the analysis of results and possible adjustments to the implemented routine, aligning with the iterative cycle of action research to strengthen the effectiveness and sustainability of the proposed practice.
Regarding the ethical aspects of the research, the institutional approval term from the company was provided, ensuring the ethical compliance of the study with the principles of transparency and respect for the organization and its collaborators. The research faced limitations related to resistance to cultural change and the availability of collaborators’ time, which were monitored and considered in the evaluation and adjustment stage.
3. Results and Discussion
The action research implemented revealed significant insights into the management of lessons learned in electrical equipment supply projects, focusing on reducing rework and strengthening organizational knowledge. Initially, an absence of structured routines for recording and sharing experiences was identified, which contributed to the recurrence of failures and negative impacts on efficiency and customer satisfaction. The intervention, which included the creation of recurring meetings and a digital repository, demonstrated a remarkable ability to mitigate specific problems, especially those related to documents and systemic processes. However, the analysis also pointed to persistent challenges in areas requiring greater interdepartmental alignment and overcoming cultural resistance, highlighting the complexity of institutionalizing knowledge in industrial environments.
Step 1. Initial Scenario
The initial diagnosis of the action research confirmed the central problematic, evidencing that the absence of a formal system to document and share the knowledge generated in projects resulted in recurring failures. These failures directly impacted project schedules, costs, and execution quality, a scenario that corroborates the observations of Debs and Hubbard (2023) on the difficulties in capitalizing on lessons learned due to time constraints and lack of standardization. The analysis of data collected between June and October 2024, a period during which 169 new projects were implemented, allowed for the mapping of ten distinct themes of failures, categorizing them by frequency, impact, documents involved, and affected areas.
Among the identified themes, “Incorrect deadline” stood out with 59 occurrences, representing 35% of the total failures, followed by “Commercial values” with 37 occurrences (21%) and “Databook” with 26 occurrences (15%). “Cancellation curve” also presented 25 occurrences (15%), while “Inspection” and “Product stocking” registered 20 occurrences each (12%). Themes such as “Freight modality” (16 occurrences, 9%), “Payment Condition” (15 occurrences, 9%), and “Diligence” (13 occurrences, 8%) were also relevant. The theme “Translation” had only one occurrence (1%), indicating its low frequency in the analyzed period.
The prioritization of these themes was carried out through a Probability and Impact Matrix, adapted from the PMBOK (PMI, 2017), classifying the risk of recurrence of failures. The themes of “Incorrect deadline”, “Commercial values”, and “Product stocking” were classified as high risk, with scores of 0.56, 0.40, and 0.24, respectively. This indicates that, in addition to being frequent, these failures have a significant potential to cause schedule delays, rework, and financial impact. “Cancellation curve”, “Inspection”, and “Databook” were considered intermediate risk, with scores of 0.12 each, suggesting the need for attention, but with slightly lower impact or probability.
The challenges addressed in the lessons learned revealed the complexity of the sales cycle and project execution. Failures included undefined inspections in the proposal, product stocking issues that affected physical space and revenue, and the implementation of sales orders with incorrect deadlines, compromising customer relationships. Other important inconsistencies were discrepancies in shipping methods, values in commercial documents, and the lack of adequate specification in the “Databook”, in addition to the need for alignment on payment conditions and the inclusion of the cancellation curve in proposals.
The analysis of the documents most impacted by the failures showed that the “Proposal” was the document with the highest concentration of problems, with nine occurrences, followed by “SAP/OV” with five occurrences and “Purchase Order” with four occurrences. The “Order Form” and the “Closing Spreadsheet” registered three and two occurrences, respectively, while “GFS” presented two. This distribution highlights that commercial and project transition documents are critical points where inconsistencies manifest, requiring greater rigor in standardization and verification.
Regarding the areas involved in the identified problems, Contract Administration and Sales were the most affected, with twelve and nine occurrences, respectively. Production Planning and Control (PPC) registered three occurrences, while Engineering, Logistics, and Testing presented two occurrences each, and Billing one. This concentration of problems in the Contract Administration and Sales areas points to a lack of alignment between operational and commercial sectors, corroborating the literature that highlights the need for integration between marketing, sales, and operations for the viability of the production plan (Telha and Carvalho, 2025).
The distribution of problems throughout the process phases revealed that the “Implementation” phase was the most critical, concentrating seven occurrences. The “Manufacturing” and “Billing” phases followed with four and three problems, respectively, while “Logistics” and “Design” registered one and two occurrences. This concentration in the initial implementation phase reinforces the importance of early corrective actions, as the cost to correct defects is significantly lower in the initial stages of the project compared to later phases, such as manufacturing and maintenance (Dawson et al., 2010). The results suggest that failures are not random, but are concentrated in critical interfaces between commercial and operational areas, indicating weaknesses in integration and cross-functional alignment.
Step 2. Implementation
The proposed intervention was structured in two complementary fronts, aiming to address the limitations identified in the literature regarding the absence of formal spaces for collective reflection and the fragility in knowledge retention. The first action consisted of creating a “Recurring Lessons Learned Meeting”, a structured forum for the presentation, analysis, and debate of operational failures and learnings from previous projects. These meetings, held bi-weekly online, involved the participation of a multidisciplinary team, including representatives from Sales, Contract Administration, Production Planning and Control, Logistics, and Billing, in addition to the support of senior management, as recommended by Osobajo et al. (2025) for the successful implementation of a lessons learned culture.
During the meetings, the Contract Administration team prioritized the highest risk topics identified by the Probability and Impact Matrix. Through “brainstorming” sessions, participants debated the root causes of errors and defined process improvements, lasting fifteen to thirty minutes per meeting. The implementation of this routine did not require additional financial investment, utilizing the existing IT infrastructure in the company, although the real cost of the intervention was accounted for by the hours dedicated by employees to the preparation and execution of the meetings, recognizing the value of time as an organizational resource.
The second area of intervention was the creation of a “Repository for consulting Lessons Learned”, a centralized and standardized database, made available on a cloud platform. This repository was developed under the researcher’s responsibility and its access was released to all participating teams. The main objective was to standardize and internalize knowledge, creating an easy-to-use online space for searching lessons learned, which aligns with the recommendations of Ferrada et al. (2016) to overcome challenges in implementing lessons learned systems through online and shared platforms.
The repository was parameterized with classification categories that included the impacted area, the project phase, the document involved, and the error frequency, facilitating the search and retrieval of knowledge, as suggested by Greer (2008). Each registered topic also received specific keywords to optimize the search. After its creation, a brief training was conducted in the first meeting to ensure all teams knew how to use the system. Like the meetings, the implementation of the repository did not require direct financial investment, but rather the cost of working hours for its creation, maintenance, and addition of new topics.
From a project management perspective, the recurring meeting acted as a fundamental mechanism for integration between areas and for the governance of critical information, promoting interdepartmental alignment. In parallel, the digital repository functioned as robust support for Knowledge Management and procedure standardization, transforming tacit knowledge into an accessible and reusable organizational asset. This systematic approach aimed not only to solve specific problems but also to strengthen the company’s culture of continuous improvement and organizational learning.
Step 3. Results obtained
The evaluation of the effectiveness of the lessons learned routine was carried out by comparing the occurrence rates of failures in two equivalent periods: the five months prior to and the five months after the presentation of the topics to the teams involved. The results demonstrated a reduction in the occurrence rates for most of the monitored topics, with emphasis on “Cancellation Curve”, which showed an expressive drop from 18% to 5%, resulting in a reduction of 13 percentage points. The topic “Databook” also registered a significant decrease, going from 20% to 11%, a reduction of 9 percentage points.
These substantial reductions in “Cancellation Curve” and “Databook” were associated with the implementation of systemic and documentary changes, not just verbal dissemination of lessons learned. This finding is crucial, as it suggests that formal standardization mechanisms, such as updating documentary templates and system changes, have a greater capacity to prevent the recurrence of failures. The institutionalization of knowledge directly into project artifacts and routines, through standardization of documentation and processes, facilitates the reapplication of knowledge and implements a culture of best practices and continuous improvement, as highlighted by Osobajo et al. (2025) and Greer (2008).
Other themes also showed notable reductions, such as “Product Stocking”, which decreased from 14% to 6% (8 percentage points), “Incorrect Deadline”, from 39% to 31% (8 percentage points), and “Commercial Values”, from 21% to 13% (8 percentage points). “Payment Condition” and “Diligence” also had drops of 6 percentage points each, going from 11% to 5% and from 10% to 4%, respectively. “Freight Modality” reduced from 10% to 7% (3 percentage points), and “Inspection” from 12% to 11% (1 percentage point).
Despite the observed reductions, issues such as “Incorrect deadline”, “Commercial values”, and “Product stocking” still maintained high levels of occurrence. This indicates that the mere presentation and categorization of problems in meetings were not sufficient to eliminate their structural causes, especially in more complex cross-functional processes. The persistence of these failures highlights the need for additional and more in-depth interventions to address the root causes of these problems, which often involve multiple areas and dependencies.
Regarding the theme “Translation”, although the occurrence rate has decreased from 1% to 0% after the intervention, the reduced number of occurrences in the analyzed period prevents us from robustly affirming the effectiveness of the intervention for this specific problem. The low initial frequency does not allow us to infer that the mitigation was a direct result of the implemented actions, but rather that the problem was already marginal. This point highlights the importance of considering the occurrence base when evaluating the significance of reductions.
Regarding the engagement of areas in the implementation of the routine, constant participation was observed from Contract Administration, Production Planning and Control, and Engineering. However, the adherence of the Sales teams was approximately 60%, with different levels of engagement among the five teams involved. This variability in the participation of the Sales area has been a point of monitoring by senior management, indicating that organizational culture and leadership engagement are critical factors for the full institutionalization of lessons learned, as pointed out by Osobajo et al. (2025).
Step 4. Post-implementation
In the post-implementation stage, the lessons learned routine demonstrated a more organic integration into the company’s dynamics, albeit with challenges. For issues classified as higher risk and that showed insufficient reduction, such as “Incorrect deadline” and “Commercial values”, a specific working group was structured. This group aimed to deepen the investigation of root causes and propose complementary mitigation actions, reinforcing the cyclical nature of action research and the orientation towards continuous improvement, which is inherent to this methodology (Mello et al., 2012).
The research faced significant limitations, including resistance to cultural change from some teams, limited availability of collaborators’ time for meeting participation, and the challenge of adhering to the practice of recording lessons learned. These issues were monitored and considered throughout the evaluation and adjustment process, aiming to mitigate impacts and continuously improve the implemented solution. Overcoming these behavioral and organizational barriers is fundamental for the long-term sustainability and effectiveness of knowledge management practices.
In summary, the implementation of the systematized lessons learned routine proved to be an effective tool for reducing recurring failures and strengthening organizational knowledge retention in electrical equipment supply projects. The results showed that process standardization and knowledge institutionalization in shared repositories are more effective in mitigating errors than mere oral dissemination, promoting interdepartmental alignment and increasing project execution efficiency. However, the persistence of failures in high-risk areas and the variability in team engagement highlight the need for continuous effort to overcome cultural barriers and deepen interventions, ensuring the consolidation of an organizational learning culture.
4. Conclusion
This study sought to implement and evaluate a systematized routine of lessons learned in the administration of customized product contracts, with the purpose of reducing rework and strengthening organizational knowledge retention. The absence of structured processes for recording and sharing experiences was initially verified, which resulted in recurring failures, concentrated mainly in the implementation phase and in commercial documents, affecting the Sales and Contract Administration areas. The intervention, which included the creation of recurring meetings and a digital repository, demonstrated a capacity to mitigate specific problems. A reduction in the occurrence rates of failures was observed for most of the monitored themes, with significant drops in “Cancellation Curve”, which decreased by 13 percentage points, and “Databook”, with a reduction of 9 percentage points. These improvements were associated with the implementation of systemic and documentary changes, indicating that the institutionalization of knowledge in shared repositories, combined with process standardization, promoted interdepartmental alignment and increased efficiency in project execution.
The main contribution of this work lies in the proposition and evaluation of a practical intervention applicable to project management in an industrial environment, articulating Knowledge Management, process standardization, and organizational learning, and providing empirical evidence that documentary standardization is significantly more effective in mitigating errors than mere oral dissemination. However, the study faced limitations, such as cultural resistance to change from some teams, limited availability of collaborators’ time for meeting participation, and the challenge of adhering to the practice of lessons learned register. The persistence of failures in high-risk topics, such as “Incorrect deadline” and “Commercial values,” highlights the need for more in-depth interventions. Therefore, it is suggested to apply qualitative assessment tools to the repository users and create specific working groups to investigate the root causes of topics that maintained high occurrence rates, aiming for the continuous consolidation of the company’s learning culture.
Bibliographic References
Coughlan, P.; Coghlan, D. 2002. Action research for operations management. International Journal of Operations & Production Management 22(2): 220-240
Dawson, M.; Burrell, D.; Rahim, E.; Brewster, S. 2010. Integrating software assurance into the software development life cycle (SDLC). Journal of Information Systems Technology and Planning 3: 49-53
Debs, L.; Hubbard, B. 2023. Gathering and Disseminating Lessons Learned in Construction Companies to Support Knowledge Management. Construction Economics and Building 23(1/2): 56-76.
Ferenhof, H. A.; Forcellini, F. A.; Varvakis, G. 2013. Lições aprendidas: agregando valor ao gerenciamento de projetos. Revista de Gestão e Projetos – GeP, São Paulo, v. 4, n. 3, p. 197-209.
Ferrada, X.; Núñez, D.; Neyem, A.; Serpell, A.; Sepúlveda, M. 2016. A lessons-learned system for construction project management: a preliminary application. Procedia Social and Behavioral Sciences 226: 302-309
Gil, 2002 [Referência completa não encontrada no documento original]
Greer, S. 2008. A Lessons-Learned Knowledge Management System for Engineers. Chemical Engineering 115(8): 50-53.
Jugdev, K. 2012. Learning from Lessons Learned: Project Management Research Program. American Journal of Economics and Business Administration 4(1): 13-22
Kerzner, H. 2017. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 12. ed. New York: Wiley.
Lisboa, M.G.P.; Godoy, L.P. 2012. Aplicação do método 5W2H no processo produtivo do produto: a joia. Iberoamerican Journal of Industrial Engineering 4(7): 32-47.
Mello, C.H.P.; Turrioni, J.B.; Xavier, A.F.; Campos, D.F. 2012. Pesquisa-ação na engenharia de produção: proposta de estruturação para sua condução. Produção 22(1): 1-13
Osobajo, O.A.; Lawani, A.; Oke, A.; Kamudyariwa, X.B.; Adebayo, Y. 2025. From learning to action: exploring barriers and strategies for embedding lessons learned through a social learning lens. International Journal of Managing Projects in Business 18(2): 331-352.
PMI. 2017. A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 6. ed. Pennsylvania: Project Management Institute.
Rodrigues, W. M. 2018. A construção do conhecimento por meio de lições aprendidas em gestão de projetos. Orientador: Cristiano Heurich. 2018. 96 f. Dissertação (Mestrado Profissional em Administração – Gestão de Projetos) – Programa de Pós-Graduação em Administração, Universidade Nove de Julho, São Paulo, SP, Brasil.
Sampieri, R.H.; Collado, C.F.; Lucio, M.P.B. 2013. Metodologia de pesquisa. 5.ed. Porto Alegre: Penso
Schindler, M.; Eppler, M. J. 2003. Harvesting project knowledge: a review of project learning methods and success factors. International Journal of Project Management, v. 21, p. 219–228
Telha, C.; Carvalho, M. 2025. Integration of sales and operations: a dynamic mixed-integer programming game. Dynamic Games and Applications 15: 306-328.
Thiollent, 2019 [Full reference not found in the original document]
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq
To learn more about the course, click here and access the MBX Academy platform