Article

October 20, 2026

Proposal for an application model of WBS and LPS in industrial maintenance projects in mining

Proposal for an Application Model of WBS and LPS in Industrial Maintenance Projects in Mining

Valmir de Paulo Bernardes Junior; Paula Regina Fortes

DOI: 10.22167/2675-6528-202602389

Article derived from a Final Course Project (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute for textual synthesis and organization.

Summary

Industrial maintenance in mining, a sector of high economic and strategic relevance in Brazil, faces limitations in traditional planning models, such as low integration, reduced collaboration, inconsistency, and reactive management. Given this scenario, the objective was to propose a planning and management model for industrial maintenance projects in mining, integrating the Advanced Work Packaging (AWP) and Last Planner System (LPS) methodologies. The research was characterized as an applied case study, developed in a portfolio of industrial maintenance projects for a mining company in Araxá, Minas Gerais. The study included the diagnosis of the existing process, identification of weaknesses, methodological selection, solution modeling, and pilot application in three projects. Qualitative results indicated improvement in integration among stakeholders, greater clarity in scope definition, centralization of planning information, better alignment between engineering, procurement, and execution, as well as increased predictability and early handling of constraints. It was concluded that the integration between AWP and LPS constituted a promising alternative for increasing the maturity of planning and control for industrial maintenance projects, with potential for replication in similar contexts.

Keywords: Advanced Work Packaging; Project management; Last Planner System; Industrial maintenance; Mining.

1. Introduction

Brazilian mining holds considerable economic and strategic relevance, driven by job creation, tax collection, and the supply of essential raw materials for various productive sectors. It is a strategic area for the country’s economic development, with significant weight in the trade balance (IBRAM, 2023; Luz; Sampaio; França, 2010).

In this context, industrial maintenance plays a fundamental role in ensuring the reliability, availability, safety, and operational performance of assets. Industrial operations in mining require significant maintenance effort and time, especially due to high demands, market competitiveness, high asset utilization, and severe deterioration and load conditions, which increase the probability of failures and unplanned shutdowns (Kardec; Nascif, 2009; Darling, 2011). To ensure an effective process, industrial maintenance has evolved in recent years, adopting predictive and preventive practices, and assuming a more strategic role in companies (Silva, 2025).

Despite the growing importance and observed advances, many organizations still view maintenance as a “necessary evil”. To reverse this scenario and optimize asset availability, consistent maintenance planning is essential, going beyond employee experience and promoting integration between engineering, production, and planning areas (Silva, 2025; Reis et al., 2013). Industrial maintenance planning involves defining scope, allocating resources, and scheduling shutdowns, culminating in the development of plans and schedules (Kardec; Nascif, 2009; Almeida, 2015). However, the effectiveness of this planning depends directly on the adoption of structured methods and the quality of the information used (Mendes et al., 2013).

Studies indicate that traditional maintenance planning in industrial environments still presents significant limitations. Among the recurring weaknesses, the low integration between planning and execution, the absence of robust analytical methods, the dependence on reactive approaches, and the difficulty in anticipating restrictions stand out. These deficiencies result in unreliable plans, increased rework, unplanned interruptions, and reduced team productivity (Reis et al., 2013; Mendes et al., 2013). Conventional maintenance planning, therefore, is not fully capable of dealing with the complexity of modern industrial systems, requiring more structured and integrated approaches (Kardec; Nascif, 2009).

In this context, the need arises to explore and apply new methodologies that, although not having a strong presence in the maintenance area, have already shown proven results in other segments. Two of these approaches are Advanced Work Packaging (AWP) and the Last Planner System (LPS). AWP covers the entire project lifecycle, from engineering to construction, defining work packages with a delivery cadence to ensure compliance with deadlines and costs, as well as improvements in safety and quality (CII, 2026). Its central idea is to promote a cultural transformation for the collaborative development of projects, with the construction phase guiding the planning of the engineering and procurement stages.

The Last Planner System (LPS), in turn, stems from the Lean philosophy and seeks to create a predictable workflow. It involves field leadership in planning for the early identification of impediments, allowing them to be resolved before impacting execution (LCI, 2026). The LPS implements routines to organize the flow of information and increase execution efficiency, integrating field leadership with other project interface areas through collaborative sessions, aiming for a constraint-free production process. The literature addressing the integration of these methodologies is still scarce, opening space for the production of scientifically based material to explore the topic (Rebai et al., 2023).

Given the opportunities for improvement and the gap in the literature on the joint application of these methodologies in industrial maintenance, the integration between AWP and LPS presents itself as a promising hypothesis to enhance results. The justification for this study lies in the need to overcome the limitations of conventional planning and elevate the maturity of maintenance project management. Thus, the present work aimed to propose a planning and management model integrating AWP and LPS methodologies, for use in industrial maintenance projects in mining areas.

2. Material and Methods

The present study was characterized as a research of an applied nature, developed through a case study. Its objective was to propose a planning and management model for industrial maintenance projects, integrating the Advanced Work Packaging (AWP) and Last Planner System (LPS) methodologies, as outlined in the introduction.

The research was conducted in the industrial area of a mining company located in Araxá, Minas Gerais. This company operates in the production of niobium, a strategic metal. The empirical object of the investigation was a portfolio of 14 industrial maintenance projects, managed by the Industrial Maintenance and Revitalization Management (GMRI) of the contracted consultancy.

The maintenance projects analyzed involved recoveries and revitalizations in industrial plants, addressing operational safety risks, equipment failures, end-of-life, or process improvements. Activities included structural integrity (recovery of metallic and civil structures), mechanical (equipment replacement and piping assembly), and electrical and instrumentation (infrastructure revitalization and power connections).

The research strategy comprised an initial diagnosis of the existing process, the identification of weaknesses, the selection of adequate methodologies, the modeling of a solution, and the pilot application of this solution in real projects. This procedure aimed at a deep understanding of the scenario and the proposition of a structured approach.

The diagnosis of the project planning and management process began on January 5, 2026, and extended until February 5, 2026. During this period, data collection was carried out through meetings with the professionals responsible for the scope and for participation in the existing planning and monitoring rituals within the company.

For data collection, materials such as scope spreadsheets, schedules, timelines, action spreadsheets, and reports were used. The analysis of this data sought to map the traditional process and identify patterns of recurring restrictions and impediments, in addition to questioning the main problems faced during the process.

Between January 28 and February 20, 2026, the solution design was carried out, which was based on the consultancy’s expertise and the proposition of AWP and LPS methodologies. The choice of these approaches was based on their proven results in similar projects and their adherence to the weaknesses identified in the existing process.

After approval by the project portfolio management, the solution began to be implemented on February 23, 2026. The solution modeling redefined the phases of the planning and management process, incorporating the concepts and tools of the AWP and LPS methodologies, with a focus on integration and proactivity.

In the scope definition stage, AWP was employed to promote a collaborative process, involving all stakeholders, such as maintenance, operation, engineering, and suppliers. A RACI matrix was developed to define roles and responsibilities, and the scope was planned as a Work Breakdown Structure (WBS).

The master plan was developed based on the AWP, in collaborative sessions with stakeholders, recording assumptions, constraints, risks, and priorities. An integrated master schedule was created, centralizing information from the engineering, procurement, and execution phases, and serving as the main management tool.

The engineering and procurement stages followed the master schedule strategy, with weekly updates to identify deviations. Weekly project performance meetings were held with all stakeholders to present planning adherence, analyze deviations, evaluate the critical path, and address constraints.

Executive planning, aligned with the AWP, allowed the implementation of activities to begin as engineering and procurement packages were completed. The detailed schedules of the execution companies were developed based on the master schedule strategy.

For monitoring and control, the Last Planner System (LPS) was adopted to organize the information flow and increase execution efficiency through structured routines. The first routine implemented was the “Look Ahead” meeting, conducted by the consultancy.

The “Look Ahead” meetings were held on Wednesdays, with an analysis horizon of activities planned for the next six weeks, using a presentation for scope visualization and a spreadsheet for action plan control. The objective was the early identification of constraints.

Subsequently, the Weekly Scheduling meetings were initiated, conducted by the contractors on Thursdays, to schedule activities without restrictions. The daily “Check In” and “Check Out” meetings were implemented to align the day’s activities, identify short-term operational impediments, and verify compliance with the schedule.

Finally, “War Room” meetings were initiated on Tuesdays, conducted by the consultancy. In these meetings, project performance indicators, such as schedule adherence and contractor performance, were presented for tactical and strategic action-taking.

The solution’s application occurred in three pilot projects, selected for being at different development levels: one to be initiated, one in an intermediate engineering phase, and one already underway. This diversity allowed the application of the solution’s stages in distinct contexts.

3. Results and Discussion

The application of the planning and management model, which integrates the Advanced Work Packaging (AWP) and Last Planner System (LPS) methodologies, revealed significant qualitative gains in the industrial maintenance projects at the studied mining company. It is fundamental to recognize that the implementation of these approaches requires a cultural transformation, meaning that significant quantitative results are not achieved immediately. However, the benefits were perceived even in a short period, driven by the support and encouragement of project leadership, a crucial factor for the success of the implementation and acceptance of the new practices by those involved.

In the scope definition phase, the AWP methodology was employed to promote a collaborative process, involving all stakeholders, such as maintenance, operation, engineering, and suppliers. To structure this integration, a RACI matrix was developed, which organized the communication flow and highlighted the roles and responsibilities of each collaborator. This approach was essential to dissolve departmental “silos”, reduce scope inconsistencies, and increase the engagement of those involved, who felt an integral part of the project from the beginning, contributing to joint decisions.

The Project Breakdown Structure (WBS), developed in the proposed format, proved to be a valuable tool, as it synthesized the entire project strategy into a single document. This scope consolidation, validated with stakeholders, was an important differentiator in maintenance projects, where the emergence of extra activities or scope gap claims during execution is common. The WBS, by being collaboratively developed and approved by all, significantly reduced the chances of failures in this crucial phase, contributing to more satisfactory results aligned with expectations.

In the master and executive planning phases, the adoption of AWP brought notable gains by organizing the workflow in an integrated manner, from engineering development and procurement to execution. The methodology allowed each construction package to be linked to corresponding engineering and supply packages. This structure facilitated the prioritization of packages together with the client and operations area, eliminating the need to wait for the completion of all engineering or the delivery of all materials to start construction.

The integrated management of the construction, engineering, and supply triad, guided by the master schedule, allowed prioritizing what was most important and thus anticipating execution, aligning with the AWP principle of “execute with the end in mind.” This schedule centralized information from all stages in a single file, becoming the main project management tool. Another benefit was the ease of visualizing the critical path and quickly identifying the impacts of deviations in any phase, as all stages were interconnected.

The engineering and procurement schedules were structured as details of the master schedule, respecting the defined strategy and ensuring feedback of updates. Weekly project performance meetings, involving all stakeholders, were implemented to analyze planning adherence, identify deviations, evaluate the critical path, address constraints, and manage risks. These meetings were held until the end of the project, ensuring continuous reporting of the master schedule to stakeholders and promoting constant alignment.

In executive planning, the execution companies were instructed to develop their detailed schedules based on the master schedule strategy, standardizing the approach with AWP. This allowed activities to be initiated as engineering packages were released and materials delivered, without the need to wait for the complete conclusion of previous stages. This synchronization between the engineering, procurement, and execution phases contributed to a more efficient workflow and one less prone to delays.

For monitoring and control, the Last Planner System (LPS) was the chosen approach to organize the information flow and increase execution efficiency through structured routines. The transition from a reactive to a proactive scenario was quickly perceived, with constant alignment and information flowing in an organized manner. Problems began to be anticipated and resolved daily, providing a more consistent rhythm to the execution of activities and minimizing interruptions.

The “Look Ahead” meetings were implemented weekly, with a six-week analysis horizon, to identify constraints in advance and eliminate them before they could impact execution. In these sessions, a visual presentation of the planned scope and a spreadsheet for action plan control were used, facilitating evaluation and decision-making. The effectiveness of these meetings depended directly on the consistency of the executive planning, with detailed schedules that allowed for a more precise analysis of the constraints.

Subsequently, the Weekly Scheduling meetings were initiated, conducted by the contractors, focusing on unrestricted activities. These meetings, held on Thursdays, ensured timely resolution of pending issues or preparation for the following week. Daily, “Check In” and “Check Out” meetings were implemented by the contractors to align the day’s activities, identify short-term operational impediments, and verify compliance with the schedule, allowing for immediate action on deviations.

The “War Room” meetings, held on Tuesdays and led by the consultancy, presented project indicators based on the previous week’s data. Information such as planned vs. actual progress, physical progress S-curve, activities with deviations, root cause analysis, and Planned Percentage Complete (PPC) were discussed to support tactical and strategic actions. The PPC, monitored daily in “Check Out” meetings, was consolidated and presented, providing a clear performance metric.

The experience demonstrated that LPS routines function as a PDCA (Plan-Do-Check-Act) cycle. The “Look Ahead” and “Weekly Scheduling” meetings represent the “Plan” phase, the execution of activities corresponds to “Do”, the “Check In” and “Check Out” meetings are the “Check”, and the “War Room” acts as the “Act”. This cyclical structure allowed for continuous and adaptive management, with a focus on improvement and proactive problem-solving, increasing execution predictability and efficiency.

Among the best practices and lessons learned, it was highlighted that “Look Ahead” meetings are more effective with consistent and detailed executive planning. Daily “Check In” and “Check Out” meetings are more objective and efficient when held with all participants standing. It was also observed that the root cause analysis of deviations, when performed by contractors before the “Check Out” meeting, saves time and improves the quality of the evaluation, contributing to more agile and informed management.

Despite the tangible qualitative benefits, the research faced the limitation of scarce historical data from the existing process, which made quantitative measurement of results unfeasible. This difficulty is common in maintenance projects, characterized by high pressure and urgency. However, the proposed model, developed based on a considerable time of ideation and adaptation, represents a reliable basis for replication in other projects, offering a structured path for improving management.

In summary, the integration of AWP and LPS methodologies proved to be a promising alternative for improving the planning and management of industrial maintenance projects in mining. The qualitative results indicated a substantial improvement in stakeholder integration, greater clarity in scope definition, centralization of planning information, alignment between engineering, procurement, and execution, and more proactive constraint management. These findings confirm that the proposed model meets the study’s objective, enhancing the maturity of maintenance project planning and control, with the potential for replication in similar contexts.

4. Conclusion

The present study aimed to propose a planning and management model for industrial maintenance projects in mining, integrating the Advanced Work Packaging (AWP) and Last Planner System (LPS) methodologies. It was found that the application of the model resulted in significant qualitative gains, driving an improvement in integration among stakeholders, greater clarity in scope definition, and centralization of planning information. A more effective alignment was observed between the engineering, procurement, and execution areas, facilitating the prioritization of work packages and the anticipation of execution. The implementation of LPS routines, such as “Look Ahead” and “Weekly Scheduling” meetings, transformed management from reactive to proactive, allowing for the early identification and resolution of constraints, which provided greater predictability and efficiency to the execution of activities. The proposed model, therefore, constitutes a promising alternative for elevating the maturity of planning and control for industrial maintenance projects.

Despite the tangible qualitative benefits, the research faced the limitation of scarce historical data from the existing process, which made the measurement of quantitative results unfeasible. This difficulty is common in maintenance projects, often characterized by high pressure and urgency. However, the developed model represents a reliable basis for replication in other projects, offering a structured path for management improvement. It is suggested for future studies to apply this solution in contexts where historical data is available, enabling the measurement of results and the quantification of efficiency and productivity gains.

Bibliographic References

Almeida, Paulo Samuel. Manutenção mecânica industrial: conceitos básicos e tecnologia aplicada. São Paulo: Érica, 2015.

CII, Construction Industry Institute. Advanced Work Packaging (AWP) overview. [S.I.]: Construction Industry Institute, [s.d.]. Disponível em: https://www.construction-institute.org/awp-overview. Acesso em: 30 mar. 2026.

Darling, Peter (Ed.). SME mining engineering handbook. 3. ed. Englewood: Society for Mining, Metallurgy & Exploration, 2011.

IBRAM, Instituto Brasileiro de Mineração. Mineração em números 2023. Brasília, DF: IBRAM, 2023.

Kardec, Allan; Nascif, Júlio. Manutenção: função estratégica. 3. ed. Rio de Janeiro: Qualitymark, 2009.

LCI, Lean Construction Institute. Last Planner System. [S.I.]: Lean Construction Institute, [s.d.]. Disponível em: https://leanconstruction.org/lean-topics/last-planner-system/. Acesso em: 30 mar. 2026.

Luz; Sampaio; França, 2010 [Referência completa não encontrada no documento original]

Mendes, A. A. et al. Estabelecimento de um plano de manutenção baseado em análises quantitativas no contexto da manutenção centrada na confiabilidade. Produção, São Paulo, v. 23, n. 2, p. 1-13, 2013. Disponível em: https://www.scielo.br/j/prod/a/xNCjWWWVn3CQLx83dsbNXhv/. Acesso em: 30 mar. 2026.

Rebai, Slim; Albalkhy, Wassim; Hamdi, Olfa; Lafhaj, Zoubeir. Lean construction and AWP: similarities, differences, and opportunities. In: Annual Conference of the International Group for Lean Construction (IGLC), 31., 2023, Lille. Proceedings… Lille: IGLC, 2023. p. 1428-1439. Disponível em: https://iglc.net/Papers/Details/2184. Acesso em: 30 mar. 2026.

Reis, A. C. B. et al. Diagnóstico da gestão da manutenção em indústrias de manufatura de médio e grande porte. Produção, São Paulo, v. 23, n. 3, p. 1-13, 2013. Disponível em: https://www.scielo.br/j/prod/a/McBjtFWgVn7ywnvqSLmGpCN/. Acesso em: 30 mar. 2026.

Silva, Márcio José Reis da. A evolução dos métodos de manutenção: para além do reparo imediato. Revista Contemporânea, [S.I.], v. 5, n. 7, p. 1-11, 2025. Disponível em: https://ojs.revistacontemporanea.com/ojs/index.php/home/article/download/8602/5971. Acesso em: 30 mar. 2026.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving the independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated the automated reading of files, the organization of curves into current-potential matrices, the generation of the potential map, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed by device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of the results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and enhance the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used for the definition and identification of the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.