PMBOK in data-driven decision making: Case study in a multifamily venture.
André Lucas Silva do Nascimento; Adriano Machado da Silva
DOI: 10.22167/2675-6528-202600567
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The construction sector frequently faces challenges due to the lack of constant monitoring, resulting in decisions based on empiricism and late detection of deviations. The study analyzed the impacts of a systematic schedule management routine, based on the PMBOK Guide and the Last Planner System (LPS), on the quality of the decision-making process, seeking to offer a replicable model for evidence-based decision-making. A case study was conducted at a construction company in Fortaleza (CE) during the execution of a project with 66 housing units. The method involved data collection through interviews and documentary analysis, followed by the development of a baseline schedule, definition of a responsibility matrix (RACI), application of Earned Value Analysis (EVA), and establishment of a schedule management routine with stakeholders. The results showed that the integration of these methodologies allowed for the prioritization of planning and the early identification of operational and strategic constraints. The use of performance indicators (IDC and IDP) replaced intuition with objective metrics, providing physical-financial visibility and enabling corrective actions before losses were consolidated. It was concluded that the tools and instruments referenced in the PMBOK Guide, considered structured and low-cost to implement, are effective in mitigating risks and increasing predictability in the sector. The established routine democratized access to information among stakeholders, making management proactive and evidence-based, a determining factor for meeting established deadlines and costs.
Keywords: Earned Value Analysis; Control; Indicators; Last Planner System; planning.
1. Introduction
The construction industry is a fundamental pillar of the economy, but it frequently faces complex challenges that affect project efficiency and predictability. Speed and assertiveness in the decision-making process are crucial elements for the success of any undertaking, directly influencing deadline adherence, cost management, and the assurance of delivery quality. These three pillars are often referred to as the “Iron Triangle” in the context of project management. However, the absence of constant schedule monitoring is one of the main causes of failures in this sector (Formoso, 2001).
The late detection of schedule deviations leads to significant losses, compromising cash flow and established planning. This happens because managers often lack indicators and information that allow for the identification of deviations in their early stages. Consequently, anomalies are only perceived when the damage is already consolidated, preventing the development of effective corrective plans based on viable technical solutions (Ballard et al., 2008). This scenario forces decision-makers to operate based on empiricism and intuition, which often leads to the disregard of solutions with better cost-benefit in favor of emergency measures of low efficiency and high cost.
The project’s visibility across different horizons – long, medium, and short term – is essential for effective schedule management. This perspective allows for early risk analysis and the implementation of corrective actions to mitigate losses. In the long term, structured planning enables progress verification and milestone achievement, providing strategic and managerial support through cost and schedule performance indicators. In the short and medium term, continuous monitoring of activity execution, especially critical ones, is fundamental to prevent delays (Tommelein et al., 2008). The difficulty in making evidence-based decisions is, therefore, the central problem, resulting in reactive management that acts only after losses have occurred (Ballard, 1994).
To mitigate these challenges, project management methodologies are applied. The “PMBOK” Guide establishes fundamental guidelines for the management of scope, schedule, and stakeholders, integrating tools such as the Work Breakdown Structure (WBS) for scope definition and the RACI Matrix for responsibility assignment. Complementarily, the “Last Planner System” (LPS) emerges as a robust methodology for projects in environments of high complexity and uncertainty, such as civil construction (Mattos, 2010). The LPS grounds schedule effectiveness in linking constraints to the competent hierarchical levels for their resolution, segmenting planning into three horizons: long, medium, and short term. This approach ensures that the execution commitment is aligned with the actual availability of resources and the prior removal of constraints (Ballard and Howell, 2003).
The relevance of this work lies in the need to improve schedule management in the civil construction sector, which historically presents low productivity rates and high exposure to financial risks. It is therefore justified by the possibility of integrating the best practices of the “PMBOK” Guide and the agile methodology of the “Last Planner System”, promoting schedule monitoring and the provision of data and indicators that support the decision-making process through the integration of planning with execution. In view of this, this work is limited to the application of schedule management processes, as advocated by the “PMBOK” Guide, during the planning and execution phases of a residential development composed of 66 housing units, and aims to analyze the impacts of implementing a structured project management methodology on schedule performance control, offering a replicable model for evidence-based decision-making, replacing empiricism with structured metrics, and highlighting the contribution of methodologies to risk mitigation and compliance with established deadlines.
2. Material and Methods
The present study was characterized as a research of an applied nature, with a qualitative approach and descriptive character. A case study was conducted in a construction and development company in Fortaleza, Ceará, during the execution of a residential development composed of 66 single-family housing units. The participants were professionals directly involved in the project development, including the engineering director, the planning and control coordinator, and the engineer responsible for the construction execution.
Primary data collection was carried out through interviews, conducted in alignment meetings with professionals, to identify the schedule management process, difficulties, and bottlenecks. Complementarily, documentary collection was performed, which included the analysis of executive projects, budget, and opening terms. The company’s ERP system was consulted for actual cost data. For continuous monitoring, a routine of weekly measurements was implemented, with the filling of electronic spreadsheets by the field team, recording the progress of activities based on the Work Breakdown Structure (WBS) of the baseline schedule.
The data processing began with the elaboration of a physical-financial schedule, established as the project baseline, using MS Project software. The WBS (Work Breakdown Structure) was defined in three levels: Discipline, Activity, and Input, as recommended by the PMBOK Guide (2025), aiming to integrate schedule, cost, and scope. The sizing of work package durations was based on budgeted productivity coefficients, and the precedence types (Finish-to-Finish, Finish-to-Start, Start-to-Finish, Start-to-Start) were applied to establish the activity flow.
A schedule management routine was established, based on the guidelines of the PMBOK Guide and the Last Planner System (LPS) methodology. This routine was structured into long-term, medium-term, and short-term planning, according to the LPS hierarchy (Ballard and Howell, 2003). Long-term planning focused on objectives and milestones; medium-term planning mapped constraints and developed the responsibility matrix; and short-term planning detailed execution and sequencing goals.
After the schedule was developed, a kick-off meeting was held to formalize the project’s start, presenting the physical-financial schedule, labor histogram, and disbursement flow. Monitoring was operationalized through weekly planning meetings, aimed at analyzing deviations and mapping constraints (PMBOK, 2017). The Responsibility Matrix (RACI) was used to correlate stakeholders with work packages, linking responsible parties and defining deadlines for resolving pending issues (PMBOK, 2017).
Earned Value Analysis (EVA) was applied to assess the project’s performance in relation to schedule, scope, and cost (Marco and Narbaev, 2013). For this purpose, the Cost Performance Index (CPI) and the Schedule Performance Index (SPI) were calculated. The metrics used were Planned Value (PV), Earned Value (EV), and Actual Cost (AC), obtained from the company’s ERP system, representing, respectively, the scheduled budget cost, the realized budget value, and the actual incurred cost.
Finally, management reports were developed that consolidated the information, analyses, and indicators obtained from the schedule management routine. These reports, according to the PMBOK Guide (2025), aimed to promote visual management and make data accessible to all stakeholders, facilitating evidence-based decision-making. Weekly meetings were held to discuss the results, identify deviations and their root causes, and develop action plans for correction.
3. Results and Discussion
The case study revealed that the implementation of a systematic schedule management routine, based on the guidelines of the PMBOK Guide and the Last Planner System (LPS) methodology, significantly impacted the quality of the decision-making process in a multi-family development. Initially, data collection through interviews with the engineering director, the planning and control coordinator, and the engineer responsible for execution allowed for the identification of the project’s start and end dates, the completion milestones for each discipline, and the maximum resource availabilities. These conversations also revealed the main difficulties faced in previous projects, such as the scarcity of qualified labor and other factors that compromised the progress of the works, providing an essential overview for structuring the proposed solutions.
The documentary analysis, which included executive projects for structural, installation, and architectural disciplines, as well as the executive budget, was crucial for understanding the construction methodologies employed. The resources necessary for carrying out the activities and the productivity coefficients used in cost composition were verified. This stage allowed for an in-depth understanding of the project’s technical and financial premises, aligning the planning with the construction company’s real capabilities. Weekly execution measurements, taken through electronic spreadsheets filled out by the field team, provided data on the actual start and end of activities, progress percentage, completed work packages, and production lots, information that was subsequently used for Earned Value Analysis.
Data Processing
The development of the physical-financial schedule, defined as the project baseline, was a fundamental step. Using MS Project software, the planning was structured based on the premises of the Opening Term and the guidelines of the planning and control department. The Work Breakdown Structure (WBS) was developed to integrate information on deadlines, costs, and scope, breaking down the work into levels of Discipline, Activity, and Input. This approach, according to the PMBOK Guide (2025), facilitated cost appropriation and financial analysis, making management more practical and aligned with project objectives.
The sizing of work package durations was based on the productivity coefficients budgeted for the minimum team. This calculation, which involved dividing the quantity of service by productivity, allowed for the adjustment of the necessary resources to complete the activities within the stipulated deadline. The definition of precedences between work packages, using types such as Finish-to-Finish (FF), Finish-to-Start (FS), Start-to-Finish (SF), and Start-to-Start (SS), established a logical flow between activities. Resource allocation was then adjusted to align execution with the deadline dates, ensuring the viability of the schedule.
To complement the planning, a cascade-format activity schedule, with a visual bar representation, and the project’s S-Curve were developed. The S-Curve, which illustrates the project’s cumulative progress over time, and the Labor Histogram, which details human resource allocation by period, provided a comprehensive view of the physical-financial planning. These visual tools were essential for monitoring and communicating the project’s progress, allowing stakeholders to have a clear understanding of the distribution of efforts and resources over time.
Schedule Management Routine
The schedule management routine was established based on the guidelines of the PMBOK Guide (2025), aiming to provide analyses and indicators that would assist decision-making and increase adherence to the schedule and cost baseline. The identification of stakeholders, such as directors, managers, and the person responsible for execution, was fundamental to understanding their interests, conflicts, and operational bottlenecks. This proactive engagement of stakeholders, through the systematic collection and analysis of information, allowed the decision-making process to be oriented towards value delivery, considering all relevant project interests.
The Last Planner System (LPS) methodology was integrated to detail the base schedule, hierarchizing the planning into three horizons. Long-term planning, of a strategic nature, defined the start and end dates of each discipline, offering a macro view of the project timeline. Medium-term planning, of a tactical nature, focused on mapping constraints and developing the responsibility matrix, visualizing the activities to be executed and the resources and impediments to be resolved. Finally, short-term planning, at an operational level, detailed the monthly goals and production batches, aligning the execution commitment with the real availability of resources and the prior removal of constraints, as advocated by Ballard and Howell (2003).
The project’s kick-off meeting formalized the start of the venture, aligning stakeholder expectations. The premises of the schedule baseline, long-term and medium-term planning, and the detailing of short-term planning for the first month of work were presented. This meeting established the execution goals, the foreseen disbursements, and the initial mapping of restrictions, ensuring that all involved parties had access to the schedule baseline information and files, and to the meeting minutes, promoting a common understanding of the agreed-upon objectives and deadlines.
The execution progress was recorded weekly using a template spreadsheet, developed based on short-term planning. This tool allowed the field team to quickly and effectively update the status of activities, including actual starts and finishes, as well as the percentage of completion. This routine of continuous monitoring was essential for schedule tracking, enabling the analysis of deviations between planned and executed progress in weekly planning meetings. In these meetings, issues affecting the critical path were discussed, and constraints that could compromise future goals were mapped out, according to the PMBOK (2017) guidelines.
The RACI Responsibility Matrix, an analytical tool from the PMBOK Guide (2025), correlated stakeholders to work packages, linking a responsible party to each constraint. This matrix was updated during weekly planning meetings, where scheduled activities and pending issues were analyzed. Defining the responsible party and the deadline for resolving each constraint was crucial to avoid delays in starting the service fronts, contributing to the project’s visual control and effective management of responsibilities.
Earned Value Analysis (EVA)
Earned Value Analysis (EVA) was applied to evaluate the project’s performance in three dimensions: schedule, scope, and cost, as highlighted by Marco and Narbaev (2013). For this, Planned Value (PV), Earned Value (EV), and Actual Cost (AC) were used. PV represented the budgeted cost of scheduled work, obtained from the project baseline. EV corresponded to the budgeted cost of the work actually performed, measured by the execution team’s measurements. AC was the actual cost incurred for the work performed, obtained through queries to the company’s ERP system.
The cost performance index (CPI) and schedule performance index (SPI) were calculated based on these metrics. The CPI, obtained by the ratio between Earned Value and Actual Cost (EV/AC), indicated that if the CPI were equal to 1, the execution would be according to the budget. If the CPI were greater than 1, the execution would be consuming more than budgeted, and if it were less than 1, the project would be generating savings. The SPI, calculated by the ratio between Earned Value and Planned Value (EV/PV), indicated that if the SPI were equal to 1, the progress would be as planned. If it were greater than 1, the progress would be above plan, and if it were less than 1, the progress would be below plan.
The analysis of the project data revealed an accumulated Planned Value (PV) that progressed from 1.11% in March 2026 to 100% in September 2026. However, the accumulated Earned Value (EV) reached only 1.88% in April 2026, remaining at 0% in the subsequent months, which indicates a significant mismatch between planning and execution. The accumulated Actual Cost (AC), in turn, started at 5.76% in March 2026 and reached 9.47% in April 2026, also registering 0% in the following periods. These results highlighted low earned value execution in relation to cost and planning, pointing to challenges in schedule management.
The performance indicators calculated for the project, in a specific update period, showed a schedule performance index (SPI) of 0.15, indicating that the project’s progress was significantly below the baseline plan. The project status was classified as “LATE +15 days”. The cost performance index (CPI), in turn, was 3.04. According to the interpretation established in the study, a CPI greater than 1 meant that the project execution was consuming more than budgeted. This combination of indicators revealed a schedule delay and resource consumption above expectations for the value added, evidencing the need for urgent corrective actions.
Management Reports
The preparation of management reports consolidated all the information, analyses, and indicators obtained from the schedule management routine. These reports, which included dashboards with tables and progress and performance charts, were fundamental for the practice of visual management, making the data accessible and easy to understand for all stakeholders. The democratization and dissemination of this information reduced communication failures and optimized the integration between the supply, technical room, and execution departments, which act collaboratively in the development of civil construction projects.
The use of metrics and performance indicators, centralized in a single document, enabled quick and transparent access to information, allowing direct consultation by all stakeholders, regardless of the data source. Weekly meetings to discuss results allowed for the identification of deviations and their root causes, enabling the development of action plans for the timely correction of schedule and cost deviations. Continuous monitoring of indicators allowed for the adoption of corrective actions before losses were consolidated, increasing the predictability of the undertaking.
Data Interpretation – Qualitative Analysis
The qualitative data analysis, synthesized in a case study summary, correlated the management problems identified in the construction company with the proposals of the PMBOK Guide. Problems such as delays and breaks in activity sequencing were addressed by the critical path method and the precedence diagram, while rework and material waste were mitigated by the prioritization of planning and weekly earned value monitoring. Budget deviations and lack of materials on site were treated by Earned Value Analysis and the logistical supply schedule, respectively.
The lack of clarity in defining responsibilities and the lack of knowledge about the project status were addressed by the RACI Responsibility Matrix and by management reports, which promoted visual management and information transparency. Reactive actions and interference with the main risks, identified as bottlenecks, were combated by monitoring using performance indicators and by planning meetings. This integration of PMBOK tools and methodologies proved to be efficient in solving the identified problems, transforming reactive management into a proactive and evidence-based process, which is crucial for meeting deadlines and the project’s financial health.
In summary, the combined application of the PMBOK Guide and the Last Planner System in schedule management allowed for effective planning prioritization, from the strategic to the operational level. The early identification of constraints through the RACI Matrix and continuous monitoring with Earned Value Analysis, using the CPI and SPI indicators, replaced empirical decision-making with objective metrics. This approach provided physical-financial visibility, enabling timely corrective actions and increasing project predictability, which is fundamental for mitigating risks and ensuring the fulfillment of established deadlines and costs in the civil construction sector.
4. Conclusion
The present study sought to analyze the impacts of implementing a structured project management methodology on schedule performance control, with the aim of offering a replicable model for evidence-based decision-making. It was found that the integration of the guidelines from the PMBOK Guide and the Last Planner System (LPS) methodology allowed for effective prioritization of planning, from the strategic to the operational level. This approach enabled the early identification of operational and strategic constraints, a crucial aspect for proactive project management. It was observed that the use of cost performance indicators (CPI) and schedule performance indicators (SPI), derived from Earned Value Analysis (EVA), replaced intuition with objective metrics, providing physical-financial visibility of the project. Such visibility facilitated the adoption of timely corrective actions, mitigating the consolidation of losses and increasing project predictability.
The main contribution of this work lies in the demonstration of a management model that transforms the decision-making process, making it evidence-based and replicable in the civil construction sector. The tools and instruments referenced in the PMBOK Guide, characterized by their structure and low implementation cost, have proven effective in mitigating risks and ensuring compliance with established deadlines and costs. The established management routine has democratized access to information among stakeholders, optimizing communication and integration between sectors. It is concluded that proactive and data-driven management is a determining factor for the financial health and success of projects, overcoming reactive management based on empiricism.
Bibliographic References
Ballard, G., & Howell, G. A. (2003). An update on Last Planner. In Proceedings of 11th Annual Conference of the International Group for Lean Construction. Blacksburg. >http://www.academia.edu/811460/An update on last planner> Acessado em 12/04/2026.
De Marco A., Narbaev T. (2013). Earned Value-Based Performance Monitoring of Facility Construction Projects. In: JOURNAL OF FACILITIES MANAGEMENT, vol. 11 n. 1, pp. 69-80. ISSN 1472-5967. Disponível em: https://iris.polito.it/handle/11583/2502327. Acesso em 12/04/2026
Formoso, T. C. Planejamento e controle da produção em empresas de construção. Porto Alegre: Universidade Federal do Rio Grande do Sul, 2001.
HAMZEH, F.; BALLARD, G.; TOMMELEIN, I. D. Improving Construction Work Flow-The Connective Role of Lookahead Planning. In: ANNUAL CONFERENCE OF THE INTERNATIONAL GROUP FOR LEAN CONSTRUCTION (IGLC), 16. Anais. Manchester, 2008. Disponível em: <https://iglc.net/Papers/Details/572>
MATTOS, A. D. Planejamento e Controle de Obras. 1. ed. São Paulo: Pini, 2010. 420 р. ISBN 9878-8S-7266-223-9.
Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide – 7th Edition). PMI, 2017.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq