Procurement management plan for contracting in a Research and Development project

Marcela Dantas Simão Ugêda Barros; Bruno de Lima Santoro

DOI: 10.22167/2675-6528-202601158

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The complexity of service contracting in research and development projects in the public sector highlighted the need for instruments capable of organizing technical, procedural, and managerial decisions with greater consistency. The study aimed to develop an acquisition management plan for service contracting in a research and development project at a public institution in the state of São Paulo, based on the best practices of the PMBOK, 6th edition. The research was characterized as applied, with a qualitative approach and a single case study design, and was developed through documentary analysis and participant observation. Based on the analysis of the investigated context, the main artifacts of the plan were elaborated, including the list of acquisitions, the make-or-buy analysis, the RACI matrix, the Terms of Reference, the technical evaluation criteria for proposals, and the contractual execution control mechanisms. The results indicated that the proposal structured the project’s acquisition cycle, supported the definition of the supply strategy, clarified roles and responsibilities among the actors involved, favored greater objectivity in the technical evaluation of proposals, and provided an organized basis for monitoring contractual execution. It was concluded that the developed plan proved to be aligned with the analyzed context and potentially useful for supporting greater predictability, traceability, decision-making clarity, and effectiveness in the management of contracting in research and development projects in the public sector.

Keywords: Contractual governance; PMBOK; Traceability; Supplier selection; Public sector.

1. Introduction

In contemporary management, projects represent essential tools for transforming strategies into concrete results. According to the Project Management Institute (PMI, 2013), a project is defined as a temporary endeavor undertaken to create a unique product, service, or result. This temporary nature implies a well-defined beginning and end, being closed when its objectives are achieved, become unviable, unnecessary, or by decision of the sponsor. However, temporality does not refer to brevity, but rather to the project’s engagement, whose result can be long-lasting and generate significant social, economic, and environmental impacts.

In this context, Research and Development (R&D) projects constitute organized initiatives to promote technological innovations, often oriented towards market challenges. They play a decisive role in the development of academic institutions, both public and private, and organizations in various segments. According to the Oslo Manual (OECD, 2018) and the Frascati Manual (OECD, 2015), R&D refers to creative and systematic work carried out to expand the stock of knowledge and conceive new applications for existing knowledge. To be classified as R&D, activities must simultaneously meet five criteria: novelty, creativity, orientation towards an uncertain outcome, systematic nature, and transferability or reproducibility (OECD, 2015).

Although strategic, R&D projects can present administrative weaknesses that compromise performance, scope adherence, deadlines, costs, and quality. For this reason, the application of good project management practices is fundamental to align objectives, mitigate risks, and ensure consistent organizational results (Dendena et al., 2013; Gomes and Raimundo, 2023).

In the international scenario, the Project Management Institute (PMI) brings together project management professionals and systematizes a body of knowledge recognized as good practices. Its main reference is the “Project Management Body of Knowledge” (PMBOK), in its 6th edition, published in 2017. This international standard serves as a basis for professional development programs and certifications (Rosset et al., 2020). Among the knowledge areas defined by PMBOK 6th edition, Project Procurement Management stands out, which covers the processes of planning, conducting, and controlling the acquisition of products, services, or results needed for projects, from external suppliers (PMI, 2017).

The importance of procurement management is reinforced by the growth of service outsourcing, a practice increasingly adopted by organizations that resort to specialized companies to meet specific technical and operational demands (Angeli et al., 2022). In planning, purchase decisions, approach, and potential suppliers are documented. In execution, proposals are obtained and suppliers are selected according to predefined criteria. In monitoring and controlling, relationships and contractual performance are managed, formalizing changes. In closing, the acceptability of deliverables and the settlement of obligations are verified (Angeli et al., 2022). The project manager, according to the PMBOK 6th edition, is responsible for defining the procurement management strategy, evaluation criteria, risk allocation, and benefit-sharing mechanisms (PMI, 2017).

In the public sector, procurement planning constitutes the internal phase of the bidding process, in which the need to bid, the appropriate modality, and the estimated deadline are evaluated (Morais, 2009). The application of procurement processes in this context must be guided by high standards of transparency, strict regulatory compliance, and adherence to technical criteria. This reduces the margin of managerial freedom compared to the private sector, but expands the mechanisms for transparency and control (Morais, 2009; Gomes and Raimundo, 2023).

Despite the relevance of procurement management for the performance of R&D projects in the public sector, applied studies that propose structured instruments adapted to the institutional and regulatory specificities of this context are still scarce. There is a gap in the focus on the integrated organization of planning, conducting, and controlling contracting. The complexity of contracting in R&D projects in the public sector, especially regarding the need to reconcile regulatory compliance, technical specification, deadlines, and contractual monitoring, highlights the need for a structured instrument that organizes these decisions.

Given this scenario, this study is justified by the need to improve procurement management in R&D projects in the public sector, seeking greater predictability, traceability, decision-making clarity, and effectiveness. Thus, this study aimed to develop a procurement management plan for contracting services in a research and development project of a public institution in the state of São Paulo, based on the best practices of PMBOK 6th edition.

2. Material and Methods

This study was characterized as a research of an applied nature, with a qualitative approach and a single case study design. The central purpose was to develop a procurement management plan for service contracting in a research and development project, conducted by a public institution located in the state of São Paulo. The choice of the case study allowed for the analysis of the phenomenon in its real context, considering the institutional specificities and operational challenges that influence public sector procurement management.

The unit of analysis corresponded to the procurement management process linked to the selected research and development project, focusing on the stages of planning, conducting, and controlling service contracting. The institutional environment investigated involved decision-making instances, contractual management sectors, legal support, information technology (IT), and the project management office (PMO), among other areas related to the processing and execution of procurement.

Data collection was predominantly carried out through documentary analysis, complemented by participant observation. For the documentary analysis, institutional documents produced between December 2024 and June 2025, related to the planning and execution of the project’s procurements, were examined.

The analyzed documents included the project work plan, records of previous hirings, drafts, opinions, formal communications, minutes, monitoring reports, and acceptance records. The selection of these materials was guided by criteria of relevance and adherence to the object of study, seeking to highlight stages, decisions, responsibilities, and control mechanisms related to the project’s procurements.

Participant observation complemented the documentary analysis, allowing the institutional flow of contract processing to be followed. This stage was carried out through the author’s professional involvement in the analyzed context, which enabled a deeper understanding of the routines, interactions between areas, and stages of contract processing for the project.

The analysis of the data was guided by the three procurement management processes foreseen in the PMBOK 6th edition (PMI, 2017): Plan Procurement Management, Conduct Procurements, and Control Procurements. These processes were used as analytical categories to organize the interpretation of the documentary material and the observations made, serving as the basis for the elaboration of the proposed plan.

In the process of Planning Procurement Management, the Project Work Plan was adopted as a central reference to identify the items that would require procurement. Proposal evaluation criteria were established, and a Terms of Reference model was developed, based on records of previous contracts and alignments with the involved areas.

To Conduct Procurements, procedures were described for the disclosure of the bidding instrument, receipt and analysis of proposals, including technical and commercial evaluation. Tools such as request documents, compliance checklists, and technical-commercial evaluation matrices were considered to support supplier selection.

The Control Procurements process focused on the administration of contractual relationships and supplier performance monitoring. Mechanisms were defined for deliverable verification, deadline control, non-conformance recording, and acceptance formalization, based on the Work Breakdown Structure (WBS) and the Project Organizational Structure (POS).

Regarding ethical considerations, the research exclusively used documentary analysis and participant observation of institutional flows. No data were collected through interviews, questionnaires, or any personally identifiable data, which resulted in the waiver of submission to the Research Ethics Committee (CEP/CONEP).

3. Results and Discussion

The results of this research were presented in accordance with the previously established methodological sequence, addressing the three processes of procurement management according to PMBOK 6th edition: planning, conducting, and finally, controlling procurements. The analysis of the context of a research and development project in a public institution in the state of São Paulo revealed the complexity inherent in service contracting, justifying the need for a structured plan to optimize management and ensure adherence to best practices.

Initially, the application of the Plan Procurement Management process enabled a detailed structuring of the project’s contracting needs. This stage was based on the planned deliverables, the established deadlines, and the constraints defined in the Project Work Plan. As a result, essential artifacts were consolidated to support the execution of procurements, notably the Project Procurement List, the technical specifications, and the proposal evaluation criteria, elements that underpinned subsequent decisions.

The Project Acquisition List, one of the main deliverables of this phase, was developed to directly link the planned deliverables to the respective contracting objects. This instrument detailed information such as the type of acquisition, its criticality, the planned modality, and the demanding area. For example, acquisitions such as the licensing of the Microsoft Office corporate suite and the development of a digital tele-service platform were classified as highly critical, while the licensing of statistical software for research and the leasing of assets for technological support infrastructure were considered of medium or high criticality. The acquisition of consumable materials for administrative support was classified as low criticality, and the training in MS Project Web App, as medium criticality. This systematization reinforced the traceability between the technical scope and the contracting planning, contributing to the reduction of documentary rework and the mitigation of misalignment risks.

The Criticality column in the Project Procurement List played a fundamental role, allowing items to be distinguished according to their potential impact on the initiative’s objectives. This differentiation functions as a prioritization tool, as high-criticality procurements, such as those for institutional software and digital platforms, intensely affect dimensions like deadline, cost, scope, quality, and risks, requiring greater attention in planning and monitoring. This approach, aligned with Law No. 14.133/2021 (Brazil, 2021) and the governance frameworks of the Federal Court of Accounts (Brazil, 2020; Brazil, 2021), reinforced the rationality of procurement planning by supporting the definition of priorities and the adoption of proportional risk management measures.

Next, the Make-or-Buy Analysis was employed to support the definition of the supply strategy for deliveries linked to the identified procurements. This tool allowed for the evaluation, for each item, of the alternative most aligned with the project’s needs, considering aspects such as criticality, technical complexity, availability of internal competencies, implementation timeline, and the need for specialized support. The analysis revealed a predominance of the “buy” decision (external contracting) for several items, such as institutional software licensing, the development of the digital tele-service platform, the acquisition of statistical software, and the leasing of assets for supporting technological infrastructure.

The decision for “buy” did not only indicate the absence of internal capacity, but reflected an institutional strategy of contracting oriented by the nature of the project, by the technical specialization required, and by the need for greater predictability in execution. For example, for the institutional software infrastructure, standardization and support reinforced the option to purchase licenses. For the digital platform, technical complexity and the need for sustained implementation justified contracting specialized services. The “make-or-buy” analysis showed a deliberate orientation towards a combination of internal coordination and external execution, considered more adequate to the characteristics, deadlines, and degree of complexity of the acquisitions foreseen in the project (PMI, 2017; Brasil, 2021).

To support the hiring strategy and ensure greater consistency in procurement governance, the RACI Matrix was developed. This artifact was structured from the main activities of the hiring and contractual management flow, formalizing the distribution of roles and responsibilities among the institutional actors involved. The matrix specified who executes, who is accountable, who must be consulted, and who needs to be informed in each activity, such as the planning of procurement management, standardized technical specification, and the market request instrument.

In the studied context, the RACI Matrix proved to be relevant for supporting the organization of assignments and reducing ambiguities in the interaction between institutional actors. It was observed that execution functions were concentrated in the Contract Manager, the Contracts Area, the Evaluation Committee, and the PMO, while the approval and final accountability assignments were associated with the Directorate and the Contract Manager. This arrangement highlighted the separation between operational and decision-making instances, favoring greater clarity in conducting the process and contributing to the articulation between planning, procedural instruction, technical evaluation, contractual formalization, execution monitoring, and contract closing (Brower et al., 2020).

Based on the artifacts produced in the previous stages, a standardized Terms of Reference (TR) model was developed to support the technical instruction of more complex and critical procurements. The TR served an integrating function between procurement planning and future contractual execution, converting previously established definitions into structured, comparable, and verifiable technical parameters. Its adoption contributed to more precisely defining the object of the procurement, reducing information asymmetries between the contracting party and proponents, and providing greater technical consistency to the preparatory documents.

The incorporation of technical evaluation criteria, minimum qualification requirements, and documentary control mechanisms in the TR favored process standardization, expanded its traceability, and reinforced procurement governance. However, its effectiveness depends on the maturity of prior planning, the precision of specifications, and the institutional capacity to translate internal needs into technically verifiable requirements. Even in procurements with greater innovation or technical uncertainty, the TR proved relevant for creating more favorable conditions for objective proposal analysis, mitigating misalignment risks, and increasing predictability in conducting subsequent procurements.

In summary, the Plan Procurement Management step transcended the mere identification of demands, structuring technical and managerial elements to guide the project’s procurement cycle. The consolidation of priority procurements, the “make-or-buy” analysis, the definition of responsibilities, and the development of the TR strengthened the governance of the process and reduced uncertainties in the preparatory phase. These actions created favorable conditions for advancing to the Conduct Procurements process, focused on market interaction, receiving and analyzing proposals, and defining the suppliers to be contracted.

Conducting Procurement

The Conduct of Acquisitions stage corresponded to the operationalization of the definitions produced in the planning, converting the previously elaborated artifacts into procedures for interaction with the market and supplier selection. The use of the Terms of Reference model proved adequate for structuring the conduct of contracting through a sequential flow of internal validation, administrative processing, legal analysis, publicity, receipt of proposals, negotiation, and technical analysis, in line with the governance and formalization requirements of the contractual process.

The flow of the R&D project’s procurement process showed a sequence of activities and the participation of different institutional areas. After the elaboration of the Terms of Reference, the document went through successive validation and forwarding stages between the requesting area, the contracts area, the institutional projects sector, and the purchasing sector, until its submission to the legal department for compliance analysis and opinion issuance. Once this opinion was concluded, the documentation returned to the administrative flow for publication through formal channels, such as the institutional website and a widely circulated newspaper.

This procedure increased the transparency of the process and favored the participation of potential proponents, by conferring publicity and predictability to the contracting. From the publication, a period of approximately seven business days was established for the receipt of proposals and the required documentation from interested suppliers. This understanding converges with the literature, which points to the influence of the quality of the documentation, clarity of the requirements, and predictability of the stages on supplier participation and the perception of integrity of the procedure in competitive public sector processes (Kelly et al., 2021).

The conduct of procurements was not restricted to the simple opening of the process to the market, but depended on an articulated sequence of validations, referrals, and controls between administrative, technical, and legal instances, reconciling publicity, compliance, and technical adherence. The formalization of this flow contributed to making the procedural sequence of contracting more explicit and to organizing the points of validation, referral, and control among the involved instances. This arrangement showed potential to favor greater procedural predictability, clarity regarding responsibilities, and better traceability of the process, although its effectiveness depends on the coordination capacity between the involved sectors and adherence to internal deadlines.

Once the deadline for proposal submission and the negotiation round were closed, the technical analysis phase began. The proposal with the lowest value, provided it complied with the required documentation and was technically aligned with the objective, was submitted to the Evaluation Committee. For this purpose, an evaluation body was foreseen, composed, at a minimum, by the requesting department and the contracts department, with the participation of the PMO, when applicable, and a related technical department, introducing a multidisciplinary analysis in the appraisal of proposals and bringing the technical evaluation closer to the requirements of institutional governance and compliance.

Once the evaluating instance was defined, objective parameters were established for the technical judgment of the proposals, through a standardized evaluation system, structured based on five criteria and scores from one to five. The adopted criteria were: adherence to the object, execution methodology, adequacy of the proposed deliverables, technical qualification of the team, and prior experience of the proponent. Each criterion was scored from one (does not meet or insufficiently meets) to five (fully meets and exceeds expectations). The final grade was obtained by summing the scores, up to a maximum of 25 points, with subsequent proportional conversion to a scale of zero to 100, favoring greater comparability between proposals.

This systematic technical evaluation offered objective parameters for appraising the proposals, encompassing relevant dimensions and reducing the weight of strictly intuitive assessments. However, the existence of previously defined criteria does not completely eliminate the presence of evaluative judgment, especially in qualitative aspects, which is why its application depends on the clarity of the parameters, the preparedness of the evaluators, and the consistent recording of justifications attributed to the scores. In the studied context, its adoption proved pertinent for supporting a more transparent evaluation aligned with institutional governance and compliance requirements.

In procurements of greater technical complexity, it was foreseen that the documentary analysis of the proposals could be complemented by the execution of a Proof of Concept (PoC), understood as a preliminary stage of practical validation of the proposed solution. Although this provision was formulated as a general methodological guideline for more complex objects, its application proved especially relevant in the contracting of the Digital Tele-service Platform, given the criticality of the service and the need to verify, in a controlled environment, the adherence of the solution to the technical requirements of the project (Souza and Pedron, 2024).

The forecast of carrying out a PoC added robustness to the evaluation process, creating the possibility of verifying the practical adherence of the solution before full contractual execution. This result proved particularly relevant for objects with a higher degree of innovation or strong dependence on functional performance, where documentary analysis alone may be insufficient to reduce uncertainties. As a limitation, the PoC may demand additional time, technical team mobilization, and prior definition of clear evaluation criteria, which is not always simple in environments with operational constraints. In the analyzed case, its relevance was greater in critical technological procurements, where early risk mitigation tends to compensate for the additional effort required by this stage.

After the evaluation stage was completed and the contract was formally signed, the “kick-off” meeting was held, understood as the initial alignment meeting between the parties involved in the contract execution. This meeting corresponds to the first formal meeting between the participants, with the purpose of aligning objectives, roles, responsibilities, and expectations regarding execution. Although the PMBOK 6th edition does not treat the contractual “kick-off” meeting as a specific artifact of Procurement Management, its realization proved consistent with the PMI (2017) framework, which recognizes the “kickoff meeting” as an initial alignment mechanism among those involved.

In the scope of public procurement, the Ministry of Planning, Budget and Management (MPOG, 2011) indicated that the initial meeting after contract formalization constitutes an important management mechanism, favoring the alignment of the contracted object, the execution model, the parties’ attributions, and the challenges inherent to implementation (Melo and Pereira, 2012). From this perspective, the institutionalization of this moment contributed to the reduction of interpretive ambiguities, the prevention of operational misalignments, and the strengthening of contractual governance, by creating more favorable conditions for the follow-up and monitoring of execution.

Thus, the process of Conducting Procurements was not limited to supplier selection, but consolidated the technical, procedural, and relational foundations necessary for contractual execution. The structuring of the flow, the definition of objective evaluation criteria, the possibility of supplementing with proof of concept, and the formalization of the initial alignment between the parties reinforced the contracting governance and increased the predictability of subsequent stages. The conclusion of this phase led to the process of Controlling Procurements, focused on monitoring execution, verifying deliverables, and addressing any deviations throughout the contract term.

Control Acquisitions

The Controlling Procurements stage was described, in the analyzed case, through mechanisms focused on monitoring contractual execution based on the parameters defined in the previous stages. In alignment with the PMBOK 6th edition (PMI, 2017), this stage focused on managing the contractual relationship, monitoring supplier performance, and formally handling adjustments, corrections, and potential contractual changes. The adopted mechanisms included verification of deliverables, deadline control, compliance analysis, recording of non-conformities, and formal acceptance, composing a structure for monitoring and validating execution.

In the context studied, this systematization proved relevant to support process traceability, the articulation between technical monitoring and administrative processing, and the linking of deliverables to the work packages defined in the Project Work Breakdown Structure (WBS) and to the responsibilities defined in the Project Organizational Structure (POS). The control of procurements was operationalized from the initial alignment promoted in the “kick-off” meeting, at which time the contracted scope, expected deliverables, execution deadlines, acceptance criteria, and communication flows between the parties were reaffirmed. The institutionalization of this initial milestone proved relevant by establishing a common basis of understanding between the client and the supplier, reducing interpretive ambiguities and creating more favorable conditions for systematic monitoring of execution.

The management of contractual relationships occurred continuously, with the participation of the PMO and the areas responsible for oversight, through periodic interactions with the supplier, focused on monitoring the progress of activities, verifying intermediate milestones, and timely addressing any deviations. This monitoring favored greater visibility of the evolution of deliverables and enabled preventive action in the face of risks of delays, execution inconsistencies, or misalignments with the agreed-upon scope. The oversight of contractual execution in public institutions can present operational weaknesses and a lack of specific competencies (Marinho and Andrade, 2018), which reinforces the need for systematic monitoring mechanisms capable of reducing deviations, improving communication among those involved, and expanding the administration’s response capacity during contract execution.

From this perspective, the control of procurements ceased to be merely reactive and began to operate as a mechanism for coordinating contract execution. Another relevant result of this stage was the incorporation of formal change management procedures, applicable whenever needs for adjustment in scope, deadlines, execution conditions, or other contractual elements arose. The existence of defined flows for recording, analyzing, and formalizing these changes contributed to preserving the documentary integrity of the process and reducing the risk of informal alterations or decisions without adequate traceability (Limberger et al., 2014).

At the end of each delivery, the object presented by the supplier was validated based on previously established technical criteria, followed by the respective formal acceptance and the registration of measurement or attestation for administrative and financial processing. This procedure allowed for an objective link between contractual execution and the deliverables effectively received and accepted, reinforcing the consistency between technical monitoring and administrative processing. As a consequence, procedural security in the contractual cycle was enhanced, as the release of payments began to be supported by documentary evidence of compliance with the agreed-upon obligations (Guarido et al., 2021).

In order to synthesize the main mechanisms adopted in the monitoring of contract execution, several control instruments used throughout the contract’s validity period were systematized. The kick-off meeting, for example, aimed to align scope, deliverables, and deadlines, with minutes recorded and a validated schedule, being the responsibility of the Contract Manager and PMO at the beginning of the execution. Periodic monitoring of deliveries aimed to track the progress of activities and supplier performance, with formal reports and communications, under the responsibility of the PMO throughout the entire contract term.

The record of occurrences and non-conformities sought to identify execution deviations, delays, or inconsistencies, with notifications and reports, being the responsibility of the Contract Manager whenever a deviation was identified. Formal change management, in turn, aimed to evaluate and formalize changes in scope, deadlines, or execution conditions, with change requests and opinions, under the responsibility of the Contract Manager and Contracts Department, when contractual alteration was necessary. The technical validation of deliverables, carried out by the requesting department and the technical Committee at the end of each delivery, verified the adherence of the object to the established requirements and criteria.

The formal acceptance and measurement/attestation confirmed the adequate receipt of the delivery and authorized administrative processing, with registration in an acceptance term and forwarding dispatch, being the responsibility of the Contract Manager and the requesting area after technical validation. Finally, administrative and financial processing ensured documentary support for payment processing, with an administrative process, invoice, and attestation documents, under the responsibility of the Contracts and Finance Area after formal acceptance. This organization favored the understanding of procurement control as a continuous process of monitoring, validation, and formalization of contractual execution.

The articulated use of these mechanisms proved compatible with the pursuit of greater alignment between planning, contracting, and execution, although their effectiveness depends on the regularity of records, coordinated action among the involved areas, and the institutional capacity to address deviations and changes in a timely manner. In public sector R&D projects, where the contracting of specialized services can involve a high degree of technical uncertainty and dependence on multiple institutional actors, the existence of structured control mechanisms has proven essential to mitigate risks of misalignment and sustain the effectiveness of deliverables throughout the contract term (Rodrigues and Reis, 2023). Thus, the process of Controlling Procurements went beyond the mere formal verification of contractual compliance, by consolidating practices of monitoring, validation, and formalization capable of reinforcing the alignment between planning, contracting, and execution.

In summary, the developed procurement management plan integrated technical, managerial, and procedural dimensions into a cohesive framework, offering a usable benchmark for organizing service contracting in R&D projects in the public sector. The findings demonstrated that consolidating planning instruments, such as the Procurement List and the make-or-buy analysis, favored the link between technical scope and supply strategy. In execution, the formalization of technical criteria and validation flows increased objectivity in supplier selection. In control, the definition of monitoring and change management mechanisms proved essential to sustain adherence between the planned, contracted, and executed, contributing to greater predictability, traceability, decision-making clarity, and consistency in contractual execution.

4. Conclusion

The study sought to develop an acquisition management plan for service contracting in a research and development project of a public institution in the state of São Paulo, based on the best practices of PMBOK 6th edition. It was verified that the structuring of planning, through the Acquisition List and the make-or-buy analysis, favored the link between the technical scope and the supply strategy, in addition to clarifying roles and responsibilities with the RACI Matrix. In the conduct of acquisitions, the formalization of objective technical criteria and validation flows, including the standardized Terms of Reference, increased objectivity in supplier selection and process traceability. In control, it was identified that the definition of monitoring, delivery validation, and change management mechanisms was essential to sustain the adherence between the planned, the contracted, and the executed. The proposed plan integrates technical, managerial, and procedural dimensions into a cohesive structure, offering an applicable framework for organizing service contracting in R&D projects in the public sector. Its main contribution lies in its ability to support greater predictability, traceability, decision-making clarity, and consistency in contractual execution.

However, the applicability of the plan is conditioned by the characteristics of the institutional context analyzed, especially regarding internal flows, governance arrangements, organizational maturity, and the regulatory requirements applicable to contracting. The effectiveness of instruments such as the Terms of Reference and the Proof of Concept, for example, depends on the maturity of previous planning, the accuracy of specifications, and the institutional capacity to translate needs into verifiable requirements, which may demand additional time and team mobilization. Coordination between the involved areas and the regularity of records are also critical factors for the full effectiveness of control mechanisms. It is suggested that future studies explore the adaptation and validation of this plan in other public sector environments with similar challenges, investigating the institutional specificities and the necessary adjustments for its successful implementation, in order to consolidate its contribution as a structuring reference.

Bibliographic References

Angeli, V.A.; Tonomaru, J.; Santos, P.S.B. 2022. Gerenciamento de aquisições de um Projeto de uma Planta Industrial para tratamento de óleos e gorduras. Research Society and Development 11(2): 1-23.

Brasil. 2021. Lei nº 14.133, de 1º de abril de 2021. Lei de Licitações e Contratos Administrativos. Disponível em: https://www.planalto.gov.br/ccivil_03/_ato2019-2022/2021/lei/l14133.htm. Acesso em: 28 mar. 2026.

Brasil. Ministério do Planejamento, Orçamento e Gestão [MPOG]. 2011. Metodologia de Gerenciamento de Projetos do SISP. Disponível em: https://www.gov.br/governodigital/pt-br/estrategias-e-governanca-digital/sisp/documentos/arquivos/mgp-sisp_versao_1-0.pdf. Acesso em: 28 mar. 2026.

Brasil. Tribunal de Contas da União [TCU]. 2020. Referencial Básico de Governança Organizacional para Organizações Públicas e Outros Entes Jurisdicionados ao TCU. 3ed. Disponível em: https://cdn.cade.gov.br/Portal/centrais-de-conteudo/publicacoes/referencial-basico-de-governanca-organizacional.pdf. Acesso em: 28 mar. 2026.

Brower, H.H.; Nicklas, B.J.; Nader, M.A.; Trost, L.M.; Miller, D.P. 2020. Creating effective academic research teams: two tools borrowed from business practice. Journal of Clinical and Translational Science 5(1): 1-5.

Dendena, A.C.M.; Ferreira, M.A.T.; Guimaraes, L.O., Castro, J.M.; Versiani, A.F. 2013. Processo de gestão de projetos de P&D: Um estudo de caso na CEMIG. Revista Economia & Gestão 13(31): 138-161.

Gomes, S.G.N.; Raimundo, S.S.C. 2023. Gerenciamento de projetos aplicado ao produto de inovação. Technology Science 5(1): 8-18.

Guarido, F.A.A.; Nogueira, E.E.S.; Saraiva, M.C.C.M. 2021. Resiliência nos valores públicos e sua permanência: uma análise dos contratos administrativos no Brasil. Cadernos EBAPE.BR 19(1): 745-760.

Kelly, S.; Marshall, D.; Walker, H.; Israilidis, J. 2021. Supplier satisfaction with public sector competitive tendering processes. Journal of Public Procurement 21(2): 183-205.

Limberger, T.; Teixeira, A.V.; Abreu, M.B.G. 2014. Contratos administrativos e gestão pública – proposições a partir de estudos de casos na Administração Pública federal indireta. A&C – Revista de Direito Administrativo & Constitucional 14(58): 155-176.

Marinho, R.C.P.; Andrade, E.P. 2018. Fiscalização de contratos de serviços terceirizados: desafios para a universidade pública. Gestão & Produção 25(3): 444-457.

Melo, Y. C.; Pereira, M. C. 2012. Plataforma de aprendizagem para gestão de projetos: dois casos de implementação de projetos de automação para a indústria automobilística. Gestão & Produção 19(3): 457-470.

Morais, J. J. 2009. Princípio da eficiência na Administração Pública. ETHOS JUS: revista acadêmica de ciências jurídicas 3(1): 99-105.

Organisation for Economic Co-operation and Development [OECD]. 2015. Frascati Manual: Guidelines for Collecting and Reporting Data on Research and Experimental Development. Disponível em: <https://www.oecd.org/content/dam/oecd/en/publications/reports/2015/10/frascati-manual-2015_g1g57dcb/9789264239012-en.pdf>. Acesso em: 6 out. 2025.

Organisation for Economic Co-operation and Development [OECD]. 2018. Oslo Manual 2018: Guidelines for Collecting, Reporting and Using Data on Innovation, 4th Edition. Disponível em: <https://www.oecd.org/en/publications/oslo-manual-2018_9789264304604-en.html>. Acesso em: 6 out. 2025.

Project Management Institute [PMI]. 2013. A Guide to the Project Management Body of Knowledge (PMBOK Guide). 5ª ed. Pennsylvania: Project Management Institute.

Project Management Institute [PMI]. 2017. A Guide to the Project Management Body of Knowledge (PMBOK Guide). 6ª ed. Pennsylvania: Project Management Institute.

Rodrigues, B.C.; Reis, P.R.C. 2023. Partes interessadas internas e desempenho em contratações públicas na perspectiva das teorias dos stakeholders e dos custos de transação. Cadernos Gestão Pública e Cidadania 28(1): 1-23.

Rosset, A.C.S.; Macêdo, D.F.; Santos, D.G.; Finger, A.B. 2020. Gerenciamento de aquisições no setor público segundo o PMBOK: Estudo de caso em uma empresa pública. Revista Gestão e Organizações. 5(4): 34-59.

Souza, R.R.C.; Pedron, C.D. 2024. “Ver para crer”: a importância da prova de conceito em projetos com robôs. REUNIR Revista De Administração Contabilidade e Sustentabilidade 14(3): 133-149.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.