October 20, 2026
Techno-Economic Optimization of Deep Foundations: An Approach Based on Value Engineering and Lean Construction
Techno-economic Optimization of Deep Foundations: A Value Engineering and Lean Construction Based Approach
Weverton Stevan Nogueira; Gleison De Souza
DOI: 10.22167/2675-6528-202602435
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
Project management in civil engineering is an essential tool, integrating risk, scope, schedule, quality, and cost management to ensure financial efficiency and added value to ventures. In a context of complex works and rigorous budgets, the foundation represents a significant initial investment. The study analyzed the technical-economic feasibility of replacing continuous flight auger piles with drilled shafts in a real project in Campinas, São Paulo. From the perspective of Lean Construction Management and Value Engineering, the reassessment of geotechnical profiles and the application of the Ishikawa Diagram allowed for the diagnosis of overprocessing waste in the original project. The alteration of the execution method, validated by technical consultancy and new field tests, promoted a cost reduction of 47.96% in the stage, generating a nominal saving of over R$ 188,000.00. The results demonstrated that the optimization positively impacted the Economic Value Added (EVA) and cash flow, providing guidelines for decision-making based on the joint analysis between structural performance and financial efficiency.
Keywords: Lean construction; Waste; Operational efficiency; Value engineering; Applied geotechnics.
1. Introduction
Civil construction is a fundamental pillar for socioeconomic development, driving urban growth and improving infrastructure. The inherent complexity of this sector demands integrated project management, which harmonizes various disciplines such as engineering, architecture, economics, and administration. The success of an undertaking is not limited to technical excellence, but crucially depends on structured management that balances quality and profitability (Nahime, 2024).
In the current construction scenario, cost management emerges as a strategic pillar in project management, directly influencing the economic viability and sustainability of works. The Project Management Institute (PMI, 2021) defines cost management as the set of processes including planning, estimating, budgeting, and financial control, aiming for project completion within budget. Vargas (2021) adds that this continuous process is essential for decision-making and for improving project performance, ensuring the balance between cost, schedule, and quality.
Within this context, the foundation phase assumes a strategic role, representing one of the elements with the highest cost and technical risk in a construction budget. The foundation design must consider the loads transmitted by the structure and the interaction with the soil, as different soil types exhibit distinct behaviors (Pinto, 2019). Deep foundations, such as continuous helical piles and drilled shafts, are widely used in multi-story buildings (Caputo, 2015). The choice of foundation type must reconcile structural performance criteria, geotechnical characteristics, and execution costs, aiming to optimize resources and ensure project efficiency.
With the advancement of management methodologies in civil construction, approaches that integrate productive and economic efficiency have emerged. Lean Construction Management, for example, adapts Lean Manufacturing principles to the sector, focusing on waste elimination, resource optimization, and value aggregation to the construction process (Oakland and Marosszeky, 2017). Complementarily, Value Engineering contributes to validating the maintenance of the technical function at the lowest possible cost, connecting decision-making intelligence to the asset’s financial performance (Howell and Ballard, 2003).
In housing developments, the foundation phase represents a substantial initial investment, requiring precise technical analysis and maximum operational efficiency. However, initial projects may present overprocessing, as observed in a real development in Campinas, São Paulo, where the choice of continuous helical piles was reevaluated. The analysis of geotechnical profiles and the application of tools such as the Ishikawa Diagram revealed waste inherent in the original design, indicating a gap in the technical-economic optimization of foundations.
The relevance of this study lies in demonstrating how strategic management, based on real data and methodologies such as Lean Construction and Value Engineering, can influence efficient technical decisions, promote waste reduction, and provide guidelines for joint decision-making that integrates structural performance and financial optimization. Given this scenario, the present study aims to analyze the technical-economic feasibility of replacing continuous flight auger piles with drilled piles in a real housing development located in Campinas, São Paulo.
2. Material and Methods
This research was characterized as an applied case study, adopting a mixed approach that integrated qualitative and quantitative elements. According to Gil (2017), applied research seeks the solution of practical problems, aligning with the objective of optimizing the technical-economic viability of foundations. The case study design followed Yin’s (2015) guidelines, allowing the investigation of a real phenomenon in its contemporary context, with a focus on the comparative analysis of foundation systems.
The empirical object of the study was a real housing development, composed of four residential blocks and 80 units, located in Campinas, São Paulo. To preserve institutional confidentiality, the name of the responsible construction company and the exact location of the construction site were omitted. The characterization of the development was limited to its technical specificities and general scope, without details that could compromise confidentiality.
The primary data collection began with documentary research and analysis of the organization’s records. Initially, existing Standard Penetration Test (SPT) reports and the load plans of the original structural project were examined. These documents provided the basis for understanding the initial geotechnical conditions of the site and the structural load requirements.
The SPT sounding procedure, standardized by NBR 6484 (ABNT, 2020), was fundamental for soil characterization. This test, which determines the Standard Penetration Resistance (NSPT), was carried out by driving a split-spoon sampler, allowing for the collection and tactile-visual classification of samples. Two boreholes were distributed in the area of each block, according to NBR 8036 (ABNT, 1983), using a sounding tripod with a pulley and manual winch.
The research conduction followed a logical flow, divided into four main stages. The first stage consisted of the technical evaluation and reconsideration of the foundation method. After receiving the initial project, the reevaluation of the sounding reports was carried out, where the possibility of enabling mechanically excavated piles was identified, considering the depth of the water table and the resistance of the upper soil layers.
In the second stage, the on-site validation and project redesign were carried out. A specialized geotechnical consultancy was hired to perform test borings, also known as pilot holes, at the construction site. With the technical validation of soil stability and confirmation of the absence of water at the required depth, the foundation project redesign was requested to adapt to the new execution method.
The third stage involved a comparative cost analysis. A detailed budgetary survey was carried out for both foundation scenarios: continuous flight auger piles (original design) and excavated piles (revised design). This survey included the measurement of costs for mobilization, inputs, labor, and the fees of the new design consultancy, related to the redesign.
The fourth stage involved the application of management tools. With the quantitative data collected, the Ishikawa Diagram, also known as the Cause and Effect Diagram (Ishikawa, 1976), was used. This tool was employed to map the causes of cost variations and to identify how technical decisions impacted the budget and the efficiency of the foundation process.
For the data analysis, the foundation of Lean Construction Management was used, aiming to identify the reduction of waste in the production process. The principles of Value Engineering were applied to validate the maintenance of the structural function at optimized cost (Koskela, 1992). The organization and comparison of financial data pertinent to execution budgets were made possible through electronic spreadsheets.
The analysis of financial data was carried out comparatively between the two foundation methods. Although the initial scope predicted the use of Economic Value Added (EVA) for an in-depth financial analysis, the impossibility of accessing confidential accounting data from the organization directed the work towards a technical decision based on Value Engineering and project management, focusing on execution budgets.
Ethical considerations were observed throughout the entire process, ensuring the confidentiality of the construction company’s and the development’s information. The research focused exclusively on the technical-economic aspects of replacing the foundation system, without disclosing sensitive data that could identify the company or the exact location of the work.
3. Results and Discussion
The initial analysis of the undertaking revealed the complexity inherent in project management in civil engineering, especially in the foundation phase, which represents a significant contribution to the budget. The study focused on the technical-economic feasibility of replacing continuous helix piles with excavated piles, using real data from a housing development in Campinas, São Paulo. Geotechnical reassessment and the application of methodologies such as Lean Construction Management and Value Engineering allowed for the identification and mitigation of waste, resulting in substantial cost optimization and improvement of operational efficiency, as detailed in the findings below.
Geotechnical Analysis and Foundation System (SPT)
In the preliminary analysis process of the foundation soil, geological-geotechnical investigations were carried out, essential for determining the soil’s bearing capacity and the location of the water table, according to NBR 6484 (ABNT, 2020). This procedure is crucial for ensuring construction safety and preventing collapses, especially in multi-story developments, such as the one studied (Caputo, 2015). The Standard Penetration Test (SPT) acts as an “X-ray” of the soil, measuring the Standard Penetration Resistance (NSPT) through the number of blows required to drive the sampler.
For the undertaking in question, two boreholes were executed per block, totaling an area of approximately 190 m² per block, in accordance with NBR 8036 (ABNT, 1983). The analysis of one of the boreholes showed that in the first five meters, the soil presented low compactness, requiring only three blows for penetration, and was classified as slightly silty medium clayey sand (loose). However, from the sixth meter onwards, a significant increase in resistance was observed, with 20 blows for penetration, indicating slightly clayey medium silty sand (compact).
Between the seventh and eighth meters, the soil resistance increased even further, demanding about 35 blows for penetration, in a very compact fine to medium silty slightly clayey sand soil. Initially, the presence of water at specific points in the terrain led to the choice of continuous flight auger piles, aiming for maximum operational safety. However, the observation of very compacted soil from the seven-meter mark, capable of absorbing structural loads safely and economically, motivated the reevaluation of the executive method, seeking optimization.
Pile foundations
Deep foundations are widely used in large-scale buildings, where structural loads require reaching more consistent soil layers. In Brazil, NBR 6122 (ABNT, 2022) standardizes projects and executions, classifying them into piles, caissons, and large-diameter bored piles, with various methods. Piles are the most common in medium and high-density housing developments, divided into displacement piles and excavation piles, according to Cintra and Aoki (2010).
Continuous flight auger (CFA) piles, one of the methods evaluated, are executed quickly by continuous soil removal with a helical auger and simultaneous concrete injection through the central stem. This system is advantageous in soils with a high water table or low cohesion, as the concrete pressure stabilizes the borehole, preventing collapses (Antunes and Tarozzo, 2019). In contrast, mechanized bored piles use short augers for intermittent drilling, being viable in soils with borehole stability that allow for gravity concreting.
The mechanically excavated pile is a technically and economically advantageous alternative in soils with high compactness and low water presence (Falconi et al., 2019). Both methods, continuous flight auger and excavated, stand out for their agile execution and lower risk in urban soils, avoiding the intense vibrations of methods like the Franki pile, which could affect the neighborhood (Cintra and Aoki, 2010). The choice between them, in the project under analysis, considered the need to reconcile productive efficiency and risk mitigation, adapting to the particularities of the construction site.
Project Management and Lean Construction Management
Modern project management transcends task execution, consolidating itself as a strategic competence that integrates diverse areas of the organization (PMI, 2021). Kerzner (2015) highlights that the manager must have an expanded vision to select methods that optimize return on investment, in addition to fulfilling the scope. In the civil construction sector, this integrative approach transforms technical challenges into opportunities for efficiency gains, aligning site decisions with the profitability and quality strategy of the undertaking.
Lean Construction Management, adapting principles from the Toyota Production System, establishes production as a value stream, focusing on waste elimination and resource optimization (Koskela, 1992; Oakland and Marosszeky, 2017). This philosophy of continuous improvement is based on pillars such as Safety and Quality, Technical Decision Making, and Economic Efficiency (Value for Money). Technical Decision Making, in particular, must be agile and based on real project data and geological variability analyses, avoiding excessive conservatism.
The identification of the seven wastes of Lean Construction, according to Koskela (1992), Liker (2005), and Picchi (2017), is fundamental to understanding the impact of the methodological choice on project performance. In the context of foundations, overprocessing was a critical waste. It occurs when the execution method exceeds the technical requirements of the project, manifesting through the use of high operational cost technologies in soils that would accommodate simpler methods, generating resource consumption without proportional structural gain. The mitigation of this waste converts analytical intelligence into productive efficiency.
Value Engineering and Decision Making
Given the macroeconomic scenario, with the National Construction Cost Index (INCC) registering a 0.21% increase in December 2025 and an accumulated 6.10% over the last 12 months (FGV, 2026), technical decision-making integrates the economic efficiency strategy. The initial phase of an undertaking is critical, requiring analytical capacity to adjust engineering solutions to the reality of the terrain (Nahime, 2024). The application of Value Engineering allowed for a detailed analysis of direct costs and the evaluation of replacing continuous helix piles with mechanized excavated piles.
To validate the safety of the transition, a specialized geotechnical consultancy was hired to review the load-bearing capacity calculations and the Percussion Sounding reports, which were re-executed. The consultancy confirmed the feasibility of changing to excavated piles, based on the total pile resistance, defined by the balance between lateral friction and tip resistance. This approach ensured structural safety in stable soils without water interference at the foundation levels (Cintra and Aoki, 2010).
The Fishbone Diagram, or Cause and Effect Diagram, developed by Ishikawa (1976), was used to map the variables that increased the cost. The analysis showed that the isolated presence of water in the “Environment” induced a “Method” of financial overprocessing, disregarding the real resistance of the geotechnical profile. The mobilization of a continuous flight auger was identified as an inefficient use of resources, generating mobilization costs without real technical benefit and violating the principle of Value for Money (VFM), according to Koskela’s logic (1992).
The transition to the excavated pile method mitigated overprocessing, converting technical intelligence into financial savings. The diagnosis, consolidated by the Ishikawa Diagram, revealed that maintaining the continuous flight auger method would result in productive inefficiencies, such as concrete overconsumption (Material) and the need for costly auxiliary equipment, such as concrete pumps (Machine). The elimination of the requirement for specialized teams with high unit costs and the reduction of logistical complexity (Labor) transformed technical knowledge into productive efficiency, balancing structural performance and economic feasibility.
The technological substitution, validated by technical advisory and load calculations, positively impacted the venture’s cash flow and financial efficiency. Management prioritized profitability by reducing immediate disbursement, allowing capital reallocation to other project fronts, aligned with Kerzner’s (2015) vision. Although net profit data is confidential, the optimization positively impacted the Economic Value Added (EVA), decreasing immobilized capital in the initial phase and increasing the operating margin, which demonstrates the effectiveness of Value Engineering for the project’s economic health.
Evaluation of Financial Results between Executive Methods
The comparative analysis between the initially designed foundation method (continuous helix piles) and the revised method (excavated piles) demonstrated a significant financial optimization. The original project, with continuous helix piles, predicted a total investment of R$ 392,490.56. This amount included R$ 110,814.00 for drilling and concreting, R$ 171,577.60 for 413.44 m³ of 30Mpa concrete, R$ 26,000.00 for pump rental, R$ 24,700.00 for backhoe rental, and R$ 59,398.96 for steel and rebar assembly.
In contrast, the implementation of the excavated piles, after the project revision, demanded a total amount of R$ 204,243.65. The detailed costs for the revised project were: R$ 39,750.00 for drilling excavated piles, R$ 112,653.14 for 289.225 m³ of 25Mpa concrete, R$ 20,000.00 for the project revision, and R$ 31,840.51 for steel and rebar assembly. The difference between the two scenarios resulted in a nominal saving of R$ 188,246.91, which ratified the effectiveness of the critical analysis of the original planning.
This saving represented a reduction of 47.96% on the budget foreseen for the foundation stage. This result demonstrated that the application of Value Engineering allowed for savings of almost half the initially estimated cost, without compromising structural safety. More than a simple reduction in expenses, this amount reflected the elimination of capital waste that would have been allocated to oversized processes, optimizing the project’s overall cash flow and enhancing the return on invested capital.
The economy of R$ 188,246.91, when reinvested or used to reduce project debt, generates economic value. The technical decision not only preserved cash but also increased the asset’s residual profitability, ensuring that the return on invested capital (ROIC) surpassed the weighted average cost of capital (WACC). This finding consolidates cost management as a strategic engineering tool, demonstrating that technical decisions based on real data directly influence the asset’s economic feasibility.
Guidelines for Optimization of Foundation Projects in New Ventures
The case study allowed for the establishment of a roadmap of guidelines for managers seeking productive and financial efficiency in new ventures. Upon receiving a deep foundation project, the manager should view it as a technical hypothesis to be tested under the scrutiny of Value Engineering and Lean Construction principles. To guide this reanalysis, a strategic questioning flow is proposed, starting with the reassessment of geotechnical uncertainty.
The first guideline focuses on re-evaluating geotechnical uncertainty, questioning the quality of the base information. The manager must verify if the available SPT reports are sufficient to map the ground variability, the timing of the tests in relation to the start of the work, and if there is a discrepancy between the water level indicated in the project and the reality observed in the field. Furthermore, it is crucial to question whether the designed solution considered the most pessimistic scenario due to a lack of data or for real technical necessity.
The second guideline addresses the identification of overprocessing, from Koskela’s (1992) perspective, investigating whether there is an excess of technology for the effort required. It should be questioned whether the chosen method, such as the continuous helix, is indispensable for structural integrity or if a simpler method, such as the excavated pile, would meet the resistance calculations. It is also important to identify the costs of “non-value adding,” such as the mobilization of large fleets and auxiliary equipment (pumps, backhoes) that could be eliminated.
The third guideline consists of diagnosing root causes, using the Ishikawa Diagram, when detecting a high cost. The manager must apply this tool to understand the origin of the expense, questioning whether the high cost is due to materials (concrete overconsumption), labor (costly specialized teams), or an executive method incompatible with site logistics. It is essential to verify if the project choice was based on executive tradition or on an updated Value Engineering analysis.
The fourth guideline involves validation by independent consultancy, focusing on risk management and ensuring regulatory compliance (NBR 6122). The manager must assess whether the investment in an external project review is justified by the potential savings, and if the new load-bearing capacity calculations have undergone a proof of concept based on real field data. This step ensures that the change in method has technical and regulatory backing.
Finally, the fifth guideline focuses on the analysis of financial flow and opportunity cost, from the perspective of Value Engineering. The technical decision must be translated into financial language, evaluating the impact of reducing fixed capital in the foundation on the project’s total Economic Value Added (EVA). Furthermore, it is crucial to analyze how the generated savings can reduce the financial exposure of the work against interest rates and the weighted average cost of capital (WACC).
The application of these guidelines transforms project management from a static process into a cycle of continuous improvement. Technological transition, when based on quality data and tools, demonstrates the possibility of increasing the profitability of a real estate asset without compromising safety. This consolidates the role of the managing engineer as an agent of economic and technical efficiency, capable of integrating structural performance and financial optimization in new developments.
In summary, the research demonstrated that geotechnical reevaluation and the application of Lean Construction and Value Engineering principles were crucial for optimizing foundation design. The substitution of continuous helix piles for excavated piles, technically validated, resulted in savings of 47.96%, or R$ 188,246.91, positively impacting cash flow and Economic Value Added. These findings confirm that the integration between strategic management and technical execution, combined with rigorous data analysis, is fundamental for the economic feasibility and profitability of civil construction ventures.
4. Conclusion
The present study analyzed the technical-economic feasibility of replacing continuous helix piles with excavated piles in a real housing development located in Campinas, São Paulo. It was found that the reevaluation of geotechnical profiles, initially interpreted conservatively, revealed the presence of highly compacted soil from seven meters deep, which allowed for the adoption of a simpler and equally safe foundation method. The application of Lean Construction Management and Value Engineering principles, with the aid of the Ishikawa Diagram, diagnosed the overprocessing in the original project, identifying waste related to the use of oversized technology, concrete overconsumption, and high mobilization and labor costs. Technical validation by specialized consultancy confirmed the safety of altering the execution method, resulting in a nominal saving of R$ 188,246.91, corresponding to a 47.96% reduction in foundation stage costs. It was observed that this optimization positively impacted the project’s cash flow and Economic Value Added (EVA).
The main contribution of this work lies in demonstrating how strategic management, by integrating methodologies such as Lean Construction and Value Engineering with rigorous analysis of real geotechnical data, can support efficient technical decisions that optimize resources and increase the profitability of civil construction projects. To this end, practical guidelines were established to guide managers in re-evaluating geotechnical uncertainty, identifying overprocessing, diagnosing root causes, validating through independent consultancy, and analyzing financial flow and opportunity cost. A limitation of the study was the impossibility of accessing confidential accounting data from the organization, which restricted the financial analysis to execution budgets. It is suggested that future studies apply and validate these guidelines in different construction contexts, deepening the analysis of the impact on Added Economic Value and return on invested capital, consolidating the role of the managing engineer as an agent of economic and technical efficiency.
Bibliographic References
Antunes, W.R.; Tarozzo, H. 2019. Estacas hélice contínua e hélice de deslocamento. p. 341-348. In: Falconi et al. Fundações: teoria e prática. 3ed. Oficina de Textos, São Paulo, SP, Brasil.
Associação Brasileira de Normas Técnicas [ABNT]. 1983. NBR 8036: Programação De Sondagens de Simples Reconhecimento dos Solos para Fundações de Edifícios – Procedimento. ABNT. Rio De Janeiro, RJ, Brasil.
Associação Brasileira de Normas Técnicas [ABNT]. 2020. NBR 6484: Solo – Sondagens De Simples Reconhecimento Com SPT – Método De Ensaio. ABNT. Rio De Janeiro, RJ, Brasil.
Associação Brasileira de Normas Técnicas [ABNT]. 2022. NBR 6122: Projeto e execução de fundações – Procedimento. ABNT. Rio De Janeiro, RJ, Brasil.
Caputo, H.P. 2015. Mecânica do solo e suas aplicações: fundamentos. 7ed. LTC. Rio de Janeiro, RJ, Brasil.
Cintra, J.C.A.; Aoki, N. 2010. Fundações por estacas: projeto geotécnico. Oficina de Textos, São Paulo, SP, Brasil.
Falconi et al., 2019 [Referência completa não encontrada no documento original]
Fundação Getúlio Vargas [FGV]. 2026. INCC-M: Resultados 2025. Disponível em: <https://portal.fgv.br/noticias/incc-m-2025>. Acesso em: 08 dev. 2026.
Gil, A.C. 2017. Como elaborar projetos de pesquisa. 6ed. Atlas. São Paulo, SP, Brasil.
Howell, G.A.; Ballard, G. 2003. Lean Project Management. In: Building Research & Information Taylor & Francis 31: 1-15.
Ishikawa, K. 1976. Guide to Quality Control. Tokyo: Asian Productivity Organization, Tokyo, Japan.
Kerzner, H. 2015. Gerenciamento de projetos: uma abordagem sistêmica para planejamento programação e controle. 13ed. Blucher, São Paulo, SP, Brasil.
Koskela, L.1992. Application of the new production philosophy to construction. Stanford: Stanford University. (Technical Report, n. 72). Disponível em: <file:///C:/Users/TM012/Downloads/Koskela-TR72.pdf> Acesso em: 08 fev. 2026.
Liker, J.K. 2005. A Toyota Way:14 princípios de gestão do maior fabricante do mundo. Bookman, Porto Alegre, RS, Brasil.
Nahime, B.O. 2024. Construção civil: planejamento e execução. 1ed. Atena, Ponta Grossa, PR, Brasil.
Oakland, J.S.; Marosszeky, M. 2017. M. Total Construction Management: lean Quality in construction Project delivery. 1ed. Routledge, New York, NY, EUA.
Picchi, F. A. 2017. Entenda os “7 desperdícios” que uma empresa pode ter. Lean Institute Brasil. Disponível em: <https://www.lean.org.br/artigos/1131/entenda-os-7-desperdicios-que-uma-empresa-pode-ter?srsltid=AfmBOoo4uHalzkyCtkaltraVCm7C99m1zkx8UjQF3sCYAxGiqwCGepqd> Acesso em 14 de abril de 2026.
Pinto, C.S. 2019. Propriedades dos solos. P. 55-120. In: Falconi et al. Fundações: teoria e prática. 3ed. Oficina de Textos. São Paulo, SP, Brasil.
Project Management Institute [PMI]. 2021. Guia do Conhecimento em Gerenciamento de Projetos e o Padrão de Gerenciamento de Projetos (Guia PMBOK ®). 7ed. PMI. Newton Square, PA, EUA.
Vargas, R.V. 2021. Manual prático do plano de projeto: utilizando o PMBOK ® Guide. 7ed. Brasporto. Rio de Janeiro, RJ, Brasil.
Yin, R.K. 2015. Estudo de caso: planejamento e métodos. Tradução por: Herrera, C. М. Bookman. Porto Alegre, RS, Brasil.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq