Optimization of internal logistics flows to absorb the complexity of new vehicle models in the automotive industry
Optimization of Internal Logistics Flows to Absorb the Complexity of New Vehicle Models in the Automotive Industry
Wagner Donizete Pedro; Daniel Luis Garrido Monaro
DOI: 10.22167/2675-6528-202602432
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The global automotive industry has undergone accelerated transformation, driven by new Industry 4.0 technologies and solutions, which demanded the restructuring of production systems and, especially, internal logistics. The study aimed to apply the PDCA cycle integrated with project management tools to optimize internal logistics routes in an automotive industry, facing growing operational complexity. The research was conducted through a qualitative, applied, and action-research approach, with direct involvement in the organizational environment. The methodology was structured in the PDCA stages, including the development of the Work Breakdown Structure (WBS), schedule definition, operational diagnosis through direct observation, application of tools such as spaghetti chart and time study, and implementation of the proposed improvements. The results showed the identification of waste related to movement, overlapping flows, and imbalance between routes, allowing the reconfiguration of the logistics system without additional investments. A reduction in operational interferences, better workload distribution, and a significant increase in route saturation level were observed, approaching the established goal of 95%. It was concluded that the integration between PDCA and project management enabled a structured, efficient, and adaptable approach, capable of promoting sustainable operational gains in highly complex scenarios.
Keywords: Route balancing; Operational efficiency; Material flow; Change Management; Internal logistics.
1. Introduction
The global automotive industry is undergoing a process of accelerated transformation, driven by the introduction of new technologies such as electrified vehicles and solutions associated with Industry 4.0. In the Brazilian context, this transition not only modifies the product but also reconfigures production systems, directly impacting manufacturing processes and, significantly, internal logistics. This scenario imposes challenges that demand structured approaches to planning, control, and management, central characteristics of the project management discipline (Oliveira et al., 2021; Souza and Lima, 2022).
The introduction of new vehicle models, with a high degree of technological complexity, demands a comprehensive reassessment of the material flow, from receiving to supplying the assembly lines. In this context, internal logistics transcends its operational role to assume a strategic function, becoming a primary driver of flexibility, speed, and responsiveness of production systems. Pires (2016) highlights that this change in role intensifies the need for inter-area coordination, integrated planning, and structured decision-making.
In the face of this dynamic and complex environment, effective change management becomes indispensable. Specialized literature indicates that successful organizational and operational transformations are directly related to the application of formal management methods, capable of systematically planning, executing, monitoring, and controlling changes (Carvalho and Rabechini Jr., 2019). Thus, internal logistics can be treated as a set of temporary initiatives, with clear objectives, defined constraints, and measurable results, aligning with the classic concept of a project. Ballou (2006) already emphasized the strategic role of logistics, and subsequent studies reinforce that this alignment is enhanced by consolidated project management practices, including scope definition, risk analysis, schedules, and performance indicators (Kerzner, 2017; Novaes, 2019).
The continuous pursuit of waste elimination and operational efficiency increase remains a fundamental principle in modern management. Value stream mapping emerges as an essential tool to support data-driven decisions. Martins (2020) emphasizes that the redesign of internal processes, when conducted in a structured manner, allows for the identification of bottlenecks, waste, and improvement opportunities. When integrated with the logic of project management, this redesign becomes more effective, as it follows formal cycles of planning, execution, verification, and corrective action, such as the PDCA cycle.
Project management therefore assumes a crucial role in enabling sustainable improvements in internal logistics. The application of tools such as the PDCA cycle, change management, and monitoring through indicators allows for structuring the implementation of improvements, reducing risks and increasing the predictability of results (Carvalho and Rabechini Jr., 2019). Thus, the complexity inherent in the production of electrified vehicles can be managed without the immediate need for large investments in new assets. Traditionally, the increase in operational complexity was addressed by adding physical resources, a strategy that often increases costs and compromises sustainability. In contrast, the literature indicates that approaches based on process reorganization, efficient use of existing resources, and application of project management practices demonstrate greater adherence to the principles of efficiency and continuous improvement (Peinado and Graeml, 2020; Tubino, 2021). The relevance of this study lies in the application of project management as a structuring approach to increase the efficiency of internal logistics in an environment of growing technological complexity, without resorting to substantial investments in new resources, expanding the field of application of the discipline and promoting a change in perspective on its strategic role in industrial management.
In this scenario, the problem arises of how the union between the PDCA continuous improvement cycle and project management tools can enable logistical efficiency in contexts of high complexity. The integration of these principles is particularly relevant, as both share fundamentals such as focus on flow, waste elimination, structured planning, and systematic process improvement (Womack and Jones, 2004; Bowersox et al., 2007). Thus, the present study aimed to apply project management knowledge areas and tools with a focus on the PDCA methodology, to carry out a systematic diagnosis of internal logistics routes in an automotive industry.
2. Material and Methods
The present study was conducted through an action research, characterized by a qualitative approach and applied nature. Action research proved to be adequate due to the need for planned intervention in the logistic process of an automotive industry, allowing the researcher’s direct involvement in the organizational environment to monitor and analyze problems, decisions, and actions dynamically (Thiollent, 1986). The qualitative approach was employed to understand the interrelationships between resources, processes, and people, interpreting phenomena in their real context (Gil, 2002). The applied nature of the study aimed to generate practical knowledge for the optimization of logistic resources (Prodanov and Freitas, 2013).
The research was conducted in a multinational company in the automotive sector, located in an industrial hub in the Mata Norte region of Pernambuco. The organization, with operations initiated in 2015, was undergoing a renewal of its product line, incorporating new technologies such as “Bio-Hybrid”, which demanded adaptations in its production and logistics processes. The project team was composed of representatives from strategic areas, including logistics engineering, responsible for the analysis and application of tools, and the “handling” area, with supervisors and team leaders who contributed operational information and in the implementation of changes.
Additionally, the EHS (Environment, Health and Safety) area participated to assess the impacts of the changes from the perspective of employee health and safety, ensuring compliance with legal requirements. The manufacturing area, as an internal client, validated the implemented actions and indicated any operational impacts. The selection of participants occurred due to their direct involvement in the analyzed logistical and productive processes, ensuring the relevance of their contributions to the project.
The research was structured in three main stages, based on the PDCA cycle (Plan, Do, Check, Act), which served as a project management tool and guiding element for the intervention. The PDCA, also known as the Deming Cycle, constitutes a systematic managerial method for achieving performance objectives in industrial processes (Campos, 2002). The stages of the cycle were adapted to the context of optimizing internal logistics routes.
In the Planning (“Plan”) phase, the Work Breakdown Structure (WBS) was developed to organize the scope of work and hierarchically structure the necessary deliverables. The WBS allowed the project to be broken down into smaller, manageable activities, facilitating team alignment and the definition of responsibilities (Vargas, 2016; PMI, 2021). Subsequently, the project schedule was developed, using the Gantt Chart technique, to temporally organize the stages and establish the logical sequence of activities.
The initial diagnosis of the process was conducted to map the supply logistics routes for parts on the assembly line, focusing on routes impacted by the complexity of the new models. To this end, direct and participant observation was carried out in the production environment, following the flow of materials and logistics operations. This approach allowed for an understanding of the system’s real functioning and the identification of operational patterns, as well as the collection of data for performance analysis.
The main tools applied by the logistics engineering team during the diagnosis included the Spaghetti Chart, used to visualize the physical flow of materials and operators, identifying unnecessary movements and layout optimization opportunities (Shingo, 1996). Time study was applied to measure the time spent in each stage of the supply process, allowing the identification of operational inefficiencies and bottlenecks (Barnes, 1997).
The data collection was conducted by the logistics and handling engineering team through direct field timing, using a digital stopwatch. Five consecutive cycles of each of the three logistic routes (A, B, and C) were fully monitored under normal operating conditions, without observer interference. The total cycle time, travel time, refueling stop time, loading and unloading time, and any unproductive times were recorded.
The collected data were organized in an electronic spreadsheet and integrated with previously gathered information, such as the quantity of packages supplied per day and the distance traveled per route. For the calculation of displacement time, the average speed of the equipment was considered. The daily transport frequency was determined by dividing the total quantity of packages supplied per day by the convoy’s transport capacity, equivalent to three packages per trip. The available daily productive time was 1,245 minutes, after deducting breaks and meal intervals.
In the Execution phase (“Do”), the planned actions were implemented, mobilizing teams and resources to ensure the delivery of results (PMI, 2021). The focus was on applying change management practices, such as communication planning and team engagement, to mitigate resistance to process changes (Chiavenato, 2014). Resource management practices, such as intelligent allocation and monitoring, were adopted to optimize the use of existing labor, equipment, and routes (Kerzner, 2017; Verzuh, 2016).
The Analysis and Validation phase (“Check” and “Act”) involved a new collection and analysis of post-intervention data to compare the performance of the restructured logistics system with the initial condition. Distances traveled were measured, operational flows were reviewed, and execution times for supply routes were re-evaluated. The analysis of the results was carried out by comparing the initial and post-intervention scenarios, using the same mapping and evaluation tools to standardize measurement criteria (Slack et al., 2018).
3. Results and Discussion
The application of the Plan-Do-Check-Act cycle, integrated with project management tools, proved to be an effective mechanism for optimizing internal logistics routes in the automotive industry, in a scenario of increasing operational complexity. The results obtained demonstrated the capacity of this structured approach to identify inefficiencies, propose data-driven solutions, and implement improvements in a controlled manner, without the need for additional infrastructure investments. The action research allowed for direct intervention in the organizational environment, facilitating a deep understanding of the processes and validation of the proposed interventions, aligning with the principles of scientific knowledge construction and real-world problem-solving, as advocated by Thiollent (1986).
Planning (“Plan”)
The project planning phase was initiated with the elaboration of the Work Breakdown Structure (WBS), which organized the scope of work and hierarchized the essential deliverables and activities. The WBS, as illustrated in the
, allowed the project to be broken down into smaller, manageable tasks, facilitating the alignment of the logistics engineering team regarding responsibilities, execution steps, and schedule monitoring. This structuring provided greater clarity in defining diagnostic activities, route analysis, and the development of improvement proposals, ensuring a systematic approach from data collection to solution proposition.
Complementary to the WBS (Work Breakdown Structure), a project schedule was developed, using the Gantt Chart technique, presented in the
. This schedule established the logical sequence and temporal distribution of activities, defining deadlines for each stage and facilitating progress monitoring. The alignment between scope and time was crucial for structuring the project’s advancement, reducing risks of rework and execution deviations, and promoting clear and shared communication among the involved areas, ensuring that all participants had a clear vision of the deliverables and their role in the expected results.
The initial diagnosis of the logistics process focused on mapping the supply routes of parts on the assembly line, with special attention to the areas impacted by the introduction of new vehicle models. It was identified that the internal movement system was structured by logistic trains, composed of an industrial tugger that pulled three interconnected wheeled bases, responsible for the sequential transport of material packaging between the warehouse and the points of use on the production line. The
illustrates this composition, which aimed for agility and regularity in the flow.
The logistics engineering team delimited area CH as critical, where three main routes (A, B, and C) concentrated supply activities. To standardize information and reduce variability, the Plan For Each Part (PPCP) was reviewed and updated with the “handling” team. The PPCP consolidated essential data such as point of use, replenishment frequency, quantities, packaging type, and internal transport method, according to the model presented in the
. This standardization is fundamental for the stability of the production process, as highlighted by Slack et al. (2018).
The analysis of operational complexity revealed that Route A supplied 80 types of parts in 102 daily packages, serving Line 4 and part of Line 5. Route B, with 86 types of parts and 113 daily packages, served Lines 1 and 2, and part of Line 7, presenting the largest variety of items and volume. Route C, in turn, supplied 56 types of parts in 86 daily packages, covering Line 3, part of Line 5, and Line 6. These initial data already indicated an unequal distribution of workload among the routes.
The update of the “spaghetti chart” for routes A, B, and C, according to the
, allowed visualizing the real routes and identifying unnecessary displacements, flow overlaps, and areas of greatest concentration. The measurement of distances covered revealed that Route A covered 854 meters per cycle, Route B 1,004 meters, and Route C 1,078 meters. Route B, despite not being the longest, concentrated the greatest operational load due to diversity and volume, while Route C, with the greatest physical displacement, indicated inefficiency in the relationship between route and volume transported, in addition to overlaps with routes A and B, potentiating risks of congestion and operational interferences, according to Peinado and Graeml (2007).
Time study was performed to measure the time spent in each supply cycle, including travel, stops, loading, unloading, and unproductive times. Five consecutive cycles were timed for each route, under normal operating conditions. The collected data, organized in a spreadsheet, allowed for the calculation of the total daily time required per route and the operational saturation index, considering an available productive time of 1,245 minutes per day. The initial results, presented in the
|
Indicator |
Route A |
Route B |
Route C |
|
Lines served |
L4 and partial L5 |
L1, L2 and partial L7 |
L3, L6 and partial L5 |
|
Types of supplied parts |
80 |
86 |
56 |
|
Packages supplied/day |
102 |
113 |
86 |
|
Distance per cycle (m) |
854 |
1.004 |
1.078 |
|
Cycles performed per day |
34 |
38 |
29 |
|
Total daily time (min) |
839 |
978 |
762 |
|
Daily available time (min) |
1.245 |
1.245 |
1.245 |
|
Saturation (%) |
67,4 |
78,5 |
61,2 |
|
Saturation target (%) |
95 |
95 |
95 |
, evidenced that none of the routes reached the saturation target of 95%.
A
|
Indicator |
Route A |
Route B |
Route C |
|
Lines served |
L4 and partial L5 |
L1, L2 and partial L7 |
L3, L6 and partial L5 |
|
Types of supplied parts |
80 |
86 |
56 |
|
Packages supplied/day |
102 |
113 |
86 |
|
Distance per cycle (m) |
854 |
1.004 |
1.078 |
|
Cycles performed per day |
34 |
38 |
29 |
|
Total daily time (min) |
839 |
978 |
762 |
|
Daily available time (min) |
1.245 |
1.245 |
1.245 |
|
Saturation (%) |
67,4 |
78,5 |
61,2 |
|
Saturation target (%) |
95 |
95 |
95 |
demonstrated that Route A operated at 67.4% saturation, Route B at 78.5%, and Route C at 61.2%. Although Route B showed the highest occupancy rate, all routes were below the ideal threshold of 95%, indicating underutilization of operational capacity and room for redistribution of activities and balancing. This initial scenario confirmed the need for intervention to optimize the use of logistical resources and absorb the growing complexity of new vehicle models, aligning with the study’s objective.
Execution (“Do”)
In the execution phase, planned actions were implemented with a focus on change management and team engagement. A meeting with all stakeholders presented the diagnosis results, highlighting the disparities between routes in terms of items addressed, packaging volume, distances traveled, and corridor usage. This transparent and data-driven communication, according to Chiavenato (2014), was crucial for building a shared perception of the need for improvement and mitigating resistance to the proposed changes, ensuring adherence to new operational routines.
To promote engagement and encourage active participation, a “brainstorming” dynamic was conducted, where representatives from different areas contributed suggestions for solutions to the identified inefficiencies. This collaborative approach broadened the quality of the proposals and strengthened the teams’ commitment to the project. In parallel, logistics engineering presented a preliminary improvement plan, focused on the critical points identified, such as the longest path of Route C (1,078 m) and the overlap of flows with Routes A and B, which indicated an imbalance between logistical effort and operational load.
The analysis of the “spaghetti chart” revealed that Route B, while serving lines 1 and 2, covered the area of line 3, originally served by Route C. It was then proposed to redistribute the parts from line 3 to Route B, eliminating overlaps and optimizing the flow. Additionally, the physical proximity of lines 5 and 6 to line 4 (served by Route A) supported the proposal to incorporate them into Route A, aiming to rationalize movements and reduce logistical effort, in accordance with the principles of route optimization (Shingo, 1996).
Initial rebalancing simulations indicated significant impacts on the operational load of the remaining routes. The number of daily cycles for Route A would increase from 34 to 50, and for Route B from 38 to 51. Furthermore, the distance traveled by Route A would increase from 854 m to approximately 1,050 m. These preliminary results highlighted the need for complementary analyses to ensure that the proposed improvements generated efficiency gains without compromising the operational capacity of the logistics system, requiring a reevaluation of alternatives.
Given the foreseen impacts, additional alternatives were evaluated to mitigate the effects and increase operational capacity. Among the possibilities raised in the brainstorming, the redefinition of corridors, change in circulation direction, and improvements in the warehouse layout stood out. The most viable alternative, which required validation from the EHS area, was increasing the capacity of the logistic trains, expanding them from three to four interconnected wheeled bases, which proved to be a strategic solution to absorb the complexity without major investments.
The implementation of this improvement, with the new four-base train format, demonstrated potential to reduce redistribution impacts. Simulations indicated that the number of daily cycles could be reduced from 50 to 37 on Route A and from 51 to 38 on Route B, showing a significant gain in operational capacity. The EHS team validated the change after monitoring several cycles, confirming the absence of safety risks. A reduction in refueling frequency was also observed, corroborated by the manufacturing team, indicating efficiency gains already in the initial phase.
With the operational and safety validation of the new configuration, the progressive redistribution of Route C’s parts to routes A and B began. With each cycle, an additional set of parts was incorporated, allowing for continuous monitoring of impacts and necessary adjustments. The gradual reduction of Route C’s load resulted in capacity gains, enabling the absorption of new demands arising from the introduction of new vehicle models without the need for additional investments, demonstrating the flexibility and adaptability of the logistics system, according to Corrêa and Corrêa (2012).
Analysis and Validation (“Check” and “Act”)
After the implementation of the proposed interventions, a new stage of data collection and analysis was carried out to compare the performance of the restructured logistics system with the initial scenario. This phase included measuring the distances traveled, reviewing operational flows, and re-evaluating the execution times of the supply routes. The comparative approach, recommended in Operations Management by Slack et al. (2018), allowed for an objective evaluation of efficiency gains and waste reduction, ensuring the standardization of measurement criteria.
The “spaghetti chart” was updated for the post-intervention scenario, according to the
, visualizing the new paths adopted by the routes. The graphical analysis showed a significant reduction in the overlap of logistics flows and a decrease in the number of crossing points between routes, which contributed to reducing the risk of congestion and interference in the cycle time of supply operations. This spatial reorganization indicated an improvement in the fluidity of the internal logistics process and a greater rationalization of movements, aligning with the principles of lean manufacturing (Shingo, 1996).
The review of the chronanalysis of the logistic routes was conducted through direct field timing, analogous to the previous stage, to ensure the comparability of data and measure the time effectively spent in each complete supply cycle in the new operational scenario. The consolidated results of the post-intervention scenario were systematized in the
|
Indicator |
Route A |
Route B |
|
Lines served |
L4, L5 and L6 |
L1, L2, L3 and partial L7 |
|
Types of supplied parts |
113 |
109 |
|
Packages supplied/day |
149 |
152 |
|
Distance per cycle (m) |
1.050 |
1.004 |
|
Cycles performed per day |
37 |
38 |
|
Total daily time (min) |
1.169 |
1.177 |
|
Daily available time (min) |
1.245 |
1.245 |
|
Saturation (%) |
93,9 |
94,6 |
|
Saturation target (%) |
95 |
95 |
, allowing an integrated analysis of the main operational indicators and the evaluation of the impacts of the implemented improvements.
A
|
Indicator |
Route A |
Route B |
|
Lines served |
L4, L5 and L6 |
L1, L2, L3 and partial L7 |
|
Types of supplied parts |
113 |
109 |
|
Packages supplied/day |
149 |
152 |
|
Distance per cycle (m) |
1.050 |
1.004 |
|
Cycles performed per day |
37 |
38 |
|
Total daily time (min) |
1.169 |
1.177 |
|
Daily available time (min) |
1.245 |
1.245 |
|
Saturation (%) |
93,9 |
94,6 |
|
Saturation target (%) |
95 |
95 |
revealed a significant increase in the utilization level of logistics routes, bringing them closer to the saturation target of 95%. Route A reached 93.9% saturation, while Route B achieved 94.6%. These indices indicate a better use of available capacity and greater operational balance, as discussed by Slack et al. (2018), who emphasize the importance of aligning capacity and demand for the efficiency of production systems. The operational discontinuity of Route C fully released its logistical resources, which became available to absorb the growing demand from new vehicle models.
Route A, in the post-intervention scenario, began to serve lines 4, 5, and 6, incorporating 33 new types of parts and 47 additional packages per day, with a distance traveled of 1,050 meters per cycle and 37 daily cycles, totaling 1,169 minutes of daily time. Route B, in turn, served lines 1, 2, 3, and part of line 7, incorporating 23 new types of parts and 39 additional packages per day, maintaining a distance of 1,004 meters per cycle and performing 38 daily cycles, with a total time of 1,177 minutes. These results demonstrate that the increase in operational load was efficiently absorbed by the remaining routes, without significantly compromising the performance of the displacements.
In summary, the integration of the PDCA cycle with project management tools allowed for substantial optimization of internal logistics routes. A reduction in waste related to movement and overlap of flows, balancing of workload among routes, and a significant increase in the saturation level, approaching the 95% target, were observed. This approach enabled the logistics system to absorb the complexity of new vehicle models and increased demand without the need for additional investments, demonstrating the effectiveness of process reconfiguration and more efficient use of existing resources.
4. Conclusion
The application of the PDCA cycle, integrated with project management tools, proved to be an effective mechanism for optimizing internal logistics routes in an automotive industry, given the growing operational complexity. Waste related to movement, flow overlap, and route imbalance was identified, allowing for the reconfiguration of the logistics system without the need for additional investments. A reduction in operational interferences, a better workload distribution, and a significant increase in route saturation level, approaching the established goal of 95%, were observed. This approach enabled the logistics system to absorb the complexity of new vehicle models and the increase in demand, demonstrating the effectiveness of process reconfiguration and more efficient use of existing resources. The study’s main contribution lies in the practical demonstration of the applicability of this integration in a real industrial environment, proposing a structured model for logistical analysis and intervention that can be replicated in similar contexts, in addition to highlighting the importance of change management and team engagement for the success of operational improvements.
However, the study presented some limitations that should be considered. The analysis was conducted in a single organizational context, which may restrict the generalization of the results to other productive environments. Furthermore, the temporal horizon of evaluation was limited to the initial and post-intervention period, not contemplating long-term analyses that could evidence the sustainability of the implemented improvements. Therefore, for future work, it is recommended to expand the application of the proposed model in different industrial contexts and to conduct longitudinal studies to evaluate the sustainability of improvements over time. It is also suggested to incorporate more advanced quantitative techniques, such as computational simulation and mathematical optimization, to deepen the analysis of logistical efficiency, and to investigate the integration of the model with Industry 4.0 technologies, such as real-time tracking systems and data analysis, in order to enhance the operational gains achieved.
Bibliographic References
Ballou, R. H. (2006). Gerenciamento da cadeia de suprimentos: logística empresarial. 5. ed. Porto Alegre: Bookman.
Carvalho, M. M.; Rabechini Junior, R. (2019). Impactos da gestão de projetos no desempenho organizacional. Revista de Administração Contemporânea, 23(2), 221-241.
Kerzner, H. (2017). Gestão de projetos: as melhores práticas. 3. ed. Porto Alegre: Bookman.
Martins, R. S. (2020).
Novaes, A. G. (2019). Logística e gerenciamento da cadeia de distribuição. 4. ed. Rio de Janeiro: Elsevier.
Oliveira, D.; Silva, A. L.; Ferreira, C. H. (2021). Logística interna e flexibilidade produtiva no setor automotivo brasileiro. Revista Gestão & Produção, 28(1), 1-18.
Pires, S. R. I. (2016). Gestão da cadeia de suprimentos: conceitos, estratégias, práticas e casos. 3. ed. São Paulo: Atlas.
Souza, R. A.; Lima, F. A. (2022). Logística 4.0 e seus impactos na indústria automotiva brasileira. Revista Produção Online, 22(1), 320-345.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq
To learn more about the course, click here and access the MBX Academy platform