Article

October 13, 2026

The use of “Microsoft Project” to identify the critical path of projects and civil works

The Use of “Microsoft Project” to Identify the Critical Path of Civil Projects and Works

Marcos Vinícius de Pinho; Aline Gisele Zanao Benatto

DOI: 10.22167/2675-6528-202603242

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

The growing complexity of ventures and the need for strict adherence to deadlines have made project management and construction management tools essential in contemporary civil construction. Efficient schedule planning and critical activity monitoring are determining factors for success, allowing for risk reduction, resource optimization, and client satisfaction. The study aimed to analyze the application of Microsoft Project software as a support tool for identifying and visualizing the critical path in civil projects and constructions. The research was conducted through two case studies, which involved the analysis of real schedules for an energy substation and a single-family residence. Microsoft Project functionalities were applied to determine activities with no float and evaluate their influence on the total project duration. The results demonstrated that Microsoft Project contributed significantly to efficient schedule management, facilitating decision-making and control of priority activities. The critical path was identified in phases such as earthmoving, foundations, buildings, and finishes in the substation, and in project approval, foundations, masonry, and finishes in the residence, providing greater reliability in meeting deadlines. It was concluded that the use of Microsoft Project, combined with the Critical Path Method, is fundamental for structuring, calculating, and visualizing schedules, improving the clarity of activity logic and supporting decision-making regarding deadlines.

Keywords: Critical path; Civil construction; Construction management; Project management; Microsoft Project.

1. Introduction

Civil construction is one of the most relevant sectors for the socioeconomic development of a country, acting as one of the main indicators of economic activity and a significant generator of employment and income. Due to its dynamic and multiplier nature, the sector’s performance is directly linked to the fluctuations of the macroeconomic environment, being influenced by variables such as interest rates, inflation, public policies for infrastructure investment, and credit availability. The impact of civil construction extends to various areas of society, being considered a thermometer of a nation’s development (Costa and Santos, 2023). In periods of economic instability, efficiency in project management becomes even more essential to ensure the competitiveness and sustainability of companies in the sector.

In this context, data from the Brazilian Chamber of the Construction Industry (CBIC, 2020) show that delays and budget overruns are recurring problems, generating losses for both companies and clients. Project management therefore assumes a strategic role, as it allows for rigorous control of deadlines, costs, resources, and quality of the ventures.

Among the most used tools in engineering venture management, Microsoft Project stands out, a software widely recognized for its ability to plan, monitor, and control the execution stages of a project. One of the most relevant functionalities of this tool is the visualization of the critical path, which makes it possible to identify the activities that determine compliance with the schedule and, consequently, the success of the project.

The Critical Path is defined as the set of interdependent activities of a project that have no float, meaning any delay in one of them directly impacts the total duration of the undertaking. This technique is widely used in schedule planning and control, as it allows for the identification of activities that require closer monitoring throughout execution (Project Management Institute [PMI], 2021). An activity is considered critical when the earliest start time is equal to the latest time it can be performed without altering the project’s completion date. These parameters are determined from the Activity on Nodes (AON) Network Diagram, a tool that graphically represents the logical sequence and interdependencies between tasks (Kerzner, 2022).

According to Vargas (2023), the critical path corresponds to the sequence of activities that must be performed according to the planned schedule, ensuring that the project is completed within the stipulated deadline. Understanding the critical path is fundamental for efficient schedule management, as it allows the identification of activities with and without flexibility. The Critical Path Method (CPM) is widely used in project management, especially in civil construction, due to its efficiency in planning, controlling, and optimizing deadlines. Developed in the late 1950s by Morgan R. Walker and James E. Kelley, the method remains one of the most effective tools for identifying critical activities, minimizing delays, and ensuring compliance with schedules in large-scale projects (Silva and Andrade, 2022).

The correct identification and monitoring of the critical path allow managers to make assertive decisions regarding resource allocation, risk mitigation, and activity prioritization, avoiding delays and waste. Thus, the use of Microsoft Project not only contributes to the technical-operational control of the ventures but also aligns with macroeconomic demands for greater productivity, efficiency, and transparency in the use of available resources. Therefore, this work aims to analyze the importance of using Microsoft Project in managing construction project schedules, with an emphasis on critical path visualization, considering the impact of macroeconomic conditions on project execution and performance. It therefore seeks to demonstrate how the adoption of technological planning tools can strengthen the competitiveness of companies in the sector in an increasingly challenging economic scenario.

2. Material and Methods

This research was conducted using the case study method, an investigation strategy that, according to Yin (2015), allows for an in-depth analysis of a contemporary phenomenon in its real context, especially when the boundaries between the phenomenon and the context are not clearly defined. For Gil (2019), the case study consists of a research procedure that involves the detailed and exhaustive examination of one or a few objects, in order to allow for their broad and in-depth knowledge.

The case study was developed from the creation of schedules used in civil works projects, including the construction of an energy substation and a single-family residence. Both projects were located in Ipatinga, Minas Gerais. These ventures were selected because they represent medium-sized works, involving recurring challenges related to planning, critical path identification, resource allocation, and schedule management.

Data collection was carried out through the practical analysis of schedules in Microsoft Project software. The Critical Path Method (CPM) was used to identify the activities of greatest relevance and priority in civil works planning, according to the guidelines of the Project Management Institute (PMI, 2021). This approach enabled the practical analysis of the application of the tool and project management techniques.

Microsoft Project was used to model the civil construction project schedules, allowing for the practical application of CPM. This software is widely recognized for its ability to plan, monitor, and control the execution stages of a project, being an indispensable tool for planning professionals (Microsoft, 2023; Vargas, 2023). The tool offers simulation and dependency analysis features.

The scheduling modeling began with the insertion of activities according to the Work Breakdown Structure (WBS) of each project. The WBS for the power substation was organized into eight work packages, while that for the single-family residence was structured into three main packages, which included project approval, procurement, and construction execution. This hierarchical structuring allowed for scope control, definition of responsibilities, and deadline planning, as recommended by PMI (2021).

After defining the activities, durations were assigned based on real planning data and practical experience, respecting the executive characteristics of each type of work. Subsequently, precedence relationships between activities were established, prioritizing finish-to-start (FS) and start-to-start (SS) links, to represent the constructive logic of the projects. Lag times were also inserted into specific activities, such as concrete curing periods, to ensure greater adherence of the schedule to field reality.

After consolidating this information, Microsoft Project automatically calculated the schedule, allowing the identification of the Critical Path through the application of the CPM method. CPM is based on the construction of a logical network of activities, establishing precedence relationships between tasks. From this network, the earliest start, earliest finish, latest start, and latest finish of each activity were calculated, allowing the determination of total and free floats (PMI, 2019; Kerzner, 2022).

The Critical Path visualization was performed using the Gantt chart, where critical activities were highlighted, indicating the absence of total float. The software enabled the logical organization of activities through the definition of tasks, durations, predecessors, successors, milestones, and resources. The tool integrated time, resources, and costs, providing subsidies for decision-making in project management (Microsoft; Vargas, 2023).

The display of the Critical Path in Microsoft Project followed steps such as defining activities, establishing dependencies, assigning durations and resources, automatic schedule calculation, and visualization in the “View” > “Gantt Chart” > “Format” > “Critical Path” tab. The application of CPM through the software made the analyses dynamic, with automatic recalculation of the critical path and activity floats with each change.

Thus, the use of Microsoft Project associated with CPM demonstrated how classic time management techniques can contribute to more efficient planning and adequate prioritization of activities in civil works. The methodological focus was on demonstrating the software’s functionalities for structuring and analyzing schedules, without comparing different types of work.

3. Results and Discussion

The analysis of the application of Microsoft Project as a tool to support the identification and visualization of the critical path in civil projects and works revealed significant findings in two distinct case studies. The results demonstrate the software’s ability to structure complex schedules, identify critical activities, and provide subsidies for decision-making, aligning with project management principles. The research highlighted how schedule modeling, the definition of precedences, and the automatic calculation of the critical path contribute to more robust planning and more efficient deadline control in civil construction ventures, as advocated by the Project Management Institute (PMI, 2021).

In the first case study, concerning the construction of a power substation in Ipatinga, Minas Gerais, the schedule totaled 316 days, distributed across 46 activities organized into eight major phases. The detailed modeling in Microsoft Project allowed for a hierarchical organization of activities, with clearly established durations and precedence relationships. This structuring is fundamental for planning consistency and effective control of the work’s deadlines, facilitating scope understanding and responsibility definition, as highlighted by Kerzner (2022).

The identification of the critical path in the substation revealed that activities with no float concentrate on the stages of earthworks, foundations, buildings, finishes, and demobilization and handover of the work. These activities, by having a total float equal to zero, indicate that any delay in their execution would directly impact the project’s completion date. The visualization of predecessors and the Gantt chart in the software was crucial for understanding the logical sequence of activities and identifying the schedule segments with less flexibility, directing the planning focus to tasks that require greater monitoring.

The Work Breakdown Structure (WBS) of the SE Ipatinga Substation, which totaled 316 days, was decomposed into work packages such as mobilization (53 days), earthworks (68 days), foundations (39 days), buildings (79 days), drainage (16 days), paving and accesses (22 days), finishes (39 days), and demobilization and handover (38 days). The building and earthworks phases, with 79 and 68 days respectively, were the most representative in terms of duration, suggesting a greater potential impact on the overall project schedule. This hierarchical decomposition reflects the executive logic of civil works, facilitating the modeling of precedence relationships in the schedule.

Among the activities that make up the substation’s critical path, earthwork (cut and fill), slope stabilization, foundation excavation and concreting, masonry and roofing execution, as well as final finishing and technical handover services stood out. The observation that these activities directly influence the total project duration reinforces the importance of correctly defining dependencies and rigorous monitoring throughout the construction execution. The existence of sections with limited parallelism was also verified, which restricts the possibilities of rescheduling without impacting the overall deadline, a common characteristic in technically more complex undertakings due to physical and operational constraints.

In the second case study, which analyzed the construction of a single-family residence, the schedule presented a total duration of 218 days, structured into three major work packages: project approval, supplies, and construction execution. Modeling in Microsoft Project allowed for the organization of these stages, definition of their dependencies, and automatic calculation of the schedule dates. The residence’s WBS (Work Breakdown Structure), with a duration of 218 days, was subdivided into project approval (156 days), supplies (15 days), and construction (167 days), with project approval at the city hall being a 90-day activity, standing out for its significant duration and impact on the overall deadline.

The analysis of the single-family housing schedule indicated that the main critical path activities were related to the development and approval of projects, foundations, masonry, finishes, and project delivery. Scenario simulations in Microsoft Project practically demonstrated that delays in critical path activities directly impact the project’s final date, while delays in activities with float do not alter the overall deadline. This finding corroborates the theoretical concept of the Critical Path Method (CPM), which establishes that only critical tasks determine the total duration of the undertaking (PMI, 2021; Vargas, 2023; Kerzner, 2022).

A distinctive aspect of the single-family home project was the classification of all activities as belonging to the Critical Path, resulting in an entirely critical schedule. This means that any delay, regardless of its nature or magnitude, would directly impact the project’s final deadline, as all activities had zero total float. This behavior stems mainly from the logical structure adopted in the schedule modeling, with a predominance of finish-to-start (FS) precedence relationships and a significant absence of links that allow parallelism, such as start-to-start (SS).

The predominance of finish-to-start (FS) relationships and the scarcity of start-to-start (SS) relationships have established a network of essentially sequential activities, where the start of each task is rigidly conditioned by the completion of its predecessor. This configuration eliminates the possibilities of activity overlap and, consequently, the generation of float. Additionally, the very constructive nature of residential construction, which tends to follow a linear logic, especially in the structural and finishing stages, contributes to the formation of a continuous chain of critical activities, limiting schedule flexibility.

Another factor that contributed to the total criticality of the residency schedule was the project approval stage. Its long duration and dependence on external agents introduce a significant temporal constraint right at the beginning of the schedule. As it is a predecessor activity to practically all executive stages, its insertion into the logical chain reinforces the critical nature of the planning, since any delays cannot be absorbed by non-existent float. From a managerial point of view, a totally critical schedule represents a scenario of high rigidity and high sensitivity to uncertainties, requiring integral monitoring of all tasks and increasing exposure to delay risks.

In a comparative analysis, the behavior of the residence schedule differs substantially from that observed in the substation project. While the substation presented a more distributed Critical Path, with activities endowed with float and greater reprogramming flexibility, the residence, although simpler, exhibited an excessively sequential logic and a more rigid schedule. This contrast highlights that schedule criticality is not necessarily associated with the complexity of the undertaking, but rather with the way its precedence network is structured and modeled.

The results obtained in both case studies demonstrate that the use of Microsoft Project, combined with CPM, allows not only the visualization of activities determining the deadline but also a more robust managerial analysis. The software transforms the activity structure and its logical relationships into visual and calculated information, allowing the identification of the critical path, analysis of float, and simulation of impacts from schedule changes. This capability reinforces the tool’s role in supporting deadline management, without replacing the technical analysis and planner’s knowledge.

The reliability of the results obtained in a schedule is directly related to the quality of the definition of dependencies between activities, as pointed out by PMI (2019) and Kerzner (2022). The earliest and latest start and finish parameters are calculated from the logical network formed by the predecessors, which means that the Critical Path is determined not only by task durations, but, mainly, by the established precedence structure. The planner’s role is decisive in translating the project’s constructive logic into technical links within the software, ensuring the accuracy of float calculations and the correct identification of critical activities.

Microsoft Project offers essential functionalities for building, tracking, and controlling the schedule, such as the main tab, which organizes sections like “Tasks”, for inserting and linking activities; “Resources”, for registering and managing labor, equipment, and materials; “Project”, for general schedule configurations; “Reports”, for generating management charts; and “Format”, for visual customization. These sections allow planning techniques, such as activity sequencing and critical path calculation, to be performed in a structured and intuitive manner (Microsoft, 2023).

The Task, Duration, Start, and Finish fields form the basis for schedule modeling in Microsoft Project. The Task field describes activities, Duration estimates the time required, and the Start and Finish fields are calculated automatically based on durations and predecessor relationships. This interaction demonstrates the practical application of time planning concepts, allowing visualization of the impact of dependencies and identification of critical activities, highlighting how the tool operationalizes the theoretical principles of project time management (PMI, 2019).

The correct modeling of predecessors is crucial for the Critical Path identified by Microsoft Project to reflect the reality of the undertaking. The software allows configuring four main types of relationships between activities: Finish-Start (FS), Start-Start (SS), Finish-Finish (FF), and Start-Finish (SF). In civil works practice, FS and SS relationships predominate, representing mandatory construction sequences and parallel activities. The adequate use of these relationships strengthens planning reliability and enhances the manager’s ability to anticipate the impacts of delays and optimize resource allocation throughout the project.

The Gantt chart, a widely used graphical tool, allows for the simultaneous visualization of the task list and its distribution over time, highlighting start and end dates, durations, and dependency relationships. Microsoft Project automatically highlights critical path activities, usually in a different color, allowing the planner to immediately identify tasks that directly impact the project’s final deadline. This functionality is essential for continuous execution monitoring, enabling progress updates and corrective decision-making when necessary (PMI, 2019).

To calculate and visualize the Critical Path in Microsoft Project, the steps include defining activities with their durations and descriptions, establishing dependencies according to the execution logic, assigning resources, automatic schedule calculation by the software, and displaying the Critical Path on the Gantt chart, usually in red. Furthermore, analyzing float, by enabling the “Total Float” column, helps identify potential schedule adjustments, confirming that the software enhances the process but does not replace the planner’s technical knowledge for project modeling.

In summary, the application of Microsoft Project, together with the Critical Path Method, proved to be an indispensable tool for efficient schedule management in civil construction. The ability to structure, calculate, and visualize activities and their interdependencies provides greater clarity of the activity logic, facilitates the identification of the critical path, and supports decision-making regarding deadlines. The results suggest that the judicious introduction of parallelism, when technically feasible, can contribute to increased planning flexibility, reduced overall criticality, and improved deadline management capacity in civil works, strengthening the competitiveness of companies in the sector.

4. Conclusion

The study aimed to analyze the application of Microsoft Project software as a tool to support the identification and visualization of the critical path in civil projects and works. It was found that the software contributed significantly to efficient schedule management, facilitating decision-making and the control of priority activities. In the case studies, the critical path was identified in phases such as earthmoving, foundations, buildings, and finishes in the power substation, and in project approval, foundations, masonry, and finishes in the single-family residence. It was observed that Microsoft Project transforms the activity structure and its logical relationships into visual and calculated information, allowing for robust managerial analysis. The reliability of the obtained results demonstrated the importance of the correct definition of dependencies between activities by the planner, showing that schedule criticality is intrinsically linked to its logical structure. The main contribution of the study lies in demonstrating how the use of Microsoft Project, combined with the Critical Path Method, is fundamental for structuring, calculating, and visualizing schedules, improving the clarity of activity logic and supporting decision-making regarding deadlines, which strengthens the competitiveness of companies in the sector.

As a limitation, the work was developed from two specific case studies, focusing on the functionalities of Microsoft Project related to planning and the critical path. The results, therefore, should be interpreted as evidence applied to the analyzed cases, without any claim of generalization to all types of ventures. For future work, it is recommended to expand the application of the software to other ventures and to specifically explore additional functionalities for resources, costs, reports, and integration with other project management tools. The judicious introduction of parallelism, when technically feasible, can contribute to increasing planning flexibility, reducing overall criticality, and improving the ability to manage deadlines in civil construction projects.

Bibliographic References

Costa, G. S.; Santos, B. A. M. L. 2023. A importância do planejamento de obras visando a demanda de construções residenciais no município de Maricá (RJ). Revista Boletim do Gerenciamento.

Câmara Brasileira da Indústria da Construção [CBIC]. 2020. Estudos sobre atrasos e impactos financeiros em obras de construção civil. Brasília: CBIC.

Gil, A. C. 2019. Métodos e técnicas de pesquisa social. 7. ed. São Paulo: Atlas.

Kerzner, H. 2022. Project Management: A Systems approach to planning, Scheduling, and Controlling. 13. ed. Hoboken: Wiley.

Microsoft. 2026. Microsoft Project documentation. Microsoft Learn, 2023. Disponível em: https://learn.microsoft.com/project. Acesso em: 09 fev.

Project Management Institute [PMI]. 2019. Practice standard for scheduling. 3. ed. Newtown Square: PMI.

Project Management Institute [PMI]. 2021. A guide to the project management body of knowledge (PMBOK® Guide). 7. ed. Newtown Square: PMI.

Silva, R. F.; Andrade, L. P. 2022. Aplicação do Método do Caminho Crítico no gerenciamento de projetos da construção civil. Revista Brasileira de Engenharia e Gestão de Projetos, v. 14, n. 2, p. 45-59.

Vargas, R. V. 2023. Manual prático do plano de projeto: utilizando o PMBOK® Guide. 12. ed. Rio de Janeiro: Brasport.

Yin, R. K. 2015. Estudo de caso: planejamento e métodos. 5. ed. Porto Alegre: Bookman.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.