Agile Methodologies in Cost Management: a study in commercial projects
Agile Methodologies in Cost Management: a Study in Commercial Projects
Tábata Thereza Correa de Souza; Jonatas de Oliveira
DOI: 10.22167/2675-6528-202603475
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The construction sector, especially in the commercial construction segment, has experienced significant growth in Brazil, driven by the demand for modern and flexible spaces. In this context, cost management has emerged as a strategic factor, given that delays and poorly controlled budgets can compromise the profitability and credibility of companies. The application of agile methodologies in the cost management of commercial projects was investigated, seeking to understand their benefits and challenges compared to traditional practices. The research was characterized as a descriptive case study, employing mixed methods with qualitative and quantitative data. Information collection included field observations, document analysis, and budget data surveys, following Yin’s (2015) recommendations for evidence triangulation. The results showed that the use of agile practices, such as Scrum and Kanban, provided greater transparency in monitoring construction stages, facilitated cost forecasting and control, and enabled incremental deliveries aligned with client expectations. An overall saving of 3.1% compared to the initial budget was observed. Frequent meetings contributed to faster decision-making and reduced risks and waste. It was concluded that the adoption of agile methodologies in cost management represents a relevant advancement for the construction industry, promoting efficiency, flexibility, and competitiveness.
Keywords: Civil construction; Cost control; Project management; Kanban; Scrum.
1. Introduction
The civil construction industry plays a fundamental role in economic and social development, driving related sectors such as commerce and services. In recent years, the commercial construction market in Brazil has experienced consistent growth, motivated by the demand for modern and flexible spaces. In 2022, the civil construction sector reached a spending of R$ 439 billion, with a growth of approximately 16%, according to the Annual Construction Industry Survey (Nakamura, 2024). This scenario was corroborated by the economic recovery, with the Brazilian Gross Domestic Product growing 3.4% in 2024 and the retail sector registering an increase of 4.7% (Pati, 2025).
Despite this promising scenario, the execution of commercial works presents complex challenges, especially in cost management. Poorly controlled budgets, unforeseen execution issues, and delays can compromise the profitability of companies and their credibility with clients and investors. In this context, cost management transcends the technical sphere and assumes a strategic role, crucial for the viability and success of the ventures.
Faced with this reality, the need arises to investigate innovative approaches to optimize cost management in commercial projects. Traditionally, civil construction has been guided by management methodologies based on rigid and sequential planning, known as traditional practices. Although structured, these approaches often demonstrate limitations in contexts that demand speed of execution, high adaptability, and incremental deliveries.
In this sense, agile methodologies emerge as a promising alternative. Originating in the technology sector, they are based on principles such as flexibility, continuous adaptation, and team collaboration (Beck et al., 2001). The use of short development cycles, progressive value delivery, and constant focus on customer satisfaction are practices that, when transposed to civil construction, can contribute to greater financial predictability, waste reduction, and better resource allocation. However, despite their widespread diffusion in other areas, the application of agile methodologies in civil construction, especially in cost management, is still incipient and lacks studies that evaluate their real effectiveness.
Within the spectrum of agile methodologies, this study specifically addresses Scrum and Kanban. Scrum, with its iterative and incremental structure, is supported by three pillars of transparency, inspection, and continuous adaptation, aiming for more dynamic cost control (Schwaber and Sutherland, 2017). Kanban, in turn, emphasizes the visualization of work in progress, optimizing flow and productivity through visual boards, which consist of at least three columns, allowing for early identification of bottlenecks and more efficient resource management (Anderson, 2011). These approaches, combined with the strategy of incremental deliveries and the concept of Minimum Viable Product (Ries, 2011), offer a framework for more adaptive cost management that is responsive to the inherent changes in commercial projects.
The problematic that guides this study is: in what way can the adoption of agile methodologies contribute to more efficient cost management in commercial construction projects, considering the specific challenges of this segment? The relevance of the research lies in filling this gap, deepening the knowledge about the application of agile methodologies in a sector that traditionally uses distinct approaches, contributing to academic advancement and the improvement of professional practices in commercial project management. In this context, the central objective of this research is to identify the benefits and challenges of applying agile methodologies in the cost management of commercial projects, using a case study as a means of investigation to analyze the comparative financial performance between traditional and agile practices. It is intended to demonstrate how the flexibility and adaptability of agile practices can contribute to more efficient cost control and greater profitability of the undertaking.
2. Material and Methods
The research was characterized as descriptive, according to the definition by Lakatos and Marconi (2003), who conceptualize it as a study that aims to observe, record, and analyze the characteristics of a phenomenon or establish relationships between variables. In this sense, the study sought to describe the management process of a commercial work, from the conception and approval of the project to the delivery of the undertaking, analyzing how agile methodologies could be adapted and implemented to optimize financial control, resource allocation, and decision-making in projects with short execution times and limited resources.
The nature of the data was classified as mixed methods, which, according to Creswell and Clark (2013), represents a procedure for collecting, analyzing, and combining quantitative and qualitative techniques in the same research design. The central assumption of this approach is that the integration of different methods can provide a more comprehensive and robust understanding of the phenomenon studied than the use of a single approach.
On the qualitative side, the data consisted of field observations, analysis of organizational charts and timelines, as well as document analysis. In the quantitative method, numerical data were used, obtained through budget spreadsheets. These data were employed for descriptive statistical analyses, allowing the identification of particularities and trends (Gil, 2002; Hair Jr. et al., 2009).
The present research adopted, regarding its design, the case study, a methodological approach suitable for investigating contemporary phenomena in their real context, especially when the boundaries between the phenomenon and the context are not clearly evident (Yin, 2018). The case in focus was the integral monitoring of a specific commercial work, from the project conception phase, through the analysis and approval process with the competent bodies, monitoring of the work, and delivery of the undertaking.
The choice of this design was justified by the need for an in-depth and holistic understanding of the management and execution process of civil construction projects, capturing the complexity of the interactions, decisions, and challenges inherent in each stage. By focusing on a single undertaking, the ‘hows’ and ‘whys’ of events and decisions were detailed, exploring the particularities that manifest in the real construction environment, as advocated by Yin (2018) for the validity and relevance of case studies.
Data collection was carried out through multiple sources of evidence, seeking to ensure greater depth and reliability for the analyses. Documentary records from the company were used, such as budget spreadsheets, organizational charts, and project schedules, in addition to direct field observation during the project execution stages. Additionally, technical documents related to planning and cost management were analyzed. This strategy of using different collection mechanisms aligns with Yin’s (2015) recommendations for evidence triangulation.
The case study addressed considered the execution of a complete work of a commercial space located in a shopping mall in the city of São José dos Campos, São Paulo countryside. The company responsible for the work was a local construction company, specialized in the retail sector, acting in the construction, renovation, and adaptation of stores, kiosks, restaurants, and corporate spaces. The company emerged in 2013, offering the service of construction management for new store owners and shopping mall entrepreneurs.
For the project that was the object of this study, the construction company was hired to develop the architectural design and the complementary projects for a home goods store (bedding, bath, and table), approximately 90m². The construction company was also responsible for executing the construction management, with the obligation to deliver the complete space. The workflow began with an alignment meeting between the designer and the clients, where expectations, standards, stages, and delivery deadlines were defined. The project development phase lasted about 45 days for development and approval.
Based on traditional cost management methodologies, a budget spreadsheet was developed for project planning and cost forecasting. In this phase, cost management was detailed according to traditional practices, based on the construction budget spreadsheet provided by the construction company responsible for execution. Fixed and variable costs were identified, along with contingencies and unforeseen expenses, in accordance with the development of a detailed project and a thorough budget that included materials, labor, equipment, and incidental expenses.
In parallel with the detailed breakdown of the construction budget spreadsheet, a detailed physical construction schedule was developed for visualizing all execution stages. The creation of a physical construction schedule is a practice intrinsically linked to the traditional project management methodology, characterized by detailed and sequential planning, where each project phase is completed before the next begins. The plan foresaw completion within a 60-day timeframe, corresponding to approximately nine weeks.
Completing the planning stage, the implementation of agile methodologies in the project’s daily routine was scheduled. Agile methodologies emerged from the Agile Manifesto, conceived in 2001 by a group of 17 software developers with the aim of finding better ways to manage and develop systems (Beck et al., 2001). Within the spectrum of agile methodologies, this study specifically addressed Scrum and Kanban.
The “Scrum framework” is supported by a structure composed of three fundamental pillars: roles, events, and artifacts, which work together to ensure project transparency and adaptation (Schwaber and Sutherland, 2017). For the practical application of the “Scrum framework” in this case study, the roles were distributed according to technical competencies and responsibilities in the commercial construction. The “Product Owner” was assumed by the responsible engineer, the “Scrum Master” was assigned to the site supervisor, and the “Scrum Team” (Developers) was composed of field professionals (masons, electricians, painters), who self-organized for the delivery of increments in each “Sprint”.
Kanban, in turn, is a change management method that emphasizes the visualization of work in progress, optimizing workflow and productivity (Anderson, 2011). In the context of the work, the Kanban methodology was implemented through the visualization of work in progress on boards, which allowed teams to understand the status of their work. The visual representation of the workflow was done through a Kanban board, which consisted of at least three columns: “To Do”, “In Progress”, and “Done”. Tasks were represented by cards that moved from left to right, reflecting their progress.
Beyond columns and cards, effective Kanban boards incorporated principles such as work-in-progress limits, flow management, and explicit policies. The number of tasks allowed in the “In Progress” column was limited, forcing the team to focus on finishing tasks before starting new ones, aiming to avoid overload and improve quality. Flow management focused on ensuring tasks flowed smoothly, making bottlenecks visible for team collaboration. Rules about how and when tasks could be moved between columns were defined and visible to everyone.
Still within the context of implementing agile methodologies, the construction planning included dividing the project into small value deliveries, based on the premise that complexity and uncertainty are inherent to any project. By dividing the work into manageable parts, teams could deal with uncertainties more effectively. The incremental delivery strategy allowed teams to build and validate the product in smaller, functional parts, accelerating the return on investment and reducing the risk of building something that did not meet user needs, linked to the concept of Minimum Viable Product (Ries, 2011).
In this sense, the work was segmented into four phases, treated as distinct “Sprints”, each with its own planning and review, where the increment was the delivery of value promised at the end of each period. Phase 1 consisted of structural adjustments, including demolition and cabling and duct infrastructure. Phase 2 involved the completion of the infrastructure, with the installation of all structural, electrical, air conditioning, and fire fighting components. Phase 3 comprised the finishes, such as wall and ceiling closures, screed, installation of coatings, and painting. Phase 4 focused on equipment installation, including lighting fixtures, outlets, switches, air conditioning units, carpentry, and visual communication. With the division of the project into phases, the “Product Owner” defined the priority of each phase.
Finally, another planned practice was the realization of daily meetings, known in agile methodology as “Daily Scrum”. The “Daily Scrum” is a 15-minute meeting for the development team to inspect progress toward the “Sprint” Goal and adapt the plan for the next 24 hours (Schwaber and Sutherland, 2017). The execution of these meetings was the responsibility of the Scrum Master, who identified and resolved impediments quickly, preventing small problems from becoming major delays and costs. Retrospectives at the end of each “sprint” were also proposed, allowing the team to analyze what worked and identify opportunities for improvement.
In this way, the outlined methodological structure allowed for the collection of quantitative and qualitative data throughout the entire executive schedule. The application of Scrum roles and ceremonies, combined with Kanban’s visual control, provided the necessary inputs for a comparative analysis between the initial planning and the actual execution. The collected data were organized to enable the evaluation of the performance of each of the four phases of the work and the impact of agile practices on risk mitigation and the optimization of the project’s operational costs.
3. Results and Discussion
The results presented below evaluate the impact of applying Scrum and Kanban methodologies in the cost management of a commercial retail construction project. The analysis was based on a comparison between traditional budgetary planning and agile execution, using data collected through direct observation, analysis of measurement spreadsheets, and team productivity records. Initially, the project was structured based on a traditional planning approach, represented by a detailed budgetary spreadsheet, which projected a total cost of R$ 655,178.75. This model provided a comprehensive estimate of the necessary investment; however, in practice, its rigidity limited the ability to adapt to unforeseen events, such as variations in input prices, scope adjustments, and operational interferences. This limitation compromised financial predictability throughout the execution, as the traditional model tends to identify deviations only in more advanced stages of the work, hindering efficient corrective actions.
The transition to the agile approach promoted a significant change in the way of cost management, which began to be treated dynamically and continuously. The division of the project into four phases, structured as “sprints”, enabled short cycles of planning, execution, and review, allowing financial control to keep pace with the physical progress of the work in real time. This structure favored the early identification of deviations and the implementation of immediate adjustments, reducing the cumulative impact of errors throughout the project. This approach aligns with the principles of the Agile Manifesto, which values continuous adaptation and rapid response to change, as highlighted by Beck et al. (2001).
In this context, the use of Kanban proved fundamental for workflow management. The visualization of ongoing activities provided greater operational transparency, allowing for rapid identification of bottlenecks and more efficient task redistribution. This clarity contributed not only to team organization but also to the reduction of indirect costs related to labor idleness and resource misallocation, corroborating the principles of visual management and flow optimization described by Anderson (2011). The Kanban board, with its “To Do”, “In Progress”, and “Done” columns, allowed the Product Owner to track physical and financial progress, the Scrum Master to identify bottlenecks, and the Team to move cards as the work evolved.
In parallel, the adoption of the “Daily Scrum” directly influenced execution efficiency. Despite their short duration, these meetings enabled the immediate identification of impediments, promoting agile resolution of operational problems. As a consequence, a reduction in rework and delays was observed, factors frequently associated with increased construction costs. This result reinforces the importance of continuous communication and frequent inspection as control mechanisms, as proposed by Schwaber and Sutherland (2017). Retrospectives at the end of each “sprint” were also proposed, allowing the team to analyze what worked and identify opportunities for improvement, contributing to continuous learning.
The incremental delivery of phases also stood out as a determining factor for the project’s financial performance. By validating critical stages, such as infrastructure, in advance, it was possible to mitigate technical risks that, in traditional models, are usually identified only in later stages, when correction costs are significantly higher. Thus, the incremental approach acted as a preventive mechanism, contributing directly to the reduction of waste and the optimization of resource use. This strategy is directly linked to the concept of Minimum Viable Product (MVP), which allows for collecting the maximum validated learning with the minimum effort, according to Ries (2011).
The quantitative data evidenced the positive effects of this approach. A global saving of 3.1% was observed in relation to the initial budget of R$ 655,178.75, resulting in a saving of R$ 20,228.75. This financial performance was superior to that predicted by traditional planning, indicating the effectiveness of agile management in cost optimization. The phase-by-phase analysis revealed distinct but consistently positive behaviors, reinforcing the adaptability and control provided by Agile methodologies at each project stage.
The first phase, named Adequations, which involved the demolition of the existing structure and the cabling and duct infrastructure, showed a saving of 3.0%. The budgeted cost for this phase was R$ 68,428.00, while the actual cost was R$ 66,350.00. This result was associated with better coordination of demolition activities and optimization of equipment use. Daily meetings contributed to more efficient planning, reducing costs for dumpster rental and avoiding operational waste, validating the structure for the next stages.
In the second phase, focused on the Infrastructure Conclusion, which included the installation of all structural, electrical, air conditioning, and fire fighting components, the savings were 2.3%. The budgeted cost was R$ 214,373.25, and the actual cost reached R$ 209,500.00. This saving can be attributed to stricter control during the execution of the installations, combined with the possibility of real-time adjustments. The visibility provided by Kanban allowed for greater control over task progress, avoiding overlaps and rework, and enabling earlier operational tests.
The third phase, related to Finishes, which included wall and ceiling closures, screed, coatings, and painting, presented the highest percentage of savings, reaching 4.8%. The budgeted cost for this stage was R$ 89,937.50, and the actual cost was R$ 85,600.00. This superior financial performance is directly related to the early validation carried out in the previous phase, which significantly reduced the need for rework. As a consequence, there was lower consumption of materials, especially paints and coatings, evidencing the positive impact of the integration between project phases and aesthetic validation.
Finally, the fourth phase, of Equipment, which included the installation of lighting fixtures, outlets, switches, air conditioning equipment, carpentry, and visual communication, registered a saving of 3.2%. The budgeted cost was R$ 282,440.00, and the actual cost was R$ 273,500.00. This saving was mainly associated with more efficient inventory control and better scheduling of final installations. The agile approach helped to avoid both material shortages, which could cause delays, and over-purchasing, reducing storage costs and losses, culminating in the final project inspection.
Beyond the quantitative results, relevant qualitative benefits were observed. The improvement in decision-making stands out, which became more agile and based on updated data, as well as the increase in transparency in the management process. Continuous visualization of the physical-financial progress allowed for greater alignment between the team and the client, raising the level of trust and satisfaction with the project’s progress. This constant communication and focus on delivering value contributed to a more collaborative and productive work environment.
Comparatively, while the traditional model presented limitations in adapting to changes, the agile approach demonstrated a greater capacity to respond to unforeseen events. This difference was directly reflected in financial predictability, as the agile model allowed for continuous adjustments throughout execution, reducing uncertainties and avoiding significant deviations in the final cost. The results obtained corroborate the principles of empiricism that underpin Scrum, especially regarding transparency, inspection, and continuous adaptation (Schwaber and Sutherland, 2017). Similarly, they reinforce the foundations of Kanban related to workflow management and bottleneck identification (Anderson, 2011).
In an integrated manner, the results demonstrate that the main contribution of agile methodologies is not limited to the percentage reduction of costs, but lies in the transformation of the logic of financial management. Cost control ceases to be a static and reactive process, becoming dynamic, predictive, and adaptive. This change represents a relevant competitive differential for commercial projects, in which adaptability is a critical success factor. The flexibility and adaptability of agile practices contributed to more efficient cost control and greater profitability of the venture, according to the central objective of this research.
Despite the positive results, some limitations should be considered. As this is a single case study, the findings cannot be generalized to all contexts of civil construction. Furthermore, part of the analyses was based on qualitative observations, which may introduce subjectivity in data interpretation. It should also be noted that the application of agile methodologies occurred in a small-sized team, which may have facilitated its implementation. In larger-scale projects, additional challenges may arise, demanding adaptations in the application of these practices, which suggests the need for future studies in different contexts.
In summary, the application of agile methodologies, such as Scrum and Kanban, in the cost management of commercial projects has proven to be an effective alternative for optimizing financial performance. The division of the project into incremental deliveries, the visualization of the workflow, and daily meetings contributed to greater transparency, predictability, and adaptability, resulting in overall savings of 3.1% and significant qualitative benefits, such as improved decision-making and client alignment, responding to the objective of identifying the benefits and challenges of these approaches.
4. Conclusion
This study sought to identify the benefits and challenges of applying agile methodologies in the cost management of commercial projects, comparatively analyzing financial performance between traditional and agile practices. It was found that the agile approach, through Scrum and Kanban, promoted dynamic and continuous cost management, overcoming the rigidity of traditional methodologies. The division of the project into incremental deliveries, structured as “sprints”, enabled early identification of deviations and immediate adjustments. It was observed that the use of Kanban provided greater operational transparency and workflow optimization, while daily Scrum meetings contributed to agile problem-solving and rework reduction. These elements resulted in overall savings of 3.1% compared to the initial budget, in addition to qualitative benefits such as improved decision-making and increased transparency and alignment with the client. The main contribution lies in the transformation of the financial management logic, which became predictive and adaptive, conferring a relevant competitive advantage for the civil construction sector.
Despite the positive results, some limitations were identified. As it is a single case study, the findings cannot be generalized to all contexts of civil construction. Additionally, the qualitative nature of some observations may introduce subjectivity in data interpretation. It should be noted that the application of agile methodologies occurred in a small-sized team, which may have facilitated its implementation. For future studies, it is suggested to investigate the application of these practices in larger-scale projects and in different types of works, in order to deepen the understanding of the additional challenges and adaptations necessary for their effectiveness in more complex contexts.
Bibliographic References
Anderson, D.J. 2011. Kanban: Mudança Evolucionaria de Sucesso Para Seu Negócio de Tecnologia: Mudança Evolucionária de Sucesso para seu Negócio de Tecnologia. Blue Hole Press.
Beck, K; Beedle, M; Bennekum, A.V; Cockburn, A; Cunningham, W; Fowler, M; Grenning, J; Highsmith, J; Hunt, A; Jeffries, R; Kern, J; Marick, B; Martin, R. C; Mellor, S; Schwaber, K; Sutherland, J; Thomas, D. 2001. Manifesto para Desenvolvimento Ágil de Software. Disponível em: <http://agilemanifesto.org/iso/ptbr/manifesto.html>. Acesso em: 07 maio 2025.
Creswell, J.W.; Plano Clark, V.L. 2013. Pesquisa de Métodos Mistos. 2ed. Penso, Porto Alegre, RS, Brasil.
Gil, A.C. 2002. Como elaborar projetos de pesquisa. 4ed. Atlas, São Paulo, SP, Brasil
Hair Jr., J.F.; Black, W.C.; Babin, B.J.; Anderson, R.E.; Tatham, R.L. 2009. Análise multivariada de dados. 6. ed. Porto Alegre: Bookman.
Lakatos, E.M.; Marconi, M.A. 2003. Fundamentos de metodologia científica. Atlas. 5. ed. São Paulo, Brasil.
Nakamura, J. 2024. Brasil investiu R$ 439 bilhões em obras em 2022, alta de 16%, aponta IBGE. Disponível em: <https://www.cnnbrasil.com.br/economia/macroeconomia/brasil-investiu-r-439-bilhoes-em-obras-em-2022-alta-de-16-aponta-ibge/>. Acesso em: 29 maio 2025.
Pati, C. 2025. Varejo cresce 4,7% em 2024 e tem melhor resultado em 12 anos. Disponível em: <https://veja.abril.com.br/economia/varejo-cresce-47-em-2024-e-tem-melhor-resultado-em-12-anos/>. Acesso em: 29 maio 2025.
Ries, E. 2011. A Startup Enxuta: Como Empreendedores de Hoje Criam Empresas de Sucesso Usando a Inovação Contínua. Leya.
Schwaber, K.; Sutherland, J. 2017. Guia do Scrum – Um guia definitivo para o Scrum: As regras do jogo. Disponível em: <https://www.scrumguides.org/docs/scrumguide/v1/Scrum-Guide-Portuguese-BR.pdf>. Acesso em: 07 maio 2025.
Yin, R.K. 2015. Estudo de caso: planejamento e métodos. Bookman Editora. Porto Alegre, RS, Brasil.
Yin, R.K. 2018. Estudo de caso: planejamento e métodos. Bookman Editora. 5ed. Porto Alegre, RS, Brasil.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq