Last Planner System and the Predictability of Planning in Capital Projects in Mining

Luanna Pricyla Marques de Freitas; Lorena Hernández Mastrapa

DOI: 10.22167/2675-6528-202601106

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The mining sector holds a strategic position in the economy, characterized by technically and operationally complex capital projects. In the specific context of the analyzed company, instability was identified, caused by operational interferences and a disconnect between centralized planning and execution, resulting in low predictability rates. Given this scenario, the Last Planner System (LPS) practices were proposed and implemented as a solution to mitigate uncertainties and improve planning performance in the project in question. The research was classified as applied, exploratory-descriptive in nature, with a qualitative approach and quantitative data support, using the case study method with action research characteristics. The results demonstrated that structuring a process focused on collaborative management and early constraint removal increased the Percentual de Pacotes Concluídos (PPC) to levels between 73.58% and 90.24%. Monitoring showed that the increase in the Índice de Remoção de Restrições (IRR) directly contributed to the reliability of weekly goals, reducing interferences during execution. It was concluded that the Last Planner System showed significant potential as a management support tool, being effective in solving the identified predictability failures and strengthening data-driven decision-making in the analyzed capital project.

Keywords: Reliability; Performance; Collaborative management; Constraint management; Lean Construction.

1. Introduction

The mining sector represents a fundamental pillar for the global and national economy, driving industrial development. Characterized by large-scale capital projects (CapEx), these ventures demand substantial investments and involve high technical and organizational complexity, with prolonged life cycles and multiple stakeholders (Merrow, 2011; PMI, 2021). The intrinsic nature of these projects, often subject to external factors such as environmental regulations, logistical challenges, and geological variations, makes efficient management an imperative. Despite advances in management methodologies, large capital projects still face recurring challenges, such as schedule and cost overruns. Global studies indicate that a considerable proportion does not achieve schedule and budget objectives, highlighting a persistent gap in planning and control predictability.

The root of many of these challenges lies in the low reliability of planning, often stemming from a disconnect between strategic planning and the operational reality of execution (Ballard; Howell, 1998). This disconnect manifests in operational interferences, rework, and stoppages, generating waste of resources and time, impacting the project’s value stream. The inherent variability in service fronts, the complexity of interfaces between disciplines, and ineffective constraint management contribute to an unstable production environment, where the plans developed do not reflect the actual execution conditions. Faced with this scenario, the *Lean Construction* philosophy emerges as a promising approach to optimize planning performance in complex projects, focusing on waste elimination, value maximization, and the promotion of a continuous workflow (Koskela, 1992; Ballard; Howell, 2003).

Within the framework of *Lean Construction*, the *Last Planner System* (LPS) stands out as a robust methodology for improving planning reliability and production control. The LPS is designed to manage variability and promote continuous learning, transforming planning from a “push” activity process to a “pull” system based on actual execution capacity (Ballard, 2000). Its fundamental principles include collaborative plan development, proactive identification and removal of constraints through *look-ahead* planning, and continuous performance monitoring through indicators such as Percent of Work Completed (PWC) and Constraint Removal Index (CRI) (Hamzeh et al., 2015; Dave et al., 2020). Although the LPS has demonstrated remarkable effectiveness in civil construction, increasing predictability and productivity, its application and results in capital projects in the mining sector are still the subject of limited studies, representing an area with significant potential for exploration.

In the context of the analyzed company, the capital project in question faces significant operational instability, characterized by frequent interferences and logistical limitations not addressed in the initial planning phases. The traditional approach, focused on schedule development, results in low participation from field teams, preventing the incorporation of tacit knowledge from workers and leading to unrealistic targets. This disconnect between formal planning and execution reality culminates in a high number of rescheduling and deviations, negatively impacting the achievement of deadlines and budgets. The absence of a robust system to identify and remove constraints in advance exposes the project to constant interruptions, increasing costs and management complexity.

Given the criticality of the mining sector and the specific predictability challenges observed in the analyzed capital project, it becomes imperative to investigate and implement solutions that promote greater reliability in planning and execution. The literature gap regarding the in-depth application of LPS in mining projects justifies the relevance of this study, which seeks not only to fill this gap but also to offer a practical model for managing complex projects. Thus, this work aims to propose and implement the practices of the *Last Planner System* as a solution to mitigate uncertainties and elevate planning performance in the capital project in question, strengthening data-driven decision-making and collaborative management.

2. Material and Methods

The research was classified, in terms of its nature, as applied, seeking to generate knowledge directly aimed at solving a practical problem identified in the context of the analyzed project (Gil, 2017). Regarding the problem approach, a qualitative perspective was adopted, complemented by the support of quantitative data from planning performance indicators, characterizing a mixed approach (Creswell, 2014). This combination allowed for an in-depth understanding of the observed phenomena, while also providing numerical evidence to validate the proposed interventions and the results achieved in the real environment of the capital project in question.

The study’s objectives were exploratory and descriptive in nature, aiming to understand how the application of the *Last Planner System* (LPS) influences planning predictability, as well as to describe in detail the practices adopted and the results observed (Gil, 2017). Regarding technical procedures, a single case study method was employed, with characteristics of action research. This methodological choice was fundamental, as the researcher actively participated in the implementation and monitoring process of the analyzed practices, allowing for deep immersion in the context and direct intervention to improve planning (Yin, 2015; Thiollent, 2011).

The study was developed within a large-scale capital project, located in the state of Minas Gerais, in the mining sector. For ethical and confidentiality reasons, the anonymity of the company and the analyzed venture was rigorously preserved. The project in question involved typical activities of capital ventures, encompassing civil works, electromechanical assembly, commissioning, and the integration of multiple disciplines and suppliers. The unit of analysis focused on the capital project itself, allowing for an in-depth investigation into the application and impacts of the *Last Planner System* in an environment of high operational complexity and variability.

The project environment was characterized by high operational complexity, with several simultaneous work fronts and high interdependence between activities. This reality, added to the significant variability in execution, made production planning and control critical factors for project performance, especially regarding deadline compliance. The intervention and monitoring period of the *Last Planner System* practices extended for nine weeks, during which performance data were collected and analyzed, allowing observation of the evolution of planning predictability and the effectiveness of the implemented routines.

Considering the nature of a single case study and action research, there was no formal definition of population or sample in the statistical sense. The unit of observation and intervention was the capital project itself, and the participants involved were the field teams and those directly responsible for executing the activities, referred to as “last planners”. The selection of these participants occurred naturally, as they were directly involved in the operations and in the production planning and control process of the undertaking, being essential for the collaborative implementation of the *Last Planner System* practices.

The first stage of the research consisted of an in-depth situational diagnosis of the existing planning system in the organization. To this end, a meticulous survey of technical and managerial documents that guided the project was carried out. The long-term schedule, which allowed for the identification of established goals and contractual milestones, and the short-term operational plans, to understand the details of immediate execution activities, were analyzed. Complementarily, historical records of rescheduling and deviations were studied to map the recurring justifications for non-compliance with deadlines, establishing a baseline for intervention.

After the initial diagnosis, the practical intervention phase began, focusing on the implementation of *Last Planner System* (LPS) practices in the project’s routine. This stage was not limited to the mere adoption of new tools, but sought to promote a change in planning culture, migrating from a centralized model to a more collaborative and decentralized approach. The introduction of the LPS pillars aimed to create a more stable production environment, where the systematic removal of constraints would act as a shield for field teams, increasing commitment and reliability of established plans.

The implementation of the LPS involved three main areas of action. Firstly, the Medium-Term Planning was established, with a six-week visualization horizon (6-Week Look-ahead), to anticipate resource needs and potential interferences. Secondly, the Collaborative Weekly Scheduling was instituted, with meetings that included the active participation of those directly responsible for execution, the “last planners”, to define realistic tasks and deadlines. Finally, the Check-in and Check-out Routines were implemented, systematic tools to monitor the daily and weekly production flow, validating the start of activities and recording the completion or causes of variability.

The third stage consisted of continuous and systematic monitoring of performance indicators, aiming to measure the effectiveness of planning and the stability of the production flow. The monitoring focused on two fundamental indicators: the Percentage of Completed Packages (PPC), calculated weekly to measure the reliability of short-term planning, and the Restriction Removal Index (IRR), which assessed the efficiency of impediment management at the medium-term level (*Look-ahead*). Data were collected in real-time during *Check-out* routines and subsequently consolidated into structured spreadsheets for analysis.

Complementary to the quantitative analysis of indicators, a rigorous qualitative evaluation of the causes for non-compliance with planned activities was carried out. This investigation was based on records obtained during the *Check-out* routines, where each unfinished task was subject to a deviation analysis. The analysis process followed the categorization based on 6M + S, adapted to the construction context, segregating deviations into Manpower, Method, Material, Machine, Environment, Measurement, and Safety. For recurring deviations, the root cause investigation was used to understand the origin of the problem.

As part of the project management strategy and the analysis phase, a routine of weekly meetings with the final client was established. In these meetings, in addition to presenting performance indicators, such as the Percentage of Completed Packages (PPC) and the Restriction Removal Index (IRR), the main causes of non-compliance and the status of restrictions mapped on the *6-Week Look-Ahead* control panel were discussed. This reporting stage was fundamental to aligning expectations and ensuring client support in removing external restrictions, such as regulatory approvals or access to service fronts.

The ethical procedures were rigorously observed, ensuring the anonymity of the company and the analyzed venture, in accordance with research principles. Regarding methodological limitations, the implementation of the *Last Planner System* faced initial challenges, such as the cultural resistance of field teams in adopting collaborative planning. Additionally, there was an initial difficulty in collecting reliable data, which required continuous effort to improve the accuracy of the recorded information. These aspects were considered in the analysis process, recognizing the complexity of changing processes in operational environments.

3. Results and Discussion

The initial analysis of the existing planning system in the capital project revealed a scenario of low predictability and high instability, characteristics frequently observed in large mining ventures, as pointed out by Merrow (2011) and PMI (2021). The situational diagnosis, carried out through the survey of technical and managerial documents, evidenced a critical disconnection between long-term planning, which established goals and contractual milestones, and the short-term operational reality. This gap generated an unstable production environment, where macro plans, by their nature, could not absorb the inherent variability of the complex and dynamic work fronts in the mining sector. The lack of alignment between different planning levels is a recurring problem that compromises the reliability of commitments and the efficiency of execution, leading to frequent deviations in schedule and cost.

The centralization of weekly schedule development was identified as one of the main contributing factors to low predictability. It was observed that the planning department was solely responsible for this activity, with limited participation from the execution teams and the direct production managers, the “last planners”. This top-down approach prevented the incorporation of tacit knowledge and practical experience from those in the field, resulting in frequently unrealistic production targets and, consequently, a high volume of rescheduling. Ballard and Howell (1998) argue that plans developed without the input of those who will actually perform the work tend to become mere bureaucratic exercises, lacking adherence to reality and, therefore, ineffective as control and management tools. The absence of a collaborative planning process undermines the teams’ sense of ownership and commitment, transforming planning from an engagement tool into an imposition.

Historical records of reprogramming and deviations, analyzed as part of the diagnosis, corroborated the thesis that the low reliability of planning was intrinsically linked to the presence of unidentified or ignored constraints during the programming phase. Such constraints manifested in various forms, directly impacting the production flow. Operational interferences, for example, were common, with conflicts between simultaneous work fronts that had not been spatially mapped, generating downtime and rework. Dependence on external releases, such as environmental licenses, regulatory approvals, or final client authorizations, represented significant bottlenecks that delayed the start of activities. Additionally, logistical limitations, such as delays in the supply of critical materials or access difficulties in remote areas of the mining project, contributed to the interruption of the flow. This reality of “pushing” activities into the field without proper impediment removal generated a chaotic and unpredictable production environment, validating the need for a more robust and proactive approach to constraint management, as advocated by the Lean Construction philosophy (Koskela, 1992).

The implementation of Last Planner System (LPS) practices represented a strategic intervention to mitigate uncertainties and increase planning predictability in the capital project. This intervention phase, which lasted nine weeks, was not limited to the mere adoption of new tools, but sought to promote a significant cultural change, migrating from a centralized planning model to a collaborative and decentralized approach. The inclusion of those directly responsible for execution, the “last planners”, in planning meetings transformed these encounters into forums for collaborative decision-making, where weekly goals were discussed from the perspective of real field feasibility, and not just based on software projections. This change is fundamental to the Lean philosophy, which emphasizes the importance of the executors’ participation to ensure the production of reliable and executable plans (Ballard & Howell, 2003).

One of the most notable preliminary advances was the increase in clarity and accountability. The definition of tasks became more granular and precise, allowing each team to accurately understand its deadlines and interfaces with other disciplines. This transparency, illustrated by the visual management board, facilitated coordination and reduced scope and resource conflicts.

Source: Original research results

Figure 1. Visual management board for collaborative weekly construction site scheduling.

As shown in Figure 1, the clear visualization of activities and their interdependencies in an accessible format on the construction site promoted a shared understanding of the plan, essential for synchronized execution. This type of visual management is a pillar of Lean Construction, as it makes the workflow transparent and allows teams to identify and resolve problems autonomously (Daniel, Pasquire & Dick, 2019). The ability to see progress and challenges in real-time empowers teams and fosters a culture of mutual accountability, contrasting with the previous model of centralized and opaque planning.

Another significant advance was the increased commitment of the teams. By actively participating in the plan’s development, the executors began to assume public commitments before their peers and leadership, which raised the sense of responsibility and engagement with the established goals. This engagement is crucial for the reliability of planning, as, according to Hamzeh, Zankoul, and Rouhana (2015), the commitment of the “last planners” to the plan is a direct predictor of execution success. The transition from a “command and control” model to a “collaboration and commitment” model is one of the pillars of LPS, which seeks to transform the project culture, making it more responsive and adaptable to real-world conditions.

The introduction of Medium-Term Planning, with a six-week look-ahead horizon (6-Week Look-Ahead), has enabled proactive constraint management. Although constraint identification was incipient in the early weeks, the tool forced the team to look ahead, mapping resource needs, releases, and other dependencies before they became critical impediments to execution.

Source: Original research results

Figure 2. Control panel and presentation of restrictions in the 6-Week Look-Ahead horizon.

Figure 2 illustrates the control panel of the 6-Week Look-Ahead, which has become a vital tool for anticipating constraints related to construction methods, material logistics, and service front releases. This forward-looking view allowed the team to “shield” production, ensuring that activities scheduled for the week were free of impediments, a central concept in LPS (Ballard & Howell, 1998). Proactive constraint management is a strategic differentiator in capital projects in mining, where mobilization costs and disciplinary interfaces are high, and workflow interruption can generate substantial financial losses and critical delays. The maturation of this phase was essential to reduce operational variability, proving that planning is a coordinated social and technical learning process, as discussed by Dave et al. (2020).

The systematic monitoring of performance indicators, specifically the Percentage of Completed Packages (PPC) and the Restriction Removal Index (IRR), revealed a gradual and consistent evolution in the reliability of short-term planning over the nine weeks analyzed. The PPC, which measures the teams’ adherence to what was agreed upon in planning meetings, registered a variation from 73.58% in the first week to 90.24% in the ninth week. This sustained growth trend is a strong indication that the LPS routines have been effectively consolidated in the teams’ daily work. Ballard (2000) suggests that a PPC stabilized at levels above 80% is an indicator of excellence in protecting execution against variability. In the context of this project, achieving and maintaining levels above 80% demonstrates that the maturity of the planning processes has been reached, resulting in a more stable and predictable workflow.

The Restriction Removal Index (RRI), which assesses the efficiency of impediment management at the medium-term level (Look-ahead), showed an even more expressive range, varying from 35.40% in the first week to 85.71% in the ninth week. This progressive advancement directly reflects the team’s learning curve in identifying and addressing impediments before the start of activities. The RRI functioned as a leading performance indicator: in weeks when constraint management was more rigorous and efficient, the workflow presented fewer interruptions, increasing the executors’ confidence in the established plans. The continuous improvement of the RRI is a testament to the effectiveness of LPS’s proactive approach in identifying and eliminating obstacles, ensuring that field teams are not mobilized for service fronts without full execution conditions.

The joint analysis of these two indicators, as illustrated in Figure 3, reveals a direct and positive correlation between the capacity to remove constraints and the fulfillment of what was planned.

Source: Original research results

Figure 3. Evolution of PPC and IRR indicators over the monitoring period.

As can be observed in Figure 3, as the IRR increased, the PPC presented a corresponding upward behavior. This correlation is a crucial finding, as it validates the fundamental principle of LPS that an activity should only be authorized for scheduling if it is entirely “clean” of constraints. The prior elimination of interferences, such as lack of materials, method uncertainties, or equipment unavailability, was the determining factor for the fluidity of service fronts. This behavior of the indicators reinforces the thesis of Ballard and Howell (1998) that “shielding” production through the early treatment of interferences is what guarantees workflow stability and reduces waste generated by unforeseen stoppages. In capital projects in mining, where the complexity and costs associated with interruptions are extremely high, this proactive management of constraints transcends the administrative sphere, becoming a strategic differentiator in risk mitigation and in meeting contractual milestones. Stability in production flow not only optimizes resource use but also improves team morale, which begins to work in a more predictable and less frustrating environment.

The qualitative analysis of the causes for non-compliance with planned activities, conducted from records obtained during the Check-out routines, complemented the quantitative evaluation of indicators. Each unfinished task was subjected to a deviation analysis, categorized using the Ishikawa Diagram structure adapted to the construction context (6M + S), segregating deviations into Labor, Method, Material, Machine, Environment, Measurement, and Safety. This standardized approach allowed for an in-depth understanding of the factors impacting planning reliability. For recurring deviations, the root cause was investigated to understand the problem’s origin, preventing the analysis from being restricted to just the symptom of the failure. This effort was directed towards identifying the main restrictive factors that compromised the predictability and continuity of the production flow in the capital project.

The constraints dashboard, as presented in Figure 4, consolidated crucial information on the status, responsible parties, nature, and discipline associated with the constraints, providing an integrated view of the main factors impacting planning reliability.

Source: Original research results

Figure 4. Planning constraints dashboard.

Figure 4 reveals that, out of a total of 249 registered restrictions, 226 were completed, 17 canceled, and only 6 remained in progress during the analyzed period. This data is a testament to the team’s high effort in removing impediments before the execution of activities, demonstrating the effectiveness of the implemented restriction management process. It is noteworthy that there were no records of impeding restrictions during the analyzed period, meaning that no activity was halted by a critical, unaddressed impediment. Of the 6 open restrictions, 3 were classified as non-impeding, indicating that, although they still required monitoring, they did not directly compromise the execution of planned activities. This result reinforces the effectiveness of the process for identifying, classifying, and pre-emptively addressing restrictions, contributing to the reduction of interferences during the execution phase and, consequently, to the improvement of the PPC.

The analysis by discipline showed a greater concentration of restrictions associated with method, environment, material, and labor. These factors are directly related to the organization of service fronts, supply logistics, and the definition of construction methods. These results indicate that a large part of the causes for non-compliance was associated with failures in integration between planning and execution, especially in medium-term planning. The predominance of restrictions related to the organization of fronts and logistics reflects a common failure in complex projects: the deficiency in the flow of information and resources. This scenario converges with the studies by Hamzeh et al. (2016), who emphasize that medium-term planning (Lookahead) fails when there is no rigorous detailing of interfaces and supply logistics before execution. The ability to systematically identify and categorize these restrictions allowed the team to develop more effective preventive and corrective actions, transforming challenges into opportunities for learning and continuous improvement.

As part of the project management strategy, a routine of weekly meetings with the final client was established. In these meetings, in addition to the presentation of performance indicators (PPC and IRR), the main causes of non-compliance and the status of restrictions mapped on the 6-Week Look-Ahead control panel were discussed. This reporting stage was fundamental to align expectations and ensure client support in removing external restrictions, such as regulatory or service access clearances. Data transparency reinforced trust between the parties and transformed follow-up meetings into strategic decision-making forums, focused on problem-solving and ensuring compliance with contractual milestones. Collaboration with the client in managing external restrictions is an often underestimated but crucial aspect for the success of complex projects, especially in regulated sectors like mining. The ability to involve the client as a partner in removing external impediments demonstrates the maturity of the implemented management system and its effectiveness in creating a more collaborative and less adversarial project environment.

Preliminary results indicate that a significant portion of the identified constraints could have been mitigated through early preventive actions, such as a better definition of execution methods, alignment between teams, and greater detail in interfaces. This finding reinforces the importance of systematic constraint management as a fundamental element for increasing the predictability and reliability of planning in capital projects in the mining sector. The LPS intervention not only corrected specific failures but also established a framework for continuous improvement, where learning from deviations and proactivity in constraint management became an integral part of the project culture. The ability to transform performance data and deviation records into actionable information for decision-making is one of the greatest legacies of the LPS implementation, enabling evidence-based management and a virtuous cycle of improvement.

4. Conclusion

It is concluded that the objective was achieved, as the Last Planner System (LPS) practices were effectively proposed and implemented to mitigate uncertainties and elevate planning performance in the analyzed capital project. The intervention demonstrated success in improving reliability, evidenced by the consistent increase in the Percent of Work Completed (PWC) from 73.58% to 90.24% and the Constraint Removal Index (CRI) from 35.40% to 85.71%. These results confirm that collaborative management and proactive constraint removal are crucial for workflow stability and predictability in mining projects. The implementation of LPS transformed planning from a centralized process into a participatory approach, strengthening data-driven decision-making and the engagement of field teams.

Despite notable advances, the application of LPS faced significant limitations, such as the cultural resistance of field teams to fully adopt collaborative planning and the initial difficulty in collecting reliable data. These challenges highlight that the system’s effectiveness transcends the mere adoption of tools, requiring a profound change in mindset and leadership. For future studies, it is suggested to deepen the analysis of performance indicators throughout the entire project lifecycle, allowing an evaluation of the sustainability of gains. It is also recommended to integrate planning data into real-time visualization platforms, such as automated dashboards or 4D BIM models, to strengthen the culture of continuous improvement and evidence-based management.

Bibliographic References

Ballard, G. (2000). The Last Planner System of production control. Birmingham: University of Birmingham. PhD Thesis.

Ballard, G.; Howell, G. (1998). Shielding production: an essential step in production control. Journal of Construction Engineering and Management, v. 124, n. 1, p. 11–17.

Ballard, G.; Howell, G. (2003). Lean project management. Building Research & Information, v. 31, n. 2, p. 119-133.

Creswell, J. W. (2014). Research design: qualitative, quantitative, and mixed methods approaches. 4. ed. Thousand Oaks: Sage Publications.

Daniel, E. I.; Pasquire, C.; Dick, G. (2019). Exploring the implementation of the Last Planner System through IGLC community. Engineering, Construction and Architectural Management, v. 26, n. 10, p. 2363–2383.

Dave, B.; Koskela, L.; Kiviniemi, A.; Tzortzopoulos, P. (2020). Implementing lean in construction: lean construction and BIM. Construction Management and Economics, v. 38, n. 8, p. 651-671.

Gil, A. C. (2017). Métodos e técnicas de pesquisa social. 7. ed. São Paulo: Atlas.

Hamzeh, F.; Ballard, G.; Tommelein, I.; Koskela, L. (2016). Improving construction workflow: the role of production planning and control. Lean Construction Journal, p. 57–72.

Hamzeh, F.; Zankoul, E.; Rouhana, C. (2015). How can “tasks anticipated” in lookahead planning impact reliable workflow and project duration? Construction Management and Economics, v. 33, n. 4, p. 243-258.

Koskela, L. (1992). Application of the new production philosophy to construction. Stanford: Stanford University. Technical Report No. 72.

Merrow, E. W. (2011). Industrial megaprojects: concepts, strategies, and practices for success. Hoboken: John Wiley & Sons.

PMI – Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® Guide). 7. ed. Newtown Square: PMI.

Thiollent, M. (2011). Metodologia da pesquisa-ação. 18. ed. São Paulo: Cortez.

Yin, R. K. (2015). Estudo de caso: planejamento e métodos. 5. ed. Porto Alegre: Bookman.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving the independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated the automated reading of files, the organization of curves into current-potential matrices, the generation of the potential map, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed by device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of the results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and enhance the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used for the definition and identification of the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.