Implementation of PMO for standardization and performance improvement of sustainable projects in hotel chains
Letícia Arruda Vieira do Nascimento; Desirée Baldin Damame
DOI: 10.22167/2675-6528-202601073
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
The hotel sector faces growing challenges related to sustainability, making the adoption of structured project management strategic for the implementation and monitoring of sustainable initiatives. The study analyzed the contribution of implementing a Project Management Office (PMO) to the standardization and performance improvement of sustainable projects in hotel chains. The research adopted a qualitative and applied approach, using literature review, document analysis, and case studies related to the sector, based on consolidated project management practices and PMBOK guidelines adapted to the hotel reality. The methodology included the application of stakeholder analysis, SWOT matrix, and risk mapping by probability and impact. The results indicated that the PMO implementation contributed significantly to the strategic alignment of sustainable initiatives, standardization of processes and indicators, improvement of deadline and cost monitoring, and strengthening of project governance and coordination among units. The limitation in results monitoring was identified as the most critical risk (score 25), followed by legal non-compliance (score 15), loss of engagement and staff turnover (score 12 each). It was concluded that the PMO acts as a structuring element for the consolidation of sustainability in hotel chains, favoring the improvement of project performance and the generation of economic, social, and environmental value, in addition to supporting the replication of good practices in the sector, transforming isolated intentions into rigorous methodological processes and ensuring regulatory compliance.
Keywords: Operational efficiency; Strategy; Governance; Risk management; Environmental impact.
1. Introduction
The growing global awareness of the environmental and social impacts of economic activities drives sustainability as an imperative for organizational longevity and competitiveness (Santos, Paula and Bem, 2023). In the tourism and hospitality sector, this demand is particularly relevant. Hotel operations are intrinsically linked to the intensive consumption of natural resources, such as water and energy, to the generation of solid waste, and to continuous interaction with local communities. The scale and complexity of environmental and social management are amplified in multi-unit networks. The adoption of sustainable practices is not only a socio-environmental responsibility but a strategic differentiator that attracts “eco-friendly” consumers and enhances companies’ reputation (Silveira and Oliveira, 2023), in addition to meeting regulatory and stakeholder pressures.
Despite the recognition of this importance, the implementation of sustainability in the hotel sector does not always occur in a structured manner and integrated into the organizational strategy. In many chains, sustainable initiatives are conducted in isolation between units, lacking standardization of processes, indicators, and systematic monitoring mechanisms. This fragmentation hinders the measurement of results, the replication of good practices, and the consolidation of sustainability as a central strategic element. The absence of a cohesive approach prevents isolated intentions from transforming into rigorous methodological processes, compromising the effectiveness and scalability of actions (PMI, 2022). Such a scenario highlights a gap in the ability to convert initial engagement into measurable long-term strategic value.
In parallel, project management has consolidated itself as an essential discipline for the effective execution of organizational strategies. The Project Management Office (PMO) emerges as a fundamental structure, responsible for standardizing processes, supporting decision-making, promoting strategic alignment, and elevating project management maturity. A PMO acts as a centralized hub, offering guidelines, tools, and methodologies to ensure consistent and efficient projects. Recent evidence indicates that organizations with PMOs show significant improvements in outcome predictability, operational efficiency, and optimized resource utilization, regardless of the sector (Syalevi, Raharjo, and Wibowo, 2024). Its function transcends supervision, acting as a catalyst for the governance and coordination of complex initiatives.
In recent years, the literature has advanced in the discussion on the integration between project management and sustainability, culminating in the concept of Green Project Management Office (Green PMO). This model proposes the explicit incorporation of environmental, social, and economic criteria in all phases of the project lifecycle. The Green PMO approach allows sustainability to be treated systematically, measurably, and integrated with business objectives, transforming intentions into concrete actions and tangible results. By establishing metrics, standardized processes, and robust governance mechanisms, the Green PMO operationalizes sustainability, ensuring that projects not only achieve traditional objectives but also consistently generate economic, social, and environmental value (Ponta, 2022).
However, in the specific context of hotel chains, the structured application of these models, especially PMOs focused on sustainable project management, is still limited. The absence of standardization and models adapted to the particularities of the hotel sector highlights a relevant practical gap, demanding approaches that effectively integrate sustainability into project management. The lack of a formal structure compromises communication, operational effectiveness, and the ability to respond to regulatory and market pressures. This work is justified by the need to offer a structured model for hotel chains, transforming sustainable initiatives into rigorous methodological processes, ensuring strategic alignment, regulatory compliance, and resource optimization. Thus, the objective of this study was to analyze the contribution of implementing a Project Management Office (PMO) to the standardization and performance improvement of sustainable projects in hotel chains.
2. Material and Methods
This research was characterized as applied, with a qualitative approach, and descriptive and propositive in nature. The study was developed from the application of Project Management concepts and tools in the context of sustainable projects in hotel chains, seeking to offer a structured model for the integration of sustainability. The applied nature aimed at solving a practical problem, while the qualitative approach allowed for an in-depth understanding of the phenomena studied, without the intention of generalizing the findings to a larger population. The descriptive character sought to detail the characteristics of the analyzed scenario, and the propositive character, to suggest solutions.
The research context involved a global hotel chain, with operations in 58 countries. The study’s focus, however, was concentrated on a specific unit located in the capital of the state of São Paulo, Brazil. This unit was selected as the primary unit of analysis, representing a microcosm of the chain’s operations. The period of the research was not explicitly delimited, but the procedures were executed for the Final Course Project presented in 2026, indicating that the collection and analysis occurred in previous years. The unit, despite having sustainability initiatives, conducted them in a decentralized manner.
There was no defined population or sample in the traditional statistical sense, as the study was configured as a case study focused on a single hotel unit. The unit of analysis was selected for convenience, based on the author’s professional experience and the availability of data for constructing a reference scenario. The indirect “participants” of the study were the internal documents and processes of the unit, as well as the identified stakeholders, whose roles and interactions were analyzed. No inclusion or exclusion criteria were established for individuals, but rather for the relevance of the observed documents and practices.
The data collection was multifaceted, combining the author’s professional experience with the analysis of practices observed in similar hotel organizations. The main data collection instrument consisted of documentary research, which included records of projects from the hotel unit, organizational charts, and execution reports. Additionally, the observation of the unit’s internal processes was employed to identify strengths and weaknesses related to sustainability management. These procedures aimed to build a detailed reference scenario and diagnose the existing project management, without the application of formal questionnaires or interviews.
The application of the methodology occurred in three sequential stages. Initially, a reference scenario for the hotel network was constructed, followed by a diagnosis of project management to identify weaknesses and opportunities for improvement. The first stage of the diagnosis involved “stakeholder” analysis, which consisted of a documentary survey of the unit’s project records. This process sought to identify all involved parties, from the board of directors to operational managers, and map their roles and responsibilities, as well as their degree of power and interest in relation to sustainability initiatives.
The second stage of the diagnosis involved the application of the Strengths, Weaknesses, Opportunities and Threats [SWOT] matrix, used to diagnose the hotel unit’s strategic positioning in relation to sustainability. The analysis of strengths and weaknesses was conducted through observation of the unit’s internal processes, identifying distinctive capabilities and operational limitations. The mapping of opportunities and threats considered external environmental variables, such as market trends and regulatory requirements, as illustrated in Figure 1. SWOT Matrix
.
The third sequential stage consisted of preliminary risk mapping, carried out from the vulnerabilities and threats identified in the SWOT analysis. For this, a probability and impact matrix was used, which quantified the threats to the continuity of sustainability actions. This tool assigned numerical values from one to five for probability (estimated frequency of occurrence) and impact (severity of the consequence on sustainability objectives), as shown in Figure 2. Probability and Impact Matrix
.
Table 1. Identification and Quantification of Risks
|
Risk Event |
Origin (SWOT Factor) |
Probability (P) |
Impact (I) |
Criticality (R=PxI) |
Classification |
|
Limitation in Monitoring |
Weakness (Lack of Standardization) |
5 |
5 |
25 |
Critical |
|
Legal Noncompliance |
Threat (Regulatory Pressure) |
3 |
5 |
15 |
High |
|
Engagement Loss |
Weakness (Lack of Training) |
4 |
3 |
12 |
Moderate |
|
Personnel Turnover |
Weakness (Decentralization) |
3 |
4 |
12 |
Moderate |
Source: Elaborated by the author (2026)
The collected data were treated and analyzed using qualitative and quantitative techniques. The “stakeholders” analysis allowed for an understanding of the power dynamics and role ambiguity within the unit, highlighting governance gaps. The SWOT matrix provided a strategic diagnosis, correlating internal and external variables to identify the unit’s positioning. Risk mapping, using the probability and impact matrix, allowed for the calculation of each risk’s criticality (Risk = P x I), classifying them into criticality zones (Green, Yellow, Orange, and Red) for prioritizing corrective actions, as shown in Table 1. Identification and Quantification of Risks
|
Risk Event |
Origin (SWOT Factor) |
Probability (P) |
Impact (I) |
Criticality (R=PxI) |
Classification |
|
Limitation in Monitoring |
Weakness (Lack of Standardization) |
5 |
5 |
25 |
Critical |
|
Legal Noncompliance |
Threat (Regulatory Pressure) |
3 |
5 |
15 |
High |
|
Engagement Loss |
Weakness (Lack of Training) |
4 |
3 |
12 |
Moderate |
|
Personnel Turnover |
Weakness (Decentralization) |
3 |
4 |
12 |
Moderate |
.
It is important to emphasize that the study presents methodological limitations inherent to its nature. As it is a case study focused on a single hotel unit, the conclusions obtained reflect a specific reality of governance and infrastructure, which prevents immediate generalization to other units of the chain or to the hotel sector as a whole. Additionally, the diagnosis was based on documentary survey and punctual observation, which may not have captured extreme seasonal fluctuations or sudden changes in guest behavior over a full year.
3. Results and Discussion
The results obtained from the diagnosis of the hotel unit allowed the identification of gaps that hinder the consolidation of sustainable and efficient management, revealing multifaceted challenges that span governance, strategy, and risk management. The detailed analysis of each finding, together with the relevant literature, offers an in-depth understanding of the underlying causes of these weaknesses and points to the pressing need for a structured approach, such as that proposed by the implementation of a Project Management Office (PMO).
In the first stage of the diagnosis, the analysis of “stakeholders”, conducted through documentary research, revealed a significant fragmentation in the hotel chain’s governance. This process consisted of mapping individuals through the organizational chart and project records, ranging from senior management to the operational teams of Food and Beverage. By cross-referencing planning documents with execution reports, it was found that, although the organizational top management’s strategic interest in sustainability is high, there is a critical gap in communication and alignment between different hierarchical levels. This disconnection is a fundamental obstacle, as the success of sustainability initiatives directly depends on the balance between the decision-making power of management and the interest and execution capacity of the operational teams. Project management literature, as advocated by the Project Management Institute (PMI, 2022), emphasizes that effective governance is the backbone for the successful execution of complex strategies, and the absence of a formal communication and decision-making structure can lead to misaligned and ineffective projects.
When organizing the stakeholders, it was noticed that there is a group at the operational base with a high interest in carrying out sustainable projects, but which, paradoxically, lacks the necessary support or resources from management to transform their good intentions into practical results. This disconnect between strategy and operation creates an execution vacuum, where team enthusiasm is neutralized by a lack of direction and support. The absence of a clear bridge between strategic vision and tactical implementation is a recurring problem in organizations with fragmented governance, as pointed out by Syalevi, Raharjo, and Wibowo (2024), who highlight the importance of a PMO to align objectives and resources, ensuring that strategic initiatives are translated into concrete and measurable actions. The implementation of a PMO, in this context, would act as a catalyst, filling this gap by establishing formal communication channels and standardized processes that connect the board to operational teams, transforming interest into action and potential into performance.
Assignment verification revealed that there was no formal appointment of responsible parties for specific goals, such as waste reduction or energy consumption. This identification of governance gaps demonstrated that sustainability decisions lack a standardized approval flow, resulting in an ambiguity of roles that leads to employee disengagement. According to Trentim (2022), genuine engagement only occurs when there is clarity about “who does what,” and the lack of this definition leads to a loss of purpose for teams, as there is no structured training or processes to sustain initiatives in the long term. The absence of clear responsibilities not only dilutes accountability but also hinders the development of expertise and the accumulation of organizational knowledge in sustainability. A PMO could mitigate this fragility by formalizing roles and responsibilities, establishing a clear approval system, and implementing continuous training programs, ensuring that knowledge is institutionalized and does not depend on isolated individuals.
Continuing the diagnosis, the application of the Strengths, Weaknesses, Opportunities, and Threats (SWOT) matrix deepened the understanding of the unit’s strategic positioning regarding sustainability. As presented in Figure 3, the analysis revealed a scenario of internal and external strengths that, although presenting potential, are compromised by structural weaknesses.
Source: Elaborated by the author (2026)
Figure 3. SWOT matrix applied to the hotel chain.
The observation of internal processes revealed that the unit’s main weakness is the lack of standardization and the team’s lack of technical training, which leads to duplication of efforts and inconsistency in results. This fragility is a direct impediment to the scalability and efficiency of sustainable initiatives. According to Ponta (2022), maturity in sustainable projects depends on the transition from isolated actions to documented and repeatable processes, ensuring that performance does not fluctuate with the scale of the operation. Without standardization, each project is reinvented, consuming time and resources unnecessarily, and the results are difficult to compare or optimize. The lack of technical training, in turn, means that even when there is goodwill, the team may not have the necessary skills to implement best practices in sustainability, such as proper waste separation or energy consumption optimization. A PMO would be crucial for developing and implementing operational standards, creating manuals of best practices, and coordinating continuous training programs, thereby elevating the team’s technical competence and ensuring consistency in execution.
On the other hand, the existence of installed infrastructure for sustainability and the initial engagement of local management were identified as Strengths, demonstrating that a sustainable culture is already present, albeit in a disorganized manner. This indicates that the organization already possesses the necessary human and material elements, only lacking a governance model to direct this potential towards measurable goals aligned with the network’s global strategy. This internal strength is a valuable asset, as resistance to change is often one of the biggest challenges in implementing new strategies. The fact that there is initial engagement and existing infrastructure suggests that the unit is ready for a transition to more structured sustainability management. The PMO’s role, in this context, would not be to create the culture from scratch, but rather to channel and optimize existing enthusiasm and resources, transforming scattered initiatives into a cohesive and strategically aligned program, maximizing the return on investment in sustainability.
In the external environment, opportunities are directly linked to guests’ growing demands for ecological practices and the active search for spaces with an “Eco-Friendly” positioning, as well as the possibility of reducing fixed costs. According to Silveira and Oliveira (2023), the hotel sector is facing a transition where sustainability has ceased to be a differentiator to become a requirement for market survival, demanding that organizations prove their impacts through auditable data. The demand for sustainable hotels represents a significant market opportunity, which can be capitalized through effective sustainable project management. Furthermore, the implementation of sustainable practices, such as energy and water efficiency, can lead to a substantial reduction in operational costs, transforming sustainability from a cost into a generator of financial value. A PMO can help identify, prioritize, and manage projects that capitalize on these opportunities, ensuring that the unit not only meets market expectations but also gains competitive and financial advantages.
However, these same regulations and expectations can turn into critical threats if the unit fails to standardize its processes in time to meet legal goals and environmental certifications. As highlighted by the Project Management Institute (PMI, 2021), regulatory compliance is a pillar of project management, especially in sustainability contexts. Environmental regulatory pressure, along with the loss of customers to competitors with a green seal, constitutes a real threat to the unit’s reputation and economic viability. Pereira (2023) warns that, in the current corporate scenario, “green pressure” is one of the biggest threats to the continuity of non-standardized businesses. Lack of standardization and monitoring can lead to non-compliance, fines, and, more seriously, the loss of environmental certifications that are increasingly valued by consumers and business partners. A PMO, by establishing robust monitoring and control processes, can ensure that the unit is always in compliance with regulations and that its sustainable practices are auditable and certifiable, transforming threats into opportunities for brand strengthening.
Finally, the preliminary risk mapping, operationalized by a probability and impact matrix (Figure 2, as described in the methodology), quantified the threats to the continuity of the sustainability actions identified in the SWOT analysis. The procedure involved converting internal weaknesses and external threats into critical events, followed by assigning weights from 1 to 5 for Probability (P) and Impact (I). Based on this logic, the main risks were scored according to Figure 4, which details the criticality of each.
Source: Elaborated by the author (2026)
Figure 4. Probability and Impact Matrix
Through the criticality calculation (Risk = P x I), the risks were classified and prioritized. The data visualization through Figure 4 allows for a strategic interpretation of the hotel unit’s vulnerability, demonstrating that the limitation in monitoring results is the most severe risk, which reached the maximum score of 25, remaining in the red zone of the matrix (Figure 2). This risk can be classified as a “structuring risk”, as its systemic nature affects the organization’s ability to effectively manage all other sustainability initiatives.
Table 1. Identification and Quantification of Risks
|
Risk Event |
Origin (SWOT Factor) |
Probability (P) |
Impact (I) |
Criticality (R=PxI) |
Classification |
|
Limitation in Monitoring |
Weakness (Lack of Standardization) |
5 |
5 |
25 |
Critical |
|
Legal Noncompliance |
Threat (Regulatory Pressure) |
3 |
5 |
15 |
High |
|
Engagement Loss |
Weakness (Lack of Training) |
4 |
3 |
12 |
Moderate |
|
Personnel Turnover |
Weakness (Decentralization) |
3 |
4 |
12 |
Moderate |
Source: Elaborated by the author (2026)
The limitation in monitoring results, with criticality 25 (Table 1), means that it is not just an isolated failure, but a major impediment to the visibility of all other sustainability indicators. Without the standardization proposed by the methodology of a Project Management Office (PMO), the unit operates in the dark, depending on intuition rather than data. Management cannot identify whether waste reduction or energy saving goals are being met; the lack of standardization generates operational “energy loss.” Each time a process is done differently, the unit consumes more time and resources than necessary. The Project Management Office (PMO), therefore, is not just an “organizer,” but a waste reducer. Thus, it characterizes reactive management. Without concrete data, sustainability problems become “invisible” to the board, making it impossible to calculate financial losses at the moment they occur. To resolve this most serious risk, it is necessary to stop managing based solely on impressions and start deciding based on facts and data. The practical solution is the use of indicator panels (Dashboards), which can be made in spreadsheets or simple software, to monitor daily water and energy consumption and waste production. With these numbers in hand, it is possible to create reports that show the board how much money the hotel is saving with each sustainable action. When management realizes that sustainability reduces costs and avoids waste, the project ceases to be seen as an “extra task” and begins to be treated as an intelligent financial strategy for the business, as argued by Medeiros et al. (2024) when discussing the optimization of results through process integration.
Regarding legal non-compliance, the score of 15 (resulting from the intersection of Impact 5 and Probability 3, as per Figure 4) reflects a high-risk scenario for the unit. Although the hotel does not yet suffer severe penalties, the gravity of a potential regulatory sanction is alarming. The maximum impact of 5 was assigned due to the environmental regulatory pressure identified in the SWOT analysis. In this context, Pereira (2023) warns that, in the current corporate scenario, “green pressure” is one of the biggest threats to the continuity of non-standardized businesses. An administrative sanction or the loss of an environmental certification (such as the LEED or ISO 14001 seal) would not only generate immediate financial losses but would cause irreparable damage to its reputation. The leakage of a sanction nowadays on social media and booking platforms (Booking, TripAdvisor) would cause a “Catastrophic” (5) impact, generating financial losses due to the loss of customers and impacting the brand’s global network. The implementation of a PMO focused on business sustainability can establish internal audit processes and continuous monitoring of regulatory requirements, ensuring that the unit not only complies with legislation but also anticipates future demands, protecting its reputation and ensuring its competitiveness in the market.
Finally, the risks of loss of engagement and staff turnover, both with criticality 12 (Table 1), are in the moderate zone but should not be overlooked. They reveal that the decentralization of projects (cited in the “stakeholders” diagnosis) generates a vicious cycle, as the lack of clarity in roles leads to team discouragement, which increases turnover and, consequently, causes technical knowledge to be lost. The risk of turnover is only critical because the knowledge is proprietary to the individual and not the organization. In this context, Chiavenato (2020) states that intellectual capital is the main asset of service companies, emphasizing that, in the hotel industry, high turnover causes “organizational amnesia.” When an employee leaves, the work method that was not properly documented by the Project Management Office (PMO) leaves with them. As a result, the high cost of retraining new employees drains the budget that should be invested in sustainable technologies. This scenario reinforces the conclusion that the unit’s problem is not a lack of sustainable intention, but the fragility of the control method, which is currently incapable of converting employee effort into measurable strategic value.
Given this scenario, it is essential to create a sustainability committee, with monthly meetings with the heads of R&A and Governance. This ensures that power (board) supports interest (operation), creating a formal channel for communication and decision-making. Furthermore, it is crucial to have recurring training for the operational base, ensuring that initial engagement transforms into technical competence and the “step-by-step” of sustainable actions (e.g., waste separation, water waste control) is documented. This reduces dependence on specific individuals and mitigates the risk of staff turnover, as knowledge becomes institutionalized and accessible to all. A PMO can be responsible for structuring and managing these training and documentation programs, ensuring the continuity of sustainable practices and the retention of the organization’s intellectual capital. The standardization of processes and the creation of a knowledge repository are typical functions of a PMO, which would allow the unit to transform individual experience into an organizational asset, reducing vulnerability to turnover and strengthening the capacity for long-term sustainable project execution.
4. Conclusion
It is concluded that the objective was achieved, as this study analyzed the contribution of implementing a Project Management Office (PMO) to the standardization and performance improvement of sustainable projects in hotel chains. The diagnosis carried out in the hotel unit revealed that, despite the existing infrastructure and initial engagement, fragmented governance and the absence of a standardized methodology compromise the effectiveness of sustainability initiatives. The analysis of
interested parties
demonstrated that a PMO would act as a bridge between the board and operations, formalizing roles and centralizing communication. By integrating tools such as SWOT analysis and risk mapping, it became evident that the PMO would eliminate the “invisibility” of failures, establishing metrics and real-time monitoring, mitigating the critical risk of lack of indicators and legal non-compliance. Therefore, the PMO is essential for transforming isolated intentions into rigorous processes, ensuring strategic alignment, regulatory compliance, and reduction of financial losses.
Despite the results achieved, this study presents important limitations. As it is a case study focused on a single hotel unit, the conclusions cannot be generalized to the entire chain or the sector. Furthermore, the diagnosis was based on documentary survey and punctual observation, which may not capture seasonal fluctuations or changes in guest behavior over a full year. For future research, it is suggested to apply the methodology to other units in the chain for a comparative analysis of maturity in sustainability. It is also recommended a cost-benefit study of the implementation of automated environmental management software and an investigation into the impact of financial incentive programs for employees on reducing turnover and on the efficiency of sustainable practices in the Food and Beverage sector.
Bibliographic References
CHIAVENATO, Idalberto. Gestão de pessoas: o novo papel dos recursos humanos nas organizações. 6. ed. Rio de Janeiro: Grupo GEN/Atlas, 2020.
Elaborado pelo autor, 2026 [Referência completa não encontrada no documento original]
MEDEIROS, J. P. et al. Optimizing project management outcomes through collaboration and process integration. International Journal of Project Management, Amsterdam, v. 42, n. 2, p. 101-115, 2024. Disponível em: https://www.sciencedirect.com/science/article/pii/S1548066624000055. Acesso em: 23 dez. 2025.
Pereira, 2023 [Referência completa não encontrada no documento original]
PONTA, L. Sustainable project management: frameworks and cases. 2. ed. London: Routledge, 2022.
PROJECT MANAGEMENT INSTITUTE (PMI). Sustainability in project management. Newtown Square: PMI, 2022. Disponível em: https://www.pmi.org/learning/sustainability. Acesso em: 19 jan. 2026.
SANTOS, R. A. dos; PAULA, H. S. de; BEM, E. da S. Critérios de sustentabilidade para a gestão hoteleira: uma análise aplicada ao setor de turismo. Revista Brasileira de Pesquisa em Turismo, São Paulo, v. 17, n. 3, p. 1-20, 2023. Disponível em: https://rbtur.org.br/rbtur/article/view/2840. Acesso em: 19 jan. 2026.
SILVEIRA, M. A.; OLIVEIRA, R. Gestão da sustentabilidade na hotelaria moderna. Rio de Janeiro: GEN, 2023.
SYALEVI, R.; RAHARJO, T.; WIBOWO, W. S. The impact of Project Management Offices on organizational performance: a comprehensive review of the literature. International Journal of Information Systems and Project Management, Guimarães, v. 12, n. 1, p. 45–63, 2024. Disponível em: https://revistas.uminho.pt/index.php/ijispm/article/view/5933. Acesso em: 19 jan. 2026.
TRENTIM, Mario Henrique. Gestão de projetos: guia profissional: do planejamento à execução. 2. ed. São Paulo: Atlas, 2022.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq