Impacts of the Schedule on the Economic-Financial Viability of Hospital Projects: NPV, IRR and Payback in the Implementation of Health Services
Moisés de Araujo Sousa; Karoline Arguelho da Silva
DOI: 10.22167/2675-6528-202601236
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
The healthcare sector has experienced significant growth in demand for care services, driven by an aging population and an increase in chronic diseases, which has led to robust investments in expansion and new services. The relationship between schedule compliance and the economic-financial viability of hospital projects was analyzed, focusing on the implementation of a specialized medical outpatient clinic. The methodology adopted was based on a case study, which involved a comparative analysis between the planned and executed schedule of a specialized medical outpatient clinic, identifying factors that contributed to delays and their financial impacts. A financial model was developed with realistic, pessimistic, and critical scenarios to evaluate how schedule variations affected projected cash flow and the Net Present Value (NPV), Internal Rate of Return (IRR), and Payback indicators. The results showed that non-compliance with the schedule negatively impacted the project’s viability, mainly due to the postponement of revenue generation, increased operational costs, and the need to revise financial assumptions. A reduction in NPV and IRR, and an increase in Payback were observed in delayed scenarios, compromising the investment’s attractiveness. In critical scenarios, NPV became negative and Payback increased significantly. The study’s contribution lies in reinforcing the importance of integrating schedule management with economic-financial viability analysis, highlighting the need for continuous monitoring of project stages and periodic reviews of financial scenarios, even after approval, and incorporating the time factor as a critical element in decision-making for healthcare projects.
Keywords: Outpatient clinic; Economics; Efficiency; Finance; Investments.
1. Introduction
The healthcare sector has experienced significant growth in recent decades, driven by factors such as an aging population, an increasing incidence of chronic diseases, and expanded access to medical services. This scenario has led healthcare institutions to make increasingly robust investments in expanding their structures and implementing new services, which requires greater rigor in economic-financial feasibility analyses.
Efficient project management in the healthcare sector plays an essential role in the sustainability of these hospital institutions. Projects for the implementation of new services, such as an outpatient clinic, for example, demand rigorous planning to ensure that deadlines are met and resources are used in an optimized manner. Success depends not only on the correct allocation of resources but also on the ability to keep the schedule aligned with the organization’s financial and operational expectations.
In the hospital context, the implementation of a new health service requires high investments and detailed planning. The implementation time becomes a determining factor for the project’s success, given the operational complexity and the dependence on care and commercial strategies. The schedule, therefore, must be treated not only as an operational planning tool but as a strategic instrument capable of directly influencing the project’s overall and financial performance (PMI, 2021; Kerzner, 2018).
To assess the economic and operational sustainability of projects, the feasibility study is a critical step. In this context, indicators such as Net Present Value (NPV), Internal Rate of Return (IRR), and Payback are widely recognized in the literature as fundamental tools for evaluating the feasibility and return on investment. NPV, according to Ross, Westerfield, and Jaffe (2015), allows us to evaluate whether the expected financial returns are sufficient to overcome the initial investment and the opportunity cost of capital. IRR, according to Gitman (2010), represents the project’s profitability, equating the present value of cash flows to the initial investment. Payback, in turn, indicates the time required to recover the invested capital, being relevant for liquidity and risk analysis (Damodaran, 2012).
Failure to meet the schedule generates significant financial impacts, directly affecting the project’s cash flow. Delays in execution postpone revenue generation, reducing the present value of these flows and, consequently, decreasing the NPV. Damodaran (2012) and Ross, Westerfield, and Jaffe (2015) emphasize that the value of an investment is directly related to the timing of cash flows generation, and the time value of money is a fundamental principle of investment analysis. Thus, the greater the delay in cash generation, the lower the economic value of the project. Furthermore, the Payback is impacted, increasing the time required to recover the initial investment.
It is crucial to distinguish between economic feasibility and financial feasibility, with the main factor being the difference in temporal focus. Economic feasibility is focused on long-term profitability and profit, while financial feasibility concentrates on liquidity, cash flow, and short- to medium-term commitments. Ross, Westerfield, and Jaffe (2015) state that economic feasibility is related to its value generation capacity over time. Damodaran (2012) highlights that a project can present positive economic value but face financial difficulties if there is a temporal misalignment between cash inflows and outflows, especially in the short term, not guaranteeing resource availability to sustain operations.
In the context of healthcare services, these effects are potentiated due to the high structure of incremental fixed costs and the dependence on project maturation time according to healthcare demand. Even projects with positive economic feasibility may present short-term financial constraints when there is misalignment between planning and execution. This reinforces the importance of integrating schedule management and economic-financial feasibility analysis, highlighting the need for continuous monitoring of project stages and periodic reviews of financial scenarios even after approval, to mitigate risks and ensure investment sustainability.
In light of this scenario, this study contributes to strengthening the integrated vision between schedule management and economic-financial feasibility analysis, broadening the traditional approach by highlighting the relevance of time as a critical element for value generation. Thus, the present work aims to analyze the impact of economic-financial feasibility resulting from the non-compliance with the delivery schedule of a project for the implementation of a medical specialty outpatient clinic, considering the indicators of NPV, IRR, and Payback.
2. Material and Methods
This study was characterized as a research of an applied nature, with a predominantly quantitative approach and qualitative support. Its objective was to analyze the impact of the economic-financial viability resulting from the non-compliance with the schedule of a project for the implementation of a medical specialty outpatient clinic, considering the indicators of Net Present Value (NPV), Internal Rate of Return (IRR), and Payback.
The unit of analysis was the implementation of a medical specialty outpatient clinic, designed to offer consultations and generate demand for diagnostic exams, such as ultrasounds and magnetic resonance imaging. The outpatient clinic was also designed to act as a partner of an accredited network of hospitals, facilitating the referral of patients for surgical treatments and more complex procedures.
The research strategy adopted was the case study, which involved a comparative analysis between the planned schedule and the effectively executed schedule of an implementation project. The investigation was structured in three main and correlated stages, aiming to understand the influence of the time factor on the sustainability of health projects.
In the first stage, called Analysis and Case Study, project documents for the outpatient clinic implementation were collected. The schedule planning, financial reports (Income Statement – DRE and Cash-flow statement – DFC) and execution monitoring records were analyzed. All materials were consolidated into a file in Microsoft Excel software.
The second stage, Financial Modeling, focused on the analysis of economic-financial feasibility through the indicators NPV, IRR, and Payback. These indicators were calculated from projected cash flows, which considered operational revenues, fixed costs, variable costs, and Capital Expenditures (CAPEX). A financial model was developed to simulate the behavior of these indicators under different schedule and cash flow scenarios.
To evaluate the influence of the schedule, three analysis scenarios were structured. The Realistic Scenario considered the project execution according to the initial schedule, without delays. The Pessimistic Scenario simulated a delay of up to six months in the project implementation deadline. Finally, the Critical Scenario projected a delay of up to nine months in implementation, reflecting more severe impacts on financial and operational assumptions.
From the definition of these scenarios, the cash flows were recalculated and the respective financial indicators were adjusted. A comparative analysis was carried out between the scenarios to identify the sensitivity of the financial results in relation to the time factor. This approach allowed us to understand how postponing the start of operations impacted revenue generation and the investment payback period.
In the composition of the projected Income statement for the year (DRE), revenue-generating sources and operational expenses were evaluated, including taxes, variable costs, general and administrative expenses, personnel expenses, and clinical staff costs. From a qualitative point of view, the main factors that contributed to the deviations in the schedule were analyzed, covering aspects of project execution, resource management, operational dependencies, and external constraints.
The third stage, Schedule Management and Impacts on Economic-Financial Viability, focused on evaluating the financial impacts arising from schedule deviations. The aim was to demonstrate the importance of continuous monitoring of project stages and periodic review of financial assumptions, even after the approval of the feasibility study, in order to improve the integration between planning and execution.
The financial indicators NPV, IRR, and Payback were calculated based on the discounted cash flow theory, which considers the time value of money. The NPV measured the economic value generated by the project, discounting future flows at a cost of capital rate (Ross, Westerfield, and Jaffe, 2015). The IRR determined profitability, equating the present value of cash flows to the initial investment (Gitman, 2010). The Payback indicated the time to recover the invested capital, considering discounted cash flows (Damodaran, 2012). All calculations were performed in Microsoft Excel software.
3. Results and Discussion
The implementation of the medical specialties outpatient clinic, the central object of this study, aimed to expand the offer of medical consultations, generate demand for diagnostic exams, and serve as an entry point for more complex procedures in hospital units. Strategically, the outpatient clinic was not limited to generating direct revenue from consultations, but played a crucial role in the value chain of other health institutions, contributing to the increase in care volume and optimizing the use of hospital resources. The project structure involved initial investments in physical infrastructure, acquisition of equipment, hiring of medical, care, and administrative teams, as well as the implementation of management and care support systems, elements that demanded rigorous planning for their execution.
For the development of the implementation schedule, the project was structured in sequential phases, using the Gantt chart. This tool allowed for the horizontal visualization of activities, highlighting their duration, sequence, and interdependence. The activities were distributed sequentially, with the deadline represented in months on the horizontal axis, facilitating progress monitoring and project schedule control, as recommended by the Project Management Institute (PMI, 2021). The interdependence between the schedule stages is particularly high in health projects, which increases the project’s sensitivity to operational deviations and delays, directly impacting the final implementation deadline.
The calculations of the economic-financial feasibility indicators were performed for three distinct scenarios – realistic, pessimistic, and critical – as defined in the methodology. This approach allowed for an evaluation of how variations in the project implementation timeline affected cash flows and, consequently, the Net Present Value (NPV), Internal Rate of Return (IRR), and Payback indicators. In the delayed scenarios, cash flows were adjusted to reflect the postponement of revenue generation, while the costs associated with the implementation period were maintained, highlighting the direct impact of the schedule on the investment’s financial attractiveness.
Realistic scenario
In the realistic scenario, the project execution occurred according to the initial planning, without delays. This allowed revenue generation to begin on schedule, maintaining consistency between planning and execution. Commercial negotiations and partnerships were established according to the premises, and project maturity, with 100% of the planned volume, was reached in the first six months of operation, specifically in January 2022. This scenario, considered the base scenario, served as a reference for financial modeling, which included detailed assumptions about capital investments, costs, personnel expenses, medical contracts, and other operational services.
The financial indicators for the realistic scenario presented robust and positive results, which facilitated their approval by the executive committee. The Net Present Value (NPV) proved to be relevant and positive, indicating that the project would generate economic value superior to the initial investment, considering the opportunity cost of capital. The Internal Rate of Return (IRR) was 56%, a value significantly higher than the discount rate of 16% used, confirming the high profitability of the investment. The Payback, in turn, indicated that the invested capital would be recovered in a period of 1.9 years, reflecting a rapid recovery of the investment and a low liquidity risk.
Pessimistic scenario
In the pessimistic scenario, a six-month delay in project implementation was considered, which required adjustments in cash flow. The main factor for this delay was the uncertainty and misalignment in commercial negotiations with partner agreements, generating discredit and insecurity among the clinical staff. Although the medical team remained on the project, the commercial issue impacted the start of construction, postponing the beginning of operations and, consequently, the start of revenue generation. The project’s maturity, with the total volume of services, was only reached in August 2023, one year and seven months later than predicted in the realistic scenario.
The financial impacts in this scenario were notable. Although the NPV still remained positive, with a value of 853,517 BRL, there was a significant reduction compared to the realistic scenario. The IRR decreased considerably, reaching 22.5%, which, although still higher than the discount rate of 16%, represented a substantial drop in the project’s expected profitability. The Payback, which in the realistic scenario was 1.9 years, increased to 4.1 years, indicating that the time needed to recover the initial investment more than doubled. This postponement of the return on invested capital made the project less attractive, increasing the perceived risk by investors.
Critical scenario
The critical scenario considered an even more severe delay of nine months in the project implementation. This delay was attributed to insecurity in commercial negotiations and the prolonged evolution time of the works, generating more critical impacts and making the project financially unviable. In addition to the implementation delay, a delay in the ramp-up of procedure volumetry was considered, with project maturity being reached only in October 2023 and, even so, with only 90% of the initially projected volumetry. Discontent and slowness in closing commercial agreements prevented value generation and credibility with external stakeholders, compromising revenue capacity.
In this scenario, the financial indicators revealed a situation of unviability. The NPV became negative, with a value of (1,250,124) BRL, indicating that the project would not be able to generate sufficient economic value to cover the initial investment and the cost of capital. The IRR dropped drastically to 6.4%, falling below the discount rate of 16%, which means the project would not offer a minimum acceptable return for the investment. The Payback increased to 5.5 years, demonstrating that the project would not even be able to recover the initial investment within a reasonable period, evidencing a sharp loss of financial attractiveness and a high risk of non-return of capital.
The comparative analysis between the scenarios shows that variations in the schedule exert a direct and significant influence on the economic-financial feasibility indicators. The postponement of cash flows, resulting from delays, reduces the present value of future revenues, negatively impacting the NPV. The greater the delay, the greater the loss of economic value of the project, according to the principle of the time value of money (Damodaran, 2012; Ross, Westerfield, and Jaffe, 2015). In addition to the change in cash flows, the alteration in the ramp-up of procedure volume also contributed to the reduction in value, as pent-up demand may not materialize over time, and commercial negotiations may fail.
Regarding the IRR, the extension of the project implementation deadline shifts positive cash flows to more distant future periods. This reduces the internal rate of return, making the project less attractive when compared to other investment opportunities. The Payback, in turn, increases proportionally to the delay, raising the time needed to recover the initial investment and, consequently, the project’s financial risk. These results reinforce the importance of considering the schedule not only as an operational tool but as a fundamental strategic variable in project feasibility analysis, as highlighted by Kerzner (2018) and PMI (2021).
The findings obtained reinforce the understanding that the schedule must be treated as a strategic variable in project feasibility analysis. The analysis demonstrated that delays not only postpone revenues but alter the economic structure that had been projected, potentially compromising the financial sustainability of the venture. In the context of healthcare services, this effect is amplified due to the presence of high fixed costs and the need for a maturation period for healthcare demand. Even projects that initially showed positive economic feasibility can become less attractive or even unviable when subjected to schedule delays, as evidenced in the critical scenario.
The main contribution of this analysis lies in demonstrating that the feasibility study should not be static. It is essential that the schedule be continuously monitored, that financial assumptions be periodically reviewed, and that new scenarios be recalculated throughout the project execution. This approach allows for greater effectiveness in the integration between planning and reality, reducing risks and increasing the quality of decision-making. The integration between schedule management and economic-financial feasibility analysis is crucial to ensure the sustainability of health investments, highlighting the need for continuous monitoring of project stages and periodic reviews of financial scenarios, even after initial approval.
4. Conclusion
The study sought to analyze the impact on economic-financial viability arising from the non-compliance with the schedule of a specialty medical clinic implementation project, considering the indicators of Net Present Value (NPV), Internal Rate of Return (IRR), and Payback. It was verified that the non-compliance with the schedule negatively impacted the project’s viability, mainly due to the postponement of revenue entry, increased operational costs, and the need for revision of financial assumptions. A reduction in NPV and IRR, and an increase in Payback were observed in scenarios with delays. In critical scenarios, NPV became negative and Payback increased significantly, compromising the investment’s attractiveness and indicating unviability. The analysis demonstrated that delays not only postpone revenues but alter the projected economic structure, an effect amplified in the healthcare sector due to high fixed costs and the maturation time of healthcare demand.
The main contribution of this study lies in reinforcing the importance of integration between schedule management and economic-financial feasibility analysis, highlighting the need for continuous monitoring of project stages and periodic reviews of financial scenarios, even after initial approval. This approach expands the traditional feasibility analysis by incorporating time as a critical element in decision-making for health projects, demonstrating that feasibility studies should not be static. As a limitation, changes in assumptions such as average ticket price and implementation costs were not considered, focusing primarily on the impacts of the schedule on cash flows and volume ramp-up. For future studies, it is recommended to broaden the analysis to different types of health services and apply robust qualitative models, including additional simulations and risk analysis, in order to deepen the understanding of the financial impacts arising from delays in complex projects.
Bibliographic References
DAMODARAN, Aswath. Avaliação de investimentos: ferramentas e técnicas para determinar o valor de qualquer ativo. Rio de Janeiro: LTC, 2012.
GITMAN, Lawrence J. Princípios de administração financeira. 12. ed. São Paulo: Pearson, 2010.
KERZNER, Harold. Gestão de projetos: as melhores práticas. Porto Alegre: Bookman, 2018.
PROJECT MANAGEMENT INSTITUTE (PMI). Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK®). 7. ed. Newtown Square, PA: PMI, 2021.
ROSS, Stephen A.; WESTERFIELD, Randolph W.; JAFFE, Jeffrey. Administração financeira. 10. ed. Porto Alegre: AMGH, 2015.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq
To learn more about the course, click here and access the MBX Academy platform