Time management applied to the reduction of engineering services delivery

Luciano Pereira da Silva Neto; Luís Felipe Vendramim

DOI: 10.22167/2675-6528-202601116

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The delivery of engineering services is frequently impacted by delays resulting from failures in planning, execution, and time control, in addition to factors such as rework, scope changes, resource unavailability, and poor communication between teams. These challenges compromise deadline predictability and operational efficiency. The time management practices adopted in the delivery of engineering services were evaluated, identifying critical factors that impact deadlines, with the purpose of proposing a model for reducing delivery time applicable to companies in the sector. The methodology employed a quali-quantitative survey, using a Likert questionnaire, descriptive analysis, risk matrix, performance indicators (KPIs), and a 5W2H action plan. The results revealed the predominance of prior planning and the importance of continuous monitoring of services and identification of deviations. The main causes of delay identified were rework and the lack of complete technical information. A risk matrix organized these factors according to their probability and impact. KPIs were defined, such as the percentage of activities completed on time, the number of rework instances, and the variation between planned and executed deadlines. The 5W2H plan structured actions such as process standardization, schedule control, and risk anticipation to mitigate delays. It was concluded that effective time management in engineering services depends on the integration of planning, control, and risk mitigation, offering a structured set of management tools for improving temporal performance.

Keywords: Schedule; Temporal performance; Performance indicators; Project planning; Rework.

1. Introduction

Project management is of great importance in environments characterized by technical complexity, multiple stakeholders, and strict deadline constraints (Buganová et al., 2019). In engineering-intensive sectors, projects and services demand precise coordination between interdependent activities, specialized resources, and detailed technical information. In this scenario, time plays a central role, as delays compromise not only operational performance but also costs, quality, and organizational credibility (Abreu et al., 2025). The ability to manage time effectively therefore becomes a competitive differentiator and a pillar for business sustainability, requiring systematic approaches to mitigate risks and optimize results.

Time management in projects can be understood as the set of practices focused on planning, organizing, monitoring, and controlling the activities necessary for the delivery of a defined scope within established deadlines. In engineering services, this dimension acquires additional relevance, as the work frequently involves sequential steps, critical technical decisions, and high dependence between multidisciplinary teams. Thus, time ceases to be just an operational variable and becomes a strategic management element (Li et al., 2017). The schedule emerges as the main instrument for the temporal representation of engineering projects and services. It allows visualizing the duration of activities, their dependencies, and the logical sequence of execution, serving as a reference for performance monitoring throughout the service lifecycle. The absence of structured schedules or the merely formal use of this instrument tends to reduce the predictability of deadlines, making it difficult to identify deviations and adopt corrective actions in a timely manner (Rashed et al., 2024).

In the context of engineering, temporal planning faces specific challenges related to scope definition, variability of execution conditions, and the need for technical adjustments during service development. Changes in requirements, project revisions, and adaptations due to external constraints frequently impact the schedule, demanding replanning capability and agile decision-making. When these changes are not adequately managed, delays become recurrent and cumulative (Aljadhai et al., 2024). Another relevant aspect concerns the quality of technical information used in time planning. Insufficiency or inconsistency of this information compromises the estimation of activity durations and favors rework. In engineering services, rework represents one of the main sources of temporal waste, as it implies repeating tasks already executed, reorganizing the schedule, and redirecting previously allocated resources (Aven et al., 2007). The technical experience of the professionals involved, although crucial, must be complemented by systematized time management practices to ensure standardization and consistency in results (Batz-Barbarich et al., 2024).

The execution and control of deadlines are critical steps to ensure that temporal planning translates into effective performance. Periodic monitoring of activity progress allows for the identification of deviations from the schedule and understanding their causes before the impacts become irreversible. In engineering services, where multiple activities occur simultaneously, the absence of this monitoring hinders team coordination and increases the risk of widespread delays (Wang, L. et al., 2024). The identification of critical activities represents another fundamental element of time management in engineering projects and services. Not all activities have the same impact on the final deadline, and the inability to recognize those that condition the total duration of the service limits the prioritization of managerial efforts. Delays in critical activities tend to directly affect delivery, while delays in non-critical activities can be absorbed without compromising the overall schedule (Xiao et al., 2021). Time management in engineering is also strongly associated with resource availability, whether human, material, or technological. The pursuit of reducing delivery time in engineering services has directed attention to practices that promote greater predictability, standardization, and control (Suresh et al., 2024).

Given the inherent complexity of engineering services and the persistent challenges in time management, which manifest in recurring delays, rework, and operational inefficiencies, it becomes imperative to deepen the understanding of adopted practices and the factors impacting temporal performance. The relevance of effective time management for the competitiveness and sustainability of companies in the sector justifies the need to investigate current approaches and identify improvement opportunities. Thus, the present work aimed to evaluate the time management practices adopted in the delivery of engineering services, identifying the critical factors that impact deadlines, with the purpose of proposing a model for reducing delivery time applicable to companies in the sector.

2. Material and Methods

This research was characterized as a survey-type study, with a quali-quantitative approach, conducted with professionals working in different civil engineering companies. This methodological choice allowed for the systematic collection of data on perceptions, practices, and behaviors in organizational contexts (Dasović et al., 2020). The quantitative approach enabled the measurement of responses through descriptive statistical analysis, while the qualitative approach contributed to the interpretation of results, providing a comprehensive understanding of the investigated phenomenon (Guerra et al., 2024). This methodological combination favored the integrated analysis of data, conferring greater consistency to the investigation of time management practices in engineering services (Bahia et al., 2023).

The research environment was characterized by the participation of professionals from various civil engineering companies, without restriction to a single organization. This multifaceted context allowed for the capture of perceptions from distinct operational realities, project management maturity levels, and ways of conducting engineering services. The observed organizational diversity broadened the scope of the analysis, incorporating variations in time management processes, practices, and structures, making the findings more representative of the sector. Data collection occurred during a defined period, without exact dates in the original TCC.

The target audience of the research was composed of professionals directly involved in the execution, monitoring, or management of engineering services, including technical profiles, analysts, coordinators, and managers. As an inclusion criterion, participants with direct experience in the analyzed services and effective participation in planning, decision-making, or execution activities were considered. Professionals without direct involvement with the services or without involvement in time management were excluded, ensuring the adherence of the responses to the object of study.

The research sample was characterized as non-probabilistic, intentional, or judgment type. Participants were selected based on their performance and experience in engineering services, ensuring adherence to the study’s objective. Additionally, sampling occurred by convenience, with access to respondents through specific professional groups and the LinkedIn platform. The questionnaire was sent to 50 potential participants, of whom 34 responded, resulting in a response rate of 68%, considered adequate for applied research in an organizational context.

For data collection, a structured questionnaire was used, developed based on project management principles applied to time management, detailed in Appendix I. The instrument covered aspects such as activity planning, deadline definition, execution monitoring, deviation identification, and practices for reducing delivery time. Adapted to the engineering context, the questionnaire contained 23 statements, organized into five progressive thematic blocks: Respondent Profile, Time Planning, Execution and Deadline Control, Main Causes of Delay, and Practices for Reducing Delivery Time. The application took approximately 10 minutes.

The questionnaire statements were evaluated using a five-point Likert scale, ranging from 1 (Strongly disagree) to 5 (Strongly agree). This scale allowed for the measurement of different levels of agreement and intensity of respondents’ perceptions, enabling quantitative analyses and managerial interpretations. Before the final application, the questionnaire underwent a preliminary check to ensure clarity, objectivity, and homogeneous understanding. Subsequently, the instrument was made available in digital format, through the Google Forms platform, and was applied during the period defined for data collection.

The obtained data were organized and analyzed using descriptive statistics, with the results presented in absolute and percentage frequencies, according to the nature of each variable. The graphical representation of the results was performed with the aid of GraphPad Prism software version 10.2. This software allowed the construction of graphs that clearly visualized the distributions of the responses and the comparison between the different thematic blocks of the research instrument, contributing to the managerial interpretation of perceptions.

The construction of the risk matrix aimed to systematically structure the main risks associated with meeting deadlines in engineering services, based on perceptions collected in the questionnaire. The process followed a qualitative approach, supported by descriptive quantitative data, organizing the risk factors in a logical and coherent manner. The identification of risks was based on the questionnaire’s statements related to the causes of delays and the practices for execution and control of deadlines, selecting factors potentially capable of negatively impacting the service delivery time. The qualitative analysis considered the probability of occurrence and impact on the delivery time, evaluated on a five-level ordinal scale, from low to high, standardizing the classification. The assignment of levels was based on the frequency and intensity of respondents’ perceptions, ensuring collective grounding.

After defining the probability and impact levels, the risks were positioned on the matrix, which adopts a two-dimensional structure. The horizontal axis represented the probability of occurrence and the vertical axis the impact on the deadline. Each risk was allocated to a specific cell of the matrix, allowing its relative criticality to be visualized. The matrix was conceived as a classification and prioritization tool, not as an instrument for absolute risk quantification. Its methodological purpose was to organize the identified factors according to relative levels of managerial attention, respecting the perceptual nature of the data.

The definition of time performance indicators (KPIs) was carried out to structure the monitoring and control of time in engineering services, aligning the perceptions collected in the questionnaire with the main identified risks. The proposed KPIs were structured based on easily obtainable quantitative measures, expressed through percentages or absolute values, allowing their application in different organizations. These indicators were conceived as a decision-making support tool, enabling continuous monitoring of temporal performance and the identification of delays in service execution.

The 5W2H analysis was employed as a methodological step to structure the proposition of management actions aimed at reducing delivery time in engineering services. Its construction started from the risks organized in the matrix and the defined deadline performance indicators, transforming the diagnosis into a systematized action plan. The application of 5W2H followed a sequential logic, defining what, why, where, when, who, how, and how much. This approach detailed the actions clearly and objectively, favoring their understanding and replicability in different organizational contexts, integrating risk analysis and performance indicators into a structured plan.

Considering the nature of the research, the absence of sensitive data collection, and the exclusive participation of adults in an organizational context, the study was exempted from review by the CEP/CONEP system. This exemption was supported by the Ethics Exemption Form [FDE] issued by ESALQ/USP. All participants were duly informed about the research objectives and agreed to participate through the Consent agreement [TCLE]. It was guaranteed that participant identification would be kept confidential and that the results would be used exclusively for scientific purposes, including publication.

As methodological limitations, it should be noted that the research was conducted based on the respondents’ perception, without contemplating the analysis of real historical data from schedules or objective measurements of schedule performance. Furthermore, the sample focused on engineering professionals, which may limit the generalization of the results to other sectors with distinct operational dynamics. The proposed performance indicators and action plan are conceptual in nature, not having been empirically implemented or validated in a specific organization, which represents a frontier for future investigations.

3. Results and Discussion

The characterization of the research participants’ profile provided an essential overview to contextualize perceptions of time management in engineering services. The predominance of mechanical engineering professionals, who represented 64.7% of the sample, followed by civil engineering with 14.7%, as illustrated in Figure 1 A, highlights the relevance of these segments for the study. This demographic distribution not only validates the applicability of the findings to technically complex sectors but also underscores the need for time management approaches that consider the specificities of each discipline. Mechanical engineering, for example, often deals with projects involving meticulous technical detailing and complex interdependencies between components, where delays in one phase can have significant cascading effects. Similarly, civil engineering, with its execution projects and rigid schedules, requires robust temporal control to avoid cost and schedule overruns (Buganová et al., 2019). The diversity of roles, including mechatronic engineering (8.8%), electrical engineering (2.9%), and other areas (8.8%), reinforces the research’s scope and the need for a time management model adaptable to different technical and operational contexts.

Source: Original research results

Figure 1. Profile of the questionnaire respondents

The analysis of the respondents’ professional experience time revealed a predominantly experienced sample, with 32.8% of participants having more than 10 years of practice and 26.5% between 6 and 10 years, as detailed in Figure 1 B. This data is of utmost importance, as the perceptions collected come from professionals with consolidated experience in the sector, whose practical experiences enrich the analysis of challenges and best practices in time management. Accumulated experience allows for a deeper understanding of the causes of delays and effective strategies to mitigate them, lending greater credibility to the research results (Batz-Barbarich et al., 2024). The inclusion of professionals with 3 to 5 years (23.5%) and up to 2 years (11.8%) of experience also ensures a perspective on the initial career stages, where process formalization and mentoring can be crucial for developing time management skills. The combination of these different experience ranges offers a holistic view of the maturity of time management in the sector.

The types of engineering services most frequently performed by the participants, presented in Figure 2, indicate that “Calculations/projects” was the most mentioned (23 indications), followed by “Execution of works/services” (12 indications). The activities of “Consulting” (11 indications), “Maintenance” (10 indications), and “Others” (10 indications) also showed relevance. This distribution underscores that the participants are involved in activities that are intrinsically dependent on rigorous temporal planning and control. Calculations and projects, for example, are the basis for any engineering undertaking and require well-defined deadlines to ensure the delivery of accurate and timely technical documentation. The execution of works, in turn, is a dynamic and complex process, where time management is fundamental to coordinating teams, resources, and construction stages, minimizing interruptions and delays (Li et al., 2017). The diversity of services reinforces the need for a time management model that is flexible and applicable to different phases of the engineering project lifecycle, from conception to delivery and maintenance.

Source: Original research results

Figure 2. Distribution of the types of engineering services provided by the research participants

Regarding time planning, the results show a strong incorporation of this practice in engineering services, although with variations in formalization. The statement about planning activities before the start of services obtained 19 “strongly agree” responses and 12 “agree”, with only 2 disagreements and 2 neutral positions (Figure 3 A). This finding corroborates the literature that points to prior planning as a pillar for predictability and uncertainty reduction in complex projects (A. Kassem et al., 2019). Companies that invest in detailed planning from the outset tend to have greater clarity on the scope, necessary resources, and deadlines, which translates into greater operational efficiency. Practical implications include the need for standardization of planning methodologies, such as the development of detailed schedules and the definition of milestones, in addition to promoting planning workshops with all stakeholders to ensure alignment and mitigation of potential risks before they materialize.

Source: Original research results

Figure 3. Time planning

The definition of deadlines based on historical data or technical experience also proved to be a consolidated practice, with 19 participants fully agreeing and 11 agreeing, while 4 disagreed and 1 maintained a neutral position (Figure 3 B). This reliance on professional experience, although it can accelerate decision-making and adapt to specific contexts, can also limit the standardization and traceability of estimates, especially in innovative projects or those with little historical basis (Abreu et al., 2025). To mitigate this limitation, organizations should seek to integrate individual experience with formal estimation methods, such as parametric or analogy-based estimation, and maintain a lessons learned database to continuously refine deadline estimates. The creation of a repository of historical data from completed projects, with deadline performance metrics, can provide a more robust basis for future estimates, reducing subjectivity and increasing accuracy.

The logical sequencing of activities obtained a high level of consensus, with 16 “strongly agree” responses and 16 “agree” responses, and no disagreement (Figure 3 C). This result is crucial, as the logical organization of activities and the understanding of their interdependencies are fundamental to avoiding overlaps, rework, and operational bottlenecks, especially in engineering services with multiple technical interfaces (Acebes et al., 2024). The practical application of this finding lies in the use of project management tools that allow for clear visualization of dependencies, such as network diagrams and scheduling software. Furthermore, periodic review of the sequencing, especially after scope or resource changes, is vital to maintain schedule coherence. The lack of logical sequencing can lead to significant inefficiencies, where teams await the completion of predecessor tasks or begin work without the necessary information, generating waste of time and resources.

The identification of critical activities impacting the deadline revealed a positive but less homogeneous perception, with 13 participants fully agreeing and 13 agreeing, but with 4 disagreeing, 1 fully disagreeing, and 3 neutral positions (Figure 3 D). This dispersion suggests that, although the importance of criticality is recognized, its practical application may be inconsistent, compromising the prioritization of managerial efforts and the ability to respond to delays in determining stages (Bastos et al., 2025). The non-identification or mismanagement of critical activities can result in widespread delays, even if non-critical activities are completed on time (Xiao et al., 2021). Companies should invest in training on critical path analysis and schedule optimization techniques, in addition to implementing regular schedule reviews to re-evaluate the criticality of activities, especially in dynamic projects. The use of project management software that automatically calculates the critical path can be a valuable tool to ensure that managers have constant visibility of the most deadline-sensitive activities.

Finally, the documentation and communication of the schedule to the involved team showed greater variability in responses, with 14 “strongly agree” and 7 “agree”, but also 7 neutral positions and 6 disagreements (3 “disagree” and 3 “strongly disagree”) (Figure 3 E). This heterogeneity points to weaknesses in the formalization and sharing of the schedule as an instrument for collective management, which can lead to misalignments, priority conflicts, and coordination difficulties between teams (Goh et al., 2014). Effective schedule communication is vital to ensure that all team members and stakeholders understand their responsibilities, deadlines, and interdependencies. Practical implications include the implementation of project kick-off meetings to present the schedule, the use of collaborative platforms for real-time sharing and updating, and the creation of formal communication channels to discuss deviations and adjustments. The absence of clear communication can result in rework and delays, as teams may operate with outdated or incomplete information.

In the execution and control of deadlines, the results indicate that temporal performance monitoring is a relatively consolidated practice. Periodic monitoring of service progress obtained 18 “strongly agree” responses and 13 “agree”, with only 4 neutral positions and no disagreement (Figure 4 A). This high level of agreement reinforces the perception that continuous monitoring is essential for deadline management, providing visibility into progress and allowing for the anticipation of potential deviations (Kim et al., 2022). The monitoring practice should be systematic, with the definition of monitoring frequencies (daily, weekly, monthly) and the use of clear performance indicators (KPIs). The implementation of regular status meetings and real-time schedule updates are practices that can further strengthen this aspect, ensuring that managers have accurate information for decision-making.

Source: Original research results

Figure 4. Deadline control

The identification of schedule deviations during execution also showed a predominantly positive perception, with 17 participants fully agreeing and 14 agreeing, while 2 disagreed and 2 remained neutral (Figure 4 B). This data suggests that professionals can perceive delays even during execution, which is fundamental to reducing accumulated impacts and supporting timely corrective decisions (Koszykowski et al., 2025). However, mere identification is not enough; it is crucial that this identification is followed by a root cause analysis and the implementation of effective corrective actions. Companies should develop an early warning system for schedule deviations, integrating monitoring with trend analysis tools. Training teams to identify and report deviations proactively, rather than reactively, can transform deviation management into a competitive advantage, allowing for adjustments before problems worsen.

The adoption of corrective actions when there is a risk of delay showed equally favorable results, with 14 “strongly agree” responses and 16 “agree”, 3 neutral positions, and 2 disagreements (Figure 4 C). This behavior indicates that the identification of temporal risks tends to be accompanied by mitigation initiatives. However, the literature suggests that many of these actions may be reactive, focused on solving problems already manifested, rather than preventive (Li et al., 2017). To improve this practice, organizations should develop contingency plans for identified risks, establishing clear triggers for the activation of these actions. The creation of a “lessons learned” database on successful and unsuccessful corrective actions can serve as a valuable resource for future interventions, promoting a culture of continuous improvement and organizational learning.

Regarding communication between the parties involved about deadlines, the results indicate greater dispersion, with 11 “strongly agree” and 14 “agree”, but also 8 neutral positions and 4 disagreements (2 “disagree” and 2 “strongly disagree”) (Figure 4 D). This variability points to weaknesses in the communication of temporal aspects, which can compromise team alignment and hinder activity coordination (Meng et al., 2022). Ineffective communication is one of the main causes of project delays, as it leads to misunderstandings, duplication of efforts, and lack of synchrony between teams. Companies should implement a formal communication plan, defining who communicates what, to whom, when, and how. The use of digital collaboration tools, periodic alignment meetings, and standardized progress reports can significantly improve communication, ensuring that all stakeholders are aware of the schedule status and any deviations.

Finally, regarding the use of time control tools, such as spreadsheets, software, or visual boards, the results demonstrate relevant, but not homogeneous, adherence. Fourteen participants fully agreed and 13 agreed, while 5 maintained a neutral position and 4 expressed disagreement (3 “disagree” and 1 “strongly disagree”) (Figure 4 E). These data indicate that, although control tools are widely used, there is still a portion of services where time control occurs informally or in a poorly structured manner (Suresh et al., 2024). Informality in control can lead to a lack of traceability, difficulty in identifying deviations, and a reduced capacity for trend analysis. Organizations should promote the adoption of more robust project management tools, such as specialized software, and offer training to ensure professionals know how to use them effectively. The standardization of tools and control methods is essential to ensure the consistency and reliability of temporal performance data.

The main causes of delay in engineering services were investigated, revealing recurring factors that compromise deadline adherence. Rework was widely recognized as a critical factor, with 23 “strongly agree” responses and 8 “agree”, while only 2 “strongly disagree” and 1 remained neutral (Figure 5 A). This result corroborates the literature that identifies rework as one of the main sources of time and resource waste, disrupting the execution flow and negatively impacting productivity (Wang, K. et al., 2024). Rework can be caused by failures in initial planning, incomplete technical information, unmanaged scope changes, or execution errors. To mitigate this risk, companies must invest in more rigorous project review and validation processes, promote a “do it right the first time” culture, and implement quality control systems that identify and correct errors early. Root cause analysis of rework is fundamental to implementing effective preventive actions.

Source: Original research results

Figure 5. Lag time

The lack of complete technical information demonstrated an even more expressive consensus as a cause of delay, with 25 participants fully agreeing and 5 agreeing, while only 1 fully disagreed, 1 disagreed, and 2 remained neutral (Figure 5 B). This finding reinforces that the insufficiency or imprecision of technical information at the beginning or during the execution of services compromises decision-making, favors operational errors, and directly contributes to the increase in delivery time (Kim et al., 2022). The quality of information is the basis for effective planning and execution. Practical implications include the implementation of a robust process for gathering requirements and information at the beginning of the project, conducting formal technical reviews, and using document management systems that ensure the availability of updated and complete information for all teams. Lack of data can lead to incorrect assumptions, which manifest as delays and additional costs.

Scope changes during execution were also pointed out as a critical factor, with 23 “strongly agree” responses and 8 “agree”, in addition to 1 “strongly disagree”, 1 “disagree”, and 1 “neutral” (Figure 5 C). This data highlights that unplanned or poorly controlled changes tend to generate significant impacts on the schedule, requiring replanning of activities and adjustments in resource allocation, which frequently results in delays (Koszykowski et al., 2025). Scope management is one of the pillars of project management, and its failure can destabilize the entire schedule. Companies must implement a formal change control process, which includes assessing the impact of each alteration on the schedule, cost, and resources, and formal approval by all stakeholders. Proactive communication about the implications of changes is essential for managing expectations and avoiding surprises that can lead to delays.

Regarding resource unavailability, the results demonstrate a widely favorable perception of its impact on delivery time. Twenty-one participants fully agreed and 10 agreed, while 1 fully disagreed and 2 maintained a neutral position (Figure 5 D). This result indicates that limitations related to labor, materials, or equipment compromise the continuity of activities, generating interruptions and extending the initially planned deadlines. Resource management is a constant challenge in engineering projects, where inadequate allocation or lack of availability can paralyze critical activities (A. Kassem et al., 2019). Practical implications include detailed resource planning, with early identification of labor and material needs, negotiation with suppliers to ensure availability, and the creation of contingency plans for resource scarcity. Optimizing resource allocation through management software can help maximize utilization and minimize idleness.

Finally, team integration showed positive results, albeit with greater dispersion. Twenty-two participants fully agreed and 4 agreed with the statement that integration directly influences deadlines, while 7 maintained a neutral position and 2 expressed disagreement (1 “strongly disagree” and 1 “disagree”) (Figure 5 E). This pattern suggests that, although integration is recognized as a relevant factor, its influence may vary depending on the level of coordination, communication, and organizational maturity (Lima et al., 2019). Low integration between teams, especially between technical areas, field teams, and management, can lead to misalignments, decision-making delays, and rework (Asad et al., 2019). To improve integration, companies should promote cross-functional collaboration, hold regular coordination meetings, use unified communication platforms, and establish shared goals and objectives among teams. Building a teamwork culture and valuing open communication are essential to optimize workflow and reduce delays.

Practices for reducing delivery time in engineering services were also evaluated, indicating strong alignment among participants regarding the relevance of structured management approaches. Process standardization achieved broad agreement, with 24 participants indicating “strongly agree” and 9 “agree”, while only 1 disagreed and 1 remained neutral (Figure 6 A). This result highlights that standardization is perceived as a determining factor for reducing operational variabilities, contributing to greater predictability of deadlines and a lower incidence of rework. Standardized processes provide a clear roadmap for activity execution, reducing the need for ad hoc decisions and minimizing errors. Practical implications include the documentation of standard operating procedures (SOPs), the implementation of checklists and templates for recurring activities, and the performance of process audits to ensure compliance. Standardization not only speeds up execution but also facilitates the training of new teams and continuous improvement.

Source: Original research results

Figure 6. Practices for time reduction

The use of project management methodologies as a means to improve deadline compliance was also overwhelmingly positive, with 20 participants fully agreeing and 10 agreeing, while 4 remained neutral and 1 disagreed (Figure 6 B). This data indicates that structured management practices are recognized as tools capable of supporting the planning, execution, and control of services, favoring the alignment between scope, time, and resources (Meng et al., 2022). The adoption of methodologies such as PMBOK, Agile, or Lean Construction can provide a robust framework for managing the complexity of engineering projects. Companies should invest in training their professionals in project management methodologies, adapting them to their specific needs. The implementation of a project management office (PMO) can centralize the governance and dissemination of these methodologies, ensuring their consistent application throughout the organization.

The clear definition of responsibilities showed a high level of consensus among respondents, with 23 “strongly agree” responses and 9 “agree”, in addition to only 2 neutral positions and no disagreement (Figure 6 C). This result reinforces that clarity regarding roles and responsibilities reduces ambiguities, overlap of activities, and communication failures, aspects frequently associated with delays (Rashed et al., 2024). When each team member knows exactly what is expected of them, efficiency increases and conflicts decrease. Practical implications include the development of responsibility matrices (such as the RACI matrix), the creation of detailed job descriptions, and explicit communication of responsibilities at the beginning of each project. Periodic review of these definitions, especially in long-term projects or those with team changes, is fundamental to maintaining alignment and avoiding responsibility gaps.

Regarding risk anticipation, the results indicate a broadly favorable perception of its contribution to reducing total service time. Twenty-three participants fully agreed and 7 agreed, while 4 maintained a neutral position and there were no records of disagreement (Figure 6 D). This pattern shows that prior identification of risks allows for the adoption of preventive measures, reducing the occurrence of unexpected events that negatively impact delivery times (Wang, K. et al., 2024). Proactive risk management is a competitive differentiator, allowing companies to prepare for potential challenges before they become real problems. Practical implications include the creation of a risk register, conducting periodic risk analyses, defining mitigation and contingency plans for the most critical risks, and assigning responsibilities for risk monitoring and risk treatment. A culture of risk anticipation should be integrated into all project phases, from planning to execution.

Finally, the assertion that the application of good management practices can be replicated in different engineering companies also obtained high agreement. Twenty-three participants fully agreed and 9 agreed, while only 1 disagreed and 1 remained neutral (Figure 6 E). This result suggests that the analyzed practices are perceived as adaptable to different organizational contexts, regardless of the size or type of service provided, reinforcing their potential for broad application in the engineering sector (Mishra et al., 2026). Replicability is a crucial aspect for knowledge dissemination and continuous improvement of the industry. Companies can facilitate this replication by creating a repository of best practices, training and mentoring programs, and promoting a culture of learning and knowledge sharing. However, adapting these practices to the specific realities of each organization is fundamental to ensuring their effectiveness.

From the analysis of the responses obtained in the questionnaire, it was possible to structure a risk matrix that organizes the main factors that negatively impact the fulfillment of deadlines in engineering services. Figure 7 presents this matrix, which reflects recurring patterns observed during the execution of services and is directly associated with technical, organizational, and managerial failures, according to the perception of the research participants.

Source: Original research results

Figure 7. Risks associated with delays

One of the most relevant risks identified in the matrix was rework, positioned with high probability and high impact. This finding is consistent with the high frequency of concordant responses in Figure 5 A, indicating that the repetition of activities, resulting from errors, late revisions, or lack of standardization, significantly compromises temporal performance. Rework not only consumes additional resources and disrupts the sequencing of previously planned activities, but also affects team morale and customer quality perception (Wang, K. et al., 2024). The high criticality of rework in the risk matrix emphasizes the urgent need for preventive actions, such as improving the quality of initial technical information and implementing rigorous validation processes at each project stage.

Another significant risk refers to the lack of complete technical information, also with high probability and high impact on the risk matrix. As demonstrated in Figure 5 B, the almost unanimous perception of the participants regarding this factor highlights that the absence or insufficiency of adequate technical data at the beginning or during the execution of services tends to generate decisions based on incomplete premises, increasing the probability of operational errors and subsequent adjustments (Kim et al., 2022). This risk is a primary vector for delays, as it prevents precise planning and efficient execution. The mitigation of this risk requires a concentrated effort in the requirements gathering phase, with the active participation of all stakeholders, and the implementation of document management systems that ensure the accessibility and updating of technical information.

Scope changes during execution were identified as another relevant risk in the matrix, with high probability and significant impact. Unforeseen or poorly controlled changes require replanning of activities, redistribution of resources, and in many cases, revision of originally established deadlines (Koszykowski et al., 2025). The recurrence of this risk, evidenced in Figure 5 C, points to weaknesses in the initial definition of scope and in change management, increasing the exposure of services to temporal deviations. Effective management of this risk requires the implementation of a formal change control process, which assesses the impact of each alteration on the schedule and costs, and transparent communication of these implications to all stakeholders involved.

The unavailability of resources, whether human, material, or equipment, constitutes another significant risk to meeting deadlines, with high probability and moderate to high impact on the matrix. The interruption or slowdown of activities due to lack of resources directly impacts the progress of the schedule, especially in engineering services characterized by strong interdependence between tasks (A. Kassem et al., 2019). Figure 5 D reinforces this perception. This risk highlights the importance of integrated planning between scope, time, and resources, with the creation of contingency plans for resource scarcity and the optimization of allocation to avoid bottlenecks.

Finally, the low integration between teams was identified as a relevant organizational risk, with moderate probability and moderate to high impact on the matrix. Although the perception of its influence is more heterogeneous (Figure 5 E), failures in articulation between technical areas, field teams, and management tend to generate misalignments, delays in decision-making, and rework, compromising the continuous flow of activities (Asad et al., 2019). This risk highlights that factors related to communication and coordination directly influence the temporal performance of services. Actions to improve integration include promoting interdepartmental meetings, using collaborative platforms, and clearly defining roles and responsibilities to foster a more cohesive and efficient work environment.

Based on the results obtained and the main causes of delay identified, the use of KPIs is proposed as a tool to support the control, monitoring and continuous improvement of engineering services. The adoption of these indicators allows qualitative perceptions to be transformed into managerial information, favoring decision-making and systematic monitoring of the temporal performance of services (Buganová et al., 2019).

One of the proposed indicators is the percentage of activities completed on time, which aims to measure the degree of adherence of the service to the planned schedule. This indicator allows for the evaluation of the efficiency of activity planning and execution, showing whether the defined deadlines are being effectively met. Low values of this percentage indicate the need to review the planning, the sequencing of activities, or the control strategies adopted during execution. Continuously monitoring this KPI allows managers to identify delay trends and intervene proactively, adjusting resources or redefining priorities.

Another relevant indicator refers to the number of reworkings per service, directly associated with the causes of delay identified in the research (Figure 5 A). This indicator allows monitoring the recurrence of technical failures, information inadequacies, or integration problems between teams that result in the repetition of activities. An increase in the number of reworkings tends to negatively impact delivery deadlines, making this indicator fundamental for identifying operational inefficiencies and for proposing corrective actions aimed at standardizing and improving the quality of technical information. A consistent reduction in this KPI would signal an improvement in the quality of planning and execution.

The use of the variation between planned and executed deadline indicator is also proposed, which allows measuring the temporal deviation that occurred during the service execution. This indicator provides an objective view of the difference between expected performance and actual performance, assisting in the identification of delay patterns and in the analysis of the effectiveness of corrective actions taken. Recurring deviations indicate weaknesses in the deadline estimation process, in execution control, or in the management of risks associated with the schedule. Variance analysis can reveal the accuracy of initial estimates and the effectiveness of the control strategies implemented, providing valuable insights for the continuous improvement of time management processes.

The proposed indicators allow monitoring time performance from different perspectives, encompassing both the execution of activities and the occurrence of failures and deviations. The systematic use of these KPIs contributes to strengthening deadline control, improving service predictability, and consolidating a time-management-oriented approach in engineering services (Buganová et al., 2019). The integration of these KPIs into a managerial control panel can provide a clear, real-time view of temporal performance, enabling managers to make data-driven decisions and implement corrective actions agilely and effectively.

Based on the risks identified in the risk matrix and the proposed KPIs, an action plan was developed structured according to the 5W2H logic, with the objective of guiding the implementation of managerial actions aimed at reducing delivery time in engineering services. The proposed plan seeks to transform the research findings into practical actions, applicable in different organizational contexts, as detailed in Table 1.

Table 1. Action plan for reducing delivery time based on 5W2H analysis

What

Why

Where

When

Who (Who)

How

How much

Key Performance Indicator (KPI)

Standardize technical information

Reduce rework and delays

Service planning phase

Before the start and during execution

Service Manager / Technical Lead

Use of standardized models, technical checklists, and prior validation of information

Low cost (organizational effort)

Number of reworkings per service

Develop and maintain documented and shared schedules

Improve team control, predictability, and alignment regarding deadlines

All engineering services

Throughout the service cycle

Project / Service Manager

Use of spreadsheets, scheduling software, or visual boards

Low or nonexistent

Percentage of activities completed on time

Identify and monitor critical activities

Avoid punctual delays compromising the final service deadline

Services with higher technical complexity

During planning and periodic reviews

Service manager and technical team

Analysis of dependencies between activities and prioritization of critical tasks

Non-existent

Variation between planned and executed deadline

Anticipate and treat deadline risks

Minimize impacts of scope changes, resource unavailability, and integration failures

All engineering services

Before the start and during execution

Service Manager

Use of the risk matrix for defining preventive and corrective actions

Low indirect cost

Variation between planned and executed deadline

Clearly define responsibilities and communication flows

Reduce delays arising from misalignment between teams

All levels involved in the service

Service start

Service Leadership / Coordination

Application of responsibility matrix and formal communication routines

Non-existent

Percentage of activities completed on time / Number of reworkings

Source: Original research results

The first action refers to the standardization of technical information and planning processes (What). This action aims to reduce the occurrence of rework and minimize delays due to incomplete or inconsistent information (Why), risks identified as critical in the risk matrix (Figure 7). Standardization should be applied in the initial phase of services (When), covering technical documents, scope, assumptions, and execution criteria (Where). The responsibility for this action falls on the service manager or technical responsible (Who), using standardized templates, technical checklists, and prior information validation (How), without the need for significant financial investments (How much). Monitoring the effectiveness of this action can be done through the KPI “number of reworkings per service”. The implementation of a document management system and the creation of a centralized repository of technical information are practical steps to ensure that all teams have access to consistent and up-to-date data, minimizing the probability of errors and rework.

The second proposed action consists of the systematic use of documented and shared schedules (What), aiming to improve the control and predictability of deadlines (Why). This action should be implemented during planning and maintained throughout the execution of services (When), being applied to all engineering services conducted by the organization (Where). The person responsible for the elaboration and updating of the schedule should be the project or service manager (Who), using simple tools such as spreadsheets, scheduling software, or visual boards (How). The cost associated with this action is low or non-existent (How much), and its effectiveness can be monitored through the KPI “percentage of activities completed on time”. Clear documentation and sharing of the schedule promote alignment of expectations between stakeholders and the team, reducing variability in perceptions and ensuring that everyone works based on the same information (Goh et al., 2014).

As a third action, the identification and monitoring of critical activities (What) is proposed, with the objective of preventing punctual delays from compromising the final service deadline (Why). This practice should be incorporated during planning and revisited whenever there are relevant changes (When), applying especially to services with greater technical complexity (Where). Responsibility is assigned to the service manager together with the technical team (Who), through the analysis of dependencies between activities and prioritization of critical tasks (How). This action does not require additional costs (How much) and can be monitored by the KPI “variation between planned deadline and executed deadline”. Critical path analysis is an essential tool for this action, allowing managers to focus their efforts on activities that have the greatest potential to impact the final deadline, optimizing resource allocation and decision-making (Xiao et al., 2021).

Another relevant action is related to the anticipation and treatment of schedule risks (What), focusing on reducing the impacts associated with resource unavailability, scope changes, and integration failures between teams (Why). This action should preferably occur before the start of execution and be periodically reviewed (When), involving all engineering services (Where). The service manager is primarily responsible (Who), using the risk matrix as a support tool for defining preventive and corrective responses (How). The costs are indirect and associated with planning effort (How much), with the effectiveness of this action reflected in the improvement of schedule indicators and the reduction of deviations. The creation of a detailed risk register, identifying triggers and contingency plans, is fundamental to transforming risk management from a reactive to a proactive approach, minimizing the occurrence of unexpected events that cause delays (Wang, K. et al., 2024).

Finally, a clear definition of responsibilities and communication flows (What) is proposed, with the aim of improving integration between teams and reducing delays arising from organizational misalignments (Why). This action should be established at the beginning of the services (When) and applied at all levels involved in execution (Where). The responsibility for defining roles lies with the service leadership (Who), and it can be operationalized through responsibility matrices and formal communication routines (How). The associated cost is minimal (How much), and its effectiveness can be observed indirectly through the improvement of KPIs related to deadline compliance and rework reduction. The implementation of a formal communication plan, which defines the frequency and channels of communication, along with the use of collaborative tools, can mitigate the communication weaknesses identified in the research (Meng et al., 2022), promoting a more integrated and efficient work environment.

4. Conclusion

It is concluded that the objective was achieved, as the present work comprehensively evaluated the time management practices adopted in the delivery of engineering services, identifying the critical factors that impact deadlines and, consequently, proposing a structured model for reducing delivery time applicable to companies in the sector. The research results showed that, although prior planning and progress monitoring are recognized and adopted practices by professionals, the effectiveness of time management is frequently compromised by recurring challenges. Among the critical factors identified, rework, lack of complete technical information, unmanaged scope changes, resource unavailability, and low integration between teams stand out. To mitigate these problems, the research proposed a detailed action plan, based on performance indicators (KPIs) and the 5W2H methodology, aiming to optimize workflow and deadline predictability.

However, it is essential to acknowledge the inherent limitations of this study. The research was conducted based on respondents’ perceptions, meaning the results were not supplemented by analyses of actual historical data from schedules or objective measurements of schedule performance. Additionally, the sample focused on engineering professionals, which may limit the generalization of findings to other sectors with distinct operational dynamics. The proposed performance indicators and action plan are conceptual in nature, not having been empirically implemented or validated in a specific organization. For future research, it is recommended to apply the proposed model practically and monitor it longitudinally in engineering companies, integrate schedule indicators with cost and quality metrics, and conduct comparative investigations across different types of companies or related sectors to enhance and adapt the model to diverse organizational contexts.

Bibliographic References

A. Kassem, M., Khoiry, M. A., e Hamzah, N. 2019. Using probability impact matrix (PIM) in analyzing risk factors affecting the success of oil and gas construction projects in Yemen. International Journal of Energy Sector Management, 14(3), 527–546.

Abreu, A., Ribeiro, P., e Lima, A. 2025. Analysis of maturity in Project Management of an Information Technology company using the Prado-PMMM methodology. Procedia Computer Science, 256, 1558–1566.

Acebes, F., González-Varona, J. M., López-Paredes, A., e Pajares, J. 2024. Beyond probability-impact matrices in project risk management: A quantitative methodology for risk prioritisation. Humanities and Social Sciences Communications, 11(1).

Aljadhai, S., Alqahtani, F. K., Aldakhel, A., Alharbi, M., e Yamany, M. S. 2024. Assessment of scope definition for building projects in Saudi Arabia. Journal of Asian Architecture and Building Engineering, 24(5), 3863–3878.

Asad, M. M., Hassan, R. B., Sherwani, F., Abbas, Z., Shahbaz, M. S., e Soomro, Q. M. 2019. Identification of effective safety risk mitigating factors for well control drilling operation. Journal of Engineering, Design and Technology, 17(1), 218–229.

Aven, T., Vinnem, J. E., e Wiencke, H. S. 2007. A decision framework for risk management, with application to the offshore oil and gas industry. Reliability Engineering & System Safety, 92(4), 433-448.

Bahia, P. Q., Belo, R. d. L. S., Ferreira, L. R., e De Souza, R. R. C. 2023. A TÉcnica Do Estudo De Caso Como Estratégia Metodológica Aplicado Na Pesquisa Científica. Revista Contemporânea, 3(6), 5955–5984.

Bastos, R. A., Pierott, R. M. R., Navarro, L. L. L., Tam, V. W. Y., Najjar, M. K., e Haddad, A. N. 2025. Comparative analysis of communication in project management approaches: waterfall, agile, and hybrid. International Journal of Construction Management, 1–29.

Batz-Barbarich, C., Strah, N., e Tay, L. 2024. The impact of changing engineering perceptions on women’s attitudes and behavioral intentions towards engineering pursuits. International Journal of STEM Education, 11(1).

Buganová, K., e Šimíčková, J. 2019. Risk management in traditional and agile project management. Transportation Research Procedia, 40, 986–993.

Dasović, B., Galić, M., e Klanšek, U. 2020. A Survey on Integration of Optimization and Project Management Tools for Sustainable Construction Scheduling. Sustainability, 12(8).

Goh, H. H., Lee, S. W., Chua, Q. S., Goh, K. C., Kok, B. C., e Teo, K. T. K. 2014. Renewable energy project: Project management, challenges and risk. Renewable and Sustainable Energy Reviews, 38, 917–932.

Guerra, A. d. L. e. R., Stroparo, T. R., Costa, M. d., Castro Júnior, F. P. d., Lacerda Júnior, O. d. S., Brasil, M. M., e Camba, M. 2024. Pesquisa qualitativa e seus fundamentos na investigação científica. Revista de Gestão e Secretariado, 15(7).

Kim, J., Lim, J., Lim, H.-C., e Kim, D. Y. 2022. Improving Sustainable Project Success Strategies Focused on Cost and Schedule for Electrical Construction Project Management. Sustainability, 14(5).

Koszykowski, M., e Orzeszko, W. 2025. Machine learning in project schedule creation: a systematic literature review. Journal of Scheduling.

Li, X., Xu, J., e Zhang, Q. 2017. Research on Construction Schedule Management Based on BIM Technology. Procedia Engineering, 174, 657–667.

Lima, R., Tereso, A., e Faria, J. 2019. Project management under uncertainty: resource flexibility visualization in the schedule. Procedia Computer Science, 164, 381–388.

Meng, F., Yu, S., e Xue, J. 2022. Construction Schedule Management System for Large-Scale Construction Projects Based on Multisensor Network. Comput Intell Neurosci, 2022, 3003552.

Mishra, U., e Ganesh, N. 2026. A data-driven comparative analysis of Agile and Waterfall methodologies: Predicting cost and schedule variances using statistical and machine learning approaches. Array, 29.

Rashed, A. N. Z., Yarrarapu, M., Prabu, R. T., Raj Antony, G. S., Edeswaran, L., Kumar, E. S., Aswitha, K., Snehith, N., e Ahammad, S. H. 2024. Connected smart elevator systems for smart power and time saving. Sci Rep, 14(1), 19330.

Suresh, D., e Annamalai, S. 2024. Effect of schedule management plan in project management worth using structural equation modelling. An Acad Bras Cienc, 96(2), e20230117.

Wang, K., Dong, P., Chen, W., Ma, R., e Cui, L. 2024. Research on risk management of ship maintenance projects based on multi agent swarm model simulation method. Heliyon, 10(19), e38785.

Wang, L., Li, J., Ye, Q., Li, Y., e Feng, A. 2024. Automatic Planning Method of Construction Schedule under Multi-Dimensional Spatial Resource Constraints. Buildings, 14(10).

Xiao, L., Bie, L., e Bai, X. 2021. Controlling the schedule risk in green building projects: Buffer management framework with activity dependence. Journal of Cleaner Production, 278.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.