Project management for increasing the load of a oil company’s distillation unit

Project Management for Increasing the Load of an Oil Company’s Distillation Unit

Victor Virgens de França; Paula Regina Fortes

DOI: 10.22167/2675-6528-202602403

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

A study analyzed the application of project management tools in an industrial project to increase the load of an atmospheric distillation unit. The objective was to compare two scenarios: Scenario 1, which represented the practices adopted up to the Basic Design stage, and Scenario 2, structured based on the more integrated application of project management best practices. The methodology employed a single case study, of an applied nature, with a qualitative approach complemented by quantitative analyses. Eight aspects were evaluated: scope, schedule, costs, human resources, procurement, communication, risk management, and quality. Data collection involved documentary survey and direct observation. The results indicated that the project already had a good level of maturity in Scenario 1 in terms of scope, team organization, communication, and quality. However, the main opportunities for improvement were concentrated in the aspects of schedule and risk management, which were treated reactively and with low decision-making integration in Scenario 1. Scenario 2 showed significant advances due to better organization of schedule planning and the formalization of risk management, which expanded the anticipation capacity and support for managerial decisions. It was concluded that the most relevant gains did not stem from the introduction of new tools, but from the more disciplined and integrated use of existing tools, reinforcing that the evolution of maturity in industrial project management occurs gradually and focused on the critical issues of schedule and risks, especially through the strengthening of integration between planning, control, and risk management from the initial phases.

Keywords: Load Increase; Schedule; Risk Management; Industrial Project.

1. Introduction

The oil and gas sector constitutes one of the central pillars of the global economy, playing a strategic role in energy security, international trade, and geopolitical stability. The International Energy Agency (2023) highlights that, despite the growing energy transition, fossil fuels continue to represent more than 75% of global energy consumption, with oil alone accounting for approximately 30% of this matrix. In this context, companies in the sector face the challenge of maintaining high levels of operational and technological efficiency, while balancing environmental, social, and economic demands.

In the Brazilian scenario, the oil and gas sector occupies an even more relevant position, contributing about 10% of the Industrial Gross Domestic Product and being responsible for a significant share of national exports (ANP, 2023). With the discovery of pre-salt and the development of new offshore fields, Brazil has consolidated itself as one of the world’s leading oil producers. However, the efficient use of these resources requires robust investments in industrial infrastructure, technological innovation, and, above all, efficient management of complex projects.

Industrial projects in the oil and gas sector, such as refinery construction and modernization, are among the most complex in the world in terms of scope, investment, and risks involved (Merrow, 2011). These projects require the articulation of various engineering disciplines, international logistics, management of public and private stakeholders, in addition to the need to ensure operational safety in a highly regulated environment (Cleland and Ireland, 2007; Kerzner, 2017).

Failures in the management of these ventures generate significant economic and financial impacts. Studies by the Independent Project Analysis Institute (2021) indicate that over 60% of industrial megaprojects exceed their initial deadlines and budgets by at least 30%, frequently due to planning failures, poorly defined scope, and deficient risk control. In the context of industrial project management, the challenges are amplified by the inherent characteristics of these ventures, such as long execution cycles, dependence on international suppliers, and high interdependence between stages.

According to the Project Management Institute (2021), the areas of scope, schedule, cost, risks, and communication are critical for success in large-scale engineering projects. In particular, failures in integration and schedule control are pointed out as recurring causes of failure, especially in environments of high technical and regulatory uncertainty.

A specific type of project with extremely high operational and financial impact is associated with industrial distillation units, responsible for the fractionation of crude oil into high value-added derivatives. These units constitute the main entry point of the refining process, so their capacity and operational reliability directly condition the refinery’s overall productivity. From a managerial point of view, failures, delays, or inefficiencies in the implementation or operation of these units can generate relevant impacts in multiple dimensions, such as compromising start-up deadlines, significantly increasing investment and operational costs, and increasing exposure to technical and operational risks (Nelson and Folk, 1996). The high technical complexity of distillation projects imposes additional challenges on project management, demanding high levels of coordination, planning, and engineering excellence to mitigate risks and ensure expected performance.

Thus, the management of projects aimed at the implementation or modernization of distillation units in refineries represents a critical field for improvements. In projects with high technical complexity and economic relevance, such as those in the oil and gas sector, applying structured management practices, especially those based on PMBOK (PMI, 2021), and quantitative analysis tools like Earned Value Analysis, can represent the difference between success and failure. In this context, the objective of this work is to analyze a real project of an industrial distillation unit in an oil and gas company, focusing on identifying weaknesses in the project management processes and proposing improvements. To this end, based on the diagnosis of the current situation (Scenario 1), a comparison is made with an alternative scenario (Scenario 2), structured based on the application of Project Management techniques and methodologies, in order to analytically evaluate their potential effects on the operational and financial performance of the undertaking.

2. Material and Methods

For the development of this work, the methodological strategy of a single case study, of an applied nature, with a predominantly qualitative approach, complemented by quantitative support analyses, was adopted. This methodological option proved adequate for the study’s objective, which consisted of analyzing, in an in-depth and contextualized manner, the application of project management tools in a real industrial project to increase the load of an atmospheric distillation unit in the oil and gas sector.

The choice of a single case study was based on the need for a detailed understanding of the practices effectively adopted in the project, as well as the opportunities for improvement associated with a more structured application of project management best practices. As highlighted by Yin (2015), this approach allows for the investigation of contemporary phenomena embedded in real contexts, where the boundaries between the object of study and the organizational environment are not clearly delimited.

Within the scope of this work, two scenarios were defined for comparative analysis. Scenario 1 corresponded to the project management scenario effectively practiced during the project’s execution, reflecting the tools, processes, and routines observed in the organization. Scenario 2 represented an alternative scenario, constructed from the more structured and integrated application of project management best practices, according to recommendations from specialized literature and the PMBOK® Guide.

The comparison between the scenarios did not aim to point out operational failures or evaluate individual performance, but rather to analyze differences in managerial approach, degree of formalization, integration between tools, and decision-making support capacity, in light of previously defined criteria. The comparative analysis was structured around eight evaluation aspects, selected for presenting high relevance and recurrence of problems in complex industrial projects, especially in Revamp ventures.

The evaluation aspects considered were: Scope (clarity and formalization of objectives and deliverables, degree of detail of the Project Breakdown Structure); Schedule (accuracy of estimated versus actual schedule, indicators used for monitoring); Cost (difference between planned and executed budget, causes of budget overrun); Human Resources (number of people involved, formalization of roles and responsibilities,

business volume

); Procurement Management (compliance with deadlines); Communication (communication within the project); Risk Management (formal identification of risks, risk response plan); and Quality (existence and application of technical criteria for acceptance of deliverables, occurrence of rework or technical non-conformities, use of quality control tools).

The study execution involved three main stages: data collection, qualitative analysis, and quantitative analysis. Data collection was carried out through documentary research and direct observation, adopting the strategy of evidence triangulation, with the objective of increasing the reliability and analytical consistency of the results.

The documentary survey was based on the analysis of the main records produced throughout the project, including schedules, meeting minutes, progress reports, procurement documents, financial controls, risk records, non-conformities, and technical engineering documents. These materials were selected for their relevance and reliability, allowing for a consistent understanding of the project’s conduct and the management practices adopted.

The selection of the documentary collection considered its relevance to the eight evaluation aspects defined in the study, the traceability and formal validity of the documents, the coverage of the temporal scope analyzed, understood between October 2025 and January 2026, and the minimum completeness of information, in order to allow consistent comparison between the two scenarios.

Complementarily, direct observation of management practices and project-related meetings was carried out, totaling eight meetings attended in the same reference period. These meetings included status update meetings, interface analysis, risk discussions, and lessons learned consolidation, with the participation of representatives from project management, engineering, procurement, operations, and quality areas. The observation records were made objectively and systematically, covering the main topics discussed, decisions made, and associated actions.

It is emphasized that the data used are real, but they were treated for confidentiality preservation, through anonymization of identifiers, suppression of sensitive information and, when applicable, normalization and presentation in relative terms, such as percentages and indices. This approach maintained the consistency of the relationships between project timeline, cost, and performance, without exposure of absolute values, in accordance with the applicable academic requirements for studies of an applied nature.

The qualitative analysis was performed based on the technical interpretation of the practices observed in Scenario 1, confronting them with good project management practices. Classic project management tools were used, as described in the PMBOK® Guide (PMI, 2021), such as the Project Charter, the Work Breakdown Structure (WBS), the Project Schedule, the S-Curve, the responsibility matrix (RACI), and the risk matrix (probability x impact).

Furthermore, the documentation associated with the procurement and communication areas, fundamental for project performance, was evaluated. Each Project Management tool was selected for its strategic role in project planning, execution, and control, according to conceptualizations by authors such as Meredith and Mantel (2011) for the Project Charter, Kerzner (2017) for the WBS (Work Breakdown Structure), Heerkens (2002) for the Schedule, Pinto (1996) for the S-Curve, Verzuh (2015) for the RACI Matrix, and Hillson (2003) for the Risk Matrix.

The quantitative analysis, in turn, used treated and normalized data to preserve the confidentiality of the company’s information, while maintaining the consistency of the relationships between cost, deadline, and project performance to compare the two scenarios. Recognized metrics in the field, such as Earned Value Analysis (EVA) and Net Present Value (NPV), were used, which enabled the measurement of project performance in economic and productive terms.

EVA is an integrated methodology that combines scope, cost, and schedule to measure project performance and progress, allowing for real-time deviation identification, as described by Fleming and Koppelman (1994). NPV is a financial method for investment appraisal, which calculates the present value of future cash flows discounted at a minimum attractive rate (Ross, Westerfield & Jaffe, 2013), evaluating economic feasibility and comparing alternatives.

In this way, the adopted methodology allowed for the realization of an applied study, aligned with professional and academic demands, focusing on providing relevant contributions both to the practice of project management in the refining sector and to theoretical development in the area, in full coherence with the objective of analyzing the project and proposing improvements based on the comparison between scenarios.

3. Results and Discussion

The results presented in this section were obtained from a comparative analysis between two project management scenarios in an industrial undertaking to increase the load of an atmospheric distillation unit. Scenario 1 represented the management practices adopted up to the Basic Design stage, while Scenario 2 was structured based on the more integrated and disciplined application of good project management practices, according to specialized literature and the PMBOK Guide (PMI, 2021). The evaluation considered eight critical management aspects, allowing for the identification of the maturity level of existing practices and the dimensions where the more structured application of tools would generate greater managerial value, aligning with the study’s central objective.

In general, the research indicated that the project already possessed a good level of maturity in Scenario 1 in aspects such as scope definition, team organization, internal communication, and the quality of engineering deliverables. In these areas, the observed practices proved adequate for the complexity of the undertaking and the organizational context, resulting in insignificant differences between the scenarios. On the other hand, the main opportunities for improvement were concentrated in the aspects of schedule and risk management, which were treated in a more reactive manner and with low integration into the decision-making process in Scenario 1, as detailed in the following subsections.

A. Scope

The aspect related to the project scope demonstrated a good level of maturity already in Scenario 1, evidenced by the structured way in which the scope was defined and managed. The evaluation indicated that the main elements, such as the definition of objectives, deliverables, and scope boundaries, were clearly established and aligned among the various areas involved. Due to this initial maturity, no significant differences or relevant gains were identified between the practices observed in Scenario 1 and those proposed for Scenario 2, indicating a consolidation of scope management practices within the organization.

A1. Clarity and formalization of objectives and deliverables

The analysis revealed that the organization already used a structured Project Charter (TAP) in Scenario 1. This document formalized the project’s objectives, high-level scope, and main deliverables, institutionalizing them in the company’s management process. The analyzed TAP, which applied to both scenarios, included the project name (Revamp of the Atmospheric Distillation Unit), its justification (adequacy and load increase for operational performance improvement and strategic needs fulfillment), and the objective of implementing technical and operational modifications while respecting safety, quality, and deadline requirements. The existence of this consolidated document reflected an advanced stage of governance and strategic alignment from the initial project phases, as highlighted by Meredith and Mantel (2011).

The elements of the Project Charter also detailed the high-level scope, covering engineering, procurement, construction, commissioning, and startup, with key deliverables such as the approved engineering package, supplied equipment and materials, executed construction and assembly, and the unit commissioned and released for operation. Assumptions included maintaining refinery operation and execution according to operational windows, while constraints involved limited operational windows, regulatory requirements, and contractual deadlines. The main risks identified were delays in critical supplies, operational interferences, and late engineering adjustments, with key stakeholders such as project management, engineering, procurement, operations, and contractors. The formalization of this information through the Project Charter already constituted a consolidated practice, with no need for the elaboration of a distinct Scenario 2 for this criterion.

A2. Level of detail of the Work Breakdown Structure [WBS]

In Scenario 1, it was found that the Work Breakdown Structure (WBS) was formally defined and followed a logic of decomposing the scope into work packages compatible with the project’s complexity. This WBS served as the basis for planning the schedule, costs, and responsibilities, demonstrating adherence to good project management practices, as described by Kerzner (2017). The representative structure of the WBS included phases such as Project Management (planning, control, interfaces, communication), Engineering (conceptual, basic, detailed), Procurement (strategy, acquisitions, inspection), Construction and Assembly (preliminaries, electromechanical, electrical and instrumentation), Commissioning and Start-up (pre-commissioning, functional, assisted, stabilization), and Quality, HSE and Compliance (inspections, non-conformance control, legal requirements, final technical acceptance).

In Scenario 2, the WBS was maintained with a structure equivalent to that observed in Scenario 1, without significant changes in its hierarchy or decomposition level. The analysis indicated that the absence of relevant differences between the scenarios stemmed from the fact that the WBS was already properly structured, consolidated, and adhered to best practices in the initially evaluated scenario. The consolidated practice of decomposing the scope by technical phases, combined with the experience of the teams involved, reduced the need for additional WBS restructurings in Scenario 2, reinforcing organizational maturity in defining the scope of Revamp projects.

B. Schedule

The schedule aspect presented an intermediate level of maturity in Scenario 1. Although there was formal deadline planning and consistent use of the S-Curve for tracking physical progress, this approach allowed for an overview of the project’s progress, mainly for management reporting purposes. However, significant limitations were observed in the schedule’s detail, which compromised the ability to anticipate deviations and perform preventive management, a critical point in Revamp projects due to their high complexity and multiple interfaces, as discussed by Heerkens (2002).

In this sense, Scenario 2 presented relevant advances, mainly due to the greater detail of the schedule and the better integration between planning and control. These improvements facilitated the identification of critical dependencies, increased the visibility of the impacts of potential delays, and offered better support for decision-making. The evolution did not alter the practices already well applied in Scenario 1, but substantially improved them, making planning more robust and control more effective.

B1. Estimated schedule versus actual schedule accuracy

In Scenario 1, the project schedule was a formal planning instrument, covering the entire project cycle over approximately 48 months, from the initial phase to the unit’s operational start. However, for the complexity of the Revamp project analyzed, the schedule was structured at a high level of aggregation, mostly presenting the major phases and key milestones, with limited detail of intermediate activities and critical interfaces between engineering, procurement, construction, and commissioning. This approach allowed for general project monitoring but limited the early identification of schedule risks, especially in activities dependent on critical supplies, which was a recurring source of difficulties for the organization. As a consequence, significant schedule deviations tended to be perceived late, already when their impacts on the critical path had materialized.

In Scenario 2, the greater decomposition of the schedule, while maintaining the total horizon of 48 months, contributed to the increased accuracy of the deadline estimates and to the better visualization of the project’s critical interdependencies. The additional detailing of activities allowed for a clearer explication of precedence relationships, intermediate milestones, and interfaces between engineering, procurement, construction, and commissioning, mitigating the excessive aggregation observed in Scenario 1. This higher level of detail significantly improved project control, enabling earlier identification of deviations in predecessor activities and the anticipated assessment of their potential impacts on the critical path. Additionally, the more disaggregated schedule favored integration between planning and monitoring, allowing for the association of physical-financial progress information with specific activities, rather than just global phases. As a result, Scenario 2 presented greater deadline predictability and better support for managerial decision-making.

B2. Indicators used for schedule monitoring

In Scenario 1, the S-Curve was already used appropriately and consistently as the main tool for monitoring the physical progress of the project, offering a clear view of global progress and meeting the monitoring needs at the managerial level. The S-Curve analysis for the project, considering the total time interval of 48 months, revealed that the Basic Design was delivered approximately 2.4% late compared to the plan. Although this deviation was relatively small, it signaled a punctual loss of schedule performance, whose possible contributing factors would be discussed in other sections, especially regarding the conditions associated with future project stages. The S-Curve was also analyzed for the detailed project delivery interval (19 months), showing the same trend of delay.

C. Cost

From a methodological perspective, the project’s cost behavior was assessed based on the principles of Earned Value Analysis (EVA) and Net Present Value (NPV), allowing the association of cost performance with the project’s economic implications. EVA uses indicators such as Budget at Completion (BAC), Planned Value (PV), Earned Value (EV), and Actual Cost (AC), enabling a comparison between planned and executed progress over time (Fleming & Koppelman, 1994). In the context of this study, the project was still underway, and these tools were applied partially and progressively, limited to the information available up to the Conceptual Design and Basic Design stages. Subsequent stages (Procurement, Detailed Design, and Construction & Assembly) did not yet have actual cost information, remaining restricted to planning. The adopted approach prioritized the conceptual and methodological evaluation of cost planning and the applicability of quantitative tools, without making conclusive inferences about the overall project’s actual results.

C1. Difference between planned and executed budget

The total approved project budget, corresponding to the BAC, was normalized to 100, preserving the confidentiality of financial data. The planning defined the budget portion associated with the Conceptual Design and Basic Design stages, which corresponded to a Planned Value (PV) of 30. As these stages were fully executed according to the planned scope, the Earned Value (EV) up to this point was also 30. However, the Actual Cost (AC) incurred for these same stages was 32.4. The comparison between planned and executed values showed an 8% difference between the budgeted amount and the cost actually incurred up to this project phase, indicating that the actual cost exceeded the originally budgeted amount for these initial stages. This 8% deviation, observed in the early stages of the project, constituted an initial indication of cost efficiency loss, prompting an analysis of associated potential causes.

This deviation was also reflected in the economic analysis through the Net Present Value (NPV), calculated in a normalized way. Considering an originally estimated NPV of 100 as a reference, representative of the economic attractiveness foreseen at the project’s approval, the update of the initial stage costs, incorporating the observed 8% increase, resulted in an adjusted NPV of approximately 94. Although the project remained economically viable, the approximate 6% reduction in NPV showed that relatively modest cost deviations, when occurring in the initial phases, already produced noticeable impacts on the expected economic return, reinforcing the importance of rigorous cost control from the engineering stages. Thus, the combination of EVA and NPV allowed for the early identification of not only the loss of cost efficiency but also its economic consequences, reinforcing the importance of rigorous control in the initial stages of the project.

C2. Causes of budget overrun

The analysis of potential causes for budget overrun was carried out based on the 8% cost deviation identified by the completion of the Basic Project. This behavior indicated the presence of structural factors typical of industrial projects, among which stand out scope uncertainties, associated with limited knowledge of the actual site conditions. The still reduced maturity of engineering definitions in the initial phases also contributed, tending to generate adjustments and rework throughout the execution. Added to this is the dependence on critical supplies, subject to long lead times and market variations, as well as predominantly reactive change management, in which corrective decisions occur when optimization options are already more limited.

Although the observed deviation did not, at this stage, characterize a consolidated budgetary overrun, its early occurrence, combined with the identified reduction in NPV, signaled an unfavorable trend that could intensify in subsequent stages. In this regard, the early identification of these causes reinforced the importance of preventive actions and the strengthening of cost governance, especially before the start of the more capital-intensive phases. The management of industrial projects, according to Merrow (2011), is particularly susceptible to these challenges, which demand robust and proactive planning to mitigate financial and operational risks.

D. Human Resources

The analysis of the Human Resources aspect indicated that, already in Scenario 1, the project presented a high level of maturity in people management up to the Basic Design stage. The sizing of the teams proved compatible with the complexity of the undertaking, and the functions and responsibilities were clearly defined, including the prior use of a RACI (Responsible, Accountable, Consulted, Informed) matrix, as recommended by Verzuh (2015). The observed turnover rate was low and adequate for the analyzed stage, not constituting a critical performance factor. Given this context, no relevant gains were identified in Scenario 2 associated with the expansion of staff, the redefinition of roles, or the strengthening of retention mechanisms. The practices already adopted in Scenario 1 proved sufficient to sustain team performance, so that the differences between the scenarios were essentially limited to formal and documentary aspects.

D1. Number of people involved in the project

In Scenario 1, the project had, on average, approximately 35 to 40 professionals directly involved, distributed among the main areas of activity. The engineering team concentrated the largest contingent, with about 15 to 18 professionals, considering disciplines such as process, mechanical, electrical, instrumentation, and automation. The project management and planning areas involved approximately 5 to 6 professionals, while procurement, operation, quality, and support areas totaled about 10 to 12 people, considering different levels of dedication throughout the phases. This sizing was considered adequate when analyzed together with the technical complexity of the project, the scale of the Revamp, and the history of similar ventures conducted by the organization. The estimation of personnel quantity was based on the analysis of demands by discipline, the expected workload in each phase, and the accumulated experience in previous projects, which had already established reference parameters for this type of undertaking. The stability of the team and the technical specialization of the professionals contributed to no signs of structural understaffing or critical overload being observed in Scenario 1. Thus, Scenario 2 was established in the same way as Scenario 1 in this aspect.

D2. Formalization of functions and responsibilities

In Scenario 1, functions and responsibilities were already clearly defined and understood by the teams, including the existence of a RACI matrix previously elaborated and used in the project context. The analysis of minutes, decision-making flows, and inter-departmental interactions indicated a low level of role conflict and absence of relevant overlaps, demonstrating stable and effective organizational functioning. The project’s RACI matrix detailed responsibilities for processes such as definition of initial guidelines, communication of objectives, scope change management, schedule planning and communication, milestone and deviation communication, procurement planning, risk communication, operational window preparation, quality requirements communication, decision recording, and lessons learned communication. This result is directly associated with the company’s organizational maturity level in conducting Revamp projects, in which recurring teams, with a joint history of performance, tend to operate with well-established roles and consolidated decision-making routines from the initial phases. In Scenario 2, no relevant improvements were identified in this aspect, as the formalization of responsibilities was already present in the original scenario.

D3. Turnover during projects

Considering that the analysis was restricted to the Conceptual Design and Basic Design stages, the observed turnover was low and compatible with this project stage. Throughout these phases, the punctual replacement of two professionals was recorded, mainly for administrative reasons or internal reallocation, without relevant impact on the continuity of activities. This turnover level was considered adequate, having been absorbed by the teams without prejudice to the progress of the work, due to good internal organization, the technical specialization of the professionals, and the existence of established routines for communication and information sharing. Given the analyzed temporal scope, it was not possible to extrapolate conclusions about the turnover behavior throughout the entire project. Nevertheless, until the conclusion of the Basic Design, turnover did not constitute a critical performance factor nor an element of differentiation between Scenarios 1 and 2.

E. Acquisitions and Material Resources

E1. Compliance with deadlines

The evaluation of deadline compliance in the procurement aspect considered only the period until the completion of the Basic Project, as the Supply stage had not yet begun. In this scope, it was observed that the Basic Project was delivered with a delay of approximately 2.4% compared to the plan, as indicated by the S-Curve. This delay, although limited, assumes relevance because it directly precedes the start of the bidding processes. In projects subject to bidding processes, as is the case with this project, delays in this stage tend to reduce the schedule’s maneuverability, as procurement becomes dependent on formal, inflexible cycles, such as specification development, minimum legal deadlines, and approval. Thus, even though there were no empirical data on supply delays up to that point, the deviation observed in the Basic Project already signaled a potential risk for future bidding processes, especially if technical revisions or scope adjustments were necessary after the opening of tenders, a condition that could amplify schedule impacts in subsequent stages.

F. Communication

F1. Communication within the project

In Scenario 1, the project’s internal communication proved to be organized and functional, supported by periodic meetings, decision records, and formal interaction channels between technical teams, support areas, and management. Critical information, such as technical decisions, milestones, interfaces, and scope changes, was consistently shared, which reduced noise and contributed to alignment among the areas. The prior definition of responsibilities, already structured through the RACI matrix, played an important role in this performance, by favoring decisional clarity and fluidity in information exchange. In this context, the communication flow between engineering, procurement, construction, and operations showed good integration and provided adequate support for managerial decision-making. Given this already consolidated base, no relevant structural gains were observed in Scenario 2, as the existing communication mechanisms in Scenario 1 proved sufficient to meet the project’s needs up to the analyzed stage.

G. Risk Management

The Risk Management aspect was evaluated as the one that presented the greatest opportunity for improvement in Scenario 1, when compared to the other aspects analyzed. The evaluation indicated that, although the organization possessed technical maturity and experience to deal with risks, risk management was not systematically and consolidatedly structured throughout the project. As a result, Scenario 2 presented relevant gains, mainly due to the formalization of the Risk Matrix and the definition of response plans, aligning with Hillson’s (2003) recommendations on the importance of proactive risk management for project success.

G1. Formal Identification of risks

In Scenario 1, it was observed that some relevant risks were identified, but in a scattered manner, without consolidation into a single record or an updated Risk Matrix. These risks appeared in meeting minutes, technical discussions, or ad-hoc communications, but were not organized in a structured way, hindering systematic prioritization and monitoring. Among the main risks identified in a non-consolidated manner in Scenario 1 were: delay in the delivery of critical equipment (“long lead”), operational interferences during the Revamp execution, rework due to late engineering adjustments, operational window restrictions for interconnections (“tie-ins”), and dependence on bidding processes with rigid deadlines. The absence of a formal and updated Risk Matrix limited the project’s ability to compare risks, assess criticality, and direct preventive efforts. In Scenario 2, this gap was addressed by developing a structured Risk Matrix, allowing for an integrated view and objective prioritization. This matrix, for example, classified the delay in “long lead” equipment as high probability, high impact, and critical risk level, with Procurement as responsible. Rework due to late engineering adjustments was classified as medium probability, high impact, and high risk level, with Engineering as responsible. Operational interference during execution was medium probability, medium impact, and moderate risk level, with Operations as responsible. The operational window restriction (tie-ins) was low probability, high impact, and moderate risk level, with the Project Manager as responsible. Finally, the delay in bidding processes was high probability, medium impact, and high risk level, with Procurement as responsible. This matrix allowed for a clear visualization of critical risks, establishment of responsible parties, and direction of response planning, characterizing a significant advancement compared to Scenario 1.

G2. Risk Response Plan

In Scenario 1, a formally structured Risk Response Plan was not identified. Risk discussions generally occurred reactively, with actions primarily adopted after adverse events occurred. This approach significantly reduced the capacity for anticipation and mitigation, contributing to impacts on schedule and cost, as the alternatives available after risks materialized tend to be more restricted and costly. The absence of this framework meant that recurring issues, such as equipment delays, late engineering adjustments, and procurement bottlenecks, were addressed repeatedly and unsystematically, as observed in the meetings and documents analyzed.

In Scenario 2, an evolution was observed compared to the previous scenario, materialized by the consolidation of a Risk Matrix and the definition of response strategies compatible with the identified criticality levels. Based on this instrument, predominantly mitigation-focused responses were established. For example, for the risk of delay in “long lead” equipment, the strategy was to mitigate, with the main action being the anticipation of specifications and weekly supplier follow-up. For the risk of rework due to late engineering adjustments, the strategy was to mitigate, with actions such as intermediate technical reviews and progressive engineering freeze. For operational interference in execution, the strategy was to mitigate, with integrated planning with operations and interference simulations. For the restriction of operational window (tie-ins), the strategy was to accept/mitigate, with a reserve window in the schedule and a contingency plan. Finally, for the risk of delay in bidding processes, the strategy was to mitigate, with early initiation of the bidding process and prioritized critical packages. Scenario 2 differed from Scenario 1 by introducing a minimal anticipation logic. By linking each risk to a responsible party and a predefined action, the project began to reduce dependencies on decisions made exclusively “in reaction” to events, creating objective references for action when certain triggers were observed. This advancement did not eliminate the risks, nor did it guarantee their full mitigation, but it qualitatively altered the way of dealing with them, by allowing part of the decisions to be discussed before the problems materialized. This provided greater predictability, reduced improvisation, and offered better conditions for aligning risks with deadline and cost decisions, characterizing a real gain compared to the previous scenario, even if far from a fully mature Risk Management model.

H. Quality

The evaluation of the Quality aspect considered exclusively the deliverables made to date, restricted to the Conceptual Design and the Basic Design, since the subsequent stages have not yet been concluded and, therefore, could not be analyzed. In this scope, it was observed that the company already had consolidated quality control practices for the engineering phases, compatible with the technical complexity of the project and with the regulated industrial environment in which it is inserted. Due to this scenario, no relevant gains were identified between Scenario 1 and Scenario 2 regarding the quality management of the analyzed deliverables. The practices adopted in Scenario 1 proved sufficient to ensure the technical conformity of the Conceptual Design and the Basic Design, with the differences between the scenarios being restricted to specific aspects of organization and standardization.

H1. Existence and application of technical criteria for acceptance of deliverables

In Scenario 1, clear technical criteria were found for the acceptance of the Conceptual Design and the Basic Design, established through engineering documents, terms of reference, technical specifications, and, above all, corporate checklists for verifying deliverables. These instruments guided the content analysis, technical consistency, and adherence to project premises, ensuring that the deliverables met the defined requirements. The application of these criteria occurred systematically, with formal records of review and validation of deliverables. In Scenario 2, no relevant changes were observed in these criteria, as they were already defined and operational in the original scenario. Thus, it was concluded that, up to the Basic Design stage, the acceptance criteria were already consolidated, with no structural gains resulting from the application of the second scenario.

H2. Occurrence of rework or technical non-conformities

Until the completion of the Basic Design, the analysis did not indicate the occurrence of significant rework or relevant technical non-conformities. The observed adjustments were isolated and inherent to the natural process of maturing engineering definitions, not constituting quality failures or systematic deviations in deliverables. The existence of technical review routines and validation through checklists contributed to the early identification of inconsistencies, preventing the propagation of problems to later stages. In this context, no relevant differences were observed between Scenarios 1 and 2 regarding the occurrence of rework, reinforcing that the quality of engineering deliverables was already at an adequate level in the initial scenario.

H3. Use of quality control tools

In Scenario 1, the adequate use of quality control tools applicable to the engineering phases was verified, with emphasis on formal technical reviews, multidisciplinary validations, and the use of acceptance checklists for the Conceptual Design and the Basic Design. These tools were integrated into the project routine and ensured the conformity of deliverables before their approval. In Scenario 2, no substantive changes were identified in the use of these tools, as the control mechanisms were already consolidated. Thus, up to the analyzed stage, quality management proved to be consistent and stable, not configuring as a differentiating factor between the scenarios, nor demanding additional structural improvements.

In summary, the results demonstrate that Scenario 2 does not represent an abrupt rupture, but rather a gradual and realistic evolution of the practices already existing in the organization. The most relevant gains did not stem from the introduction of new tools, but from the more disciplined and integrated use of the tools already available, especially in the areas of schedule and risk management, which proved to be the main drivers of improvement. The evolution of maturity in industrial project management therefore occurs through the strengthening of integration between planning, control, and risk management from the initial phases, expanding the capacity for anticipation and support for managerial decisions, which is crucial for the predictability and value of complex ventures in the oil and gas sector.

4. Conclusion

The present study analyzed the application of project management tools in an industrial project to increase the load of an atmospheric distillation unit, comparing the practices adopted up to the Basic Design stage (Scenario 1) with an alternative scenario (Scenario 2), structured based on good management practices. It was found that the project already showed a good level of maturity in Scenario 1 in aspects such as scope definition, team organization, internal communication, and the quality of engineering deliverables. In these areas, existing practices proved adequate, with insignificant differences between the scenarios. In contrast, the main opportunities for improvement were concentrated in the schedule and risk management aspects. In Scenario 1, the schedule had a high level of aggregation, which limited the ability to anticipate deviations, such as the 2.4% delay observed in the delivery of the Basic Design. Risk management was treated reactively and dispersedly, without a formal matrix or structured response plans. Cost analysis, through Earned Value Analysis and Net Present Value, revealed a deviation of 8% in the actual cost of the initial phases compared to the planned cost, resulting in a 6% reduction in NPV, indicating the importance of rigorous control from the initial stages.

Scenario 2 evidenced significant advances due to the improved organization of schedule planning and the formalization of risk management, with the elaboration of a Risk Matrix and the definition of response plans that broadened the capacity for anticipation and support for managerial decisions. The study’s main contribution lies in demonstrating that the most relevant gains did not stem from the introduction of new tools, but from the more disciplined and integrated use of existing tools, reinforcing that the evolution of maturity in industrial project management occurs gradually and focused on the critical themes of schedule and risks. As a limitation, the analysis was restricted to the Conceptual Design and Basic Design stages, not allowing conclusions to be extrapolated about the behavior of turnover and quality in later phases. It is recommended that the improved practices for schedule and risk management, observed in Scenario 2, be systematically incorporated into future projects to reduce reactive action and increase the predictability and value of the ventures.

Bibliographic References

Agência Internacional de Energia, 2023 [Referência completa não encontrada no documento original]

AGÊNCIA NACIONAL DO PETRÓLEO, GÁS NATURAL E BIOCOMBUSTÍVEIS [ANP]. (2024). Anuário Estatístico Brasileiro do Petróleo, Gás Natural e Biocombustíveis 2023. Brasília: ANP. Disponível em: <https://www.gov.br/anp/pt-br/centrais-de-conteudo/publicacoes/anuario-estatistico/anuario-estatistico-2023>. Acesso em: 4 jun. 2025.

Cleland, D.I.; Ireland, L.R. (2007). Project Management: Strategic Design and Implementation. 5. ed. New York, EUA: McGraw-Hill.

Fleming, Q.W.; Koppelman, J.M. (1994). Earned Value Project Management. 2. ed. Newtown Square: Project Management Institute.

Heerkens, G. (2002). Project Management. 2. ed. New York, EUA: McGraw-Hill.

Hillson, D. (2003). Effective Opportunity Management for Projects: Exploiting Positive Risk. New York, EUA: Marcel Dekker.

INDEPENDENT PROJECT ANALYSIS INSTITUTE [IPA]. (2021). Mega Projects Performance Benchmarking Report. Reston, VA: IPA.

Kerzner, H. (2017). Project Management: A systems approach to planning, scheduling, and controlling. 12. ed. Hoboken: Wiley.

Meredith, J.R.; Mantel, S.J. (2011). Project Management: A managerial approach. 8. ed. Hoboken, NJ, EUA: Wiley.

Merrow, E.W. (2011). Industrial Megaprojects: Concepts, Strategies, and Practices for Success. Hoboken: Wiley.

Nelson, W.L.; Folk, R.L. (1996). Petroleum Refinery Engineering. 4. ed. New York, EUA: McGraw-Hill.

Pinto, J.K. (2013). Project Management: Achieving Competitive Advantage. 4. ed. Boston, EUA: Pearson.

PROJECT MANAGEMENT INSTITUTE [PMI]. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 7. ed. Newtown Square, PA, EUA: PMI.

Ross, S.A.; Westerfield, R.; Jaffe, J. (2013). Corporate Finance. 10. ed. New York, EUA: McGraw-Hill/Irwin.

Verzuh, E. (2015). The Fast Forward MBA in Project Management. 5. ed. Hoboken: Wiley.

Yin, R. K. (2015). Estudo de Caso: Planejamento e métodos. 5. ed. Porto Alegre, RS, Brasil: Bookman.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.