Article

October 19, 2026

Risk management in R&D projects: structuring and application of a risk matrix

Rogerio Ramos de Sousa Junior; Jonatas de Oliveira

DOI: 10.22167/2675-6528-202601397

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Abstract

Risk management is an essential process for conducting projects, especially in Research, Development, and Innovation (RD&I) due to the high degree of technical and scientific uncertainty. The study aimed to propose and evaluate the application of a risk matrix as a management tool in an RD&I project, considering its capacity for risk identification, prioritization, and treatment. The methodology consisted of an action-research of a qualitative and applied nature, in which risks were defined, evaluated for probability and impact, and organized into a 5×5 matrix. Response strategies were implemented for risks classified as critical and high-risk, followed by successive re-evaluation cycles. The results indicated a progressive reduction in the overall project risk over the analysis cycles, demonstrating the tool’s effectiveness in risk prioritization and monitoring. The main risk factors were associated with resource availability, activity integration, and technical-scientific uncertainties. The continuous application of the matrix, combined with critical interpretation of the results, proved essential for its effectiveness in the analyzed context. It was concluded that the risk matrix is a valid instrument to support management in RD&I projects, provided it is applied systematically and aligned with the project’s characteristics.

Keywords: Probability and impact analysis; Risk exposure; Risk prioritization.

1. Introduction

Risk management is an essential process for conducting projects, as it allows for the identification, analysis, and treatment of uncertainties that can impact their objectives. This process is not limited to identifying threats but also involves evaluating the exploitation of opportunities, in order to manage risk exposure throughout the entire project lifecycle. Thus, risk management is essential for improving the predictability of results, guiding decision-making, optimizing resource utilization, and minimizing negative impacts while maximizing positive ones, which positions it as one of the pillars of project management (PMI, 2021).

In general, risk is the manifestation of uncertainty regarding the achievement of a project’s objectives (Ferreira et al., 2013), expressed by the probability of an event occurring and its consequent impact, positive or negative, whether in relation to costs, deadlines, scopes, quality, or performance (Soares and Martens, 2018; Baches et al., 2025). The Brazilian Association of Technical Standards (ABNT, 2018), through ABNT NBR ISO 31000:2018, associates risk with the effects of uncertainty on objectives, while the Project Management Body of Knowledge (PMI, 2021) Guide describes it as an uncertain event that, if it occurs, can impact one or more aspects of the project.

In corporate environments, risk management is a topic of growing interest, being applied in different business areas, such as the chemical (Souza and Barcauí, 2014), oil and gas (Sena et al., 2014), automotive (Silva et al., 2010), and information technology (Macedo and Salgado, 2015) sectors. This broad scope contributes to more informed decisions, operational predictability, and rational resource utilization. However, although risk management is consolidated in projects with well-defined scope and outcomes, its application in Research, Development, and Innovation (RD&I) projects, especially in scientific and technological research, is still limited and challenging.

Unlike corporate projects, research projects involve a high degree of technical and scientific uncertainty, as the expected results are not always fully predictable, and the very nature of the investigation can lead to unforeseen discoveries, methodological changes, and scope redefinitions (Franzoni and Stephan, 2023). In innovative projects characterized by a high level of uncertainty, this refers to the unknown, while risk is associated with the probability of error (Russo and Sbragia, 2014). Although uncertainty greatly influences project risks, aspects such as resources, complexity, deadlines, and technical capacity also represent impact variables. From this perspective, Franzoni and Stephan (2023) identify three main components of risk in research projects: uncertainty about possible outcomes, uncertainty about the probability of these outcomes occurring, and uncertainty about the potential impact of the outcomes.

These particularities make traditional risk management models, often structured around premises of predictability and control, difficult to apply in R&D contexts. The problem becomes even more complex when research projects are conducted in partnerships between universities and companies, an increasingly common model in the pursuit of technological innovation. In these cases, additional risks emerge related to collaborative governance, communication between multidisciplinary teams, intellectual property management, cultural and organizational differences, and divergent expectations regarding results and deadlines. Given this scenario, a gap is observed: there is a lack of models and tools adapted to the reality of R&D projects, especially when developed in cooperation between public and private institutions. This gap necessitates studies that evaluate the applicability of traditional methodologies and propose adaptations that consider the specificities of research, without disregarding the fundamental principles of risk management.

In this context, the following research question arises: how can a risk matrix-based risk management methodology be used in university-enterprise cooperation R&D projects, and what precautions are necessary for its effective application? The present work aimed to propose and evaluate the application of the risk matrix as a management tool in an R&D project, considering its capacity for identification, prioritization, and treatment of risks. The application occurred in an ongoing R&D project, with the intention of analyzing its capacity to support risk management throughout the project, as well as evaluating its practical utility as a management support instrument.

2. Material and Methods

The research adopted a qualitative approach, seeking the understanding and interpretation of risk management processes in a Research, Development, and Innovation (R&D&I) project (Godoy, 1995). It was characterized as descriptive and applied, with the purpose of analyzing risk management in a practical context and intervening in the investigated environment (Gil, 2017). The design employed was action research, which allowed for participatory intervention in the project’s risk management, through the construction and application of a risk matrix, monitoring of actions, and continuous reassessment of risks in successive cycles (Gil, 2017).

The study was conducted within an ongoing R&D project, developed in cooperation between a research unit and a company in the oil and gas sector, located in Santo André, São Paulo. The project focused on the development of chemical recycling routes for polymeric materials to obtain new compounds applicable in protective coatings. The project team was multidisciplinary, composed of scholarship researchers at different training levels and technical support staff.

The identification of risks was carried out with the support of researchers experienced in the coordination of R&D projects at the research unit, using the expert opinion technique (PMI, 2013). A preliminary list of risks was elaborated through a brainstorming session, with the participation of the unit coordinator, the project coordinator, and the researchers responsible for each workstream (PMI, 2013; Ferreira et al., 2013).

Next, the analogous analysis technique was applied, considering information from previously executed projects at the unit, to identify recurring risks and occurrence patterns (Macedo and Salgado, 2015; Soares and Martens, 2018). The consolidated list of risks was submitted for evaluation by experienced researchers, through an open consultation, for additional contributions in identifying risks, causes, and consequences (Rabechini Jr., 2019; Macedo and Salgado, 2015).

Each risk was defined and organized according to a logic of cause, trigger, and consequence (Carvalho and Rabechini Jr., 2011). The identified risks were categorized into three main groups: technical-scientific, operational, and management. Risk analysis was performed by qualitatively assigning probability and impact values, according to five-level scales, evaluated based on observable criteria and prior experience.

The impact dimensions considered were schedule, cost, quality, and scope, adapted to the context of cooperative R&D projects (Carvalho and Rabechini Jr., 2011). The impact consolidation rule was adopted, in which the impact associated with each risk corresponded to the greatest impact identified among the analyzed dimensions. Risk exposure was calculated by multiplying probability by the highest impact level (P × Imax).

The risk matrix was constructed in a 5×5 format, with probability on the y-axis and impact on the x-axis, both ranging from one to five. Risks were positioned in the cell corresponding to the pair (P, Imax). To support decision-making, the matrix was organized into four qualitative zones, defined by risk exposure intervals. The structure of the matrix and the distribution of these zones are presented in Figure 1.

Figure 1. Structure of the 5×5 risk matrix and qualitative risk exposure zones
Source: Original research data

The systemic monitoring of the risk matrix began in January 2026, after the project’s opening and scope definition, and was reviewed monthly in analysis cycles. The evolution of the project’s risk exposure was analyzed by calculating the General Project Risk (GPR), which corresponded to the normalization of the sum of risk exposures based on the number of risks considered (Rabechini Jr., 2019).

Risk response strategies were based on classic management approaches: avoid, mitigate, share (or transfer), and accept (Rabechini Jr., 2019). For risks classified as high and critical, preventive actions and contingencies were defined. Preventive actions aimed to reduce risk exposure before its occurrence, while contingencies were reactive responses to minimize impacts should the risk materialize.

After the implementation of the responses, successive cycles of risk reassessment were carried out. These cycles allowed for continuous monitoring of risk exposure and evaluation of the effectiveness of the implemented actions, adjusting strategies according to the project’s evolution. No specific ethical considerations, such as Informed Consent Form (ICF) or confidentiality agreements, were identified, as the research focused on the project’s risk management and not on the collection of sensitive data from human participants.

3. Results and Discussion

The application of the risk management methodology in Research, Development, and Innovation (RD&I) projects revealed a complex panorama of uncertainties, characteristic of ventures with a high technical-scientific component and university-company collaboration. Initially, twenty-four distinct risks were identified, which were categorized into three main groups: technical-scientific, operational, and management. This categorization allowed for a structured understanding of the sources of uncertainty, aligning with the need for adapted approaches for RD&I projects, as discussed by Franzoni and Stephan (2023).

Techno-scientific risks were associated with the viability of hypotheses, methodological approaches, and the intrinsic limitations of the materials or processes studied. Operational risks, on the other hand, were directly related to experimental execution, available infrastructure, provision of inputs, equipment availability, and technical support. In turn, management risks encompassed aspects such as planning, coordination of activities, availability of human resources, financial balance, and project continuity, highlighting the breadth of uncertainties in an R&D project.

Each identified risk was detailed in terms of its cause, trigger, and consequence, allowing for an in-depth analysis of its potential impacts on project objectives. The impact dimensions considered were schedule, quality, scope, and cost, adapted for the R&D context (Carvalho and Rabechini Jr., 2011). The assessment of the probability of occurrence and the impact of each risk was carried out using five-level scales, based on observable criteria and the team’s prior experience, which provided robustness to the qualitative analysis.

From the risk exposure analysis, the risk matrix for the first analysis cycle was generated, presented in Figure 2, allowing for comparative visualization and prioritization of the identified risks.

Figure 2. Risk matrix of the first analysis cycle
Source: Original research results

Risk exposure was calculated as the product of probability by the highest impact level (P x Imax), resulting in numerical values between one and twenty-five. This approach allowed for the construction of a 5×5 risk matrix, which organized risks into four qualitative zones: green (low risk, exposure ≤ 4), yellow (medium risk, exposure 5–10), orange (high risk, exposure 11–16), and red (critical risk, exposure ≥ 17). This visualization facilitated the prioritization and continuous monitoring of risks throughout the project.

In the first analysis cycle, the risk matrix revealed a significant concentration of risks in the critical and high-risk zones. The risks with the highest exposure were R9, referring to the delay or lack of critical inputs, with an exposure of twenty-five, and R8, related to the unavailability of critical equipment, with an exposure of twenty. These findings underscore the project’s dependence on the availability of specific materials, originating from decommissioning, and on the experimental infrastructure, which directly impact the execution of activities and the schedule.

The predominance of the schedule dimension in these critical risks indicates the inherent operational constraints of R&D projects, which require high articulation and coordination (Penna and Batista, 2025). In addition to critical risks, other high-impact risks (exposure of sixteen) included R13 (delays due to negative intermediate results), R15 (failures in integration between work fronts), and R19 (difficulty in hiring human resources). These risks, along with others with twelve exposure, such as R4 (poorly known critical parameters) and R7 (failures in characterization techniques), highlighted the influence of organizational and technical-experimental factors.

The analysis of the first cycle showed that the project’s dynamics are determined not only by operational constraints, but also by the interaction between activities and the evolution of knowledge throughout the development. This behavior is typical of innovation projects, in which the high degree of uncertainty compromises the predictability of results (Russo and Sbragia, 2014). The results reinforce the need for integrated and continuous risk management, with identification and monitoring practices that adapt to the evolving nature of knowledge in R&D (Koller et al., 2025).

Responses to risks

The risk response strategies were defined based on classic management guidelines, adapted to the specificities of the R&D project (Rabechini Jr., 2019). For critical operational risks, such as R9 (delay or lack of critical inputs), the avoid strategy was adopted, involving alignment with the partner for advance mapping of inputs and definition of responsibilities. The specificity of the materials, originating from decommissioning, made obtaining them complex, increasing exposure and requiring intensive coordination. As a contingency, replanning of experimental activities and schedule adjustments were foreseen.

Risk R8 (unavailability of critical equipment) was addressed through mitigation, with actions such as identifying critical equipment, preventive maintenance, and identifying alternatives. This approach highlights the importance of planning and organizing resources in contexts where infrastructure unavailability can compromise the schedule, as pointed out by Aguiar et al. (2025) and Palma et al. (2011). The contingency involved redirecting demands to substitute equipment and replanning experimental activities.

For risk R13 (delays arising from negative intermediate results), a combined strategy of mitigation and acceptance was adopted. The treatment focused on systematic monitoring of results and partial validation of hypotheses, recognizing that, in research projects, not all deviations can be anticipated due to the inherent uncertainty in knowledge generation (Russo and Sbragia, 2014). The contingency established the redefinition of the experimental approach and adjustments to the technical scope, when necessary.

Risk R15 (failures in integration between work fronts) was addressed with the strategy of avoidance, through periodic alignment meetings, definition of interfaces, and use of centralized management tools. The high interdependence between the project’s work fronts, where the results of one stage condition the progress of the others, constitutes a structural risk factor. The contingency involved reprogramming dependent activities and updating the schedule.

The difficulty in hiring human resources (R19) was addressed through mitigation, with actions focused on reviewing and adapting the job profile and establishing institutional partnerships. The need for researchers with specific training and experience, combined with institutional incentives for student training, increased exposure to this risk. Silva et al. (2010) highlight the influence of team formation and structured discussion of activities on the effectiveness of risk management in development projects.

Risks R4 (poorly known critical parameters) and R7 (failures in characterization or analysis techniques) were addressed through mitigation. For R4, actions included initial exploratory studies and theoretical deepening, with a contingency of redefining experimental parameters. For R7, the focus was on standardizing methods and team training, with a contingency of repeating analyses or using external laboratories. These risks are intrinsically linked to the experimental process, where uncertainty in parameter definition can condition the quality and reliability of the analyses.

The unavailability of key members (R17) was addressed through mitigation and acceptance, with knowledge sharing actions and documentation of activities. R&D projects depend heavily on tacit knowledge and accumulated experience, making personnel replacement a complex process. Napolitano et al. (2020) emphasize the importance of Knowledge Management for risk treatment. Documentation and sharing, although they do not eliminate the risk, reduce its impact by preserving critical knowledge.

The failure in project management by the coordinator (R23) was addressed by the avoidance strategy, with actions focused on defining monitoring routines and using progress indicators. Risk R24 (non-use or inadequate use of management tools) was mitigated through tool standardization, team training, and usage monitoring. These management risks are structural, as project execution depends on the integration between fronts and the coordinator’s articulation, while the adequate use of tools ensures traceability and control of activities (Aguiar et al., 2025; Sena et al., 2025).

In summary, the adopted responses reflected the need to adapt risk management to the characteristics of R&D projects, marked by their experimental nature and university-company cooperation. For technical-scientific risks, mitigation strategies combined with acceptance prevailed, acknowledging the limitation of preventive approaches in the face of the uncertainty inherent in knowledge generation. For management risks, actions focused on structuring routines, using indicators and monitoring tools, as well as planning operational activities were highlighted. This pattern aligns with the view of Koller et al. (2025), who identify the convergence of technical-scientific uncertainty, collaboration challenges, and management complexity as structural factors in R&D projects.

Second analysis cycle

After the implementation of responses to risks located in the critical zone, a new assessment was carried out, revealing a significant reduction in the probability of occurrence of risks R8 and R9. For risk R9, which initially presented the highest exposure, the strategy of avoiding, by acting with the partner to guarantee the supply of materials, resulted in the reduction of the probability of occurrence from level five (very high) to level one (very low). Although the impact remained high due to the essentiality of the material, the risk exposure was reduced to the medium risk range, requiring only continuous monitoring.

Figure 3. Risk matrix of the second analysis cycle
Source: Original research results

Regarding risk R8, addressed by mitigation, the implemented actions, including the survey of critical equipment and the structuring of a preventive maintenance schedule, resulted in the reassessment of the probability of occurrence from level five (very high) to level two (low). The impact remained unchanged, but the risk exposure was reduced to the medium risk zone. This analysis demonstrated the effectiveness of the adopted response strategies, especially in treating high-impact risks, by reducing the probability of occurrence to more acceptable levels (Marcelino-Sádaba et al., 2014). Conducting a new evaluation cycle reinforced the continuous nature of risk management, allowing for reassessments and adjustments as the project evolves (Ferreira et al., 2013).

Third cycle of analysis

In the third analysis cycle, the focus was on the remaining high-impact and higher-probability risks, specifically R13, R15, and R19. Risk R15, related to the integration between work fronts, was addressed with the strategy of avoidance, through the centralization of project information on a shared platform, definition of interface responsibles, and establishment of monitoring routines. These actions allowed the probability of occurrence to be reduced from level four (high) to level one (very low), and the impact on the schedule dimension from four to three, positioning the risk in the low-risk zone.

Figure 4. Risk matrix of the third analysis cycle
Source: Original research results

For risk R19, associated with hiring difficulty, the mitigation strategy was maintained, with actions focused on reviewing and making the job profile more flexible, while preserving the essential requirements for carrying out the activities. As a result, the probability of occurrence was reduced from level four (high) to level two (low), reclassifying the risk as medium. Finally, risk R13, related to the occurrence of negative intermediate results, was addressed by a combined mitigation and acceptance strategy. The probability was reduced from level four (high) to level three (moderate), and the impact on the deadline dimension from four to three, positioning the risk in the medium risk zone.

This area of remaining risks has come to predominantly concentrate risks associated with the management category, such as failures in integration between fronts and difficulties in hiring human resources. The relevance of these risks in R&D projects is notorious, as management failures can compromise project performance in a magnitude comparable to technical failures (Macedo and Salgado, 2015). Russo and Sbragia (2014) pointed out that about twenty-nine percent of failures in innovation projects are associated with uncertainties related to management, including problems with communication, planning, and team organization.

Risk Matrix Assessment in R&D Project

The evolution of the Overall Project Risk (OPR) throughout the analysis cycles demonstrated the effectiveness of the risk matrix as a management tool. In the first cycle, the OPR was forty-two point three percent. After implementing responses to critical risks, the OPR was reduced to thirty-seven percent in the second cycle. In the third analysis cycle, a new decrease was observed, reaching thirty-two point three percent, indicating a consistent reduction in the project’s overall exposure, directly associated with the implementation of response strategies.

The maintenance of a residual exposure level, around thirty-two percent, is consistent with the nature of R&D projects, in which not all risks can be eliminated, with residual levels associated with technical-scientific uncertainties remaining (Koller et al., 2025). This residual limit is associated with the concept of reducing risk to levels as low as reasonably practicable (Duijm, 2015), depending on the organization’s risk appetite and the project’s characteristics (Souza and Barcauí, 2014). The adoption of acceptance strategies, associated with continuous monitoring, allows risk to be kept at controlled levels throughout the project execution.

The effectiveness of the risk matrix as a management tool in R&D projects is intrinsically linked to its ability to structure and prioritize risks, supporting decision-making. The representation in terms of probability and impact allows for rapid identification of the most critical risks and directs efforts towards their mitigation, contributing to the reduction of the project’s overall exposure (Duijm, 2015). However, it is essential to consider the inherent limitations of the matrix, such as the use of discrete scales, which can lead to a loss of resolution in comparing risks and a concentration of equivalent classifications, distorting prioritization (Cox Jr., 2008).

Furthermore, the definition of risk levels involves the evaluator’s judgment, which can introduce additional uncertainties into the analysis process (Duijm, 2015). Thus, the effectiveness of the risk matrix observed in this study is directly related to its use as a prioritization and monitoring tool, associated with continuous reassessments throughout the project. This reinforces the need for a critical reading of the results, especially in R&D projects, where technical uncertainty and result variability are not always fully captured by qualitative classifications, requiring a contextualized interpretation of the findings.

4. Conclusion

The present study sought to propose and evaluate the application of a risk matrix as a management tool in a Research, Development, and Innovation (R&D&I) project, focusing on its capacity to identify, prioritize, and address uncertainties. Twenty-four distinct risks were identified, categorized as technical-scientific, operational, and managerial, which were systematically organized into a 5×5 matrix, considering their probability of occurrence and impact. The application of the matrix allowed for effective prioritization, guiding the implementation of response strategies such as avoid, mitigate, and accept for the most critical risks, such as delays in obtaining inputs and unavailability of essential equipment. A progressive reduction in the Overall Project Risk (OPR) was observed over three analysis cycles, decreasing from forty-two point three percent to thirty-two point three percent, which demonstrated the tool’s effectiveness in monitoring and managing risk exposure. The main contribution lies in the empirical demonstration that the risk matrix is a valid instrument to support management in R&D&I projects, especially in university-business collaboration contexts, by structuring the risk management process and supporting decision-making.

However, the application of the risk matrix presented limitations, such as the use of discrete scales, which can generate a loss of resolution in risk comparison and concentrate equivalent classifications, and the dependence on the evaluator’s judgment in defining the levels, introducing additional uncertainties. These aspects reinforce the need for a critical interpretation of the results, especially in R&D projects, where technical uncertainty and result variability are not always fully captured by qualitative classifications. For future studies, it is suggested to expand the application of the risk matrix to include the assessment of positive risks, i.e., opportunities, in R&D projects. It is also recommended to incorporate quantitative approaches and expand the dimensions of analysis, aiming to improve the precision and robustness of the risk management method.

Bibliographic References

Associação Brasileira de Normas Técnicas [ABNT]. 2018. ABNT NBR ISO 31000: Gestão de Ris

Baches, J.F.L.M.; Abreu Días, E.R.; Fonseca, A.L.A.; Costa Filho, J.V. 2025. Ensino de ferramentas de gestão de riscos na educação profissional e tecnológica. Revista de Gestão e Secretariado 16(6): e4903-e4903.

Ferreira, B.A.A.; Almeida, J.O.R.; Leão, P.R.C.; Silva, N.P.G. 2013. Gestão de riscos em projetos: uma análise comparativa da norma ISO 31000 e o guia PMBOK®, 2012. Revista de Gestão e Projetos 4(3): 46-72.

Project Management Institute [PMI]. 2021. Um Guia do Conhecimento em Gerenciamento de Projetos. 7ed. Project Management Institute, Newtown Square, PA, EUA.

Soares, A.C.; Martens, M.L. 2018. Gerenciamento de riscos ligado à estratégia corporativa para projetos de desenvolvimento de novos produtos na indústria química. Journal of Business & Projects/Revista de Gestão e Projetos 9(3): 127-138.

Article originating from the Final Course Work of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

Article originating from the Final Course Work of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving the independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated the automated reading of files, the organization of curves into current-potential matrices, the generation of the potential map, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed by device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of the results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and enhance the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used for the definition and identification of the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.