Article

October 20, 2026

Project management in the implementation of predictive maintenance with sensors in the pharmaceutical industry

Project Management in the Implementation of Predictive Maintenance with Sensors in the Pharmaceutical Industry

Weverton Mizael Quintanilha Procópio; Bruno Henrique Sanches

DOI: 10.22167/2675-6528-202602446

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

The growing demand for operational reliability in critical industrial environments has driven the search for solutions that anticipate failures and support maintenance decision-making. The application of project management practices in the implementation of online monitoring for predictive maintenance of critical industrial assets in a pharmaceutical industry in São Paulo was evaluated. The research, of an applied nature, used a predominantly qualitative approach, supported by descriptive quantitative analysis, through a single case study. Project documents, operational records, system alerts, failure indicators, physical evidence of degradation, and management artifacts were collected and analyzed. The results indicated that the initiative improved clarity in scope definition, prioritization of critical assets, organization of interventions, and visibility into failure behavior. The main gain lay in the structured use of the generated information for monitoring and decision-making, not just in the adoption of technology. It was concluded that the effectiveness of predictive maintenance depends on how its implementation is planned, organized, and incorporated into the operational routine, demonstrating the transformation of a technological solution into usable organizational capability.

Keywords: Operational reliability; Maintenance management; Industrial maintenance; Continuous monitoring; Digital transformation.

1. Introduction

The pharmaceutical sector is recognized for its high operational complexity and the rigor applied to production processes, especially due to the quality, safety, and traceability requirements imposed by regulatory bodies. In this context, the reliability of industrial assets becomes crucial for production continuity and compliance with Good Manufacturing Practices (GMP), as unexpected failures can lead to line stoppages, waste of inputs, rework, and significant financial losses (Agência Nacional de Vigilância Sanitária, 2019; Juran and Godfrey, 1998; Mobley, 2002). In high-criticality industrial environments, process stability depends on maintenance practices capable of sustaining consistent performance and high availability (Slack et al., 2023).

In the context of digital transformation, predictive maintenance has consolidated itself as a strategy to increase reliability and reduce costs associated with unplanned downtime. Unlike corrective and preventive approaches, predictive maintenance uses data collected by sensors and Internet of Things (IoT) technologies to monitor variables such as vibration, temperature, and noise, allowing anomalies to be identified before they evolve into functional failures (Lee et al., 2015). This logic is compatible with the principles of Industry 4.0, by integrating automation, connectivity, and data analysis to support evidence-based decisions and increase the predictability of interventions (Kerzner, 2022).

The expansion of this approach is evidenced by market estimates. The global predictive maintenance market was estimated at approximately US$ 9.84 billion in 2023, with a projected growth to US$ 60.13 billion by 2030 (“Grand View Research”, 2024a). In Brazil, it was estimated at US$ 348.6 million in 2023, with projections of accelerated expansion by 2030 (“Grand View Research”, 2024a; IMARC Group, 2024). In parallel, the pharmaceutical industry remains among the most economically relevant, with estimates of US$ 1.64 trillion in 2024 and a projection of US$ 2.35 trillion by 2030 (“Grand View Research”, 2024b). In Brazil, the Interfarma Guide 2022 indicated a revenue of R$ 146.7 billion in 2021, reinforcing the sector’s relevance and the importance of initiatives focused on the reliability of productive assets (Interfarma, 2022). With the digitalization of industrial processes, the Pharma 4.0 concept has come to guide the incorporation of sensors, monitoring systems, and real-time data analysis, with an emphasis on quality, traceability, and data-driven decision-making (“International Society for Pharmaceutical Engineering [ISPE]”, 2017). Projections associated with this ecosystem indicate significant growth, following the dissemination of automation and monitoring solutions (Precedence Research, 2024). In the Brazilian context, there is evidence of expansion in the industrial sensor market and the adoption of connected solutions in segments associated with the healthcare chain (Bona Fide Research, 2024; SEGS, 2021).

However, technological adoption does not, in itself, ensure operational success or sustainability of gains. The implementation of predictive maintenance systems with sensors involves decisions related to scope, integration with existing infrastructure, supplier management, technical and operational risks, team training, and governance of the alert response process. It is an implementation structured in stages, such as solution selection, installation, integration, validation, and start of operation, followed by continuous system use.

In this context, the application of management methodologies is essential to define requirements, deadlines, costs, communications, and responsibilities, reducing rework and ensuring traceability of decisions and deliverables (“Project Management Institute [PMI]”, 2017; Kerzner, 2022). Given this scenario, this work aimed to evaluate the application of management methodologies in the implementation of sensors for predictive maintenance in a pharmaceutical industry, analyzing their effects on equipment reliability and operational efficiency of production processes.

2. Material and Methods

The research was applied in nature, using management methodologies and predictive maintenance tools to address an operational problem related to equipment reliability in a pharmaceutical industry. This framework sought to generate knowledge for process improvement and organizational decision support (Gil, 2019).

The methodological approach adopted was predominantly qualitative, with support from descriptive quantitative analysis. The design consisted of a single case study, to examine a contemporary phenomenon in its real context, preserving the interactions between technology, people, process, and management structure (Yin, 2014).

The study was conducted in a large pharmaceutical industry, located in São Paulo, SP, Brazil, without nominal identification of the organization, in compliance with institutional confidentiality guidelines. The unit of analysis focused on the implementation of online monitoring sensors for predictive maintenance on critical industrial assets.

The unit of analysis also covered the application of management practices to structure and consolidate the implementation in the productive context. The study population was composed of industrial assets amenable to monitoring by sensors, and the analytical scope included critical equipment, selected by intentional sampling, considering operational impact, failure history, and relevance.

The empirical unit comprised the prioritized assets for monitoring, the records generated during deployment, and the indicators associated with operational performance and reliability. Information was collected on occurrences, failures, system-issued alerts, and evidence of intervention.

Operational documents and records, such as occurrence logs, technical reports, and system alerts, were used. Operational and maintenance indicators, such as MTTR, MTBF, OEE, availability, and failure rate, characterized the reliability and performance of the assets (Mobley, 2002; Smith and Hawkins, 2004; Nakajima, 1988).

Management artifacts, including scope documents, schedules, responsibility assignment matrices (RACI), risk and communication logs, and governance, were sources of evidence (PMI, 2017; PMI, 2021; Kerzner, 2022). The technological infrastructure, composed of online monitoring sensors, gateways, and an alert visualization platform, was also considered.

Physical and technical evidence, such as visual records and inspections, were collected to confront alerts with observable signs of degradation. Software such as Microsoft Excel and Power BI were used for the organization, consolidation, and descriptive analysis of information, in addition to supporting the construction of tables, graphs, and dashboards.

The collection procedures were carried out in sequential stages. Initially, a survey and prioritization of critical assets were conducted based on failure history and operational impact. Subsequently, records associated with the structuring of the deployment, such as scope and schedule, were gathered.

Subsequently, the records of the online monitoring system activation were analyzed, covering sensor installation, connectivity, and alert emission. Finally, operational and maintenance indicators, along with physical evidence, were organized for integrated reading of the detected condition and interventions.

The methodological logic adopted in the study followed a flow that articulated the definition of the operational problem, the prioritization of assets, the implementation of the solution, the collection of evidence, the organization of data, and the integrated analysis. This sequence ensured traceability and coherence between the study stages.

The data analysis was conducted by evidence triangulation, combining documentary interpretation, technical analysis of operational records, and descriptive reading of indicators. In the qualitative dimension, the aim was to identify the implementation structure from the project management perspective, observing scope, governance, and coordination.

In the quantitative dimension, maintenance and performance indicators were analyzed descriptively, comparing pre-implementation (before April 2025) and post-implementation (May to December 2025) periods. The final interpretation converged the different sources of evidence for a consistent understanding of the implementation in its real context.

3. Results and Discussion

The implementation of online monitoring in critical industrial assets of a pharmaceutical industry revealed that the application of project management practices was fundamental to structuring the initiative and converting technology into operational capability. The results indicated that the clear definition of scope, prioritization of assets, organization of interventions, and visibility over failure behavior were improved. The main gain resided not only in the adoption of technology but in the structured use of the generated information for monitoring and decision-making, as per the study’s objective. The detailed analysis of qualitative and quantitative evidence allowed for an understanding of the implementation dynamics and its initial effects.

Evidence of critical asset prioritization and deployment scope definition

The implementation of online monitoring began with the careful selection of assets that presented the greatest operational criticality. This prioritization considered the history of failures, the direct impact on the production process, and the relevance to the continuity of operations. Such direction was essential to delimit the scope of the initiative, ensuring that efforts and resources were concentrated on the equipment with the greatest potential impact, avoiding dispersion on less critical assets. This initial approach is consistent with the principles of project management, which emphasize the importance of a well-defined scope aligned with organizational needs, with value-oriented prioritization (PMI, 2021; Kerzner, 2022).

This definition of scope and prioritization aligns with discussions in the area of reliability and asset management, which establish criticality as a central criterion for guiding intervention and resource allocation decisions. In complex industrial environments, the absence of clear prioritization can compromise the effectiveness of actions, leading to a dispersion of efforts and difficulty in generating consistent operational results. In the case studied, the adopted prioritization proved to be a positive point, as it established coherence between operational needs, the defined scope, and the application of available resources, indicating managerial rationality in the conduct of the initiative.

Although prioritization by criticality was consistent and adequate for the initial phase of implementation, it does not eliminate the possibility that other assets, outside the initial scope, may also present relevant vulnerabilities or risks. Therefore, the scope adopted was effective for the beginning, but it does not cover the entire operational criticality of the analyzed block. The analysis suggests that the effectiveness of prioritization depends on its continuity, involving periodic review of criteria, updating of information, and re-evaluation of the operational context over time, treating prioritization as a continuous process and not an isolated decision.

Evidence of scope validation and acceptance of technical deliverables

The materialization of technical deliveries was evidenced by the monitoring system’s records, which began to issue structured alerts, condition diagnostics, and intervention recommendations for critical assets. The system demonstrated functionality by displaying real-time monitoring and generating recommendations with the potential to support intervention. For example, a predictive alarm related to the blower system’s motor was observed, indicating the monitored condition, recommending a specific action, and estimating a timeframe for treatment. Complementarily, the system also produced similar evidence for the exhaust system’s motor, confirming its operation on multiple critical assets and the consistency of the generated recommendations.

These evidences are crucial, as they demonstrate that the implementation transcended the mere installation of technological components, advancing to the generation of usable information for decision-making. In practice, the solution began to produce interpretable signals, with the potential to guide technical analysis, prioritization, and the routing of interventions. From a project management perspective, the validation of a deliverable is not limited to its technical availability, but to its ability to fulfill the function for which it was implemented. The records indicated that the system operated in a manner consistent with the project’s purpose, offering visibility into asset behavior and supporting the identification of anomalies before functional failure.

This result aligns with the literature emphasizing that the value of technological projects depends more on the practical utility of deliverables in the organizational environment than on their formal implementation (PMI, 2021; Kerzner, 2022). In the analyzed context, the issued alerts indicated that the solution generated information with operational applicability, representing a significant advancement compared to exclusively reactive approaches. The presence of actionable recommendations was a positive point, as it reduced the gap between detection and response, which is especially relevant in industrial environments where the utility of information depends on its rapid incorporation into the workflow and decision-making process.

However, the analysis also revealed an important limitation. The issuance of alerts, by itself, does not guarantee the generation of organizational value. Full effectiveness depends on the existence of established routines, defined responsibilities, and operational capacity to interpret, prioritize, and adequately respond to recommendations. Although the observed results were consistent with the initial validation of the technical deliverables, their full effectiveness is conditioned on the continuous incorporation of the solution into the maintenance and management routine. This means that the sustainability of the generated value requires a continuous process of adaptation and institutionalization of practices.

Evidence of the conversion of alerts into work planning and control

The analysis of the evidence demonstrated that the alerts generated by the monitoring system were effectively translated into a structured plan for maintenance interventions. A preliminary schedule for the execution of activities was developed, detailing tasks, responsible parties, operational sequence, and temporal distribution. For example, activities such as dismantling the exhaust system motor, removing filters for collector cleaning, replacing bearings and bushings of the air intake system, and balancing the exhaust system motor were planned with specific dates between May 1st and 5th, 2025, with designated responsible parties for each stage. Furthermore, technical monitoring reports were prepared, evidencing the condition of the components, the nature of the identified anomaly, and its criticality, serving as a basis for prioritization and decision-making regarding the timing and urgency of the intervention.

The observed results indicate that the implementation was not restricted to alert generation, but advanced to the organization of the operational response. The value of the solution was not only in the ability to identify deviations, but in its use to structure the work to be executed. This became particularly visible when the information issued by the system began to guide activities, sequencing, definition of responsibilities, and temporal organization of interventions. From a project management perspective, this finding is relevant because it highlights the transition between technical delivery and managerial use, indicating that projects of this nature only produce value consistently when the generated information connects to the workflow and supports concrete planning and control decisions (PMI, 2021).

In the industrial context, the mere detection of anomalies does not, in itself, enhance operational reliability if these insights are not translated into coordinated action. This outcome aligns with the literature on maintenance and reliability, which emphasizes the importance of transforming condition signals into programmed interventions, reducing reliance on strictly reactive responses (Mobley, 2002; Jardine et al., 2006; ISO 55000, 2014). These authors highlight that condition monitoring only generates value when integrated into maintenance action planning, allowing for the anticipation of failures and better allocation of available resources.

In this sense, the analyzed case presented an important positive point: the information produced by the system did not remain isolated in the digital environment, but began to feed a more organized logic of response, bringing monitoring closer to operational decision-making and the programming of interventions. From a critical point of view, this was one of the most consistent findings of the study, as it evidences a concrete transition between monitoring and operational action. However, the existence of schedules and technical reports does not guarantee full execution discipline, as resource constraints, operational unavailability, and replanning can interfere with the real effectiveness of the response.

Thus, the result was positive and reinforces the managerial utility of the implementation, but it should be interpreted as evidence of the initial structuring of the operational response, and not as proof of full maturity of the planning and control process of interventions. The real effectiveness of the response and the overcoming of dependencies on key actors do not always appear fully in the analyzed records, which constitutes an important limitation for broader inferences about the consolidation of the process.

Evidence of the coherence between predictive diagnosis and physical condition of the assets

The analysis of physical evidence allowed for the verification of a direct correspondence between the alerts issued by the monitoring system and the actual condition of the monitored components. For example, pronounced wear was observed in the transmission assembly, involving the crown and chain, which was associated with a predictive alert of potential failure. The physical condition of the bucket transmission assembly, with worn crown teeth and chain, compromised the integrity of the drive and presented a risk of functional failure, with an estimated repair time of up to 72 hours. Complementarily, degradation was identified in the bearings of the exhaust system, with signs of lubrication deficiency in the ball cages and oxidation on the inner and outer ring raceways, with an estimated repair time of up to 18 hours, reinforcing the coherence between the predictive diagnosis and the observed physical state.

The alignment between the predictive diagnosis and the observed condition proved relevant by reducing the uncertainty associated with decision-making. When the alert finds a match in physical evidence, prioritization ceases to depend exclusively on subjective perceptions or isolated experiences, becoming instead supported by concrete evidence. This tends to increase the reliability of intervention decisions. This result aligns with the literature on predictive maintenance and reliability, which highlights the importance of validating monitored signals through physical or technical confirmation, especially in the initial stages of implementation (Mobley, 2002; Jardine et al., 2006; ISO 55000, 2014).

These authors emphasize that the credibility of monitoring systems depends, to a large extent, on the ability to correlate condition data with real evidence of asset degradation. From a managerial perspective, this convergence tends to favor greater confidence in the system and greater adherence of operational actors to its use. When alerts are confirmed in practice, resistance to technology is reduced, and the probability of incorporating monitoring into the decision-making process and maintenance routine increases. Among the positive points, the coherence between alert and physical condition stands out, which reinforces the usefulness of the implemented solution and its ability to support better-informed decisions.

On the other hand, it is important to acknowledge a limitation. The presence of confirmatory physical evidence in specific cases does not mean that all alerts issued present the same degree of precision or accuracy. Thus, the observed results are consistent and indicate a good initial performance of the solution, but they do not yet allow for full generalization to all operational situations. The consolidation of this reliability depends on the continuity of monitoring, the accumulation of evidence over time, and the systematic validation of the issued diagnoses, which requires a continuous process of learning and adjustment.

Evidence of governance, coordination, and traceability of execution

The synthesis of consolidated evidence indicated that the implementation was conducted as an initiative with verifiable deliverables, inter-area dependencies, and the need for coordination to transform alerts into executed actions. In managerial terms, the analyzed records pointed to the existence of initial governance and traceability between technical deliverables, decisions, and planning. This suggests that the implementation was treated in a more structured way, with integration between areas and a focus on controlling the resulting work. This result is particularly relevant because one of the main challenges in predictive monitoring and maintenance projects is precisely the conversion of technical information into an organized response.

In practice, the mere generation of alerts does not produce value if the organization lacks minimal mechanisms to interpret, prioritize, and forward these signals in a coordinated manner. From the perspective of project management literature, this finding aligns with the importance of integration, cross-functional coordination, and governance as central elements for sustaining the deliverables and benefits generated by projects (PMI, 2021; Kerzner, 2022). Furthermore, studies on benefits realization and the institutionalization of organizational changes indicate that capturing value in technological projects depends on the ability to connect technical deliverables to managerial processes, routines, and decisions (Serra and Kunc, 2015; Too and Weaver, 2014).

In the analyzed context, this aspect proved especially important because the implementation involved interaction between technology, maintenance, and operation. This means that the value of the solution depended not only on the system’s functionality but also on the organization’s capacity to absorb the generated information and transform it into coherent operational action. In this sense, the results suggest a relevant advancement in the organization of the response, which represents one of the most consistent positive points of the study. Nevertheless, it is important to acknowledge a limitation: the available evidence indicates an initial structuring of governance and coordination, but it does not allow us to state, with certainty, the degree of consolidation of this logic over time.

The sustainability of this arrangement will depend on the continuity of routines, the institutionalization of practices, and the maintenance of engagement among the involved areas. Thus, the findings indicate that the implementation has advanced beyond the technical dimension and has begun to produce effects also in the way of organizing work. However, the consolidation of this governance depends on its continuous incorporation into operational routine, so that coordination between areas ceases to be a circumstantial response and becomes a stable management practice, ensuring the perpetuity of gains.

Quantitative evidence of operational performance and reliability

The quantitative analysis was conducted based on operational records from the manufacturing plant, encompassing time series of failures, duration of occurrences, and reliability and performance indicators. These records allowed for a descriptive tracking of the monitored assets’ behavior over the observed period, especially concerning the frequency of failures and the operational impact of occurrences. The indicators used included failure rate, failure hours, MTBF (Mean Time Between Failures), MTTR (Mean Time To Repair), and availability, each with its specific analytical purpose and interpretation to characterize asset reliability and performance (Mobley, 2002; Smith and Hawkins, 2004; Nakajima, 1988).

The combined use of these indicators was important to allow a broader reading of asset behavior, avoiding interpretations restricted to a single parameter. In industrial environments, operational reliability is expressed not only by the quantity of recorded failures, but also by the duration of occurrences, recovery capacity, and the stability of equipment behavior over time. This perspective is consistent with the literature on reliability and asset management, which recommends the integrated reading of frequency, impact, and availability to support decisions more aligned with operational risk (Jardine et al., 2006; ISO 55000, 2014; Moubray, 1997).

The weekly evolution of the failure rate by area of Block 07 Manufacturing, in the post-implementation period (May to December 2025), revealed unequal behavior among the monitored areas. More pronounced oscillations were observed in certain groupings (Handling, Encapsulation, Compression, Coating) and greater stability in others. This pattern suggests that operational criticality was not homogeneously distributed in the studied block, reinforcing the importance of a segmented reading of assets and evidence-based prioritization. From a managerial perspective, this finding was relevant because it broadened visibility into the concentration of failures and favored a greater direction of the operational response.

Instead of treating the entire operation as homogeneous, the area-based reading allowed for the identification of points with higher relative exposure to failures, which tends to support more consistent decisions regarding follow-up, effort allocation, and priority setting. This result also aligns with the literature that treats reliability and asset management as processes dependent on continuous monitoring, contextualized reading of indicators, and adequate segmentation of risk sources (Jardine et al., 2006; ISO 55000, 2014; Moubray, 1997). Instead of seeking only an average aggregated value, the operational clustering analysis proved to be more aligned with industrial decision-making logic, as it allows for the localization of areas with greater vulnerability and supports more targeted responses.

Complementarily, the weekly distribution of failure hours by area of Block 07 Manufacturing indicated that failure hours were also unevenly distributed among the observed areas and weeks, with a higher concentration in certain periods. This distribution reinforces that the reading of operational performance cannot rely solely on the frequency of occurrences, as less frequent but longer failures can also represent a significant impact on operational availability. This behavior broadened the analytical utility of the implementation, as it allowed for the interpretation not only of where failures occurred most frequently, but also where they tended to produce a greater operational impact.

In practical terms, this reading favors more qualified prioritization, especially in contexts where multiple areas simultaneously compete for maintenance resources, shutdown windows, and managerial attention. Compared to the literature, this type of reading is particularly important because it aligns monitoring with a decision logic based on risk and impact, rather than just incidence (Moubray, 1997; ISO 55000, 2014; Jardine et al., 2006). This is a relevant positive point of the study, as it avoids oversimplification of operational behavior and broadens the analysis’s adherence to the managerial use of indicators.

On the other hand, the quantitative results also present limitations. Firstly, it is a descriptive reading inserted in a single case study, developed in a specific organizational context, which does not allow for automatic generalization of the findings. Secondly, the complete consolidation of comparisons still depends on greater temporal stabilization of the system and full standardization of the calculation rules between periods and assets. Thus, the indicators were treated as supporting evidence for the interpretation of operational behavior and not as isolated proof of causality. Nevertheless, the quantitative findings played an important role in the study by complementing the documentary, technical, and observational evidence, contributing to a more consistent reading of the implementation and its initial effects on operational visibility and the organization of the maintenance response.

Integrative synthesis and final discussion of the results

Considering the set of evidence, a convergence was observed between the different dimensions analyzed. The technical deliverables were materialized and began to generate usable recommendations; the alerts were converted into structured planning; the physical evidence confirmed the coherence of the diagnoses; and the operational records began to offer better visibility into the behavior of failures. This convergence suggests that the main contribution of the implementation was not only in the introduction of sensors, but in the structuring of a more organized logic of operational response. In practical terms, the project contributed to bringing monitoring, decision-making, and execution closer together, reducing the dependence on strictly reactive responses and favoring greater predictability.

From a project management perspective, this result is relevant because it evidences the transformation of a technological solution into usable organizational capacity. More than an isolated technical delivery, the implementation showed potential to strengthen the coordination, prioritization, and control of interventions. This interpretation is consistent with the literature that treats value generation in projects as a result of the effective incorporation of deliverables into the organizational context, and not just their formal implementation (PMI, 2021; Serra and Kunc, 2015; Too and Weaver, 2014). The findings also reinforce that governance, scope definition, inter-area integration, and qualified information use were central elements for sustaining the observed results.

In the analyzed case, this proved particularly important because the utility of the implemented solution depended less on the technology itself and more on the organization’s ability to absorb the emitted signals and convert them into operational action. This interpretation also aligns with the literature on asset management and condition-based maintenance, which highlights the importance of integration between monitoring, interpretation, and decision-making for the produced data to translate into operational benefit (Jardine et al., 2006; ISO 55000, 2014; Mobley, 2002). Among the most consistent positive points observed throughout the study, the coherence between diagnosis and physical evidence, the conversion of alerts into structured action, and the increased managerial visibility over failure behavior stand out. These aspects suggest that the implementation progressed beyond the technical dimension and began to produce effects also in the way work was organized.

At the same time, the analysis also highlighted relevant limitations. The main one is related to the still restricted time window for observing the effects of the implementation, which limits more robust inferences about the stability of the results over time. Furthermore, as it is a single case study of an observational nature, the findings should be interpreted with caution, especially regarding generalization to other operational or industrial contexts. It is also recognized that part of the quantitative consolidation still depends on greater stabilization of records and standardization of the comparative bases used. From an applied point of view, the study offers a relevant managerial contribution by demonstrating that online monitoring implementations tend to produce more consistent results when conducted with a clear definition of scope, prioritization criteria, response flow organization, and minimum governance mechanisms. In practical terms, this means that value generation depends not only on the installation of the technology but on the organization’s ability to incorporate it into its operational routine and decision-making process.

4. Conclusion

This study evaluated the application of management methodologies in the implementation of sensors for predictive maintenance in critical industrial assets of a pharmaceutical industry, seeking to understand their effects on reliability and operational efficiency. It was found that the initiative improved scope definition, asset prioritization, intervention organization, and visibility into failure behavior. Alerts generated by the monitoring system were converted into structured action planning, and coherence was observed between predictive diagnostics and the actual physical condition of the components. The main contribution lies in demonstrating that the value of predictive maintenance is not limited to technological adoption, but to the organizational capacity to structure the use of information for monitoring and decision-making, transforming the technical solution into a usable managerial capability.

However, the analysis revealed important limitations, such as the restricted time window for observing the effects, which prevents robust inferences about the long-term stability of the results. Furthermore, the single case study nature restricts the automatic generalization of findings to other contexts. The full effectiveness of the solution depends on the continuous institutionalization of routines, the clear definition of responsible parties, and the operational capacity to interpret and respond to alerts. It is suggested that future studies explore the consolidation of governance and interfunctional coordination over time, as well as the systematic validation of diagnoses in different operational scenarios, treating prioritization and response as continuous processes of learning and adjustment.

Bibliographic References

Agência Nacional de Vigilância Sanitária. (2019). Resolução RDC nº 301, de 21 de agosto de 2019: Boas práticas de fabricação de medicamentos. Disponível em: https://bvsms.saude.gov.br/bvs/saudelegis/anvisa/2019/rdc0301_21_08_2019.pdf. Acesso em: 28 out.2025.

Juran, J. M., e Godfrey, A. B. (1998). Juran’s quality handbook (5th ed.). McGraw-Hill. New York, NY, EUA.

Kerzner, H. (2022). Project management: A systems approach to planning, scheduling, and controlling. 13ed. John Wiley e Sons,

Lee, J., Bagheri, B., e Kao, H. A. (2015). A cyber-physical systems architecture for industry 4.0-based manufacturing systems. Manufacturing Letters, 3(1), 18–23.

Mobley, R. K. (2002). An introduction to predictive maintenance (Plant Engineering) (2nd ed.). Butterworth-Heinemann. Burlington, MA, EUA.

Slack, N., Brandon-Jones, A., e Burgess, N. (2023). Administração da produção (10ª ed.). Atlas. São Paulo, SP, Brasil.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving the independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated the automated reading of files, the organization of curves into current-potential matrices, the generation of the potential map, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed by device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of the results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and enhance the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used for the definition and identification of the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.