October 26, 2026
Project management in operational adaptation for Key Account service
Antonio Nascimento de Freitas Silva; Sérgio Kooji Kamimura
DOI: 10.22167/2675-6528-202600587
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
The service to strategic clients, known as Key Account (KA), imposes operational challenges on medium-sized companies, requiring greater capacity, logistical predictability, and process standardization. This study aimed to analyze how project management contributed to the adaptation of internal processes in a company in the logistics sector in the face of the operational and contractual demands of a KA. The research adopted a qualitative and descriptive approach, configured as a single case study, and used documentary analysis, unstructured interviews with the manager, and participant observation for data collection. Project management tools, such as Work Breakdown Structure, schedule, RACI matrix, risk matrix, 5W2H action plan, and process mapping (AS IS and TO BE), were employed to structure and analyze the adaptation. The results revealed that the previous operational model featured manual scheduling, decentralized communication, and dispersed controls, factors that limited expansion capacity. After the reorganization, an increase in operational capacity, improvement in delivery predictability, reduction in rescheduling, centralization of information, and greater operational control were observed, with relatively low investment compared to the revenue linked to the strategic contract. It was concluded that project management was fundamental in transforming contractual requirements into measurable operational improvements and in sustaining the business relationship with the economically highly relevant client.
Keywords: Performance; Scalability; Governance; Logistics; Predictability.
1. Introduction
The relationship with clients classified as Key Accounts (KA) is a consolidated practice in the corporate environment, especially in B2B markets. These clients are strategic because they concentrate a significant portion of revenue and impose high operational demands. Such demands include greater capacity, logistical predictability, and process standardization (Sandesh, Bhat, and Rao, 2023). Effective management of these partnerships is crucial for competitiveness, requiring supplier companies to continuously adapt their internal structures and routines.
For medium-sized companies, Key Account management presents challenges and opportunities. A single contract can represent a significant portion of revenue, increasing dependency risks and the need for an agile structure to respond to changes in volume, quality standards, and logistical requirements (Fakhreddin, Al-Kurdi, and Hussain, 2025). The integration between supplier and customer requires information sharing, flow synchronization, and alignment of operational goals. This implies reviewing routines, redesigning processes, and adjusting control systems in various areas, from production to administration and transportation (Aslam, Blome, and Chaudhry, 2023).
The challenges of serving a Key Account are accentuated by the complexity of processes and the need for constant performance. Pressure for deadlines, traceability, and standardization limits operational flexibility and increases exposure to failure risks (Lautenschlager, Mayer, and Albers, 2024). Managing high volumes, scheduling, delivery indicators, and communication with multiple client units requires methods that control interdependent activities. In many cases, medium-sized companies operate with manual scheduling, decentralized communication, and dispersed controls, which restricts scalability and predictability (Martins, Silva, and Costa, 2022; Wang, Li, and Zhao, 2022; Chen, Luo, and Singh, 2024).
In this scenario, project management emerges as an effective tool for organizing adaptations and controlling changes. According to the Project Management Institute (PMI, 2021), it allows for the planning, execution, and monitoring of complex initiatives, articulating resources and deadlines to achieve defined objectives. This approach converts contractual requirements into structured plans, with defined schedules, scopes, and responsibilities, making adjustments measurable. Kerzner (2022) adds that systematic management favors integration between functional areas, eliminating redundancies and improving internal communication, which is vital for reducing rework and optimizing information flow.
The application of formal planning and control practices, providing a governance model that combines predictability with operational flexibility (Maximiano, 2021), is fundamental for companies that need to respond quickly to sudden increases in demand. Given the operational gap frequently observed in medium-sized companies when dealing with the demands of strategic clients, this study is justified by the need to understand how project management can transform these pressures into measurable operational improvements. Thus, the present work aimed to analyze how project management contributed to the adaptation of internal processes of a medium-sized company in the logistics sector, in the face of operational and contractual requirements imposed by a Key Account, examining the practices adopted, the instruments used, and the results obtained in this process of business reorganization.
2. Material and Methods
The present study adopted a qualitative and descriptive approach, seeking to deepen the understanding of the contribution of project management to the adaptation of internal processes. The descriptive nature allowed for the characterization of the phenomenon in its specific context (Gil, 2019), while the qualitative approach was used to interpret meanings and organizational processes, as recommended for studies that analyze practices and behaviors in real environments (Creswell and Poth, 2018).
The research strategy was configured as a single case study, enabling the detailed investigation of a specific organizational event (Yin, 2018). The unit of analysis consisted of the organizational adaptation process necessary to meet the demands of a Key Account (KA) in a medium-sized company in the logistics sector, which began to represent a relevant share of revenue.
The study was conducted in a medium-sized company in the logistics sector, located in Brazil, which operates with deliveries in various regions of the country. The organization initiated a process of internal reorganization, with a review of operational flows and the implementation of new control mechanisms, to meet the operational and contractual requirements of a strategic client, characterizing the empirical context analyzed.
Data collection employed documentary analysis, unstructured interview, and participant observation. A company manager, directly involved in logistics management and relationship with the KA, was the interview participant. The researcher’s position as an organization collaborator facilitated direct access to operational routines, internal records, and interactions between the areas involved in the adaptation process.
Internal documents, logistical control spreadsheets, operational reports, and delivery tracking records were analyzed. This documentary analysis aimed to identify evidence of modifications made to internal processes after the contract formalization, constituting an appropriate technique in case studies to access records that reflect the actions effectively carried out by the organization (Yin, 2018).
The study followed a set of structured steps to ensure coherence between the proposed objective and the methodological procedures. Firstly, a diagnosis of the initial situation was carried out, which included mapping the existing operational flow and identifying areas for improvement. Subsequently, the adaptation project was structured, defining scope, schedule, responsibilities, and risks.
The third stage consisted of implementing the planned operational changes. Subsequently, the operational and financial results arising from the adaptations were measured. Finally, a replicable model, derived from the study’s findings, was consolidated, systematizing the practices adopted for organizational adaptation.
For the structuring and monitoring of the adaptation project, several project management tools were employed. The Work Breakdown Structure (WBS) was used to decompose the total project scope into smaller, manageable deliverables, organizing the work and facilitating execution monitoring (PMI, 2021).
The 5W2H action plan was applied as a management tool to detail the actions through the dimensions “what”, “why”, “who”, “when”, “where”, “how”, and “how much”, aiding operational planning and the implementation of changes (Daychoum, 2018).
The mapping of processes, in AS IS and TO BE formats, allowed representing the existing flow before adaptation, identifying bottlenecks and procedural redundancies, and demonstrated the desired future configuration after the proposed improvements (ABPMP, 2019).
A synthetic schedule was developed to temporally distribute the relevant project phases and milestones, serving for deadline control and activity sequencing (Kerzner, 2022). The RACI matrix was employed to define responsibilities among those involved, distinguishing direct responsible parties, approvers, consulted parties, and informed parties, with the aim of reducing decision-making ambiguities (Heldman, 2021).
The risk matrix made it possible to identify potential events capable of affecting schedule, operation, or quality, as well as to plan preventive and contingency responses (PMI, 2021). Finally, an indicator panel brought together operational and financial metrics used in monitoring results, supporting corrective decisions throughout the adaptation process (Maximiano, 2021).
The data analysis involved the measurement of operational and financial indicators. Logistic performance indicators, such as the on-time in-full (OTIF) delivery rate, rescheduling percentage, weekly scheduling time, vehicle release occurrences, and weekly processed order capacity, in addition to productivity metrics, were used.
A comparative analysis was performed between the scenario before and after the implementation of the changes. Performance multipliers were obtained by the ratio between the final and initial value of each indicator, and percentage variations were calculated to assess the evolution, especially in cases of reduction that represented operational improvement.
In the financial aspect, the revenue linked to the Key Account was estimated by multiplying the total annual revenue by the client’s estimated contractual share. The benefit/cost ratio of the adaptation was calculated by dividing the estimated protected revenue by the incremental cost of the adaptation.
The descriptive analysis organized the operational indicators in comparative formats, and percentage calculations and simple ratios were employed to measure performance evolution and estimated financial impact. Additionally, content analysis was applied to examine and interpret the information obtained from documents and the interview with the manager, organizing the data into categories and identifying patterns (Bardin, 2016).
The validity and reliability of the research were ensured by triangulating data sources, which included documents, interviews, and operational indicators, allowing for the confirmation of the consistency of the interpretations made (Creswell and Poth, 2018). Ethical considerations encompassed the preservation of institutional confidentiality and the anonymization of the analyzed information.
No company names, clients, or collaborators were mentioned, and the data were used exclusively for academic purposes. The research was conducted following the principles of scientific integrity, as per the guidelines of the American Psychological Association (2020), ensuring the responsible and contextualized use of the collected information.
3. Results and Discussion
The diagnosis of the initial situation revealed that the company’s operational processes were not aligned with the requirements of a Key Account (KA), a client with significant participation in revenue and high demands. In logistics operations, the integration of strategic clients increases the need for rigor in deadlines, reliability, and traceability, demanding structures compatible with greater operational complexity, as pointed out by Aslam, Blome, and Chaudhry (2023). The initial analysis therefore sought to understand the limitations of the existing flow to sustain this new commercial relationship.
The logistical process prior to the adaptation was predominantly manual and decentralized. The receipt of the purchase order led to the individual insertion of orders by the account manager, followed by direct contact with each receiving unit to define delivery dates. The route was adjusted according to availability, and driver and vehicle data were sent through informal channels for release. This flow depended heavily on informal coordination and successive human interactions for each delivery, which generated inefficiencies and operational risks.
Logistics operations based on recurring negotiations and decentralized communication tend to reduce predictability and increase performance variability, as observed by Martins, Silva, and Costa (2022). In the studied case, operational decisions depended on ad-hoc contacts and the experience of those involved, making the company vulnerable to absences, volume increases, or urgent demands. Decision-making concentration in the account manager, who combined commercial and operational functions, also generated capacity bottlenecks, as argued by Wang, Li, and Zhao (2022), restricting scalability and the replication of routines.
The company operated with mechanisms compatible with a smaller-scale context, simultaneously serving between five and seven accounts. Delivery scheduling was manual, communication occurred via email and WhatsApp, and there was no single logistical control base. The absence of formal delivery time prediction and the frequency of rescheduling were significant problems. In environments requiring logistical synchronization, the lack of centralized data hinders decision-making and timely response, as highlighted by Chen, Luo, and Singh (2024).
The absence of formal delivery time forecasting and the high frequency of rescheduling indicated relevant indirect costs, such as additional coordination hours, inefficient fleet utilization, and relationship wear. These predictability failures affected internal efficiency and the final customer’s perception of reliability. The previous process also had limitations in absorbing increased demand without structural changes, which was critical given the potential higher order volume and the regularity and visibility requirements imposed by the KA.
In summary, the initial diagnosis, based on documentary analysis, participant observation, and an interview with the manager, showed that the existing operational model was functional for reduced volumes but inadequate for the service standard required by a strategic client. KA’s entry not only increased the order volume but also raised the need for control, integration, and predictability. These findings justified the adoption of project management practices to reorganize internal processes.
Project Adaptation Structure
Faced with the diagnosis, the company structured an operational adaptation project to reorganize internal processes, expand service capacity, and increase logistical predictability. This project functioned as a temporary transformation mechanism, with defined deliverables, identified responsibilities, and a delimited implementation horizon. According to Kerzner (2022), projects of this nature convert strategic needs into coordinated actions, essential when the organization needs to respond quickly to external pressures.
The Work Breakdown Structure (WBS) developed to guide the operational adaptation segmented the change effort into five main blocks: initial diagnosis, change planning, implementation, control, and final evaluation. The decomposition of the project into work packages facilitates management, transforming broad objectives into monitorable and executable components, according to the Project Management Institute (PMI, 2021). This approach ensured that the project was based on concrete evidence, aligned with the principle of starting with a clear definition of the problem, as suggested by Maximiano (2021).
The first WBS block consolidated information on the current flow, operational bottlenecks, and intervention priorities, while the second block contemplated the change planning, including the definition of the new logistic flow, implementation schedule, and assignment of responsibilities. This phase translated identified needs into programmed actions, and in logistic environments, prior planning reduces improvisation and improves coordination between areas with reciprocal dependencies, according to Chen, Luo, and Singh (2024).
The third block concentrated the implementation of changes, with the creation of a centralized spreadsheet, weekly scheduling, fleet control, and operational adjustments. The presence of these elements in the WBS (Work Breakdown Structure) indicated the search for formalizing previously dispersed routines. Wang, Li, and Zhao (2022) argue that well-structured operational projects generate value by institutionalizing repetitive processes that previously depended on informal effort. The fourth block focused on project control, with operational indicators, delivery monitoring, and course corrections, evidencing continuous monitoring, essential for verifying the adherence between planning and execution (PMI, 2021).
Finally, the fifth WBS block brought together the final evaluation, comparing the previous and subsequent situations, analyzing the financial impact, and consolidating the new model. This stage demonstrated managerial concern with measuring results, an aspect often neglected in medium-sized companies. Kerzner (2022) emphasizes that the structured closure of projects strengthens organizational learning and supports future decisions, contributing to business sustainability.
The project’s synthetic schedule, distributed over six weeks, showed a partial overlap between stages, especially between diagnosis, planning, and initial implementation. This arrangement suggests the adoption of an incremental logic, where part of the deliverables was initiated before the full completion of previous phases, a common practice in environments demanding rapid response. The company prioritized implementation agility without abandoning a minimum logical sequencing, balancing commercial urgency with managerial discipline.
The RACI matrix used in the project defined roles among the commercial, logistics, operation, manager, and technical support areas. This instrument was crucial for reducing decision-making ambiguities, a frequent problem in internal changes under pressure. Clarity on executive responsibility and decision-making authority tends to reduce conflicts and delays, according to Kerzner (2022). The logistics area had a leading role as directly responsible for a large part of the deliveries, while the manager approved the main stages, ensuring strategic alignment and resource release.
The project risk matrix included resistance to change, weekly programming failures, initial team overload, and sudden growth in KA demand. The prior identification of risks in operational transformation projects expands response capacity and reduces vulnerability during implementation, with risk management being a central part of project governance, according to PMI (2021). It was observed that most risks were linked to human and organizational factors, indicating that the project’s complexity lay in internal coordination.
In narrative terms, the set of materials presented demonstrates that project management acted as a transition mechanism between a limited operational process and a model compatible with KA’s requirements. The WBS (Work Breakdown Structure) structured the scope, the schedule organized the time, the RACI matrix distributed responsibilities, and the risk matrix reduced improvisation. Thus, the project functioned as a bridge between commercial pressure and operational capacity, evidencing that the company responded to the new client with a deliberate reorganization of processes, roles, and controls.
Deployment of Changes
After the formal structuring of the adaptation project, the implementation phase of operational changes began to enable the Key Account’s service. This stage represented the conversion of planning into concrete practices, requiring coordination between areas, discipline in execution, and adaptability. According to the Project Management Institute (PMI, 2021), the implementation phase focuses on the materialization of the defined scope and demands continuous monitoring to ensure adherence between the planned and the executed.
In the analyzed case, the implementation focused on replacing manual and decentralized routines with a structured flow, offering greater predictability and logistical control. The objective was not merely to increase operational volume, but to build a system capable of sustaining service standards compatible with a strategic client. Kerzner (2022) emphasizes that successful operational changes combine process simplification, clarity of responsibilities, and monitoring mechanisms, elements that were central to the company’s approach.
One of the main elements implemented was the centralized logistic control spreadsheet, which brought together in a single database information about orders, dates, times, vehicles, and drivers. This data centralization reduced the informational dispersion of the previous model and increased managerial visibility over the operation. In logistics environments, consolidated databases favor faster decisions and greater responsiveness, according to Chen, Luo, and Singh (2024), contributing to the company’s efficiency and agility.
Another significant advance was the adoption of weekly delivery scheduling. Instead of reacting daily to requests, the company began to organize service in advance, distributing loads and schedules in a coordinated manner. This practice tends to reduce capacity conflicts, improve resource utilization, and increase predictability for both the customer and internal operations. The 5W2H action plan detailed the actions, transforming generic intentions into objective and trackable activities, with low relative investment.
Most of the implemented changes were associated with process reorganization and the use of simple management tools, rather than high investments in technology. This finding demonstrates that medium-sized companies can increase operational capacity through standardization, managerial discipline, and redesign of routines. The implementation directly addressed the problems identified in the diagnosis, replacing dispersed control with centralization, reactive programming with weekly planning, and informal communication with a defined standard, according to Martins, Silva, and Costa (2022).
The creation of new operational shifts and internal control codes signaled the expansion of productive and logistical capacity, and the internal codes favored traceability and administrative organization. These measures indicated that the company understood that serving the KA required not only a new delivery schedule but also the expansion of the supporting managerial infrastructure. The implementation also demanded operational adjustments throughout its execution, with feedback between execution and control, which is expected in real projects and increases the adherence of the final model to the context’s needs (PMI, 2021).
The new operational flow, consolidated after implementation, began with the weekly receipt of purchase orders, followed by order consolidation, delivery scheduling, and registration in a centralized spreadsheet. Subsequently, date, time, and vehicle were defined, with standardized information sent to receiving units, scheduled fleet release, monitored delivery, and subsequent update of controls. Compared to the previous model, a reduction in operational fragmentation and greater flow linearity was observed.
The formalization of routines in operational projects tends to reduce performance variability and increase replication capacity, as pointed out by Wang, Li, and Zhao (2022). In the studied case, the TO BE flow showed that project management produced a concrete change in the way of operating, converting controls and plans into executable routines. The implementation phase demonstrated that project management tools were converted into effective routines, redefining how orders were received, scheduled, communicated, and tracked, preparing the company to serve the key client.
Operational and Financial Results
After the implementation of the changes was completed, it was assessed whether the reorganization generated concrete effects on the operational performance and economic sustainability of the contract with the Key Account. The analysis focused on five dimensions: capacity increase, logistical predictability, rework reduction, financial impact, and revenue protection. The measurement of results is an essential stage of the project cycle, as it allows verification of whether the transformation delivered business value, according to Kerzner (2022).
There was a relevant growth in operational capacity, with the weekly order volume evolving from a range between five and seven to an interval between twenty and thirty orders. This suggests an expressive expansion of service capacity without structural disruption of the business, demonstrating that previous limitations were associated with process design, and not just with the physical availability of resources. The company managed to quadruple its weekly order processing capacity.
Another relevant result was the gain in predictability. The replacement of manual scheduling with a weekly agenda and the formalization of delivery times indicated a greater planning capacity for the company and the client. Chen, Luo, and Singh (2024) argue that logistical predictability reduces operational conflicts, improves asset utilization, and increases the reliability perceived by the contractor. The centralization of logistical control also represented managerial maturation, with orders, dates, vehicles, and schedules forming a single tracking base.
Operating systems with greater visibility tend to respond better to demand variations and unplanned occurrences, as highlighted by Wang, Li, and Zhao (2022). The reduction in rescheduling from 18% to 6% and in successive adjustments suggests a decrease in administrative and operational rework. Although part of this cost does not appear directly in financial statements, it manifests in additional coordination hours, inefficient fleet use, and extra effort from teams, whose productivity gains stem from the elimination of invisible waste.
Operational performance indicators reinforced that the improvement was not limited to volume increase, but included simultaneous progress in deadline, administrative time, and process stability. On-time deliveries increased from 72% to 93%, and release occurrences dropped from eleven to three per month. Weekly scheduling time was reduced from fourteen to five hours. This data indicates better integration between internal scheduling and the requirements of receiving units, a critical aspect for large clients.
From a financial perspective, the company’s annual revenue was R$ 16,000,000, with KA’s estimated participation of 35%, totaling R$ 5,600,000 in revenue linked to the strategic client. The incremental cost of adaptation was estimated at R$ 180,000. The calculated benefit/cost ratio was 31.1x, indicating an economic rationality of the decision made. Maximiano (2021) highlights that organizational projects generate value by preserving critical revenues, reducing operational losses, and expanding competitive capacity.
The protection of revenue linked to KA constituted one of the most relevant results, as the adaptation functioned as a commercial support mechanism. Without the reorganization of internal processes, the company could face difficulties in meeting contractual requirements, compromising the permanence and expansion of the relationship. In strategic terms, the results demonstrate that medium-sized companies can use formal project management practices to compete for more demanding contracts, transforming external pressure into internal improvement and expanding process maturity.
Replicable Model of Operational Adaptation for KA
Based on the observed results, it was possible to consolidate a replicable model of operational adaptation for companies that serve clients classified as KA. The model was built based on the empirical evidence identified in the initial diagnosis, the structuring of the project, the implementation of changes, and the verified operational and financial gains. This proposal is not just a theoretical formulation, but the systematization of practices that have demonstrated adherence in a real organizational context.
The creation of replicable models is a relevant contribution in applied studies, as it allows specific learnings to be transformed into useful references for other organizations. According to Yin (2018), case studies can generate analytical generalizations when findings are converted into conceptual frameworks adaptable to similar contexts. The proposed flow aims to guide medium-sized companies facing sudden growth in operational demand due to the entry of strategic clients, offering a pragmatic roadmap to convert commercial opportunities into sustainable growth.
The model begins with the initial evaluation of the KA contract, where the organization must understand the impact of the new client on its internal structure, considering the expected volume of orders, delivery frequency, contracted service levels, documentary requirements, penalties, and revenue representativeness. This stage is crucial because many projects fail when the company accepts demands beyond its capacity without previously measuring the organizational effects, which can lead to disorganization and losses.
The second stage corresponds to the diagnosis of the current process, recommending mapping the current flow, identifying bottlenecks, excessive dependence on key people, capacity limitations, and control weaknesses. According to the Project Management Institute (PMI, 2021), consistent decisions depend on a clear understanding of the starting situation. In the analyzed case, the diagnosis highlighted the incompatibility between the previous model and the standard required by KA, justifying the need for intervention.
In the third stage, a gap analysis occurs between contractual requirements and internal capacity. The objective is to compare what the client demands with what the company can deliver in terms of deadline, volume, traceability, governance, and operational reliability. This comparison allows for the prioritization of critical changes and the avoidance of dispersed investments, directing efforts towards the points of greatest impact and need.
The fourth stage refers to the formal structuring of the adaptation project, converting the operational problem into a manageable project, with definition of scope, schedule, deliverables, responsible parties, risks, and budget. Kerzner (2022) argues that project formalization reduces improvisation and increases the probability of disciplined execution. In the study conducted, this stage allowed for the coordination of different areas around a common objective, ensuring that all efforts were aligned.
The fifth stage comprises operational redesign. Based on the identified gaps, the organization develops the future flow (TO BE), defines new routines, and selects adequate control instruments. Among the recurring solutions observed in the case study, the following stand out: weekly programming, fixed delivery schedule, centralized spreadsheet, communication standardization, documentary checklist, and redefinition of operational shifts, which were fundamental for the transition.
The sixth stage corresponds to the pilot implementation. Instead of immediately expanding the new model to the entire operation, it is recommended to test the process in a controlled environment, such as a specific route, unit, or period. This practice reduces disruption risks and allows for adjustments before consolidation on a larger scale. According to PMI (2021), progressive validations tend to increase the project’s adherence to the real context, ensuring that the final model is robust and effective.
The seventh stage involves control by indicators. After the initial implementation, it becomes necessary to track metrics such as on-time deliveries, rework, programming time, documentation failures, cost per order, and customer satisfaction. Continuous measurement allows verification of whether the new process is delivering value and supports corrective decisions when necessary, ensuring continuous improvement and adaptation to new demands.
The eighth stage refers to consolidation and expansion. Once improvements are validated, the process must be formalized as an internal standard, accompanied by team training, automation of controls, and eventual replication for other relevant clients. This movement transforms a punctual response to a KA into a structural gain in organizational capacity, elevating the company’s maturity.
The model’s synthesis demonstrates that the flow is not linear only in the operational sense, but also in the managerial sense. Each step feeds back into the next: diagnosis improves the project, the project improves implementation, implementation generates indicators, and the indicators enhance future expansion. In this way, the model combines initial adaptation with a logic of continuous improvement, ensuring that the company is always evolving in its service capacity.
Another relevant aspect consists of the integrated use of classic project management tools, such as opening statement, AS IS mapping, GAP matrix, WBS (Work Breakdown Structure), schedule, RACI matrix, risk matrix, TO BE flow, and operational indicators. The analyzed case suggests that such instruments do not need to be complex to generate significant results, as long as they are applied with coherence and discipline. This pragmatic approach is fundamental for medium-sized companies seeking to optimize their operations.
From a strategic perspective, the model indicates that serving a Key Account (KA) does not depend solely on commercial effort. The permanence and expansion of the relationship require operational capacity compatible with the level of contractual demand. Thus, commercial management and project management cease to be separate dimensions and begin to operate in an integrated manner. For medium-sized companies, this conclusion is relevant, as many organizations of this profile have the flexibility to grow, but do not always have mature processes to absorb larger clients.
The replicable model offers a pragmatic roadmap for converting a business opportunity into sustainable growth, reducing risks of internal disorganization. From an academic standpoint, the model’s main contribution consists of demonstrating how results from an applied study can be transformed into a transferable managerial framework. Although each company has its own characteristics, the proposed steps offer an analytical reference for contexts in which new strategic clients increase operational complexity.
In summary, project management was fundamental to transforming Key Account contractual requirements into measurable operational improvements, resulting in increased service capacity, greater logistical predictability, rework reduction, and revenue protection. These findings confirm that the structured application of project management tools can elevate the operational maturity of medium-sized companies, enabling them to sustain highly demanding business relationships and ensure business scalability.
4. Conclusion
This study aimed to analyze how project management contributed to the adaptation of the internal processes of a medium-sized company in the logistics sector, in the face of operational and contractual demands imposed by a Key Account. It was found that the previous operational model, characterized by manual scheduling, decentralized communication, and dispersed controls, presented significant limitations in absorbing the volume and complexity demanded by a strategic client. The structured application of project management tools, such as the Project Breakdown Structure, schedule, RACI matrix, risk matrix, 5W2H action plan, and process mapping, allowed for internal reorganization. A significant increase in operational capacity was observed, with an increase in the weekly order volume, improved delivery predictability, a reduction in rescheduling from 18% to 6%, centralization of information, and greater operational control. Financial results indicated that the incremental cost of adaptation was low compared to the annual revenue linked to the strategic contract, resulting in a benefit/cost ratio of 31.1x. Project management was fundamental in transforming contractual requirements into measurable operational improvements and in sustaining the business relationship with the economically highly relevant client.
As a limitation, the study was developed from a single case in a specific company in the logistics sector, which restricts statistical generalizations to other organizational contexts. Part of the evidence also stemmed from internal records, interviews with managers, and participant observation, conditions that depend on the availability and quality of the accessed information. For future research, it is recommended to apply the replicable model of operational adaptation proposed in other economic sectors, compare multiple companies, and incorporate more extensive historical series of operational and financial indicators, with the aim of broadening the analytical robustness and transferability of the findings. The main academic contribution of this work lies in demonstrating how the results of an applied study can be transformed into a transferable managerial framework, offering a pragmatic roadmap for medium-sized companies seeking to convert commercial opportunities into sustainable growth.
Bibliographic References
American Psychological Association. 2020. Publication manual of the American Psychological Association. 7ed. American Psychological Association, Washington, DC, Estados Unidos.
Aslam, H.; Blome, C.; Chaudhry, S. 2023. Customer integration in the supply chain: the role of market orientation and supply chain strategy in the age of digital revolution. Supply Chain Management: An International Journal 28(3): 455–472.
Association of Business Process Management Professionals. 2019. Guide to the business process management common body of knowledge (BPM CBOK). 4ed. ABPMP, Chicago, IL, Estados Unidos.
Bardin, L. 2016. Análise de conteúdo. 1ed. Edições 70, Lisboa, Portugal.
Chen, Y.; Luo, H.; Singh, R. 2024. Logistics visibility and operational responsiveness in supply networks. International Journal of Logistics Management 35(2): 188–207.
Creswell, J. W.; Poth, C. N. 2018. Qualitative inquiry and research design: choosing among five approaches. 4ed. SAGE, Thousand Oaks, CA, Estados Unidos.
Daychoum, M. 2018. 40+ ferramentas e técnicas de gerenciamento. 6ed. Brasport, Rio de Janeiro, RJ, Brasil.
Fakhreddin, F.; Al-Kurdi, O.; Hussain, S. 2025. The influence of key account management on competitive and operational performance in manufacturing firms. Industrial Marketing Management 131: 77-92.
Gil, A. C. 2019. Métodos e técnicas de pesquisa social. 7ed. Atlas, São Paulo, SP, Brasil.
Heldman, K. 2021. PMP: project management professional exam study guide. 10ed. Sybex, Hoboken, NJ, Estados Unidos.
Kerzner, H. 2022. Gestão de projetos: as melhores práticas. 4ed. Bookman, Porto Alegre, RS, Brasil.
Lautenschlager, C.; Mayer, M.; Albers, S. 2024. Towards an integration of corporate foresight in key account management. Industrial Marketing Management 123: 220-233.
Martins, R.; Silva, T.; Costa, P. 2022. Coordination failures and planning constraints in logistics operations. Journal of Operations Management 68(4): 301–319.
Maximiano, A. C. A. 2021. Administração de projetos: como transformar ideias em resultados. 6ed. Atlas, São Paulo, SP, Brasil.
Project Management Institute. 2021. Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK). 7ed. Project Management Institute, Newtown Square, PA, Estados Unidos.
Sandesh, S. P.; Bhat, S.; Rao, S. 2023. Key account management in B2B marketing: a systematic review and research agenda. Journal of Business Research 156: 1–15.
Wang, J.; Li, X.; Zhao, M. 2022. Process formalization and scalability in growing firms. Management Decision 60(8): 2145-2162.
Yin, R. K. 2018. Case study research and applications: design and methods. 6ed. SAGE, Thousand Oaks, CA, Estados Unidos.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq
To learn more about the course, click here and access the MBX Academy platform