October 16, 2026
Project Management and Quality Tools in the Business and Sanitary Regulation of a Fish Warehouse
Project Management and Quality Tools in the Business and Sanitary Regulation of a Fish Warehouse
Odair de Jesus Lima; Fabiano José Stocco de Campos
DOI: 10.22167/2675-6528-202603328
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The business and sanitary regularization of fish warehouses, a sector marked by technical, environmental, and documentary requirements, demanded planning and control. The work aimed to structure an integrated management model, based on the RACI Matrix and the 5W2H action plan, to ensure the legal compliance and operational readiness of a processing unit in Governador Mangabeira, BA, after a financial feasibility analysis. The research was conducted as a single case study, of an applied nature and mixed approach, using tools such as PDCA, OKR, risk management, value-added indicators, and Discounted Cash Flow. Data collection and tool application occurred from November 2025 to April 2026. The results showed that, despite climatic unforeseen events and dependence on external bodies, the parallelism of activities enabled the integral protocol of technical documentation and the completion of physical adaptations within the planned timeframe, with a Schedule Performance Index equal to 1.0. The economic feasibility analysis indicated a positive Net Present Value of R$ 137,950.22, an Internal Rate of Return of 4.1% per month, higher than the Minimum Attractive Rate, and a Cost Performance Index of 1.0. It was concluded that the structured application of management tools reduced uncertainties, strengthened stakeholder coordination, and converted regulatory rigor into operational efficiency and competitive advantage.
Keywords: Discounted cash flow; RACI Matrix; 5W2H Plan; Sanitary regularization; Added value.
1. Introduction
The Brazilian agribusiness has consolidated itself as one of the main pillars of the national economy, driven by continuous productivity growth and the incorporation of technological innovations (EMBRAPA, 2022). In the context of fish farming, a significant expansion in the production and consumption of fish on a global scale is observed, driven by the growing demand for animal protein and the need for more sustainable production systems (FAO, 2022). In this scenario, value addition through processing and sanitary regularization becomes a strategic factor for the competitiveness of businesses (SEBRAE, 2023).
The economic feasibility of a distribution center is not limited solely to productive capacity, but also to the implementation of management capable of integrating the requirements of the Inspection Service – whether at the municipal, state, or federal level – with the efficiency of daily operations (EMBRAPA, 2022). The rural entrepreneur, when moving towards industrialization, faces a complex regulatory environment, characterized by rigorous sanitary standards and high technical demands, requiring managerial competencies that go beyond productive management.
A project, according to the Project Management Institute (PMI, 2017), is a temporary endeavor undertaken to create a unique result. This definition applies directly to the process of obtaining sanitary and environmental records. From this perspective, business and sanitary regularization must be understood as a complex project, marked by the interdependence between technical, legal, and operational variables. Such a characteristic demands a systemic approach focused on planning, control, and risk mitigation, in order to avoid waste of resources and non-compliance with legal deadlines (GIL, 2019).
The adoption of structured methodologies allows organizations to deal with constraints and multiple stakeholders more predictably, transforming project management into an instrument for converting uncertainties into manageable processes (Kerzner, 2017). In this context, financial feasibility analysis assumes a strategic role in evaluating investment attractiveness and supporting action planning. Tools such as the PDCA cycle and OKR (Objectives and Key Results) contribute to aligning objectives with measurable results, promoting focus and transparency in execution (Doerr, 2018).
Despite these contributions, studies indicate that small and medium-sized enterprises often exhibit fragilities stemming from information fragmentation and low integration among the involved agents (Maximiano, 2023; Kerzner, 2017). This disarticulation increases the risk of rework, documentary inconsistencies, and non-conformities, with inefficient communication being a critical factor in projects with greater regulatory complexity (PMI, 2017; Kerzner, 2017).
The professionalization of management is a determining factor for waste reduction and for meeting regulatory requirements (SEBRAE, 2023). In this context, the RACI Matrix stands out as a governance tool by allowing clear definition of responsibilities and organization of interactions among stakeholders (Vargas, 2018). Complementarily, the 5W2H action plan acts in the operationalization of activities, converting strategic guidelines into structured actions with definition of deadlines, responsible parties, and costs (Daychouw, 2018).
Beyond planning, the dynamic nature of regulatory processes demands control mechanisms that enable continuous project performance monitoring. The use of earned value-based metrics allows for early identification of deviations, enabling the adoption of corrective measures and continuous process improvement (Terribili Filho, 2021; PMI, 2017). This approach contributes to aligning the physical progress of adaptations with the financial conditions of the undertaking, strengthening decision-making.
In view of this scenario, project management literature points out challenges in the structured application of these tools in small-scale contexts (PMI, 2017; Kerzner, 2017), highlighting a gap in the area of sanitary and business regularization of fish warehouses. Thus, this work aims to analyze how the structured use of the RACI Matrix, the 5W2H action plan, quality tools, strategic management structures, and metrics based on the Earned Value Management (EVM) technique, associated with economic feasibility analysis, can contribute to the organization, efficiency, and predictability of the regularization process.
2. Material and Methods
The present work was characterized as a single case study, of an applied nature, with a mixed approach (qualitative and quantitative), according to Gil (2019). The research was classified as descriptive, seeking to detail the interactions between management variables and technical requirements of the Municipal Inspection Service (SIM), combining documentary compliance analysis with temporal and cost performance measurement. The object of study was the regularization process of a fish warehouse in Governador Mangabeira, BA. Data collection and the application of management tools occurred from November 2025 to April 2026, focusing on the execution and monitoring phases.
To systematize the project development, a methodological flow composed of six sequential stages was elaborated. The first stage, Diagnosis, involved mapping the current scenario, legal requirements, and existing documentation. Next, the Feasibility stage performed the financial analysis of the investment. The third stage, Governance, defined the stakeholders, roles, and responsibilities. The Execution stage comprised the planning and implementation of activities, using parallelism strategies. Subsequently, the Monitoring phase involved performance tracking and continuous improvement. Finally, the Regularization stage consisted of the protocol and submission of documentation to the Municipal Inspection Service (SIM).
The methodological foundation was based on the integration between bibliographic research and case study. The bibliographic survey used secondary data obtained from Google Scholar, SciELO, and the USP repository. Priority was given to studies published in recent years, without disregarding classic works considered fundamental to the area, such as those by Kerzner (2017), Project Management Institute (2021), Maximiano (2023), and Doerr (2018). Descriptors such as project management, PMBOK, 5W2H, RACI matrix, PDCA, OKR, fish market, and inspection service were used, allowing the identification of references related to both management tools and the specificities of the analyzed enterprise.
In the feasibility stage, the economic analysis of the undertaking was carried out using the Discounted Cash Flow (DCF) method. This method evaluated the investment’s attractiveness, considering an initial investment of R$ 344,460.00. The calculations were performed in electronic spreadsheets using Microsoft Excel software, employing Net Present Value (NPV) and Internal Rate of Return (IRR) formulas. The project’s governance was structured by the RACI Matrix, which defined the stakeholders’ responsibilities, identifying the roles of Responsible, Accountable, Consulted, and Informed (Vargas, 2018).
For operational planning, the 5W2H tool was used, which organized and unfolded the activities necessary for business and sanitary regularization. Its application allowed defining what would be done, why, where, when, who would be responsible, how, and how much it would cost, contributing to schedule control and resource allocation (Daychouw, 2018). Monitoring and continuous improvement were conducted through the PDCA cycle (plan, do, check, act), enabling performance tracking and adjustments.
Objectives and Key Results (OKR) were employed to monitor project performance, aligning strategic objectives with measurable indicators related to the fulfillment of documentary, structural, and sanitary stages (Doerr, 2018). Project performance measurement was carried out using the Earned Value Management (EVM) methodology, focusing on the Schedule Performance Index (SPI) and Cost Performance Index (CPI). EVM integrated scope, schedule, and cost into objective indicators, supporting decision-making (PMI, 2017). For interpretation, values equal to 1 indicated adherence to the plan, while values below or above 1 indicated performance below or above the forecast, respectively.
Additionally, the parallelism compression strategy was adopted, which consisted of the simultaneous execution of independent activities to reduce the project execution time (PMI, 2017). The planning was structured through decomposition into Work Packages (WP), according to the Project Breakdown Structure (WBS), and by establishing control milestones for monitoring deliveries (PMI, 2017; Kerzner, 2017). Risk management was conducted by applying the PDCA cycle, allowing continuous monitoring and adjustments in the face of risks such as the inertia of oversight bodies and intense rains. To ensure traceability, a communication plan structured at strategic and operational levels was established.
3. Results and Discussion
The structured management model, applied to the regularization process of the fish warehouse in Governador Mangabeira, Bahia, proved effective in organizing critical stages and controlling the execution of activities. The integration between planning, governance, and monitoring contributed significantly to the reduction of operational uncertainties, promoting better coordination between technical and institutional demands. This systemic approach allowed the project to advance more predictably, even in the face of challenges inherent to the regulatory environment and external conditions.
The systematization of activities proved crucial for the early identification of bottlenecks, especially those related to stages dependent on licensing bodies. This predictive capability enabled the implementation of mitigation strategies that minimized impacts on the project schedule. The parallel execution of activities, combined with continuous performance monitoring, was fundamental to maintaining project flow, ensuring continuity even in the face of external interferences and unforeseen events, as highlighted by the Project Management Institute (PMI, 2017).
The application of management tools also provided greater clarity in defining responsibilities, optimized the organization of deliverables, and offered robust support for decision-making throughout the entire project execution. As a result, considerably greater predictability in project progress was observed, contrasting with the uncertainty often associated with processes conducted without a formal management structure. The following results detail the economic feasibility analysis, project governance, and the performance of the adopted strategies.
Financial Feasibility Analysis
The economic feasibility of the project was evaluated using the Discounted Cash Flow (DCF) method, which integrates operational parameters and market projections to measure the investment’s attractiveness over time. This method is widely recognized and employed in the evaluation of agribusiness ventures, providing a solid basis for decision-making regarding project execution. The central premise of the study was the processing of tilapia, considering its regional availability and market relevance.
The initial investment was estimated at R$ 344,460.00, based on preliminary budgets for works, equipment, and regularization. This amount was subsequently detailed and validated through the development of the 5W2H action plan, which provided greater precision and traceability to costs per activity. The calculations were performed in spreadsheets for a 24-month analysis horizon, using the classic formulas for Net Present Value (NPV) and Internal Rate of Return (IRR), with monthly cash flow projections.
The main parameters adopted included an operational quantity of 30,000 kg/month of tilapia, raw material cost of R$ 12.00/kg, and a selling price of R$ 16.00/kg, resulting in a gross margin of R$ 4.00/kg. Monthly fixed costs were R$ 40,000.00, and the ICMS rate of 12% was applied according to the state legislation of Bahia. The Minimum Attractive Rate of Return (MARR) was defined at 0.8% per month, equivalent to 10% per year, to remunerate the invested capital.
The financial results were consistent, with a Net Present Value (NPV) of R$ 137,950.22, indicating that the project generates wealth above the invested capital, confirming its economic feasibility. The Internal Rate of Return (IRR) of 4.1% per month demonstrated a profitability significantly higher than the Minimum Attractiveness Rate, evidencing the investment’s attractiveness. The projected monthly net profit was R$ 22,400.00, representing free cash flow generation after all costs and taxes.
The return on investment (payback) was estimated at 15.4 months, considered adequate for agro-industrial ventures, as it indicates capital recovery within a compatible timeframe. Additionally, the operational break-even point, below 20 tons per month, provides greater robustness to the project, reducing its exposure to market fluctuations. Thus, the financial analysis confirmed that the regularization of the warehouse is not just a regulatory requirement, but a strategic decision capable of generating consistent economic return and value for the venture.
RACI Matrix and Operational Planning (5W2H)
The RACI Matrix was fundamental to structuring the governance of the fish market regularization project, allowing for the objective definition of each stakeholder’s responsibilities. This tool reduced the overlap of functions and minimized conflicts during the execution of activities, as recommended by the PMBOK (PMI, 2021), which highlights the importance of role clarity for team efficiency and project control. The matrix detailed who was Responsible (R), Accountable (A), Consulted (C), and Informed (I) for each item on the regularization checklist.
For example, for the acquisition of construction materials and equipment, the Owner was the Responsible party and Approver, while the Accountant and the Engineering Team were Consulted. For legal qualification, the Accountant was the Responsible party and the Owner the Approver. For the Preliminary Inspection and project feasibility and authorization, SIM (Organ) was the Approver, and the Technical Manager and the Owner were Consulted. This clarity was essential for coordinating the technical, administrative, and regulatory activities, involving the owner, the accountant, the technical manager, and the engineering team.
Complementarily, the 5W2H tool was used to organize and unfold the activities necessary for business and sanitary regularization. The 5W2H, which defines “What”, “Why”, “Where”, “When”, “Who”, “How”, and “How Much”, allowed for the systematic detailing of actions, responsible parties, deadlines, resources, and costs involved. Its application enabled more effective schedule control, optimized resource allocation, and precise monitoring of expected results, converting strategic guidelines into structured and measurable actions (Daychouw, 2018).
Risk Management and Application of the PDCA Cycle
Risk management was conducted through the continuous application of the PDCA cycle (Plan, Do, Check, and Act), which allowed for the monitoring of activities and the implementation of adjustments throughout the execution. During the project, relevant risks that could impact the schedule were identified, such as institutional limitations, scarcity of specialized labor, and climatic variables. These factors required the adoption of mitigation and replanning strategies to keep the project on track.
The risk matrix identified “Inertia of oversight bodies (YES)” as a regulatory risk, with an impact of delayed approval, whose response was to mitigate through process monitoring with requests for speed. “Intense rains” were classified as an environmental risk, causing interruption of activities, and the response was to accept the risk and replan the schedule. “Labor shortage” was a technical risk, resulting in delays, mitigated by planning and encompassing the necessary activities.
The “Technical Misalignment” represented a procedural risk, with a sanitary non-compliance impact, mitigated by technical standardization and rigorous execution control. “Information Fragmentation” was an organizational risk, causing communication failures, mitigated by the use of the RACI Matrix. The application of PDCA was crucial for continuous monitoring, allowing for the identification of deviations, correction of failures, and improvement of the regularization process, especially in responding to adversities such as climatic events and administrative delays, reinforcing the importance of adaptive management oriented by continuous improvement (Campos, 2014).
Management of Communication Channels and their Impact on Performance
The structuring of a communication plan segmented into strategic and operational levels was essential to ensure the continuous flow of information among stakeholders throughout the project execution. Efficient Communications Management is fundamental for the correct information to be made available to the right people, at the right time, and through the most appropriate channel, reducing failures and promoting greater integration (PMI, 2021). In the study, this definition contributed to minimizing rework and expediting compliance with regulatory requirements.
At the strategic level, formal emails and status reports were used for legal records, accountability, and formalization of protocols with SIM/Consortium, ensuring traceability and legal security of the process. At the operational level, instant messages (WhatsApp) and monthly meetings were employed for quick decision-making, clarification of technical doubts, and alignment with teams from other cities, resulting in reduced waiting time and agile mobilization of specialists and machinery.
The combination of formal communication and agile tools allowed for faster decision-making, contributing to the reduction of delays and the efficient mobilization of resources, especially in contexts of operational constraints. This approach favored the fulfillment of deadlines and objectives established for the regularization of the undertaking. The use of different channels, associated with the definition of responsibilities and the organization of information, provided greater traceability of demands and facilitated the monitoring of activities, improving coordination between the owner, technical professionals, the accountant, and others involved.
Compression Strategies: Parallelism
The parallelism compression strategy, which consists of the concurrent execution of originally sequential activities, was crucial to reduce the project duration, optimizing resource utilization and minimizing waiting time between stages. Although this technique requires greater coordination and risk management (PMI, 2021), its application allowed for the anticipation of regularization process phases, such as the elaboration of Self-Control Programs (PACs), descriptive reports, and technical training in the sanitary documentation front.
In engineering, executive projects, reports, and dimensioning were developed in parallel, allowing immediate commencement of the work after approval. In management and contracts, budgets and contacts with specialized third parties were carried out simultaneously, ensuring the mobilization of teams and inputs in record time. This approach transformed the potential institutional bottleneck into a window of technical and collaborative productivity, eliminating passive response time and significantly reducing the project’s *Lead Time*.
The practical effect of parallelism was the creation of a margin of maneuver: by the time initial approvals were issued, much of the requested documentation was already ready. This anticipation, supported by the joint and simultaneous effort of the partners, allowed the unit to achieve full documentary compliance in advance, strategically positioning the agribusiness for the final inspection. Parallelism, combined with the synchrony of stakeholders, proved to be a robust tool for managing uncertainties, ensuring that operational readiness was not held hostage by external bureaucratic delays.
The application of parallel execution required continuous monitoring due to the inherent risk of technical rework. To manage this uncertainty, an operational validation criterion was established: technical projects only advanced to the detailing and execution phases after joint validation by the Technical Manager, the owner, and the engineering team. This approach ensured that the risk of documentary incompatibility was kept under control, even with the simultaneous advancement of work fronts, guaranteeing the integrity and quality of the deliverables.
Project Performance Analysis (EVM)
Project performance measurement was carried out using the Earned Value Management (EVM) methodology, focusing on schedule performance index (SPI) and cost performance index (CPI). EVM is an essential project monitoring and control tool, as it integrates scope, schedule, and cost into objective indicators, supporting decision-making during execution (PMI, 2021). The use of EVM allowed for an integrated assessment of the project’s physical progress in relation to the plan, overcoming analyses based solely on the schedule.
The distribution of planned value (PV) and earned value (EV) percentages was defined based on the relative relevance of the project stages, considering their contribution to the completion of the scope and the weight of critical deliverables. For schedule analysis, the Schedule Performance Index (SPI) was calculated by the ratio between earned value and planned value, weighted by Work Packages (WP), which allowed for a more precise evaluation of real progress, considering technical complexity, execution effort, and impact on project progress.
The project maintained adherence to the plan in the initial months, with a schedule performance index (SPI) equal to 1.0 in December and January. However, in February, a reduction in the index to 0.84 was observed, reflecting the impact of external factors, especially rainfall in the Recôncavo Baiano. These rains temporarily made critical activities such as earthmoving and the construction of the stabilization pond unfeasible, highlighting the schedule’s sensitivity to environmental variables and the need for flexibility in planning.
Performance recovery was observed in March, with the schedule performance index (SPI) returning to 1.0, demonstrating the effectiveness of the corrective strategies adopted. The parallel execution of activities (fast-tracking) was decisive, allowing the anticipation of documentary fronts and regularization processes originally planned for later stages. This redistribution of efforts enabled documentary progress to offset physical delays, keeping the project aligned with the established baseline and ensuring compliance with the final deadline.
Regarding cost performance, the analysis was conducted through the Cost Performance Index (CPI), also based on the EVM methodology. Financial control was structured by Work Packages, with a percentage distribution of the total budget of R$ 344,460.00. Projects and technical consulting represented 6.53% (R$ 22,490.00), civil works and structural adjustments 33.97% (R$ 117,000.00), fixed assets 53.88% (R$ 185,600.00), and fees and document regularization 5.62% (R$ 19,370.00).
The measurement of the actual cost (AC) was performed based on milestone delivery validation, confirming the execution of the stages within the values previously budgeted and validated by the owner. No significant variations were identified that would require additional contributions or the use of contingency reserves. Thus, the Earned Value (EV) reached 100% at the end of the period, and the actual cost remained aligned with the plan, resulting in a consolidated Cost Performance Index (CPI) of 1.0.
This result indicated a high level of precision in financial execution and confirmed the effectiveness of the adopted management model, especially in scope control and the prevention of budgetary deviations. Although the final indices point to an ideal performance, intermediate adjustments were necessary, requiring the prioritization of critical activities. The definition of delivery milestones and the intensification of monitoring and results-based accountability were effective in promoting greater coordination among those involved and ensuring compliance with established deadlines.
OKR (objectives and key results)
To ensure strategic alignment among stakeholders and maintain focus on the project outcome, the OKR (Objectives and Key Results) framework was adopted. According to Doerr (2018), OKRs are a management tool based on defining strategic objectives accompanied by measurable key results. The use of OKRs allowed that, although each workstream maintained autonomy in its management, all converged towards measurable success outcomes and the main project objective.
The objective of “Ensuring Operational and Legal Readiness of the Industrial Unit” was broken down into several key results. “Elaboration of technical documents” and “Technical documentation protocol (Infrastructure/Environmental/SIM)” reached 100% of the target, being completed. “Execution of works and acquisition of materials” and “Acquisition of machinery and equipment / Internal compliance” also reached 100% of the target and were completed, as was “Legal and commercial qualification”.
The Schedule Performance Index (SPI) and the Cost Performance Index (CPI) were established with a target of ≥ 1.0, and both reached 1.0, thus being considered achieved. The “Delivery of documents for the release of the Municipal Inspection Seal – SIM” reached 50% of the target, being “In progress”. The results indicate that most of the objectives under the direct control of management were fully achieved, with emphasis on the completion of the technical, structural, and documentary stages, reinforcing the consistency of the adopted management model.
Value Delivery and Results Obtained
The results obtained confirm the effectiveness of the management model applied to the regularization of the fish market, culminating in the operational readiness of the unit and full compliance with the required technical and regulatory requirements. Structured management enabled the optimization of financial resources, avoiding rework and ensuring execution within the planned budget. Regarding the schedule, the parallelism strategy was decisive in maintaining the project’s cadence, converting waiting periods into productivity and ensuring deadlines were met.
The absence of structured internal control among the involved teams, such as engineering, environment, and accounting, constituted a potential risk to the project’s progress, especially regarding information integration and deadline compliance. In similar contexts, a lack of alignment among stakeholders can compromise the efficiency of activities and generate rework (Kerzner, 2017; PMI, 2021). However, in this study, this factor did not materialize as a significant problem, possibly due to the small scale of the undertaking and direct communication among those involved.
In larger organizations, the adoption of more robust integration and control mechanisms, including the use of monitoring and management software, becomes necessary to ensure greater coordination between teams and systematic monitoring of activities, as recommended in project management literature (PMI, 2021). Thus, it is evident that the integrated application of project management tools contributes to the organization, efficiency, and predictability of agro-industrial regularization processes, consolidating itself as a competitive differential for the sector.
Lessons Learned
In accordance with good project closure practices, relevant lessons were identified for replicating the management model in other agribusinesses. The definition of clear communication channels and the holding of periodic decision-focused meetings were fundamental for alignment among stakeholders, contributing to reduced response time and maintained engagement, even during phases of greater bureaucratic slowness. In this context, the clarity of responsibilities, provided by the RACI Matrix, proved decisive in avoiding ambiguities and ensuring fluidity in the execution of activities.
It was also found that the dependence on external bodies should be treated as a high-probability risk, requiring proactive management action. The adoption of parallel execution of activities (parallelism), by allowing the advancement of independent fronts without the need for sequential validations, was decisive for meeting deadlines. Furthermore, the replanning of civil works due to precipitation highlighted the need to incorporate contingency margins compatible with regional climatic factors, reducing resource idleness and optimizing capital use.
From a financial perspective, the accuracy of budgetary planning reinforced the importance of prior economic feasibility analysis to ensure the security of capital contribution. It was also observed that cost control can be maintained even in contexts of data restriction, through the use of proportional indicators, such as assigning weights to work packages for monitoring financial performance. This approach allowed for effective financial management, even in scenarios with limited information.
The integration between the RACI Matrix and the 5W2H action plan proved essential for maintaining project fluidity during the parallel execution of activities, allowing for greater predictability and reduction of internal waiting times. In summary, the adopted model contributed to transforming a scenario of fragmented information into a structured, traceable, and efficient workflow, and its application is recommended in other agribusinesses as a strategy to expand access to the formal market with safety and technical compliance, directly responding to the study’s objective of structuring an integrated management model.
4. Conclusion
The present investigation aimed to structure an integrated management model for the business and sanitary regularization of a fish warehouse, based on the RACI Matrix and the 5W2H action plan, after financial feasibility analysis, aiming for legal compliance and operational readiness. It was verified that the structured application of these project management tools, combined with methodologies such as PDCA, OKR, and EVM, proved effective in organizing critical stages and controlling activity execution. The integration between planning, governance, and monitoring contributed significantly to reducing operational uncertainties and to better coordination between technical and institutional demands. It was observed that the systematization of activities favored the early identification of bottlenecks, and the parallel execution strategy was fundamental to maintaining the project flow, even in the face of unforeseen climatic events and dependence on external bodies. The economic feasibility analysis, based on Discounted Cash Flow, indicated a positive Net Present Value of R$ 137,950.22 and an Internal Rate of Return of 4.1% per month, higher than the Minimum Attractive Rate, confirming the investment’s attractiveness. The project’s performance, measured by the Earned Value indices, remained aligned with the plan, with a Schedule Performance Index and Cost Performance Index consolidated at 1.0, evidencing efficiency in time and resource management.
The main contribution of this study lies in the proposition of a governance model that ensures technical compliance, operational predictability, and economic feasibility in agro-industrial regularization processes, transforming regulatory rigor into efficiency and competitive advantage. However, the scope of the research presented limitations, such as restricted access to primary financial data, which directed the Cost Performance Index analysis to validation by delivery milestones and global values. Furthermore, the physical issuance of the Municipal Inspection Seal (SIM) was not under the direct control of project management, depending exclusively on the competent public body. The regional and climatic scope of the Recôncavo Baiano also influences the results, suggesting that the effectiveness of recovery strategies may vary in other regions. As this is a single case study, generalization to large-scale industries or other protein segments should be done with caution. It is recommended to apply the management model in other agro-industries to expand access to the formal market with safety and technical compliance, adapting it to the particularities of each context to validate its robustness in different scenarios.
Bibliographic References
Campos, 2014 [Referência completa não encontrada no documento original]
DAYCHOUW, M. 2018. 5W2H: ferramenta de planejamento e gestão. São Paulo: Atlas.
DOERR, J. 2018. Measure what matters: how Google, Bono, and the Gates Foundation rock the world with OKRs. New York: Portfolio Penguin.
EMBRAPA. 2022. Anuário brasileiro da piscicultura: desafios e perspectivas. Brasília, DF: Embrapa Pesca e Aquicultura.
FOOD AND AGRICULTURE ORGANIZATION (FAO). 2022. The state of world fisheries and aquaculture 2022. Rome: FAO.
GIL, A. C. 2019. Como elaborar projetos de pesquisa. 6. ed. São Paulo: Atlas.
KERZNER, H. 2017. Project management: a systems approach to planning, scheduling, and controlling. 12. ed. Hoboken: Wiley.
PROJECT MANAGEMENT INSTITUTE (PMI). 2017. A guide to the project management body of knowledge (PMBOK Guide). 6. ed. Newtown Square: PMI.
PROJECT MANAGEMENT INSTITUTE (PMI). 2021. The standard for project management and a guide to the project management body of knowledge (PMBOK Guide). 7. ed. Newtown Square: PMI.
SEBRAE. 2023. Cadeia de valor do pescado: guia para o empreendedor. Brasília, DF: Sebrae.
TERRIBILI FILHO, A. 2021. Monitoramento e controle de projetos: indicadores de desempenho e gerenciamento de valor agregado. São Paulo: Edição do Autor.
VARGAS, R. 2018. Manual prático do plano de projeto: utilizando o PMBOK Guide. 6. ed. Rio de Janeiro: Brasport
ΜΑΧΙΜΙΑΝΟ, A. C. A. 2023. Administração de projetos: como transformar ideias em resultados. 6. ed. São Paulo: Atlas.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq
To learn more about the course, click here and access the MBX Academy platform