Project management applied to parametric cost estimation in civil construction works

Matheus Henrique Santos Assis; Felipe Miranda de Souza Almeida

DOI: 10.22167/2675-6528-202601215

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

Project management in civil construction demands rigorous control of costs, deadlines, and quality, making parametric estimation an essential tool for initial decisions and financial planning. Despite its theoretical recognition, gaps persist in the integrated practical application of this technique. The study aimed to analyze and systematize the application of parametric cost estimation from a project management perspective, considering its integration with budget planning, Work Breakdown Structure (WBS), physical-financial planning, and control mechanisms, aiming to understand its contribution to financial predictability in civil construction projects. A descriptive and qualitative action research was conducted, with data collection through documentary analysis and direct observation in two large-scale vertical residential developments, executed between 2021 and 2024 in the São Paulo region. The results showed that parametric estimation, when supported by a consistent historical base and integrated with the WBS, the schedule, and systematic control, contributed to greater cost traceability, better structuring of the physical-financial baseline, and reduction of deviations. The comparison between projects revealed that greater construction standardization resulted in lower budgetary dispersion and greater temporal stability. It was concluded that the integration between parametric estimation and formal project management practices constitutes a relevant instrument for increasing financial predictability and strengthening governance in civil construction projects.

Keywords: integrated planning; financial predictability; constructive rationalization.

1. Introduction

Project management has been consolidated as an essential element for the success of ventures in various sectors, with civil construction being one of the areas where its practices are most demanded. The application of structured management processes, which range from scope to cost control, contributes significantly to the delivery of results that meet the criteria of time, cost, and quality (Kerzner, 2022).

In this context, cost estimation stands out as a critical area, given its direct influence on the budget and the viability of ventures. Accuracy in cost forecasting guides initial decisions and supports adjustments during execution. It is estimated that inadequate budgetary projections can lead to significant deviations, generating financial burdens and contractual interruptions (Vargas, 2021).

Given this scenario, the adoption of robust techniques, such as parametric estimation, becomes fundamental to reduce uncertainties and improve financial planning. Parametric estimation is based on mathematical models that relate project characteristics with historical costs, allowing for quick and, when calibrated, relatively reliable projections. Heldman (2021) highlights that these techniques combine historical data and scale metrics to generate estimates that are more aligned with the project’s reality.

However, the practical application of this methodology in civil construction requires specific project management skills, including the identification of relevant parameters and the construction of reliable databases. The intrinsic variability of civil construction projects demands careful adaptations in parametric models so that they adequately reflect the profile of each project (Chitkara, 2014). Furthermore, the quality of historical data is a pillar for the effectiveness of the methods, as disorganized past information can generate distorted results (Juran and De Feo, 2019).

The integration of cost estimation with other knowledge areas, such as risk and schedule management, is strategically important. The Project Management Institute (PMI, 2021) emphasizes that estimation must be aligned with other project components to ensure consistency between dates, resources, and performance, mitigating conflicts and providing greater predictability. Industry organizations have sought to standardize data collection and storage processes, and knowledge management enhances organizational maturity, facilitating the use of historical metrics (Kerzner, 2022).

Despite academic recognition and best practices, gaps persist in how construction organizations integrate parametric estimation into project management. The literature demonstrates the need for studies that connect parametric estimation theory with the operational reality of construction sites (PMI, 2021; Heldman, 2021), especially regarding reliability and its direct impact on project cost performance. This practical and theoretical gap justifies the relevance of research seeking to bridge the gap between literature and the sector’s operational reality.

In this context, the present study is justified by the need to deepen the understanding of the application of parametric cost estimation in civil construction, aiming to improve financial predictability and project governance. The objective of this work is to analyze and systematize the application of parametric cost estimation, from the perspective of project management, considering its integration with budgetary planning, the Work Breakdown Structure (WBS), physical-financial planning, and control mechanisms, in order to understand its contribution to the financial predictability of civil construction projects.

2. Material and Methods

To achieve the proposed objective, an action-research of a descriptive and qualitative nature was carried out. Action-research involved the direct participation of the researcher to understand phenomena and contribute to the improvement of processes (Thiollent, 2011). The descriptive approach sought to observe and analyze facts without manipulation (Gil, 2019), while the qualitative approach allowed for an in-depth understanding of phenomena from the context, valuing the interpretation of the perceptions and interactions of the individuals involved (Flick, 2009).

The study focused on the application of parametric cost estimation in two high-end vertical residential developments, executed between 2021 and 2024, in the metropolitan region of São Paulo. The research was developed within a large-scale construction and development company. The developments, named Project A and Project B for institutional preservation purposes, were selected due to their market similarity, construction scale, and execution period, although they presented differences in technical guidelines and complexity.

Data collection was carried out through documentary analysis and direct observation. During the period of project development, the researcher acted as Commercial Manager, actively participating in the stages of planning, budgeting, and monitoring execution. This involvement provided an internal understanding of the decision-making and operational processes (Minayo, 2017).

Documentary analysis involved the examination of technical and managerial records, such as parametric cost estimates, budget spreadsheets, physical-financial schedules, performance reports, meeting minutes, and production control records. This strategy allowed access to primary and secondary sources of previously organized data (Lakatos and Marconi, 2017).

Direct observation was conducted participatively, based on the researcher’s insertion into the company’s practical activities, in strategic meetings, and in interactions with the engineering, budgeting, planning, and supply teams. This approach made it possible to capture the meanings attributed to organizational practices from concrete field experience.

The data analysis was structured sequentially, oriented towards the study’s objective, with a focus on understanding and systematizing the application of parametric cost estimation throughout the lifecycle of the projects. The lifecycle recommended by the PMBOK guide (PMI, 2021) was adopted as a reference, organizing the analysis into interdependent stages to map the use and integration of parametric estimation with other management tools.

The analysis process followed the project lifecycle stages, starting with technical-economic feasibility and definition of guidelines, where parametric estimation was applied as an initial decision-making tool, using historical data and cost indicators per square meter in Microsoft Excel®. Subsequently, in the preparation of budgets and construction of the Work Breakdown Structure (WBS), the preliminary budget was structured parametrically and the scope decomposed into work packages, integrating costs and the WBS in Microsoft Excel®.

Subsequently, in the development of the executive projects, technical detailing and compatibility were carried out with the support of Building Information Modeling (BIM). The physical-financial planning was elaborated by integrating the WBS (Work Breakdown Structure), budget, and schedule in Microsoft Project®, examining the linkage between work packages and the temporal distribution of costs. The execution and control phases involved performance monitoring by comparing planned versus actual, using indicators and reports, structured based on the PDCA cycle.

Finally, in the closing stage, the results were consolidated, the historical cost base was updated, and lessons learned were recorded. The final documentation and the database were used for the feedback of parametric estimates, contributing to the improvement of future projections.

The data analysis was conducted qualitatively, through the integrated interpretation of the observed documents, tools, and practices. The aim was to identify application patterns and relationships between the different stages of the process. A comparison between Projects A and B was employed as an analytical strategy to highlight how different levels of complexity and standardization influenced the application of parametric estimation.

To ensure institutional preservation, the names of the construction company and the developments were kept anonymous, referring to them as “the organization” and “Project A” and “Project B”. There was no mention of free and informed consent terms, as the research was based on organizational data and participant observation by the researcher in their role.

3. Results and Discussion

The application of parametric cost estimation was analyzed throughout the entire project lifecycle, in line with the sequence adopted in the Materials and Methods section. The integrated reading of the data showed that financial predictability did not arise from an isolated tool, but from the progressive articulation between technical-economic feasibility, definition of guidelines, budget preparation, development of the Work Breakdown Structure (WBS), executive compatibility, physical-financial planning, execution, control, and closure. From this perspective, the results were organized according to these stages, so as to clarify how parametric estimation was employed, refined, and validated in practice.

Technical-Economic Feasibility

The first stage corresponded to the technical-economic feasibility study, responsible for subsidizing the investment decision and guiding the initial scope, schedule, and cost parameters of the analyzed ventures. In this phase, parametric estimation was used as a preliminary evaluation tool, based on historical data from previous works of the organization itself, adjusted according to the characteristics of the new projects and applicable sectoral indices. This use showed adherence to the guidelines of the Project Management Institute (PMI, 2021), which recognizes parametric estimation as an appropriate technique for contexts where the scope is still maturing, but reliable parameters from similar ventures are available.

In Project A, with a total built area of 40,145.89 m², the total estimated cost without adjustment was R$ 91,844,460.64, resulting in a gross parametric cost of R$ 2,287.77 per square meter. After applying the adjustment index of 1.52, a parameter defined in the project scope, the projected value reached R$ 139,773,666.81, equivalent to R$ 3,481.65 per square meter. In Project B, with an estimated area of 40,120.00 m², the total estimated cost without adjustment was R$ 87,481,369.63, with a gross cost of R$ 2,180.58 per square meter. With an adjustment index of 1.50, also a parameter defined in the project scope, the total projected value reached R$ 131,222,054.44, equivalent to R$ 3,270.78 per square meter.

The data evidenced that, although the two ventures presented similar size and location, Project A already showed, since the feasibility phase, to be more costly in absolute and relative terms. This difference was associated with its greater architectural complexity, notably due to the ventilated facade, the higher degree of unit customization, and the incorporation of superior standard construction solutions and finishes. Project B, on the other hand, was conceived under a more rationalized logic, with greater element repetitiveness and less technical dispersion, which was reflected in a lower parametric cost.

This behavior confirms Kerzner’s (2022) observation that the reliability of parametric estimation depends not only on the quality of the historical data but also on the adequate calibration of the premises against the degree of complexity of the analyzed object. In addition to supporting initial decision-making, parametric estimation allowed the organization to establish an initial economic benchmark for project continuity. In practice, this stage was not limited to producing a consolidated cost figure but served as a basis for the joint evaluation of multiple criteria.

The joint evaluation considered the economic attractiveness of the investment, return on capital indicators and expected margin, the compatibility between the intended product and the target audience, and the adherence of technical specifications to the available budget. The parametric cost per square meter therefore acted as one of the inputs for the feasibility analysis, not as an exclusive decision criterion. This result reinforces the contribution pointed out by Heldman (2021), according to whom parametric estimation presents greater strategic utility when inserted into decision-making processes that demand speed, comparability, and a preliminary view of financial risks.

Definition of Guidelines and Budget Elaboration

After the preliminary feasibility validation, the analysis moved to the stage of defining guidelines and developing the initial budget. At this point, the feasibility data were converted into more defined technical, architectural, and commercial parameters, covering tower height, unit typology, facade solutions, common areas, finishing standards, and sustainability guidelines. From a managerial perspective, this stage represented the transition between a still aggregated reading of costs and a more organized structuring of expenses by subsystems and cost centers.

In Project A, the distribution of costs by category showed a greater concentration in structure and foundations, facades, building systems, and interior finishes, all directly influenced by choices of greater technical sophistication. Building systems represented 9.49% of the total adjusted cost, facades (frames and brises) 9.83%, structure and foundations 16.02%, interior finishes 12.24%, common areas 5.48%, and indirect expenses 5.28%. The other categories summed to 41.66% of the total R$ 139,773,666.81.

For Project B, building installations accounted for 9.87% of the total adjusted cost, facades (frames and brises) 9.51%, structure and foundations 15.99%, and interior finishes 11.99%. The other categories summed up to 52.64% of the total R$ 131,222,054.44. It is observed that, although both follow a similar logic of budgetary organization, Project A shows a greater concentration in categories associated with construction complexity, such as structure, facades, and finishes, while Project B demonstrates a more homogeneous distribution, reflecting the rationalization guidelines adopted since the feasibility phase.

This comparison reinforces that the way the scope is defined directly impacts the composition and predictability of costs throughout the project. In this phase, Microsoft Excel® played a central role, not only as an operational calculation tool but as an environment for organizing and validating data. The spreadsheets allowed for the consolidation of parametric compositions by subsystems, the application of automated formulas, cross-validation, and the use of the ABC Curve for prioritizing items with the greatest financial impact. In practice, this structure facilitated reviews, simulations, and adjustments, strengthening information traceability. This result aligns with Vargas (2021)’s understanding, highlighting that well-structured electronic tools enhance budget consistency and favor control throughout the project lifecycle.

WBS Construction

The next stage corresponded to the construction of the WBS (Work Breakdown Structure), which proved decisive in transforming the initial parametric estimate, previously more aggregated, into a structure compatible with the manageable scope of the ventures. The formalization of the WBS allowed the project to be decomposed into hierarchical levels of deliverables, connecting budget, planning, and control. The WBS adopted for both projects, at its Level 1, was “Residential Venture”. At Level 2, it included “Preliminary services”, “Foundations”, “Structure”, “Facades”, “Building installations”, “Masonry and enclosures”, “Internal finishes”, “Common areas”, and “Delivery and closure”.

At Level 3, “Preliminary services” detailed “Mobilization, site and temporary facilities”. “Foundations” included “Piles, blocks and foundation beams”. “Structure” encompassed “Reinforced concrete, formwork and rebar”. “Facades” detailed “Frames, brises and cladding”. “Building systems” comprised “Electrical, plumbing and fire protection”. “Masonry and enclosures” included “Structural or partition masonry, shafts and closures”. “Internal finishes” detailed “Cladding, ceilings, painting, sanitary ware and fixtures”. “Common areas” involved “Leisure, circulation, landscaping and shared areas”. Finally, “Handover and closing” included “Inspections, tests, final documentation and acceptance”.

Although the WBS structure was common to both ventures at their main hierarchical levels, reflecting the methodological standardization adopted by the organization, its application was not identical. In Project A, the work packages related to facades and internal finishes were broken down to a greater level of detail, due to the architectural complexity and the high degree of customization of the units. In Project B, the greater construction repetitiveness allowed the packages to be kept at a more compact aggregation level, reducing the number of sub-deliverables and simplifying control.

The construction of the WBS represented a turning point in the analysis, because it was from this point that parametric estimation began to directly engage with the project’s work packages. Before, costs were organized mainly by cost centers and subsystems; after the WBS, they became linked to specific and traceable deliverables. This result showed a gain in clarity and budgetary integrity, reducing ambiguities and making the relationship between scope and resources more visible. In practical terms, the WBS not only organized the project; it made it possible to verify, with greater precision, where costs were concentrated and how they were distributed throughout the execution. This finding is aligned with PMI (2021) and Kerzner (2022), for whom adequate scope decomposition is an essential condition to avoid omissions, overlaps, and control weaknesses.

Development of Executive Projects

With the WBS consolidated, the analysis moved on to the development of executive projects, supported by building information modeling (BIM). At this stage, the compatibility between architecture, structure, foundations, and building systems allowed for the review of quantities, refinement of specifications, and identification of interferences before the full start of execution. The use of BIM proved particularly relevant for bringing the initial parametric data closer to a base more aligned with the object that would actually be built. The effects of this refinement were most visible in Project A, whose greater architectural complexity led to relevant adjustments in structural systems and facade elements.

In Project A, the initial parametric estimate for the structure was R$ 22,392,486.12, and the revised executive budget was R$ 23,150,000.00, resulting in a variation of +3.38%. For the facade, the parametric estimate was R$ 13,730,658.89, and the executive budget was R$ 14,420,000.00, with a variation of +5.02%. The installations had a parametric estimate of R$ 13,261,862.17 and an executive budget of R$ 13,000,000.00, with a variation of -1.98%. The finishes, with a parametric estimate of R$ 17,105,389.77, had an executive budget of R$ 16,880,000.00, with a variation of -1.32%.

The data showed that the greatest variations occurred precisely in the categories most sensitive to personalization and technical complexity, especially facade and structure. Nevertheless, the differences remained below 6%, which can be considered compatible with the project’s level of maturity at this stage. From a management perspective, this result is important because it demonstrates that parametric estimation, when supported by a consistent historical base, does not lose validity with the advancement of detail; on the contrary, it functions as a robust initial reference, provided it is subsequently refined based on executive data. Heldman (2021) argues that the accuracy of estimates tends to increase throughout the project cycle, and the observed data confirm this trend.

In Project B, the behavior was even more stable, reflecting the greater constructive rationalization adopted from the initial phases. For the structure, the parametric estimate was R$ 20,980,000.00, and the executive budget was R$ 21,250,000.00, with a variation of +1.29%. The facade had a parametric estimate of R$ 12,480,000.00 and an executive budget of R$ 12,600,000.00, with a variation of +0.96%. The installations presented a parametric estimate of R$ 12,950,000.00 and an executive budget of R$ 12,880,000.00, with a variation of -0.54%. The finishes, with a parametric estimate of R$ 15,730,000.00, had an executive budget of R$ 15,600,000.00, with a variation of -0.83%.

In Project B, variations remained below 2% in the analyzed categories, indicating high adherence between the parametric estimate and the executive budget. Analytically, this difference between the two ventures was one of the study’s most relevant findings: the accuracy of the initial estimate depended not only on the technique itself but also on the application context. Projects with greater repetitiveness, lower solution dispersion, and greater standardization tended to exhibit more stable budgetary behavior. This observation confirms Kerzner’s (2022) argument that operational predictability is closely related to the project’s degree of standardization and the maturity of its planning.

Physical-Financial Planning

With the executive compatibility completed, the consolidated values were integrated into the schedule for the construction of the physical-financial planning. At this stage, the work packages defined in the WBS (Work Breakdown Structure) were linked to the activities structured in Microsoft Project®, allowing each deliverable to have an estimated duration, precedence relationships, associated cost, and temporal distribution of disbursements. This made it possible to build an integrated physical-financial baseline, reducing fragmentation between technical planning and economic control.

The critical path analysis revealed similar behavior in both ventures, focusing primarily on the macro-stages of foundations, structure, and facade. However, the schedule’s sensitivity was not identical. In Project A, the facade showed greater exposure to deviation risk due to architectural complexity and the degree of customization. In Project B, the greater construction repetitiveness favored stability in activity sequencing and greater homogeneity in planned progress. This finding is particularly relevant because it shows that the effect of parametric estimation on financial predictability cannot be analyzed without considering its connection to the schedule.

The projected cumulative distribution of physical and financial progress for Project A indicated that, by Month 3, the planned physical progress was 7% and financial progress was 9%. By Month 6, the percentages were 20% physical and 23% financial. By Month 9, 44% physical and 47% financial. By Month 12, 67% physical and 69% financial. By Month 15, 86% physical and 88% financial. By Month 18, both reached 100%. For Project B, by Month 3, the planned physical progress was 8% and financial progress was 9%. By Month 6, the percentages were 22% physical and 24% financial. By Month 9, 46% physical and 48% financial. By Month 12, 70% physical and 71% financial. By Month 15, 88% physical and 89% financial. By Month 18, both reached 100%.

The S-Curves showed financial behavior concentrated in the intermediate phase of the work, especially between months six and twelve, a period corresponding to the structural advancement and the beginning of the facades. Although both projects showed this concentration, Project B demonstrated a slight anticipation of accumulated physical progress and a more homogeneous financial distribution. Project A, on the other hand, presented greater financial pressure in the facade and finishing stages, directly reflecting the scope decisions made previously. These results show that the quality of physical-financial planning depends on the consistency of the integration between WBS (Work Breakdown Structure), budget, and schedule, as advocated by PMI (2021) and Kerzner (2022).

Execution and Control

With the integrated baseline consolidated, the execution and control phase began. In this stage, cost and schedule data were systematically compared with the planned parameters, allowing for the identification of trends, deviations, and necessary corrections. Performance monitoring was carried out by comparing planned versus actual physical progress, planned cost versus actual cost, as well as monitoring the critical milestones defined in the schedule. Operationally, periodic meetings served as a space for information validation, alignment between areas, and decision-making.

The final comparison between planned cost and actual cost at the end of execution revealed that Project A had a planned cost of R$ 139,773,666.81 and an actual cost of R$ 143,950,000.00, resulting in an absolute variance of +R$ 4,176,333.19 and a percentage variance of +2.99%. Project B, in turn, presented a planned cost of R$ 131,222,054.44 and an actual cost of R$ 132,880,000.00, with an absolute variance of +R$ 1,657,945.56 and a percentage variance of +1.26%.

The data showed that both ventures presented a cost increase in relation to the baseline, but within controlled ranges. From a managerial point of view, both results can be considered satisfactory for large-scale ventures, especially because the deviations remained below 5%, a limit often admitted as acceptable when there is structured control and documented technical justification (Kerzner, 2022). Nevertheless, the difference between the projects reaffirms that constructive rationalization contributed to greater financial predictability in Project B.

Regarding the deadline, Project A had a planned deadline of eighteen months and an actual deadline of nineteen months, with a variation of one month. Project B, on the other hand, had a planned deadline of eighteen months and an actual deadline of eighteen months, with no variation. Project A presented a one-month extension in the final deadline, attributed to technical adjustments in facade systems identified during execution. Project B, however, maintained full adherence to the originally established schedule.

According to Heldman (2021), uncertainty reduction throughout the project lifecycle is directly associated with the level of prior detail and the quality of integrated planning. The stability observed in Project B corroborated this premise, evidencing the positive effects of the standardization adopted since the initial phase. Operational control was structured based on the PDCA cycle (“Plan-Do-Check-Act”), applied in periodic follow-up meetings. During the “Check” phase, accumulated cost variations, schedule deviations, and impacts arising from technical adjustments were analyzed. In the “Act” phase, corrective measures were implemented, such as replanning critical activities, renegotiating contracts with suppliers, and reinforcing teams in priority areas. According to Juran and De Feo (2019), PDCA is an essential tool for promoting continuous improvement and systematic control of complex processes. In the analyzed projects, its application allowed variations to remain within manageable limits.

The consolidated analysis demonstrated structural differences between the ventures: Project A, characterized by greater architectural complexity and customization, showed higher exposure to cost and schedule variations. Project B, focused on construction rationalization, presented greater financial stability and full adherence to the schedule. These results highlighted that strategic decisions made in the initial phases (feasibility and guideline definition) directly impacted execution behavior. According to Kerzner (2022), operational predictability is strongly associated with the degree of standardization and planning maturity. The observed data confirmed this relationship, indicating that the alignment between parametric estimation, structured WBS (Work Breakdown Structure), and physical-financial planning contributed to reducing significant deviations during execution. The stage demonstrated that the integration between structured planning and systematic control allowed financial variations to be kept below 3% in Project A and 2% in Project B, in addition to ensuring full schedule adherence in Project B. These results reinforced the effectiveness of the adopted methodological approach, showing that integrated scope, schedule, and cost management elevated the level of predictability and reduced exposure to critical risks.

Delivery and Closing

Following the execution and control phase, the contractual delivery and closure stage for Projects A and B was initiated. This phase aimed to formalize the completion of the works, validate adherence to established requirements, and consolidate the obtained results from technical, financial, and contractual perspectives. As established by PMI (2021), project closure consists of the formal finalization of all activities, verification of scope fulfillment, and documentation of lessons learned, ensuring that the results are incorporated into organizational knowledge. In both ventures, delivery was preceded by final technical inspections, confirmation of compliance with executive designs, validation of building systems, and verification of adherence to defined quality standards.

Project B showed greater fluidity in the final inspection stage, resulting from the lower technical variability observed throughout its execution. Project A, on the other hand, required specific adjustments to facade elements and custom finishes, extending the formal completion of the undertaking by approximately one month, as evidenced in the previously presented schedule analysis. The formal acceptance occurred through the issuance of technical documents and contractual closure with strategic suppliers, consolidating the physical and administrative completion of the projects. Financial closure involved consolidating final measurements, verifying contractual addendums, settling contracts with suppliers, and updating cost centers.

The comparison between planned cost and actual cost indicated variations of +2.99% in Project A and +1.26% in Project B, both considered within a manageable range for large-scale ventures. According to Kerzner (2022), the closing stage should ensure that all contractual obligations have been met and that there are no financial pending issues that compromise the overall project outcome. In the analyzed cases, the formalization of the closure allowed for the consolidation of financial performance and the mitigation of residual risks. In addition to contractual aspects, the lessons learned were systematized, with an emphasis on the impact of architectural complexity on the accuracy of parametric estimates, the influence of construction standardization on financial stability, the importance of integrating the WBS (Work Breakdown Structure), budget, and schedule, and the effectiveness of structured control based on the PDCA cycle.

It was observed that Project B, characterized by greater rationalization and repetitiveness, presented less dispersion between preliminary estimate and final cost, in addition to full adherence to the deadline. Project A, although more complex, maintained performance considered satisfactory, with variations below the critical limit of financial risk. This comparison showed that strategic decisions adopted in the feasibility phase directly impacted the execution behavior and the final outcome of the undertaking. One of the main results of the closing stage was the update of the historical cost base used in parametric estimates. The realized values were incorporated into the organization’s internal database, allowing the recalibration of cost indices per square meter, the update of subsystem compositions, and the improvement of accuracy in future feasibility studies. According to PMI (2021), project closure should contribute to strengthening organizational maturity through knowledge management. In the analyzed projects, the feedback of the parametric base represented a significant advance in the consolidation of internal best practices.

The delivery and contractual closing stage showed that both projects were completed with financial variations below 3%. Only Project A experienced a moderate extension of the deadline, constructive standardization positively influenced predictability, and the integration between parametric estimation, WBS (Work Breakdown Structure), physical-financial planning, and systematic control contributed to consistent results. The formal closure consolidated not only the technical completion of the ventures but also the organizational learning derived from the structured application of project management. Thus, the complete cycle was closed, encompassing the stages of technical-economic feasibility, guidelines and preliminary budget, executive projects and WBS consolidation, physical-financial planning, execution and control, and delivery and closure.

The results obtained evidenced that the application of parametric estimation, in the technical-economic feasibility phase, proved consistent with the recommendations of PMI (2021) and Heldman (2021), who advocate this technique as an effective tool in contexts of initial uncertainty and availability of reliable historical data. The variations observed between preliminary estimation and executive budget remained within acceptable ranges, especially in Project B, confirming that the use of calibrated parameters and a structured historical basis contributed to greater budgetary accuracy. Thus, the findings reinforced the literature by demonstrating that the quality of the database directly influences the reliability of initial projections. The comparison between Projects A and B also confirmed the premise defended by Kerzner (2022), according to which ventures with a higher degree of standardization and repetitiveness tend to present greater operational predictability. Project B, oriented towards construction rationalization, showed less dispersion between planned and actual cost, as well as full adherence to the deadline. In contrast, Project A, characterized by greater architectural complexity and customization, presented higher variations, albeit controlled. This behavior evidenced that strategic decisions adopted in the guideline definition phase directly impacted execution performance, corroborating the relationship between planning maturity and result stability.

4. Conclusion

This study analyzed and systematized the application of parametric cost estimation in project management, considering its integration with budgetary planning, the Work Breakdown Structure (WBS), physical-financial planning, and control mechanisms, seeking to understand its contribution to financial predictability in civil construction ventures. It was found that parametric estimation, used since the technical-economic feasibility phase, provided a robust initial benchmark, which was progressively refined throughout the project cycle. Integration with the WBS proved crucial for scope organization and cost traceability, while physical-financial planning, built from this integration, allowed for a consistent baseline for performance monitoring. It was observed that constructive standardization, as evidenced in Project B, contributed to lower budgetary dispersion and greater temporal stability, with significantly smaller cost and schedule deviations compared to Project A, which was more complex. The application of systematic control, based on the PDCA cycle, allowed financial variations to be kept below 3% and ensured adherence to the schedule in most cases. The study’s main contribution lies in demonstrating that the articulation between parametric estimation and formal project management practices constitutes a relevant tool for increasing financial predictability and strengthening governance in civil construction ventures, in addition to promoting the feedback of historical cost data for future projects.

However, the study presented limitations inherent to the adopted method, such as restricted access to some strategic organizational information and the concentration of the analysis on only two similar typologies of ventures, whose data were obtained in a specific market context. The absence of inferential statistical methods also restricts the broad generalization of the findings. For future studies, it is suggested to expand the sample to include a larger number of ventures, of different typologies and in varied market contexts, in order to strengthen the external validity of the results. It is also recommended to apply inferential statistical methods to quantify the observed relationships and deepen the understanding of the factors that influence the accuracy of parametric estimation and financial predictability in civil construction.

Bibliographic References

Chitkara, K. K. 2014. Construction project management: planning, scheduling and controlling. 2. ed. Tata McGraw-Hill, New Delhi, India.

Flick, U. 2009. Introdução à pesquisa qualitativa. 3. ed. Artmed, Porto Alegre, RS, Brasil.

Gil, A. C. 2019. Métodos e técnicas de pesquisa social. 7. ed. Atlas, São Paulo, SP, Brasil.

Heldman, K. 2021. Gerência de projetos: guia para o exame PMP do PMI. 10. ed. Alta Books, Rio de Janeiro, RJ, Brasil.

Juran, J. M.; De Feo, J. A. 2019. Juran’s Quality Handbook: The Complete Guide to Performance Excellence. 7. ed. McGraw-Hill, New York, NY, EUA.

Kerzner, H. 2022. Gestão de projetos: as melhores práticas. 12. ed. Bookman, Porto Alegre, RS, Brasil.

Lakatos, E. M.; Marconi, M. A. 2017. Fundamentos de metodologia científica. 8. ed. Atlas, São Paulo, SP, Brasil.

Minayo, M. C. S. 2017. O desafio do conhecimento: pesquisa qualitativa em saúde. 14. ed. Hucitec, São Paulo, SP, Brasil.

Project Management Institute [PMI]. 2021. Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK®). 7. ed. Project Management Institute, Newtown Square, PA, EUA.

Thiollent, M. 2011. Metodologia da pesquisa-ação. 18. ed. Cortez, São Paulo, SP, Brasil.

Vargas, R. V. 2021. Manual prático do plano de projeto. 5. ed. Brasport, Rio de Janeiro, RJ, Brasil.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.