Scope change management in industrial projects: case study in a biotechnology company

Lucas Martins Mizota; Lorena Hernández Mastrapa

DOI: 10.22167/2675-6528-202601103

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The impact of scope changes, associated with communication management, on the development of an engineering project in a biotechnology company was analyzed. The objective was to identify the causes of these changes, their impacts on performance, and propose improvements aligned with good project management practices. The research, of an applied nature and qualitative approach, used a single case study in a biotechnology company, focusing on the development of an administrative building. Data were collected through value maps and documentary analysis of the project, and treated by content analysis. The results revealed that, despite a comprehensive initial survey, the project underwent recurrent scope changes, such as layout redefinitions, inclusion of new requirements, and technical adjustments. It was found that scope instability resulted from the combination of project complexity, multiple stakeholders, low requirement maturity, and, mainly, communication failures, lack of prioritization, and absence of formal validations between phases. These alterations negatively impacted deadline, cost, quality, productivity, and integration, generating rework and loss of predictability. It was concluded that scope instability in complex projects was not solely due to flaws in the initial planning, but to the absence of structured governance mechanisms. The integration of scope management and communication management, along with requirement prioritization, formal validations, and change control, proved essential to increase predictability and performance in complex industrial projects.

Keywords: Communication; Governance; Predictability; Requirements; Stakeholders.

1. Introduction

The growing complexity of industrial projects, notably in high-tech sectors such as biotechnology, drives the search for more structured management approaches. Organizations in these dynamic environments aim for greater predictability in the execution of ventures, aligning strategic objectives with operational results. However, the multiplicity of *stakeholders* and the evolving nature of organizational requirements make project management challenging, especially in defining and controlling scope (Project Management Institute [PMI], 2021; Kerzner, 2022). Scope instability, manifested by unplanned changes, can significantly compromise success, impacting deadlines, costs, and final quality. This scenario underscores the importance of robust scope management practices, integrated with effective communication.

Scope management is a central pillar in project management, establishing the boundaries of work and essential deliverables. Proper elicitation and documentation of stakeholder requirements are crucial for a solid foundation, aiming to mitigate uncertainties and reduce unplanned changes. However, scope stability is often compromised by inadequate understanding of stakeholder needs and the absence of formal validation processes (PMI, 2021). Empirical evidence indicates that failures in requirements gathering and validation are primary causes of changes and rework in complex projects (PMI, 2021; ISO, 2020). Industrial projects, due to involving multiple disciplines and technical interfaces, exhibit an even greater propensity for changes during their execution (Kerzner, 2022; Serrador; Pinto, 2015).

Communication management, in turn, plays a vital integrating role, ensuring the effective flow of information and consistent decision-making. Structured communication is essential for aligning expectations, dispelling ambiguities, and resolving conflicts inherent in complex projects. PMI (2021) points to communication failures as one of the main causes of failure, especially where there is a lack of clarity in interaction flows and channels. Proactive identification and engagement of *stakeholders* are equally critical, particularly in industrial environments where departments such as engineering, operations, and quality have distinct interests and priorities (Freeman, 1984; Bourne, 2015). The lack of adequate engagement and communication strategies exacerbates scope instability, hindering the consolidation of requirements and favoring *scope creep*, the gradual and uncontrolled expansion of scope (Kerzner, 2022).

In industrial engineering projects, such as the implementation of administrative facilities in production plants, scope management and communication challenges are amplified by the need for integration with existing structures, compliance with regulatory requirements, and adaptation to evolving demands (PMI, 2021; Kerzner, 2022). Practical experience and literature indicate that, even with structured requirements gathering tools, gaps in the initial definition can emerge, leading to successive revisions and rework (ISO, 2020; Serrador; Pinto, 2015). The recurrence of these changes, which often result in a loss of predictability and efficiency, highlights the need for more robust governance and control mechanisms. Given this scenario, this study seeks to analyze the impact of scope changes, associated with communication management, on the development of an engineering project in a biotechnology company, with the objective of identifying the causes of these changes, their impacts on project performance, and proposing improvements aligned with best project management practices.

2. Material and Methods

The present study was characterized as an applied research, seeking to generate knowledge with a practical purpose and aimed at solving real problems in a specific organizational context. A qualitative approach was adopted, which allowed for an in-depth understanding of complex phenomena related to project management, especially regarding scope changes and communication among the various *stakeholders*. This methodological choice was based on the need to interpret non-numerical data to uncover the interrelationships between organizational, technical, and human factors (Prodanov; Freitas, 2013).

In terms of technical procedures, the research was configured as a single case study, according to the approach proposed by Yin (2015). This strategy was selected for its suitability for in-depth analysis of a contemporary phenomenon embedded in its real context, where the boundaries between the phenomenon and the environment are not clearly defined. The case study allowed for intensive investigation of scope management and communication dynamics within a specific project, revealing the complexities and particularities of the biotechnology industrial environment.

The study was contextualized in the development of the preliminary design and the executive design of an administrative building, located in an industrial plant in the biotechnology sector. The company is located in the interior of the state of São Paulo, in the municipality of Barra Bonita. The analysis period covered the conception and detailing phases of the project, during which successive scope changes were observed. The research focused on an engineering project characterized by its high complexity, the multiplicity of *stakeholders* involved, and the intense interaction between the various organizational areas.

The unit of analysis consisted of the engineering project itself, which contemplated the architectural design and the fulfillment of the functional needs of a complete administrative building. This included operational, administrative, and support areas, in addition to its integration into the existing industrial environment. The scope of the undertaking was structured in two main phases: the preliminary design and the executive project, allowing for a detailed analysis of the evolution of definitions and changes that occurred at each stage of the project life cycle.

The population of interest for data collection was composed of the *stakeholders* directly involved in the administrative building project. The sample included representatives from the main organizational areas impacted, such as engineering, operations, quality, human resources, *facilities*, and EHS. The selection of these participants was based on their level of influence on the project and, mainly, on their degree of future use of the space. This criterion aimed to ensure that the demands raised reflected the real operational and support needs of the organization, providing a multidisciplinary view.

Data collection was carried out through multiple sources of evidence, as recommended by Yin (2015) to increase the reliability and robustness of the analysis by triangulation. The main instrument used was a “value map”, a structured form applied to the areas involved in the project. This instrument was designed to identify stakeholders’ perceptions regarding the pain points of the current environment, expected benefits, technical requirements, and the number of users for the different spaces of the undertaking, collecting qualitative and quantitative information in a standardized way.

Complementarily, data collection included documentary analysis of project records. Documents such as scope reviews, technical deliverables, change logs, and project development tracking materials were examined. This approach allowed for tracking the evolution of definitions and identifying formalized changes throughout the preliminary design and executive design phases. It is important to note that data from formal meetings were not considered for analysis purposes, aiming to maintain methodological consistency and standardization of the information sources used.

The research execution followed structured steps to analyze the impact of scope changes. Initially, the identification and classification of scope changes that occurred throughout the project development were carried out. This was done through a comparative analysis between the initially defined scope and its subsequent revisions. The changes were categorized according to their nature, including the inclusion of new requirements, alteration of existing requirements, *layout* redefinition, technical adjustments, and normative revisions, allowing for a comprehensive overview of the alterations.

Subsequently, the causes associated with these changes were identified, based on the analysis of data collected from value maps and project documents. The causes were organized into analytical categories, such as failures in requirements gathering, late inclusion of *stakeholders*, lack of prioritization, communication failures, and absence of formal validations between phases. Subsequently, the impacts of these changes on project performance were analyzed, considering dimensions such as schedule, cost, quality, productivity, and integration between disciplines, to understand their consequences.

Finally, based on the integration of the research findings, improvements were proposed aligned with good project management practices, as advocated by the Project Management Institute (PMI, 2021). These proposals focused on the implementation of structured governance mechanisms, integrated change control, definition of validation milestones, and communication planning among stakeholders. The objective was to offer practical solutions to increase predictability and performance in complex industrial projects, mitigating the recurrence of scope changes.

The data collected, from both the value maps and the project documents, were submitted to the content analysis technique, according to the methodology proposed by Bardin (2016). This technique allowed for the systematic organization, categorization, and interpretation of qualitative data. Initially, a floating reading of the material was performed, followed by the definition of analytical categories pertinent to the scope of the study, such as initial requirements, scope changes, causes of alterations, communication failures, and project impacts, to structure the investigation.

After defining the categories, the data were coded and grouped according to these classifications, enabling the identification of patterns and recurrences in the information. Additionally, a comparative analysis was performed between the initially defined scope, based on the surveys, and the changes that occurred throughout the project development. This comparison aimed to identify divergences between planning and execution, as well as to understand the factors that contributed to the scope changes. The interpretation of the results was based on PMI’s (2021) best practices.

As a methodological limitation of the present study, the analysis of a single case study stands out. Although this approach has allowed for an in-depth investigation of the phenomenon in its real context, the results obtained may not be directly generalizable to other projects or organizations. The specificity of the biotechnology environment and the particularities of the analyzed project suggest that, for future research, expanding to different contexts and incorporating quantitative performance metrics could enrich the understanding of the topic.

3. Results and Discussion

The analyzed project, situated in the development of the preliminary design and the executive design of an administrative building in an industrial plant in the biotechnology sector, in the municipality of Barra Bonita, SP, had as its primary objective the replacement and restructuring of the existing administrative facilities. The motivation for this undertaking lay in overcoming limitations in infrastructure, capacity, and operational integration that compromised the efficiency and well-being of employees. This context, by its nature, already imposed an inherent complexity on the project, given the need to integrate new structures into an operating industrial environment, as well as to meet multiple demands from various stakeholders. The analysis therefore focused on identifying the scope changes that occurred, their underlying causes, and the impacts generated on the overall project performance, following the established methodological guidelines.

The requirements gathering stage proved to be a fundamental pillar in the initial phase of the project. Using the value map tool, insights and needs were collected from representatives of strategic areas such as engineering, operations, quality, human resources, *facilities*, and EHS. The selection of these *stakeholders* was carefully based on their level of influence on the project and, crucially, on their degree of future use of the space. This approach aimed to ensure that the demands gathered were not merely theoretical, but an authentic reflection of the organization’s operational and support needs. Multidisciplinary participation was essential to capture different perspectives on the existing work environment, identify current operational pain points and limitations, and understand expectations regarding the new venture, thereby conferring greater robustness and reliability to the data that would underpin the scope definition.

The data collection process, spanning approximately three months, allowed for a significant deepening of information and continuous validation of the responses obtained through interactions with stakeholders. The results, organized into analytical categories, revealed a set of “pain points” that acted as central motivators for the project. Among the main identified evidence, the inadequacy of the existing infrastructure, with provisional environments and the use of containers, the insufficiency of physical space, resulting in overcrowding and lack of capacity, and problems of comfort and ergonomics, such as excessive heat, inadequate ventilation, and uncomfortable furniture, stood out. Additionally, issues of hygiene and sanitation, inefficient operational flows, security failures in access control, and an organizational image that did not align with the desired corporate standard were pointed out. These “pain points” not only justified the need for the project but also outlined the initial challenges that the scope should address.

In contrast, the survey also consolidated the benefits expected by stakeholders. Expectations converged on the improvement of the work environment, with more comfortable, organized, and safe spaces, and greater organizational integration, promoted by the proximity between areas and the reduction of travel. Operational efficiency was a key benefit, aiming to optimize workflows. Safety, quality of life, the construction of a modern and representative corporate image, and strict adherence to legal and regulatory norms and requirements completed the set of expectations. These results demonstrated a clear alignment between organizational needs and project objectives, indicating that the undertaking was perceived as a strategic solution for several chronic problems.

The identified technical requirements, which formed the basis for the development of the technical scope, included definitive construction with adequate materials, complete building systems (HVAC, lighting, electrical, and plumbing), security (CCTV, access control, flow segregation), compliance with standards such as NR-24 and RDC 216, a *layout* that promoted adequate separation and sizing of areas, and operational support with a cafeteria, locker rooms, and support rooms, in addition to accessibility. The synthesis of the quantitative user data and their space utilization characteristics, in turn, revealed a significant variability of profiles and demands among the areas, a crucial factor for the project’s sizing and flexibility. This diversity of requirements, although essential for completeness, also introduced an intrinsic complexity to scope management, as pointed out by Kerzner (2022), who highlights the difficulty in managing projects with multiple *stakeholders* and heterogeneous demands.

The consolidation of project requirements, which integrated all the demands raised into a structured vision, highlighted the complexity associated with its management. The central problem was the inadequate and provisional infrastructure, and the objective was the implementation of a structured and integrated administrative environment. Critical requirements included security, comfort, capacity, and organized flows, while normative requirements focused on compliance with technical and sanitary legislation. The complexity was classified as high, due to multiple *stakeholders* and conflicting demands, and the associated risk was a high probability of scope change. This analysis of the initial table results demonstrates that the requirements gathering was comprehensive, identifying organizational needs related to infrastructure, security, comfort, and operational efficiency, with a clear convergence of demands for the replacement of provisional structures with a more adequate and functional environment.

However, the high complexity in defining the scope, arising from the diversity of *stakeholders* and the heterogeneity of requirements, already signaled a vulnerability. According to the Project Management Institute (PMI, 2021), requirements gathering, although fundamental, must be accompanied by continuous prioritization and validation to ensure project stability. The absence of a clear hierarchy of requirements, which distinguished the essential from the desirable or postponable, hindered decision-making and favored successive scope revisions, a point corroborated by ISO 21502 (2020), which emphasizes the importance of clear prioritization criteria. Thus, the consolidation of the initial scope, although technically consistent and comprehensive, presented fragilities typical of complex projects, making it susceptible to changes throughout development due to the absence of structured prioritization and governance practices.

The consolidation of the initial project scope represented the transition from the needs identified in the value maps to formal technical and functional guidelines. This stage was crucial for structuring the preliminary design and the executive project, defining clear deliverables and boundaries. The integration of contributions from various areas such as engineering, operations, quality, human resources, *facilities*, and EHS was fundamental, incorporating requirements for space usage, safety, comfort, regulatory compliance, and integration with the industrial environment. The initial scope, therefore, was not limited to physical construction but included the expected performances and their articulation with operational routines. The consolidated structure of the initial scope, organized into functional and technical categories, such as administrative areas, support areas, technical and support areas, building infrastructure, safety and control, *layout* and flows, integration with the plant, norms and compliance, and project development, demonstrated a comprehensive and multidimensional character.

This multidimensionality of the initial scope, although necessary to meet all the needs for functionality, comfort, safety, compliance, and operational efficiency, also made it inherently complex. The project was structured in preliminary design and executive design phases, aiming for a progressive maturation of the definitions. However, this progressive logic, without formal and rigorous validation milestones between stages, increased the risk of incorporating new demands and scope instability, especially when requirements were not sufficiently stabilized. The traceability between the requirements gathered and their translation into the initial scope, although present, was not accompanied by control mechanisms that prevented the reopening of decisions already made. This situation is fertile ground for “scope creep”, the incremental expansion of scope without formal control, as described by Kerzner (2022).

Throughout the development of the preliminary design and the executive project, several changes were identified in the initially defined scope, characterizing a continuous process of revisions and adjustments. These changes were not isolated events, but a recurring phenomenon, driven by the incorporation of new requirements, adjustments to previously defined demands, and reconfiguration of proposed solutions. This behavior is an indicator of an evolutionary scope dynamic, common in projects of high complexity and with multiple *stakeholders*.

The typology of identified scope changes revealed that the alterations manifested in various forms. There was the inclusion of new requirements, which were initially unforeseen demands but were incorporated into the project. Changes to existing requirements, modifications to previously established definitions, also occurred. The redefinition of “layout” and scope expansion, with the inclusion of new environments or functionalities, were frequent. Technical adjustments in systems, infrastructure, and construction solutions, and normative revisions for adaptation to legal or technical requirements not initially considered, completed the panorama of changes.

Table 1. Main causes of scope changes

Category

Identified cause

Requirements

Incomplete initial survey or with a low level of detail

“Stakeholders”

Late inclusion of new stakeholders

Communication

Failures in alignment between areas and teams

Prioritization

Absence of requirement prioritization

Validation

Lack of formal validation between project phases

Complexity

High number of demands and interfaces

Evolution of understanding

Progressive elaboration of needs throughout the project

Source: Original research results

The analysis of the causes associated with these changes, as presented in Table 1, is crucial for understanding the root of scope instability. It was identified that the initial requirements gathering was, in some cases, incomplete or with a low level of detail, which generated the need for subsequent refinements. The late inclusion of new stakeholders also was a significant factor, introducing demands in advanced phases of the project. Failures in alignment between areas and teams, resulting from communication problems, contributed to the divergence of expectations. The absence of requirement prioritization made decision-making and prioritization difficult. The lack of formal validation between project phases allowed unstable definitions to advance. The inherent complexity, with a high number of demands and interfaces, and the progressive maturation of needs throughout the project, were also important causes.

These causes did not act in isolation, but in conjunction, creating an environment conducive to scope instability. Project management literature, such as the PMBOK Guide (PMI, 2021), emphasizes the importance of a robust requirements gathering, analysis, and validation process to mitigate changes. The late inclusion of *stakeholders*, for example, is a recurring problem that Freeman (1984) and Bourne (2015) address, highlighting the need for continuous and strategic engagement of interested parties from the initial phases. The absence of prioritization, in turn, hinders the management of conflicting demands and resource allocation, leading to reactive decisions and, often, rework, as observed by Kerzner (2022).

Table 2. Impacts of scope changes on the project

Dimension

Observed impact

Deadline

Increase in development time due to rework

Cost

Potential increase in costs associated with revisions

Quality

Risk of inconsistencies between project versions

Productivity

Reduction of team efficiency due to rework

Decision making

Difficulty in defining stable guidelines

Integration

Constant need for re-alignment between disciplines

Source: Original research results

The impacts of these changes on project performance, detailed in Table 2, were multifaceted and significant. Regarding the deadline, an increase in development time was observed due to the need for rework. In relation to cost, there was a potential increase associated with revisions and reprocessing. Quality was compromised by the risk of inconsistencies between different project versions. Team productivity was reduced due to rework and the constant need to redo tasks. Decision-making became more difficult, given the instability of guidelines. Finally, integration between disciplines was constantly challenged by the need for recompatibilization.

These impacts corroborate the literature that associates scope instability with negative consequences on project performance. Serrador and Pinto (2015) and PMI (2021) highlight that unmanaged changes lead to delays, budget overruns, and compromised quality. Reduced productivity and difficulty in decision-making are clear symptoms of a project operating in reactive mode, rather than proactive. The constant need for re-alignment between disciplines, in turn, evidences the loss of integration and fragmentation of work, which is particularly critical in industrial engineering projects, where interdependency between areas is high (ISO, 2020).

One of the main factors identified for the recurrence of changes was the maturity of the requirements at the time of their consolidation. Although the survey was comprehensive, many requirements were preliminary, requiring subsequent refinement. This process of progressive maturation is common in complex projects, but when not accompanied by formal control and validation mechanisms, it results in frequent scope changes. The absence of clear prioritization among requirements also contributed to the successive incorporation of new demands without structured decision-making criteria. The PMI (2021) reiterates that effective scope management requires not only the collection but also the prioritization and continuous validation of requirements.

The management of *stakeholders* also proved fragile, with the late inclusion of new demands and the revision of previously defined requirements, indicating gaps in the engagement and alignment process. Kerzner (2022) argues that projects with multiple *stakeholders* are more susceptible to requirement conflicts, making structured communication essential to align expectations. In this scenario, the phenomenon of “scope creep” was evident, characterized by the gradual expansion of the scope without formal control, often associated with the absence of structured change control processes and the difficulty in establishing clear boundaries for the project.

The lack of formal validation between the preliminary design and executive design phases also contributed to the continuity of changes. ISO 21502 (2020) recommends that the transition between phases should be accompanied by validation milestones that ensure the stability of definitions before project advancement. Thus, scope changes were not just a consequence of complexity, but a reflection of gaps in management processes, especially in prioritization, validation, and change management. These findings reinforce the importance of a structured approach to scope management and communication in projects with multiple stakeholders.

The analysis of scope changes revealed that, in addition to technical and structural factors, communication process failures played a central role in the occurrence of revisions. A large part of the alterations did not stem exclusively from new requirements, but from the way information was transmitted, interpreted, and validated among the parties involved. In projects with multiple *stakeholders*, communication is the main mechanism for aligning expectations, needs, and decisions. However, the results indicated gaps in this process, evidenced by the reinterpretation of previously defined requirements, late inclusion of demands, and the recurring need for revisions in solutions already discussed.

This evidence suggests that, although the requirements elicitation was structured, the subsequent communication did not guarantee the consolidation and common understanding of definitions. The problem was not just in information gathering, but in its management throughout the project lifecycle. The identified communication failures and their impacts on scope included: divergent interpretation of requirements, leading to changes in already defined solutions; lack of alignment between areas, resulting in the inclusion of conflicting demands; absence of formal validation, which generated successive scope revisions; unstructured communication, causing loss of requirements traceability; partial stakeholder engagement, which led to the late inclusion of needs; and lack of consolidated records, which resulted in the redefinition of decisions already made.

These communication failures not only influenced the scope but acted as vectors of instability. The absence of structured communication processes compromised the clarity of definitions and hindered change control, contributing to the gradual expansion of the scope. PMI (2021) highlights that communication management aims to ensure that project information is generated, distributed, stored, and retrieved appropriately and at the right time. The lack of structured communication increases the risk of misalignment among stakeholders and, consequently, of scope changes. Kerzner (2022) adds that communication failures are among the main causes of failure in complex projects, where multiple areas participate in the decision-making process.

In the analyzed case, communication did not act as an integrating element, but as a factor of discontinuity. The lack of formal validation mechanisms and the absence of standardization in information transmission contributed to the loss of alignment, directly reflecting in scope revisions. Thus, scope changes cannot be understood solely from a technical perspective, making it essential to consider the influence of communication processes. The integration between scope management and communication management is, therefore, critical for project stability, especially in ventures with high complexity and multiple *stakeholders*.

The comparison between the initial scope and the scope after revisions evidenced the evolution of the main project elements and the nature of the changes. The alterations were not concentrated in a single component but occurred transversally, affecting architectural, functional, and technical aspects. The predominance of changes associated with the redefinition of previously established solutions, especially in the *layout* and the organization of internal flows, indicates that the initial definitions, although based on a comprehensive survey, were not sufficiently stable. Elements treated preliminarily, such as the sizing of areas and building systems, underwent significant refinements, evidencing a progressive maturation of the scope. This phenomenon is common in engineering projects, but without structured validation and control mechanisms, it results in recurrent revisions and rework (PMI, 2021).

The scope expansion in elements such as support areas and security systems suggests that not all requirements were fully captured or prioritized in the initial phase, or that there was a late inclusion of needs by *stakeholders*. Kerzner (2022) highlights that the continuous introduction of new requirements without formal control characterizes “scope creep”. From a critical perspective, the scope changes did not arise solely from failures in the initial survey, but from the absence of effective stabilization and control mechanisms. The lack of formal validations between phases and the absence of clear requirement prioritization contributed to the reopening of already established definitions, favoring successive revisions.

The recurrence of changes in already defined elements reinforces the influence of communication failures. The reinterpretation of requirements, the need for solution readjustment, and the inclusion of new demands indicate that the information flow did not occur in a fully structured manner, compromising alignment. The PMI (2021) points to ineffective communication as one of the main factors of instability. Thus, the evolution of the scope highlights a pattern of recurring changes, associated with the combination of high complexity, multiple stakeholders, and weaknesses in communication and governance processes.

An estimated classification of scope changes throughout the project revealed the relative predominance of different types of alteration. Redefinitions of “layout” and flows represented approximately 35% of the changes, followed by changes to existing requirements (~25%), inclusion of new requirements (~20%), technical adjustments (infrastructure and systems) (~15%), and regulatory revisions (~5%). This distribution indicates that the largest share of changes is associated with the redefinition of previously established solutions, reinforcing that the scope, although initially structured, remained in constant adaptation. The significant occurrence of changes in already defined requirements and the inclusion of new demands demonstrate that the project was subject to continuous revisions, evidencing the absence of effective scope control and prioritization mechanisms, a behavior characteristic of complex environments with multiple stakeholders.

The predominance of changes related to “layout” and the redefinition of solutions indicates that the validation process of the initial definitions was not robust enough to guarantee their stability. The PMI (2021) emphasizes that formal scope validation and integrated change control are fundamental to avoid rework and ensure the consistency of deliverables. The absence of these mechanisms favors the reopening of decisions already made, resulting in successive review cycles. The representativeness of the alterations associated with the inclusion of new requirements reinforces the influence of communication failures, suggesting that not all needs were properly captured, understood, or aligned in the initial phases, or that there was no structured process for managing stakeholder expectations (Kerzner, 2022).

Technical adjustments, although representing a smaller portion of the changes, have a significant impact on the integration of disciplines and the consistency of the project. In industrial projects, technical changes tend to generate chain effects, requiring re-compatibilizations and increasing management complexity (ISO, 2020). In summary, the quantitative analysis reinforces the qualitative findings, showing that scope changes did not occur randomly, but followed a pattern associated with the absence of structured governance, lack of requirements prioritization, and, mainly, weaknesses in communication processes among stakeholders. It is concluded that the scope instability observed in the project is the result of a set of interrelated factors, in which communication plays a central role, acting as a catalyst for changes. This result reinforces the need for integration between Scope Management and communication management as an essential practice for controlling complex projects.

The integrated synthesis of the results demonstrates that scope instability was not caused by a single factor, but by the combination of project complexity, the high number of *stakeholders*, the low maturity of some requirements, and weaknesses in communication and validation processes. Although the project was initially structured based on a consistent needs assessment, this foundation was not accompanied by effective stabilization, prioritization, and governance mechanisms throughout its development. A relevant point is the difference between a comprehensive assessment and a truly stabilized scope. The breadth of functional, technical, and regulatory requirements provided initial robustness to the scope, but also increased its vulnerability to revisions, as the requirements presented different levels of maturity and criticality, without a clear hierarchy that differentiated the essential from the adjustable or postponable.

Another central aspect lies in the role of communication as a mediating element between requirements and changes. The results indicate that many alterations did not arise solely from new demands, but from the way information was shared and interpreted. In the absence of consolidated records, formal validations, and clear alignment criteria, the scope remained subject to reinterpretations, favoring continuous revisions and the reopening of decisions already made. These changes generated systemic impacts on project performance, affecting deadlines, productivity, integration between disciplines, and solution stability. This reinforces that the problem is not in the existence of changes, which are common in complex projects, but in the absence of a structured system to manage them in a controlled manner. In summary, broad and unprioritized requirements, coupled with communication failures, make the scope unstable and susceptible to successive revisions, generating rework and compromising predictability. Thus, scope management and communication are interdependent processes, whose integration is fundamental for the performance of complex industrial projects.

The prioritization matrix of critical factors associated with scope changes allowed for a strategic reading of what actually sustains scope instability. Instead of treating all factors as equally relevant, the analysis highlighted that some elements assume a central role, either due to the frequency with which they occur or the direct impact they exert on project performance. In this regard, communication failures between areas, the absence of formal validation between phases, and the lack of requirements prioritization stand out as the critical core. Communication failures, classified as high frequency and impact, with a very high priority level, directly affect the clarity of definitions, favor divergent interpretations, and drive successive scope revisions. This finding is in line with what PMI (2021) and Kerzner (2022) point out as one of the biggest challenges in complex projects: maintaining clarity and informational alignment. The absence of formal validation between phases, also with high frequency and impact, and very high priority, allows for the continuation of unstable definitions between the preliminary design and the executive project, increasing rework and the reopening of decisions. This point highlights the importance of *gate reviews* and formal validation milestones, according to ISO 21502 (2020), to stabilize the scope in each phase transition.

The absence of prioritization of requirements, which are also of high frequency and impact, and very high priority, hinders decision-making, prevents distinguishing critical from desirable requirements, and favors incremental scope expansions. Without a clear hierarchy, all demands seem equally important, leading to an “everything is a priority” situation, which in practice means nothing is a priority, according to project management literature (Kerzner, 2022). These three factors – communication, validation, and prioritization – not only originate changes but also contribute to their propagation throughout the project. Ineffective communication compromises alignment between areas; the lack of formal validations allows definitions to remain open and subject to revisions; and the absence of clear prioritization criteria hinders decision-making when faced with competing demands. Together, these aspects create an environment conducive to the recurrence of scope adjustments.

At a second level of criticality, factors such as the late inclusion of *stakeholders*, the low initial level of detail of certain requirements, and the high technical and multidisciplinary complexity of the undertaking appear. The late inclusion of *stakeholders* (medium/high frequency, high impact, high priority) introduces new needs in advanced phases, forcing revisions of already developed solutions. This is a classic *stakeholder* management problem, where the lack of initial and continuous engagement leads to the emergence of requirements at inopportune times, as discussed by Bourne (2015). The low initial level of detail of some requirements (medium frequency, high impact, high priority) requires later maturation of definitions and contributes to recurring adjustments and refinements. Although progressive maturation is natural in complex projects, the absence of initial minimum detail and control mechanisms for this maturation aggravates the problem.

The high technical and multidisciplinary complexity (high frequency, medium/high impact, high priority) increases the interdependence between disciplines and potentiates the effects of any scope change. Industrial projects, by their nature, are complex and involve multiple specialties, and managing this complexity requires robust tools and processes to prevent small changes in one area from generating major impacts in others (ISO, 2020). Finally, the progressive maturation of needs (medium frequency, medium impact, moderate priority) is a partially expected phenomenon in complex projects, but its effects are aggravated in the absence of structured governance. Although it is natural for needs to evolve, the way this evolution is managed determines whether it will be a source of innovation or instability.

From a practical perspective, this prioritization more assertively directs improvement actions. Instead of dispersing efforts, it becomes possible to concentrate interventions on the most relevant factors, increasing the effectiveness of the adopted measures. Thus, the analysis reinforces that scope stabilization depends less on isolated technical deepening and more on the implementation of consistent communication, validation, and decision-making governance practices throughout the project cycle. This finding is fundamental for project management, as it shifts the focus from solving technical problems to improving managerial processes.

The understanding of the investigated problem becomes more consistent when the results are analyzed comparatively, placing side by side the effectively observed scenario and that which could be achieved with the adoption of structured management practices. This comparison does not seek to build a precise numerical simulation, but rather to analytically highlight how the main identified problems would tend to behave in an environment with greater maturity in scope and communication governance. In the observed scenario, the project started with a comprehensive scope, but with significant weaknesses related to its stabilization. The absence of requirement prioritization and the low formalization of validation points contributed to the frequent reopening of definitions throughout the development, especially in the transition between the preliminary design and the executive project. As a consequence, previously established decisions were reviewed, generating rework, reduced team productivity, and loss of predictability in the internal schedule.

In contrast, in a scenario with the proposed improvements, a clear trend of greater control and reduction in decision-making volatility is observed. The implementation of a formal prioritization process would allow requirements to be classified according to their criticality, avoiding unnecessary scope expansions. Furthermore, the definition of formal validation milestones between phases would help prevent the advancement of immature solutions, while a structured communication plan would ensure greater clarity regarding responsibilities, information flows, and the recording of decisions. From an analytical standpoint, the main difference between the scenarios lies not in the elimination of scope changes – which would not be realistic in complex projects – but in how these changes are handled. In the observed scenario, they occur reactively, in an unstructured and cumulative manner. In the proposed scenario, however, they are filtered, evaluated, and formalized within a governance system. Thus, the most relevant gain is not scope rigidity, but an increase in its controllability, reflecting positively on the predictability, traceability, and consistency of the solutions developed throughout the project.

The comparison between the observed scenario and the proposed scenario with improvements reinforces that the main weakness of the analyzed case was not the lack of technical effort, but the low formalization of the coordination mechanisms that should support this effort throughout the project cycle. The observed scenario shows that the undertaking had a consistent initial foundation, but operated with insufficient instruments to preserve the stability of definitions in the face of the natural evolution of organizational demands. The proposed scenario, on the other hand, shifts the focus from simply reacting to changes to their structured management. This shift is fundamental, as it recognizes that complex industrial projects are unlikely to be immune to revisions; however, they can become more predictable when these revisions are filtered by formal criteria, agreed upon by stakeholders, and adequately recorded. Thus, the comparison highlights that the expected gain from the improvements is not only operational but also managerial, by strengthening project governance as a condition for greater scope stability.

Based on the analysis of the results, it became clear that reducing recurring scope changes depends on acting jointly on four key points: communication, validation, prioritization, and change control. More than isolated actions, these improvements need to function as a governance system, capable of providing greater scope stability throughout the project. The first proposed improvement is the creation of a formal process for prioritizing requirements. It was observed that the project gathered many demands, coming from different areas, but without a clear hierarchy. This hindered decisions and opened space for scope expansions. Therefore, it is recommended to classify requirements according to their criticality, urgency, regulatory impact, and adherence to the project objective, making choices more rational and transparent. This practice is aligned with PMI (2021) best practices, which emphasize the need for a structured process to manage requirements and avoid scope creep.

The second improvement involves the adoption of formal validation milestones between phases. In the analyzed case, the transition to the executive project occurred with definitions still open, which generated rework. The implementation of “gate reviews”, with formal records of decisions, helps to prevent the project from advancing with unstable premises. ISO 21502 (2020) reinforces the importance of formal control points to ensure scope stability at each project phase. The third improvement lies in the structuring of the communication plan. The results indicated failures in alignment between areas, which favored divergent interpretations. With clearer information flows, defined responsibilities, and standardized records, communication tends to become more reliable and traceable. An effective communication plan, as advocated by PMI (2021), is essential to ensure that the right information reaches the right people at the right time, minimizing misunderstandings and rework.

Finally, more rigorous change control is proposed, with prior impact analysis before any approval. This does not prevent adjustments, but ensures they are made consciously. Together, these actions make the process less reactive and much more predictable and consistent. The implementation of integrated change control, according to PMI (2021), is fundamental to evaluating the impacts of change requests before their implementation, ensuring that decisions are made in a structured manner and aligned with project objectives. The proposed action plan translates the study’s analytical findings into concrete management measures, consistent with the applied nature of the research. Its main contribution lies in the fact that the proposed actions were not developed generically, but derived directly from the critical factors identified throughout the analysis. This reinforces the internal consistency of the work, as it demonstrates that the recommendations stem from the results and not from external prescriptions disconnected from the case studied.

The proposed actions are complementary in nature. Prioritizing requirements in isolation tends to generate limited gains if not accompanied by formal validations between phases; similarly, a communication plan can lose effectiveness if there is no record of decisions and a structured mechanism for handling change requests. Thus, the action plan should be interpreted as an integrated governance architecture, whose purpose is to reduce scope instability through coordination between processes, roles, and decision criteria. From a practical perspective, it is noteworthy that such measures are compatible with industrial projects of similar complexity, as they do not necessarily require sophisticated structures, but rather managerial discipline, minimal formalization, and clarity of responsibilities. This broadens the study’s utility, as it allows its contribution to be extrapolated to organizational contexts facing analogous problems of recurrent scope revision in multidisciplinary environments.

4. Conclusion

It is concluded that the objective was achieved, as the study analyzed the impact of scope changes, associated with communications management, on the development of an engineering project in a biotechnology company. The causes of these changes, their impacts on project performance, and proposed improvements aligned with good management practices were identified. The research revealed that scope instability does not necessarily stem from failures in the initial requirements gathering, but rather from the absence of structured governance mechanisms capable of sustaining its stabilization throughout the project lifecycle. Communication failures, the lack of requirements prioritization, and the absence of formal validation between project phases were the critical factors that drove successive revisions. These weaknesses resulted in systemic impacts, such as increased rework, reduced team productivity, decision-making difficulties, and loss of schedule predictability, highlighting communication as a central catalyst for changes and the need for integrated scope and communications management.

As an inherent limitation of this research, it should be noted that the analysis was restricted to a single case study, which, although allowing for analytical depth, may limit the direct generalization of the results to other contexts. For future studies, it is suggested to expand the research to different industrial sectors and incorporate quantitative performance metrics, such as cost and deadline indicators, to validate and deepen the qualitative findings. The implementation of the proposed improvements, focused on requirements prioritization, formal validation, structured communication, and change management, is fundamental to increase predictability, traceability, and consistency in complex projects, transforming change management from a reactive to a proactive approach.

Bibliographic References

Bardin, L. 2016. Análise de conteúdo. São Paulo: Edições 70.

Bourne, L. 2015. Stakeholder relationship management: a maturity model for organisational implementation. 2. ed. Farnham: Gower.

Freeman, R. E. 1984. Strategic management: a stakeholder approach. Boston: Pitman.

INTERNATIONAL ORGANIZATION FOR STANDARDIZATION (ISO). ISO 21502:2020. 2020.: Project, programme and portfolio management Guidance on project management. Geneva: ISO.

Kerzner, H. 2020. Project management: a systems approach to planning, scheduling, and controlling. 13. ed. Hoboken: John Wiley & Sons.

Prodanov, C. C. 2013.; Freitas, E. C. de. Metodologia do trabalho científico: métodos e técnicas da pesquisa e do trabalho acadêmico. 2. ed. Novo Hamburgo: Feevale.

Project Management Institute [PMI]. 2021. A guide to the project management body of knowledge (PMBOK® Guide). 7. ed. Newtown Square: PMІ.

Serrador, P.; Pinto, J. K. 2015. Does Agile work? A quantitative analysis of agile project success. International Journal of Project Management, v. 33, n. 5, p. 1040–1051.

Yin, R. K. 2015. Estudo de caso: planejamento e métodos. 5. ed. Porto Alegre: Bookman.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving the independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated the automated reading of files, the organization of curves into current-potential matrices, the generation of the potential map, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed by device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of the results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and enhance the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used for the definition and identification of the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.