October 19, 2026
Managing expectations in artificial intelligence projects: Investigating the gaps between business and technology
Managing Expectations in Artificial Intelligence Projects: Investigating the Gaps between Business and Technology
Rivaldo Araujo Pereira Ximenes; Karina Tonelli Silveira Dias
DOI: 10.22167/2675-6528-202601374
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
The adoption of Artificial Intelligence (AI) in organizations is growing rapidly, but faces high rates of failure in the transition to production. The study aimed to analyze how the misalignment of expectations between business areas and technical teams impacts the performance of AI projects, identifying the origins of failures and proposing recommendations for governance. A quantitative and descriptive case study was conducted in an agribusiness company, with data collection via a structured questionnaire, based on the PMBOK pillars, applied to 41 professionals. The data were analyzed by descriptive statistics and variable cross-tabulation, considering scope, integration, communication, stakeholders, and risks. The results showed that most failures originated in the initial phases, especially in requirements gathering (39%) and premise definition (22%), indicating structural misalignment. A significant divergence was observed in the perception of scope between the areas, with less experienced professionals demonstrating unrealistic optimism, and the influence of seniority in validating demands. It was concluded that failure in AI projects is mostly associated with governance, communication, and scope management failures, not technological limitations. The findings indicated the need for greater interdisciplinary integration and improvement in expectation management from the project’s conception, proposing guidelines for feasibility validation and uncertainty communication.
Keywords: Organizational alignment; Communication; Scope; Governance; Requirements.
1. Introduction
The integration of Artificial Intelligence (AI) has consolidated itself as a strategic priority in modern organizations, driving innovation and efficiency across various sectors. However, despite the rapid growth in adoption and investment in AI-based solutions, a persistent paradox is observed: high rates of failure in transitioning these initiatives from the experimentation environment to production. Recent estimates indicate that only half of AI projects manage to overcome the testing phase and be effectively implemented (Challapally et al., 2025). This scenario is corroborated by global surveys, such as that of the McKinsey Global Institute (2023), which points out that only sixteen percent of companies manage to scale AI technology effectively. Such barriers to realization are not limited to computational or technical constraints, concentrating predominantly on governance and organizational alignment gaps (Borges et al., 2021). The discrepancy between the volume of AI initiatives and the low success rate in their scalability constitutes a critical problem that demands in-depth investigation from a project management perspective.
The understanding of AI in the corporate environment requires a fundamental distinction between its theoretical roots and its practical applications. While the trajectory of artificial intelligence dates back to seminal concepts such as the Turing Machine, in 1936, and evolves to current generative models (Valor Yébenes, 2024), operations in organizations focus mainly on so-called “Weak” or Narrow AI. According to Ludermir (2021), this category comprises specialized algorithmic systems, designed for data processing and solving delimited problems. It is precisely this specificity that makes their integration complex: by not possessing generalist reasoning or broad self-learning capabilities, these systems require rigorous alignment with business processes to generate tangible value, reinforcing the need for structured management. Unlike traditional software development, AI systems have an intrinsically probabilistic nature, demanding continuous refinement and depending directly on the quality and volume of available data (Jordan and Mitchell, 2015). This dynamic of technical uncertainty is a crucial factor in the allocation of corporate resources and, consequently, in the concentration of higher rates of failure.
From the perspective of Project Management, the causes of failure in these initiatives become more evident. Research with experts in AI projects, such as Schlegel, Schuler, and Westenberger (2023), identifies that the predominant obstacles are not algorithmic in nature, but rather bottlenecks in the planning and requirements definition stages. These phases are classified by the Project Management Body of Knowledge (PMBOK) as critical components of the initiation and planning processes, specifically within the performance domains of Stakeholders, Scope, and Integration (PMI, 2021). Complementarily, Kerzner (2017) argues that technological projects with high uncertainty fail, mostly, due to the absence of an integrated vision that aligns the strategic business objectives with the team’s technical capacity. This structural misalignment during planning makes the delivery of value in the implementation phase unfeasible, transforming technological potential into operational frustration.
In this scenario of uncertainty and complexity, the integration gap often manifests in the divergence of expectations between business areas and development teams. Davenport and Patil (2012) warn that data scientists are often allocated to organizations under miscalibrated premises, disconnected from the company’s culture and operational constraints. Amershi et al. (2019) deepen this analysis by demonstrating that software engineering applied to Machine Learning differs substantially from traditional methods: as AI systems operate by approximation and require continuous data refinement, attempting to manage them under a rigid and predictable scope proves ineffective. In practice, this methodological asymmetry generates conflicts of interest; while technical teams tend to prioritize automation for resource optimization, business units focus on gaining productive capacity. This misalignment compromises the project’s viability in its preliminary phases, even before the start of technical execution. Decision psychology also offers a framework for understanding this phenomenon, with Kahneman (2012) describing optimism bias and the planning fallacy, which lead managers to overestimate benefits and underestimate costs and technical limitations, resulting in misaligned expectations from the outset.
Given the foregoing, the persistence of high rates of failure in Artificial Intelligence projects, often attributed to non-technological factors, justifies the need for in-depth investigation into expectation management. The present research is guided by the central question of how the misalignment of expectations between business and technology areas impacts the failure rate in Artificial Intelligence projects. To answer this inquiry, the general objective of this study is to analyze the influence of expectation management on the performance of these initiatives. Complementarily, it seeks to identify the critical factors generating communication failures and strategic distancing, aiming to structure applied recommendations for the governance of AI projects in the context of Brazilian agribusiness organizations.
2. Material and Methods
The present research was characterized, in terms of its nature, as applied, since it was directed towards the resolution of practical and specific problems, focusing on the mitigation of governance bottlenecks in corporate Artificial Intelligence projects (Prodanov and Freitas, 2013). From the perspective of the approach, the quantitative and descriptive method was adopted, as advocated by Creswell (2010) and Gil (2017). This methodological choice was justified by the need to objectively and standardizedly measure professionals’ perception of strategic alignment and the structural causes of friction between business and technology areas.
The study was conducted in a large organization, operating in the Brazilian agribusiness sector, a segment that is experiencing significant progress in its technological maturity driven by digital transformation. Artificial Intelligence, in this context, moves away from its purely experimental nature to become integrated into corporate planning. Primary data collection took place in February 2026, and the unit of analysis consisted of the perception of professionals directly involved in AI projects within this company.
The study population comprised professionals from the organization with direct involvement in the lifecycle of Artificial Intelligence projects. The sample, non-probabilistic and selected for convenience and accessibility (Hair et al., 2009), totaled forty-one respondents (n=41). To ensure a breadth of perspectives, the sample included eighteen professionals from the Business and Management Area and twenty-three from the Technical and Data Area, encompassing different seniority levels, from employees with less than one year to specialists with over six years of experience.
The data collection instrument consisted of a structured electronic questionnaire, developed based on the knowledge areas established by the Project Management Institute (PMI, 2017), aiming to align the study with a consolidated reference in project management. To objectively measure professionals’ perception, the questionnaire was operationalized using a five-point Likert scale, with response options ranging from one (Strongly disagree) to five (Strongly agree), a model that enables the quantification of subjective attitudes (Likert, 1932).
Before the definitive application, the questionnaire was submitted to a pre-test with professionals working in the sector, a procedure recommended by Marconi and Lakatos (2017). This stage ensured the semantic clarity and validity of the data collection instrument, guaranteeing that the questions were uniformly understood by the participants. The questions were grouped into five analytical pillars: Integration, Scope, Communication, “Stakeholders”, and Risks, each evaluating specific aspects of AI project management.
The Integration pillar assessed the degree of strategic alignment and coherence between business objectives and the proposed technical solution. The Scope measured the clarity in collecting initial requirements and defining assumptions. Communication investigated the fluidity of information and the effectiveness in translating technical terminologies. The “Stakeholders” pillar analyzed the engagement of interested parties and conflict management. Finally, Risks quantified the teams’ capacity to predict and mitigate uncertainties inherent in data projects.
To formally structure the research deliverables, the methodological scope was divided into sequential phases, according to a Work Breakdown Structure (WBS). The Initiation stage ensured preliminary alignment through the elaboration of the Project Opening Term (TAP) and the mapping of “stakeholders”. Subsequently, the Planning phase consolidated the research requirements, including the refinement of the study, the structuring of the questionnaire, and the definition of the activity schedule, ensuring rigor and alignment with the proposed objectives.
The primary data processing was carried out through descriptive quantitative analysis, an approach supported by Field (2009) for the organization and summarization of results. Initially, the demographic profile of the sample was structured in absolute and relative frequencies, with the aim of mapping the area of activity and the seniority of the respondents. The Likert scale responses were converted into agreement means, grouped into the five established management pillars, allowing for a consolidated view of perceptions.
Additionally, variables were cross-referenced to compare success perspectives between the business and technology fronts, aiming to identify project stages where expectation misalignment occurred most frequently. Data processing, tabulation, and the generation of graphical representations were conducted using Microsoft Excel software. Complementarily, the research instrument asked respondents to identify the determining factors in failed or discontinued projects, and the chronological stage at which the failure originated.
Regarding the ethical aspects, the research was guided by the guidelines of Resolution No. 510/2016 of the National Health Council (CNS), ensuring the strict anonymity of respondents and the confidentiality of corporate information. Participation was strictly voluntary, formalized through the acceptance of the Free and Informed Consent Term (TCLE) provided in the introductory section of the form. Additionally, the development of the study obtained the due institutional approval from the analyzed organization for its execution, although it is recognized that the results are limited to the specific scenario of the agribusiness company.
3. Results and Discussion
The initial stage of the results analysis comprised the presentation of descriptive statistics of the primary data, focusing on the characterization of the respondents’ professional profile. This approach is fundamental to establishing the empirical basis of the research, ensuring that subsequent discussions are anchored in the reality of professionals involved in Artificial Intelligence (AI) projects within the agribusiness organization. The final sample totaled 41 professionals, all directly engaged in the lifecycle of AI projects. For a deeper understanding of misalignment dynamics, the data were stratified according to the main area of activity and the participants’ seniority level.
The distribution of participants revealed a slightly higher concentration in the technology execution front, with 23 professionals (56.1%) comprising the Technical and Development Team, which includes roles such as developers, data scientists, technical leads, project managers, and “Product Owners”. In contrast, 18 professionals (43.9%) were part of the Business and Management Team, representing the requesting and consuming area of the solutions. This imbalance, although not extreme, already signals a possible asymmetry in the representation of perspectives, which can influence the communication and decision-making dynamics in complex projects like those involving AI. In addition to the area of activity, the instrument mapped the specific experience time with Artificial Intelligence projects. The consolidated data indicated that more than half of the sample (53.7%) had less than one year of direct experience with AI solutions. This finding is particularly relevant, as it characterizes a group of professionals in the initial phase of data literacy, which can impact the capacity for critical validation of requirements and assumptions. The low maturity in AI, even in a large organization in agribusiness, as described by Contini and Martha Júnior (2010) regarding the sector’s technological evolution, suggests that digital transformation drives AI adoption, but proficiency in managing these projects is still under development. Vial (2019) corroborates that the asymmetry in the adoption of emerging technologies is an inherent phenomenon in digital transformation processes, which is clearly manifested in the sample’s profile.
With the sample profile established, the second stage of the quantitative analysis focused on measuring the perceived performance of project management practices. Using a five-point Likert scale, respondents evaluated the execution of Artificial Intelligence initiatives within the organization. The responses were consolidated into arithmetic means, segmented into the five knowledge areas based on PMBOK (2021): Integration, Scope, Communication, Stakeholders, and Risks. This procedure allowed for the establishment of an overview of the organization’s situational perception, facilitating the identification of trends and discrepancies among the surveyed groups.
The systematization of these results originated a performance ranking, as presented in Table 1. This structure allows identifying the disciplines with greater operational fluidity and those that configure systemic bottlenecks in the management of AI projects.
Table 1. Comparative Performance by Knowledge Field (Overall Ranking)
|
Rating |
Assessed Management Pillar |
Average Agreement (Scale 1 to 5) |
|
1st (Highest grade) |
Risks (Identification and prediction of failures/biases) |
3,46 |
|
2° |
Communication (Overall information flow) |
3,41 |
|
3° |
Stakeholders (Stakeholder Engagement) |
3,39 |
|
4° |
Scope (Clarity of requirements and assumptions) |
3,23 |
|
5th (Lowest grade) |
Integration (Macro strategic alignment) |
3,21 |
Source: Original research results
According to Table 1, the Risk pillar (identification and prediction of failures/biases) obtained the highest average agreement (3.46), indicating a relatively satisfactory perception of the organization’s ability to identify uncertainties. In contrast, the Integration pillar (macro strategic alignment) presented the lowest average (3.21). This contrast is a critical finding, as it reveals a dichotomy in management practices: the organization is capable of identifying risks, such as low input quality and algorithmic biases, but fails to integrate these vulnerabilities in a structured manner into strategic planning with business areas. Kerzner (2017) argues that highly complex ventures tend to fail not due to isolated technical limitations, but due to deficiencies in the articulation and integration of information. In the analyzed context, risk identification seems to fulfill a merely procedural function, serving as a formal record of compliance, without such diagnoses effectively guiding the necessary adjustments in strategic planning or project execution.
The gap in the integration of areas prompts critical reflection on the very definition of project success. De Wit (1988) argues that the perception of success is multifaceted and varies significantly according to each stakeholder’s perspective. In the investigated scenario, the absence of a shared vision between the technical and business fronts can result in technically robust solutions that are, however, dissociated from the organization’s strategic needs. The collected data ratify the existence of this divergence of expectations, evidencing the negative impacts that the lack of unity exerts on the continuity and value of Artificial Intelligence deliveries. The practical implication is that the mere identification of risks, without a robust mechanism for integrating these risks into strategic planning and decision-making, becomes an exercise of little value. It is imperative that risk management is not an isolated process, but rather an active component of project governance, where identified risks are translated into concrete mitigation and scope adjustment actions, with the active participation of all stakeholders. This requires an organizational culture that values transparent communication and interdepartmental collaboration, rather than functional silos.
In order to complement the descriptive data and provide depth to the averages obtained on the Likert scale, the research instrument asked respondents to identify the determining factors in failed or discontinued projects. This approach allowed for the identification of the main catalyst for rupture and the chronological stage at which the failure originated, grounding the analysis in the practical experiences of failure encountered by professionals. The analysis of relative frequencies corroborates the premise that the origin of failures lies in the planning stages. According to the consolidated data, 29.3% of respondents pointed to poorly defined scope as the determining factor for the rupture of original expectations. In a second layer of relevance, with an incidence of 22.0% each, are the lack of data literacy and communication failures between work fronts.
When correlating these factors with the project stage in which the problem was retrospectively diagnosed, the data indicate a high concentration in the initial stages. The requirements gathering phase accounts for 39.0% of the failure origins, while the definition of model assumptions accounts for 22.0% of the occurrences. Table 2 shows the detailed relationship of these percentages, highlighting that most bottlenecks are generated before the technical execution itself.
Table 2. Relationship between the main failure factors and the origin phase in Artificial Intelligence projects
|
Main Factor |
% of the Sample |
Origin of Failure Phase |
% of the Sample |
|
Poorly defined scope |
29,3% |
Start / Requirements Gathering |
39,0% |
|
Lack of technical knowledge |
22,0% |
Model Premise Definition |
22,0% |
|
Communication failure |
22,0% |
Other initial planning steps |
39,0% |
|
Organizational culture / Others |
26,7% |
Unidentified |
Source: Original research results
According to Table 2, “poorly defined scope” is the main failure factor (29.3%), predominantly originating from “Requirements Gathering (Initiation)” (39.0%). This finding is crucial as it shifts the focus of AI project failure from technological limitations to deficiencies in management and governance during the embryonic stages. Schlegel, Schuler, and Westenberger (2023) identified that the predominant obstacles in AI projects are not algorithmic, but rather bottlenecks in the planning and requirements definition phases, which aligns perfectly with the results presented here. “Lack of technical knowledge” and “communication failure”, both with a 22.0% incidence as failure factors, and with significant origins in “Model Assumption Definition” and “Other initial planning steps” (22.0% and 39.0%, respectively), reinforce the idea that the project’s strategic foundation lacks clarity.
The understanding of the approval of unfeasible requirements in the initial stages is grounded in behavioral economics and decision psychology. Kahneman (2012) describes optimism bias and the planning fallacy as phenomena that lead managers to overestimate benefits while underestimating costs, deadlines, and technical limitations. This behavior elucidates the formulation of misaligned expectations already in the conception phase, as excessive confidence in projected outcomes neglects the intrinsic complexities of Artificial Intelligence development. In the context of AI, this overestimation effect is intensified by technical knowledge asymmetry. The business area, lacking specialized domain knowledge about algorithm functioning, tends to structure its demands based on market perceptions and general discourse about the technology’s potential. Under pressure for immediate efficiency gains, an expectation of systemic performance and autonomy is consolidated, ignoring the real limitations of infrastructure and the maturity of the organization’s available data.
In this scenario, it would be up to the technical team to act as the validation and calibration agent for these expectations. However, a gap is observed in the exercise of this role. Wirth and Hipp (2000), when structuring the CRISP-DM model, postulate that business understanding must be mandatorily accompanied and mitigated by data understanding. This continuous validation becomes an indispensable requirement to ensure that the objectives defined by management are technically feasible given the informational repository and the infrastructure available in the organization. The analyzed data indicate that this articulation between technical knowledge and strategic demand does not occur satisfactorily. Instead of assuming the role of a validating agent, the technical team is restricted to the passive role of recording the requirements received from the business areas. As a result, critical variables related to asset quality, informational gaps, and structural constraints are not integrated into the scope, allowing the continuation of initiatives based on fragile premises that compromise the long-term viability of the project.
This process characterizes the phenomenon here named as “origin bias”. The project is initiated under expectations that are not supported by the available data assets, resulting in a misalignment that only becomes evident at the solution development and testing stage. In this context, the failure should not be attributed to technical execution or the competence of the specialists, but rather to the fragility in the initial problem formulation and the absence of validation rituals in the preliminary stages. The consolidation of these indicators reveals that 61.0% of failures originate before the start of technical development. In practical terms, this means that the largest portion of relevant deviations occurs prior to coding or model training, demonstrating that the project’s failure is determined by weaknesses in the conception stage. This data shifts the focus of the problem from the technological sphere to the management sphere, suggesting that the efficiency of an Artificial Intelligence initiative is decided long before the delivery of the final solution. This result indicates that the predominant risk lies not in the technology itself, but in the methodology for defining and structuring the problem in the embryonic stages of the project.
The complexity of this scenario is amplified by the intrinsic characteristics of Artificial Intelligence. As demonstrated by Amershi et al. (2019), systems based on machine learning diverge from traditional software development by demanding continuous adjustments and symbiotic interaction with the end-user. If the technical team designs solutions under the premise of full algorithmic autonomy with the objective of excluding the human factor, while the business area claims a decision support tool, the result is a technologically functional artifact that remains strategically innocuous from its conception. As a direct consequence, the project lifecycle produces frustration on both fronts. While the technical team comes to be perceived as the executor of structural reductions, the business area positions itself exclusively as a promoter of operational efficiency. This antagonism of roles elucidates the low performance observed in the scope pillar, as the definition of clear requirements becomes unfeasible when the fundamental premises of success diverge among stakeholders.
The identification of this pattern directs the investigation towards a critical gap in operational governance, raising the question as to why the technical team does not interrupt or calibrate the flow upon detecting inconsistencies. The explanation for this omissive stance is intrinsically associated with the seniority profile of the professionals and the power dynamics observed in the organization. The fourth empirical finding of this investigation lies in the correlation between the time of experience in Artificial Intelligence projects and the perception of scope clarity. The stratification of data by seniority level reveals a significant discrepancy between the groups, evidencing a structural bottleneck in the methodology for defining and validating initiatives. This variation indicates that professional maturity acts as a critical filter in identifying ambiguities, suggesting that lack of experience may compromise the ability to contest and refine initial requirements.
The disparity in perceptions becomes evident when contrasting professional maturity levels. Professionals with less than one year of experience in the field attribute a high average of 3.95 to the scope pillar, on a scale of 1 to 5, demonstrating an optimistic view regarding the clarity of guidelines. In contrast, specialists with experience between four and six years evaluate the same aspect with an average of only 1.90. This amplitude of 2.05 points reveals diametrically opposed views, suggesting that seniority brings with it a sharper and more critical perception of the ambiguities and risks inherent in the initial planning. This behavior can be understood in light of the Dunning-Kruger effect (Kruger and Dunning, 1999), which describes the tendency of individuals with less expertise to overestimate their own assessment and judgment capabilities. In the context of Artificial Intelligence, this cognitive distortion manifests in the validation of scopes and deadlines without due analytical rigor, not necessarily due to technical negligence, but by the temporary inability to anticipate the challenges and uncertainties inherent in this type of project. This perception gap among junior professionals ends up endorsing the original flaw, allowing initiatives with fragile planning to advance to the development stage.
The analysis of indicators suggests that professionals in the early stages of their careers tend to accept the requirements defined by the business area without due consideration for critical variables, such as data integrity, the need for continuous treatment, and the risks of model degradation over time. This behavior is exacerbated by the underestimation of infrastructure constraints, factors that generally only become noticeable through practical experience and accumulated repertoire. Consequently, the absence of a consultative stance by the junior technical team acts as a facilitator for the original flaw to persist into the more advanced stages of the project. In contrast, professionals with greater maturity demonstrate superior analytical caution in evaluating the initial scope. This stance reflects the ability to identify latent inconsistencies in planning and recognize when the expectations set by management diverge from the actual execution conditions. For the experienced specialist, the validation of an Artificial Intelligence project ceases to be a merely bureaucratic rite and takes on the character of a strategic filter, essential for mitigating the risks of failure arising from technical underestimation.
This scenario configures a latent organizational risk, as the predominance of less experienced professionals in project teams favors the validation of scopes without the necessary critical rigor. Consequently, initiatives advance to the execution phases without a consistent assessment of technical feasibility, which acts as the main catalyst for the misalignment of expectations observed in later stages. This dynamic shows that the absence of senior supervision in requirements gathering not only compromises the quality of planning but also institutionalizes the inherent flaw as a systemic failure in Artificial Intelligence management. Thus, the disparity in perception between professionals of different seniority levels ceases to be a mere divergence of opinions to consolidate as an indicator of fragility in project governance. This evidence points to a critical gap in scope control and validation mechanisms, as the feasibility of Artificial Intelligence initiatives becomes dependent on the individual maturity of the executor, rather than being guaranteed by a robust and standardized institutional process.
The consolidation of quantitative and qualitative data from this research allows us to confront the marketing premise that the high rate of failure in Artificial Intelligence projects stems primarily from technological limitations or algorithmic deficiencies. The integrated analysis of fundamental findings regarding the isolation of risk management, gaps in scope definition, incentive misalignment, and seniority disparity leads to the conclusion that the bottleneck lies in governance and communication. This scenario becomes evident when observing the contrast between the ability to identify risks, with an average of 3.46, and the difficulty in integrating them into planning, which shows a lower performance of 3.21, indicating that risks are recognized but do not influence strategic decisions. Furthermore, this misalignment does not occur sporadically but manifests consistently through divergences in organizational pressures and in the interpretation of the origin of failures.
The core of integration failures transcends organizational deficiencies, residing in a direct conflict of objectives between the work fronts. The data indicate that success metrics are interpreted differently by each group, creating a scenario where success from one area’s perspective can hinder another. This divergence of incentives fragments collective effort and prevents the technical robustness of Artificial Intelligence from effectively translating into strategic value for the institution. For the Business and Management fronts, the absolute priority lies in generating efficiency gains without reducing staff, as indicated by 36.4% of this group. From this perspective, Artificial Intelligence is perceived as an incremental support tool, aimed at increasing productivity and optimizing results without promoting disruptive changes in the current organizational structure. In contrast, from the technical staff’s perspective, the predominant pressure lies in cost reduction and staff downsizing, as indicated by 37.5% of respondents in this category. For these professionals, the strategic focus converges on the full automation of tasks, aiming to mitigate errors and minimize the need for human intervention. In this scenario, the concept of success is based on the substitution of manual activity by algorithmic processes, establishing a direct conflict with the vision of incremental support advocated by the business area.
This divergence of perspectives consolidates a structural misalignment between the areas. While the business front projects success based on efficiency gains and operational expansion, the technical body interprets demand from the perspective of automation and resource reduction. This mismatch compromises the project from its conception, as stakeholders operate under antagonistic expectations, hindering the definition of a common scope and the effective integration of deliverables. Davenport and Patil (2012) corroborate this perception by highlighting that data professionals often act in isolation from the organization’s strategic context, receiving directives devoid of the necessary alignment. This distancing causes teams to develop technically accurate solutions, but dissociated from the real business needs. In the investigated scenario, this functional isolation explains the fragility in requirements gathering and the consequent difficulty in converting algorithmic models into tangible corporate value.
The presentation of quantitative data, covering the sample profile, the critical evaluation of the scope and integration pillars, and the identification of gaps in requirements gathering, concludes the descriptive analysis stage. With the results consolidated in absolute and relative values, the next stage consists of correlating these variables to understand the behavioral patterns and governance mechanisms that underpin this scenario. This transition to qualitative and interpretive analysis aims to provide the foundation for the inferences necessary to answer the proposed research question. The results highlight a dichotomy in the company’s management practices. Although the organization shows satisfactory performance in Risk Management, with an average of 3.46, it simultaneously records its lowest score in the integration pillar, with 3.21. This contrast reveals a fragmented operational pattern in which the Data Science front identifies critical risks, such as low input quality and algorithmic biases, but these vulnerabilities are not systematically incorporated into strategic planning with the business areas.
The theoretical framework of project management corroborates this scenario. As Kerzner (2017) points out, high-complexity ventures tend to fail not necessarily due to isolated technical limitations, but primarily due to deficiencies in the articulation and integration of information. In the context of the analyzed institution, risk identification seems to fulfill a merely procedural function, serving as a formal record of compliance, without such diagnoses effectively guiding the necessary adjustments in the project’s planning or strategic conduct. The gap in inter-area integration prompts critical reflection on the very definition of project success. De Wit (1988) argues that the perception of success is multifaceted and varies significantly according to each stakeholder’s perspective. In the investigated scenario, the absence of a shared vision between the technical and business fronts can result in technically robust solutions that are, however, disconnected from the organization’s strategic needs. The collected data ratify the existence of this divergence of expectations, highlighting the negative impacts that the lack of unity exerts on the continuity and value of Artificial Intelligence deliveries.
In summary, expectation failure is a predictable consequence of management models that dissociate strategy from technological capability. The investigation revealed that the central difficulty lies in translating business needs into technically executable requirements. As argued by Provost and Fawcett (2013), the success of an analytical project depends on the precise decomposition of a corporate problem into data science tasks. When this transposition ignores infrastructure constraints and the quality of informational assets, failure becomes a systemic outcome. Thus, data governance and stakeholder management emerge as the pillars supporting or collapsing artificial intelligence-based initiatives. The absence of an analytical “translator” between departments often results in unattainable goals, generating frustration and wasting financial resources. Additionally, it was observed that the probabilistic nature of artificial intelligence clashes with the deterministic culture of traditional project management. While the business expects binary answers (yes or no), models offer confidence levels. This understanding gap reinforces the need for data literacy in executive layers, allowing the uncertainties inherent in mathematical models to be integrated into organizational risk planning, rather than treated as execution errors.
4. Conclusion
It is concluded that the objective was achieved by analyzing the influence of expectation management on the performance of Artificial Intelligence projects and identifying the critical factors that generate communication failures and strategic distancing. The research demonstrated that the failure of these initiatives, in the context of a Brazilian agribusiness organization, is not primarily due to technological limitations, but rather to deficiencies in governance, communication, and scope management, especially in the conception phases. The misalignment of expectations between business and technical areas, driven by divergent incentives and the lack of an analytical “translator”, was identified as the “original sin” that compromises the viability of projects from their initial stages. The disparity in perception between professionals of different seniority levels also contributes to the validation of fragile scopes, highlighting the need for more robust validation processes.
This study, however, has the limitation of having been conducted in a specific scenario within a single agribusiness company. For future work, it is recommended to apply the proposed guidelines – Unified KPI Matrix, Feasibility Validation Ritual, and Uncertainty Communication – in broader sectoral case studies. Such an approach would allow for the quantitative impact measurement on the reduction of technical rework and the increase in Return on Investment (ROI), validating the generalization of the recommendations and deepening the understanding of expectation management in different organizational contexts of AI projects.
Bibliographic References
Amershi, S. et al. Software engineering for machine learning: a case study. In: International Conference on Software Engineering: Software Engineering in Practice (ICSE-SEIP), 2019, Montreal. Anais… IEEE, 2019. p. 291–300.
Borges, A. F. S. et al. The strategic use of artificial intelligence in the digital era: systematic literature review and future research directions. International Journal of Information Management, v. 57, 102225, 2021.
Challapally, A. et al. The GenAl Divide: State of Al in Business 2025. MIT NANDA, 2025. Disponível em: https://cdn1.tenchat.ru/static/vbc-gostinder/2025-09-05/9f58d5ab-6724-401c-be8f-cd084e589a4d.pdf. Acesso em: 15 fev. 2026.
Contini e Martha Júnior, 2010 [Referência completa não encontrada no documento original]
Creswell, J. W. Projeto de pesquisa: métodos qualitativo, quantitativo e misto. 3. ed. Porto Alegre: Artmed, 2010.
Davenport, T. H.; Patil, D. J. Data scientist: the sexiest job of the 21st century. Harvard Business Review, v. 90, n. 10, p. 70–76, 2012.
De Wit, B. Measurement of project success. International Journal of Project Management, v. 6, n. 3, p. 164–170, 1988.
Field, A. Descobrindo a estatística usando o SPSS. 2. ed. Porto Alegre: Artmed, 2009.
Gil, A. C. Como elaborar projetos de pesquisa. 6. ed. São Paulo: Atlas, 2017.
Hair, J. F. et al. Análise multivariada de dados. 6. ed. Porto Alegre: Bookman, 2009.
Jordan, M. I.; Mitchell, T. M. Machine learning: trends, perspectives, and prospects. Science, v. 349, n. 6245, p. 255–260, 2015.
Kahneman, D. Rápido e devagar: duas formas de pensar. Rio de Janeiro: Objetiva, 2012.
Kerzner, H. Project management: a systems approach to planning, scheduling, and controlling. 12. ed. Hoboken, NJ: John Wiley & Sons, 2017.
Kruger, J.; Dunning, D. Unskilled and unaware of it: how difficulties in recognizing one’s own incompetence lead to inflated self-assessments. Journal of Personality and Social Psychology, v. 77, n. 6, p. 1121–1134, 1999.
Likert, R. A technique for the measurement of attitudes. Archives of Psychology, v. 22, n. 140, p. 1-55, 1932.
Ludermir, T. B. Inteligência Artificial e Aprendizado de Máquina: estado atual e tendências. Estudos Avançados, v. 35, n. 101, p. 85–94, 2021.
Marconi, M. A.; Lakatos, E. M. Técnicas de pesquisa. 8. ed. São Paulo: Atlas, 2017.
McKinsey Global Institute. The state of Al in 2023: generative Al’s breakout year. McKinsey & Company, 2023. Disponível em: https://www.mckinsey.com/capabilities/quantumblack/our-insights/the-state-of-ai-in-2023-generative-ais-breakout-year. Acesso em: 10 fev. 2026.
Prodanov, C. C.; Freitas, E. C. de. Metodologia do trabalho científico: métodos e técnicas da pesquisa e do trabalho acadêmico. 2. ed. Novo Hamburgo: Feevale, 2013.
Project Management Institute [PMI]. Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK®). 6. ed. Newtown Square, PA: PMI, 2017.
Project Management Institute [PMI]. Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK®). 7. ed. Newtown Square, PA: PMI, 2021.
Provost e Fawcett, 2013 [Referência completa não encontrada no documento original]
Schlegel, D.; Schuler, K.; Westenberger, J. Failure factors of Al projects: results from expert interviews. International Journal of Information Systems and Project Management, v. 11, n. 3, p. 22–39, 2023.
Valor Yébenes, J. A. Alan Turing y el origen de la inteligencia artificial: la superação de la intuição. Naturaleza y Libertad. Revista de Estudios Interdisciplinares, v. 18, p. 15–50, 2024.
Vial, G. Understanding digital transformation: a review and a research agenda. Journal of Strategic Information Systems, v. 28, n. 2, p. 118–144, 2019.
Wirth, R.; Hipp, J. CRISP-DM: towards a standard process model for data mining. In: International Conference on the Practical Applications of Knowledge Discovery and Data Mining, 2000, Manchester. Anais… p. 29–39, 2000.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq