Schedule management for field teams for multidisciplinary projects and environments with low connectivity.

Schedule Management for Field Teams for Multidisciplinary Projects and Low-Connectivity Environments.

Rafael Souza Boiani; Paula Regina Fortes

DOI: 10.22167/2675-6528-202601335

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The Brazilian forestry sector, with operations in extensive and remote areas in Mato Grosso do Sul, faces challenges in managing schedules for field teams due to low connectivity and information dispersion. The study aimed to analyze the application of project management tools to support the management of field team schedules in multidisciplinary contexts with limited connectivity. The research was an applied, descriptive, and qualitative study, employing action research in a real organizational environment. The methodology involved diagnosing the existing process, structuring a solution based on the Work Breakdown Structure (WBS), and developing an electronic form for activity registration and a structured spreadsheet for weekly planning, integrated with an automated communication routine. The results demonstrated significant improvements in data organization and standardization, communication anticipation, and schedule visibility. A reduction in dependence on recurring information requests and increased operational efficiency were observed, despite initial limitations in tool usage and field connectivity. It was concluded that the implementation of structured tools and process automation contributed to improving schedule management in challenging operational environments, highlighting the need for continuous use and refinement for the consolidation of benefits.

Keywords: Forestry; Organization; Planning; Action-research; Processes.

1. Introduction

The Brazilian forest sector holds unquestionable economic relevance, standing out as a fundamental pillar for the national economy. Its contribution is evidenced by a strong participation in exports, significant job creation, and robust industrial production. According to the Brazilian Tree Industry (IBÁ, 2025), the sector reached approximately 15.7 billion dollars in exports and generated about 240 billion reais in revenue. Furthermore, it supports over 2.8 million jobs, both direct and indirect. The planted forest area in the country, which reaches approximately 10.5 million hectares, consolidates Brazil’s position as one of the main global producers of pulp and its derivatives.

In the national scenario, the state of Mato Grosso do Sul has stood out as a primary expansion vector for the forestry sector. IBÁ (2025) indicates that about eighty percent of the expansion of planted areas in Brazil in two thousand and twenty-four occurred in this state, representing an increase of approximately 234 thousand hectares. This growth is driven by the vast availability of land, regional incentives, and the installation of large industrial enterprises. The strategic relevance of silviculture is further emphasized by its growing participation in the agricultural Gross Domestic Product, as indicated by the Brazilian Institute of Geography and Statistics (IBGE, 2023). The Ministry of Agriculture and Livestock (MAPA, 2022) complements this perspective, highlighting Brazil’s competitive advantages in the sector, such as high productivity and favorable climatic conditions.

Despite this growth scenario and the adoption of technologies, forestry operations present relevant challenges, mainly because they occur in extensive and remote areas, with limitations in infrastructure and connectivity. Under these conditions, field data collection still depends, in many cases, on manual processes or decentralized records, which need to be subsequently consolidated into corporate systems. This dependence results in delays in information availability, data inconsistencies, and the need for rework, compromising the agility and reliability of internal processes. The limitation of connectivity in the field and the dependence on manual data collection impact the availability and reliability of information, reducing visibility of the progress of activities and hindering standardization, monitoring, and decision-making.

These operational limitations directly impact project management, especially in schedule planning and control. Project management, according to the Project Management Institute (PMI, 2021), consists of applying knowledge, skills, and techniques to execute activities with the objective of meeting established requirements for deadline, cost, and quality. Tools such as the Work Breakdown Structure (WBS) allow for the decomposition of scope into manageable packages, while the schedule organizes activities over time, being essential for monitoring project progress. The schedule is one of the main control instruments, as it enables continuous monitoring of activities and the adoption of corrective actions. However, its effectiveness directly depends on the quality and updating of the information used (PMI, 2019). The lack of updated and integrated information, characteristic of the forestry sector in remote environments, compromises monitoring, hinders the identification of deviations, and the adoption of corrective actions in a timely manner, highlighting a significant gap between ideal project management practices and operational reality.

Given this context, the gap between ideal project management practices and the operational reality of the forestry sector, marked by low connectivity and information dispersion in multidisciplinary environments, justifies the present investigation. This work aimed to analyze the application of project management tools to support the schedule management of field teams in multidisciplinary contexts with limited connectivity.

2. Material and Methods

The research was classified as applied in nature, seeking the solution to a practical problem in a real organizational environment, through the development and implementation of tools to support schedule management. Regarding the objectives, the study was descriptive, aiming to analyze the results obtained from the application of the proposed solution. The methodological approach was predominantly qualitative, although it incorporated quantitative elements for the analysis of the results. The research design was characterized as action research, involving direct participation in problem identification, solution development, tool implementation, and results monitoring, aligning with applied research approaches in organizational contexts (BIGATON et al., 2024).

The study was conducted in the municipality of Três Lagoas, located in the state of Mato Grosso do Sul, in an organization active in the forestry sector. The specific context of the research involved a technology management department responsible for meeting multidisciplinary demands, characterized by the need to organize information, track deadlines, and improve communication among teams. The unit of analysis focused on the schedule management processes and existing communication practices within this department, before and after the implementation of the proposed tools. The research period covered the diagnostic, development, and initial application stages of the tools, contextualized in the year 2026.

Considering the action-research design, the study’s population and sample were intrinsically linked to the organizational environment where the intervention took place. The research directly involved the field teams and the technology management of the forestry sector organization in Três Lagoas, Mato Grosso do Sul, which dealt with multidisciplinary demands and connectivity limitations. There was no formal statistical sampling, but rather the full participation of employees and processes affected by the identified problem. The selection criteria were defined by direct involvement in forestry operations and schedule management, with the participants being the users and beneficiaries of the developed tools themselves.

The data collection began with an in-depth diagnosis of the existing schedule management process within the organization. This stage was carried out through direct observation of operational activities and analysis of the current practices adopted by the teams for schedule planning and control. Existing records and information flows were examined to identify difficulties related to the absence of structured tools, reliance on manual processes, and low visibility of activity progress. This initial survey provided the basis for understanding the gaps and the subsequent structuring of the proposed solution, guiding the development of the tools.

For the continuous data collection and management support, specific tools were developed. The first instrument consisted of an electronic form, designed for the standardized recording of activities performed by field teams. This form captured essential information such as activity date, resource identification, initial and final mileage, person responsible for execution, support team, location, quantity performed, area, activity type, activity/experiment identifier, requesting area, demand responsible, data sent, travel time, activity start and end, labor quantity, and observations. The second instrument was a structured spreadsheet, used for weekly planning and schedule consolidation.

Table 1. Activity monitoring form structure

Question / field

Note

Activity Date

Required field

Resource (vehicle) identification

List + “Other” option

Initial KM

Required field

Final KM

Required field

Responsible for execution

Nominal list

Support team

When applicable

Location (farm/plot)

Required field

Quantity realized

Production area or unit

Area (ha)

Conditional field

Quantity of units

Conditional field

Type of activity performed

Standardized list of activities

Activity/experiment identifier

Required field

Requesting Area

List of technical areas

Responsible for the demand

Required field

Source: Original research results

The research execution followed a structured sequence, starting with the diagnosis of the existing process, as detailed previously. Subsequently, the proposed solution was structured, organizing the work steps and the necessary components for the development of the tools. For this purpose, the Work Breakdown Structure (WBS) was employed, a technique recommended by good project management practices (PMI, 2021). The WBS allowed for the hierarchical decomposition of activities, ranging from the initial diagnosis to the evaluation of the application. This structure was organized into five main groups: process diagnosis, solution structuring, implemented tools, automated communication, and initial application evaluation.

After structuring the solution, the development of support tools proceeded, which included structured spreadsheets and the electronic form, designed to organize, control, and monitor activities. These tools were designed to facilitate information recording, deadline tracking, and improve communication among the teams involved in forestry operations. Subsequently, the tools were implemented in the real organizational environment, becoming routinely used for activity monitoring and schedule control. The implementation phase was followed by a period of continuous monitoring of the tools’ usage, aiming to observe changes and impacts on the management process.

A crucial component of the implemented solution was the automated communication routine. This routine was developed to consolidate the information recorded in the electronic form and the weekly scheduling spreadsheet, and then distribute it in a standardized manner to stakeholders. The automation of weekly schedule sending aimed to reduce the dependence on individual information requests and minimize the volume of messages exchanged between teams, contributing to the anticipation of communication and the improvement of schedule visibility. The routine was structured in stages of reading, processing, and distributing information, ensuring the efficient dissemination of updated data.

The data analysis was performed qualitatively, focusing on the observed changes in the schedule management process after the implementation of the tools. The data for analysis were obtained from direct observation of the process, both before and after the intervention, from the analysis of existing records, and from operational data generated by the developed tools themselves. The evaluation focused on aspects such as information organization, deadline control effectiveness, activity standardization, schedule visibility, communication quality, and decision-making support. This approach allowed for the identification of the proposed solution’s impacts on the operational environment.

Regarding ethical procedures, measures were taken to ensure the confidentiality of the collected information. The data presented in the study were anonymized and adapted, when necessary, to preserve the structure and logic of the tools used, without compromising the privacy or security of those involved. Concerning methodological limitations, it is important to highlight that the study was conducted in a single organizational context. This characteristic, inherent to action research in a real environment, may restrict the generalization of results to other organizations or scenarios with different operational and cultural particularities. However, the depth of analysis in the specific context was maintained.

3. Results and Discussion

The implementation of the tools developed in this study revealed a set of significant and multifaceted changes in the activity schedule management process, positively impacting the organization of information, planning, and communication among teams. The proposed solution, anchored in an electronic form for activity registration and a structured spreadsheet for weekly planning, integrated with an automated information submission routine, proved to be a catalyst for operational optimization in a challenging environment, characterized by multidisciplinary demands and connectivity limitations.

The electronic form, in particular, has reached a more advanced stage of usage maturity, with approximately two months of continuous application. This period of use has allowed for the standardized consolidation of field data, a crucial advancement for information quality. The standardization of records is a fundamental pillar in project management, as advocated by the Project Management Institute (PMI, 2021), which emphasizes the importance of consistent data for effective monitoring. Before implementation, data dispersion and inconsistency were significant barriers to schedule visibility and decision-making. With the form, the collection of essential information such as activity date, resource identification, mileage, responsible parties, location, quantity completed, activity type, and travel time began to follow a predefined model. This structuring not only facilitated recording but also ensured that critical information was not omitted, reducing ambiguity and rework in consolidation. The literature on project management information systems, such as that discussed by Kerzner (2017), reiterates that the quality of input data is directly proportional to the usefulness of the generated information for performance control and analysis. The maturity in the use of the form suggests a successful learning curve on the part of users, indicating that the tool has been assimilated and integrated into daily routines, an essential step for the sustainability of improvement.

In contrast, the weekly scheduling spreadsheet, while equally vital, was in an early stage of application, with approximately three weeks of use. This difference in usage maturity is a critical factor to consider in the analysis of results, as initial-stage processes tend to exhibit greater operational variability and may encounter greater resistance from collaborators affected by the change in routine. The implementation of new tools and processes, especially those that alter established workflows, frequently faces challenges related to cultural adaptation and the need for continuous training (DOBRANSKY; KOTLER, 2018). However, even in its initial phase, the spreadsheet already demonstrated its potential as a central planning tool, contributing to the consolidation of activities in a single environment. This centralization favored the visualization of the schedule and the definition of priorities, essential elements for the effective management of complex and multidisciplinary projects. The ability to visualize the schedule in an integrated manner, as illustrated in the spreadsheet’s structure, allows managers to identify bottlenecks, allocate resources more efficiently, and respond proactively to deviations.

Source: Original research results

Figure 1. Work Breakdown Structure (WBS) of the proposed solution

Figure 1, which represents the Work Breakdown Structure (WBS) of the proposed solution, demonstrates the systematic approach adopted for the development and implementation of the tools. The WBS, as described by PMI (2021), is a hierarchical decomposition of the total scope of work to be carried out, organized into smaller, more manageable work packages. In the context of this study, the WBS was divided into five main groups: process diagnosis, solution structuring, implemented tools, automated communication, and initial application evaluation. This detailed structuring was fundamental to ensuring that all necessary steps were covered, from understanding operational difficulties and connectivity limitations to the development of the activity registration form and the weekly scheduling spreadsheet, and the automated communication routine. The clarity provided by the WBS not only guided the development of the tools but also served as a map for the team, ensuring that the project remained aligned with the defined objectives and requirements. The application of the WBS, therefore, is not merely a methodological formality but a practice that confers robustness and predictability to the project management solution development process.

The improvement in information organization was one of the most evident results of the implementation. A significant reduction in data dispersion and an increase in record standardization were observed. Previously, the absence of structured tools resulted in fragmented information, stored in different locations and formats, hindering consolidation and analysis. The centralization of data through the electronic form and the weekly spreadsheet created a unique and consistent repository, facilitating access and retrieval of information. This standardization is crucial for data integrity and for generating reliable reports, which are the basis for strategic and operational decision-making (PMI, 2019). The ability to have organized and standardized data allows technology management and field teams to operate with greater efficiency, minimizing errors and rework due to inconsistent or incomplete information. The literature on information management, such as that of Davenport and Prusak (1998), highlights that the organization and accessibility of information are critical factors for competitive advantage and organizational effectiveness.

The automated communication routine represented a substantial advancement in the information dissemination process. By consolidating data recorded in the electronic form and the weekly schedule spreadsheet and distributing it in a standardized and recurring manner to stakeholders, this automation drastically reduced the dependence on individual information requests and minimized the volume of messages exchanged between teams. This reduction of communication “noise” is a notable benefit, as ineffective communication is frequently cited as one of the main causes of project failure (PMI, 2021). The anticipation of communication, i.e., the proactive availability of information, transformed a reactive model into a proactive one. Previously, teams and managers had to request updates, which caused delays and interruptions. Now, information is made available regularly, allowing all involved parties to have a clear and up-to-date view of the schedule without the need for constant manual intervention. This behavior aligns with best practices in project planning and communication, where predictability and information availability are relevant factors for operational efficiency (PMI, 2021). Automation not only optimized the information flow but also freed up employees’ time, who previously dedicated part of their routines to responding to status requests, allowing them to focus on higher value-added activities.

Despite the advances observed, the effective use of the information made available is not guaranteed by its mere presence. This finding highlights the importance of factors related to participant engagement and tool adoption. Technology, by itself, does not solve organizational problems if there is no culture of use and appreciation of information. Resistance to change, lack of discipline in filling out the form, and access difficulties due to field connectivity are challenges that persist and require continuous attention. The literature on change management, such as Kotter’s (1996), emphasizes that the implementation of new tools requires not only the technology but also a process of convincing and training users so that adoption is complete and benefits are maximized. The sustainability of improvements depends on continuous effort to reinforce the importance of using the tools and to integrate these new practices into the organizational culture.

The electronic form structure, as detailed in Table 1 of the Materials and Methods section, was designed to capture a wide range of operational data, from the date and location of the activity to the amount of labor and specific observations. The inclusion of mandatory fields for critical information, such as the activity date, initial and final mileage, and the person responsible for execution, ensures the completeness of the records. The use of standardized lists for “Resource identification (vehicle)”, “Type of activity performed”, and “Requesting area” contributes to data uniformity, facilitating analysis and the generation of aggregated reports. Conditional fields, such as “Area (ha)” and “Quantity of units”, which become relevant depending on the type of activity, demonstrate the tool’s flexibility to adapt to the diverse multidisciplinary demands of technology management. This granularity and standardization of input data are essential for activity traceability and performance evaluation, allowing the organization to identify trends, optimize processes, and allocate resources more strategically.

Table 2. Synthesis of the effects of the implementation of tools in schedule management

Aspect

Observed result

Organization

Improved

Planning

More structured

Communication

More organized

Message volume

Reduced

Data availability

Advance

Visibility

Expanded

Source: Original research results

Table 2 synthesizes the main effects observed after the implementation of the tools, offering a comparative view of schedule management aspects. Regarding Organization, there was a transition from a “Non-standardized” state to “Improved”. This improvement is a direct reflection of data structuring via form and spreadsheet, which eliminated dispersion and inconsistency, allowing for a unified view of operations. Planning, previously “Limited”, became “More structured”. The weekly spreadsheet, even in its initial phase, provided an environment for systematic activity scheduling, aligning with the need for a clear and executable work plan. Communication, which was “Reactive”, became “More organized” and “Proactive”. The automated routine of sending the weekly schedule ensured that information reached stakeholders proactively, reducing the need for requests and the Volume of messages, which was “Reduced”. Data availability, previously restricted, became “Anticipated”, and schedule Visibility, which was “Restricted”, was “Expanded”. These results corroborate the project management literature, which highlights effective communication and progress visibility as critical factors for success (PMI, 2019). The improvement in all these aspects indicates that the proposed solution successfully addressed the gaps identified in the initial diagnosis, promoting a more transparent and collaborative work environment.

Another relevant factor identified relates to the operational conditions of the environment, especially the limitation of connectivity in the field. In the previous scenario, this limitation made it difficult to access and update information in real-time, directly impacting schedule management. Field teams frequently operated in remote areas where internet connection was intermittent or nonexistent, forcing reliance on manual records that were consolidated later, generating delays and inconsistencies. The implemented solution contributed to partially mitigate this problem by structuring and centralizing information, allowing for better organization and subsequent data access, even if not in real-time in all situations. Although connectivity remains an inherent challenge in the forest environment, the ability to record data *offline* (when the form allows) and synchronize it later, or to have a system that stores and processes data centrally, minimizes the impact of the lack of immediate connectivity. This finding highlights the importance of developing technological solutions that consider the particularities of the operational environment, such as robustness and the ability to operate in adverse conditions, as discussed by authors like Laudon and Laudon (2016) in management information systems.

Regarding planning, the weekly schedule was structured based on a previously defined work plan. However, deviations between the planned and the executed are still observed. The main contribution of the tools, in this aspect, was not the elimination of deviations, but rather the increase in visibility regarding their occurrence. Previously, deviations could go unnoticed for long periods, accumulating negative impacts on the schedule and resources. With the tools, the discrepancy between what was planned and what actually happened became more easily identifiable. This result aligns with the principles of schedule control, in which continuous monitoring of activities allows for the identification of variations and supports decision-making (PMI, 2021). The visibility of deviations is the first step towards adopting effective corrective actions. Instead of simply recording what was done, the tools allow for a direct comparison with what *should have been done*, providing valuable *insights* for the continuous improvement of planning and execution processes. The ability to quickly identify deviations allows managers to analyze their causes, implement adjustments, and learn from past experiences, a fundamental cycle for project management maturity.

In general, the results indicate that the proposed solution contributed significantly to the improvement of the schedule management process, especially in information organization, planning, and communication. However, the results still reflect an initial stage of implementation maturity, requiring a longer period of use for the consolidation of practices and the evolution of the model. Action research, by its nature, is an iterative process involving cycles of planning, action, observation, and reflection (BIGATON et al., 2024). The current phase represents the completion of one of these cycles, and the remaining challenges, such as operational discipline in filling out the form and full adaptation to the weekly spreadsheet, point to the need for additional improvement cycles. The continued use of the tools and the active engagement of stakeholders are crucial for the benefits to solidify and become an integral part of the organizational culture. The transition from weekly scheduling to monthly scheduling, more aligned with the annual work plan, and the continuous improvement of control and monitoring mechanisms for activities are evolutionary perspectives that can lead to an even higher level of efficiency and predictability in schedule management.

4. Conclusion

It is concluded that the objective was achieved, by analyzing the application of project management tools to support the schedule management of field teams in multidisciplinary contexts and with limited connectivity.

The proposed solution, composed of an electronic form for activity registration and a weekly scheduling spreadsheet, integrated with an automated communication routine, proved to be effective.

A significant improvement was observed in the organization of information, with a reduction in data dispersion and greater standardization of records.

Communication between teams became more organized and proactive, and schedule visibility was enhanced, allowing for more efficient activity monitoring and early identification of deviations.

Despite the advances, the study identified important limitations.

The implementation is still in an early stage of maturity, especially the weekly programming spreadsheet, and the effective use of information depends on the operational discipline of users in filling out the form.

Connectivity difficulties in the field, although partially mitigated, persist as an inherent challenge in the environment.

Furthermore, having been conducted in a single organizational context, the generalization of the results may be limited.

For future studies, it is suggested that the application of the tools be continued for a more extended period, aiming at the consolidation of practices and the evolution of the model.

It is fundamental to invest in strategies to increase user engagement and improve the discipline in data recording.

The transition from a weekly to a monthly schedule, more aligned with the annual work plan, and the development of more robust control and monitoring mechanisms are perspectives for further improving schedule management in challenging operational environments.

Bibliographic References

BIGATON, Aline et al. Metodologias de pesquisa para trabalhos de conclusão de curso. Piracicaba: Editora PECEGE, 2024.

BRASIL. Ministério da Agricultura e Pecuária. Diretrizes do agronegócio brasileiro. Brasília: MAPA, 2022.

Davenport and Prusak, 1998 [Full reference not found in the original document]

DOBRANSKY; KOTLER, 2018 [Full reference not found in the original document]

IBGE – BRAZILIAN INSTITUTE OF GEOGRAPHY AND STATISTICS. Production of vegetal extraction and silviculture 2023. Rio de Janeiro: IBGE, 2023.

IBÁ – BRAZILIAN TREE INDUSTRY. Annual Report 2025. São Paulo: IBÁ, 2025.

Kerzner, 2017 [Full reference not found in the original document]

Kotter, 1996 [Full reference not found in the original document]

Laudon and Laudon, 2016 [Full reference not found in the original document]

PROJECT MANAGEMENT INSTITUTE. A guide to the project management body of knowledge (PMBOK® Guide). 7th ed. Newtown Square: PMI, 2021.

PROJECT MANAGEMENT INSTITUTE. Practice standard for scheduling. 2nd ed. Newtown Square: PMI, 2019.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and enhance the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used for the definition and identification of the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.