Schedule management for the creation of a digital video production company in Viçosa-MG

Pedro Dias de Jesus Ferreira; Emilio Antonio Amstalden

DOI: 10.22167/2675-6528-202601309

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The growing demand for audiovisual content for social networks has made schedule management relevant in creative and small-scale initiatives. Schedule management practices adopted in the creation and launch project of a video production company were evaluated, in light of the PMBOK guidelines, comparing formalized planning with actual execution, in order to identify deviations and propose improvements. The research was applied in nature, with exploratory-descriptive objectives, a mixed approach, and a single case study design. Data were collected through documentary research, semi-structured interviews, and participant observation, with subsequent triangulation of evidence. The results showed that the schedule evolved from an initially poorly formalized organization to more structured planning, with definition of dates, responsibilities, and recording windows. However, execution remained conditioned by the partners’ availability, dependence on third parties, operational problems, and the frequent need for replanning. Intuitive temporal protection practices were also observed, such as date reservations and double recording windows, but without institutionalization of systematic routines for comparing planned with actual. It was concluded that there were relevant advances in schedule planning, but limitations persisted in temporal control and managerial learning, indicating the need for more consistent records, operational alternatives, and formal monitoring mechanisms.

Keywords: Managerial learning; Case study; Operational uncertainty; PMBOK; Replanning.

1. Introduction

The growing adoption of digital media as the primary means of communication between organizations and their audiences has intensified the demand for projects focused on the systematic production of audiovisual content. In this scenario, social media platforms are no longer mere dissemination channels, transforming into strategic assets for value generation, engagement, and institutional positioning. Projects of this nature, especially small-scale ones with a focus on digital content, are characterized by high dynamism, short delivery cycles, multiple interdependencies between activities, and a strong reliance on meeting deadlines, which elevates schedule management to a critical factor for the venture’s success (Kerzner, 2022; PMI, 2021). The relevance of this context is reinforced by robust empirical data: in 2023, internet access reached 88.0% of people aged ten and over in Brazil, and 72.5 million households in the country had internet access (Instituto Brasileiro de Geografia e Estatística [IBGE], 2024; Núcleo de Informação e Coordenação do Ponto BR, 2025). This digital penetration has transformed social media into central spaces for symbolic circulation and interaction, marked by speed, interactivity, and a heightened sensitivity to publication timing (Nascimento, 2016; Vermelho et al., 2014).

Project management has been consolidated as an essential discipline for organizations of different sizes and sectors, including those operating in creative and digital environments. According to the Project Management Institute (PMI, 2021), the structured application of management practices contributes significantly to greater predictability, better resource allocation, and, consequently, to an increased probability of project success. However, creative projects, such as those in audiovisual production and digital content, frequently face challenges inherent to informal processes, overlapping roles, and the difficulty of accurately measuring activity duration, factors that can compromise the project’s temporal performance (Kerzner, 2022). Among the various knowledge areas of project management, schedule management stands out for its importance in coordinating the activities necessary for delivering project products within the established deadline. This area encompasses processes such as defining and sequencing activities, estimating duration, developing the schedule, and controlling deviations throughout execution (PMI, 2021). Specialized literature indicates that failures in these stages are among the main causes of delays, rework, and cost increases in organizational projects (Meredith and Mantel, 2018; Vargas, 2018). In digital content projects, failure to meet deadlines, in addition to compromising operational execution, directly affects the consistency of the organization’s presence on digital platforms.

The analysis of projects aimed at the production of audiovisual content for social networks therefore becomes especially relevant. In digital environments characterized by frequent updates, competition for attention, and the need for continuous presence, the regular publication of content depends on organizational capacity to plan, execute, and control production flows in short cycles. Although the literature recognizes flexibility as an important characteristic of creative projects, it also points out that these contexts operate in changing, complex, and unpredictable environments, requiring effective articulation between adaptation and coordination (Pires and Varajão, 2024). In the context of small organizations and emerging projects, such as “startups” and digital production companies in their initial phase, the formal application of schedule management practices tends to be limited, often replaced by intuitive or informal decisions. Although this approach may offer short-term flexibility, studies indicate that the absence of structured planning and systematic control mechanisms compromises the consistency of deliverables and hinders business scalability (Carvalho and Rabechini Jr., 2019; Shenhar et al., 2016). The literature on project schedule management, although consolidated (PMI, 2021; Kerzner, 2022; Meredith and Mantel, 2018), predominantly focuses on traditional sectors such as engineering and construction. There is, therefore, a research gap addressing the application and adaptation of schedule management practices in digital content production projects, especially in small organizations with lean structures, which justifies the need for case studies in this specific context.

Given this scenario, it becomes essential to investigate how the practices recommended by the PMBOK can be applied and adapted to small-scale creative projects, contributing to the improvement of temporal performance. Thus, this study is justified by the need to understand the dynamics of schedule management in an environment of high uncertainty and limited resources, providing practical insights for the improvement of project management in the digital media sector. The objective of this research is to evaluate the schedule management practices adopted in the project of creation and launch of a video production company, in light of the PMBOK guidelines, comparing the formalized planning with the actual execution, in order to identify deviations and propose improvements in the project’s schedule management.

2. Material and Methods

This research was characterized as a study of an applied nature, seeking to generate knowledge aimed at the practical improvement of project schedule management, according to the classification proposed by Gil (2017). Regarding the objectives, an exploratory and descriptive approach was adopted, aiming to provide a greater understanding of the structuring and execution of schedule planning and control practices, in addition to describing the project’s temporal performance throughout its implementation, in line with the definitions by Gil (2017) and Vergara (2016).

The methodological approach employed was mixed, combining qualitative and quantitative elements. This allowed for the objective measurement of deadlines and the interpretive analysis of the perceptions of those involved in the project. The chosen methodological design was a single case study, considered adequate for an in-depth investigation of a contemporary phenomenon embedded in its real context, according to the guidelines of Yin (2018) and Gil (2019), ensuring a detailed and contextualized analysis.

The research environment corresponded to a small-sized organization, active in the audiovisual production and digital content creation for social networks sector. The company is located in the municipality of Viçosa, in the Zona da Mata region of Minas Gerais, and is characterized by a lean organizational structure, limited financial resources, and predominantly local operation. To preserve the confidentiality of the analyzed information, the organization’s name and its address were not disclosed in this study.

The research context was inserted into the creation and launch project of this audiovisual production company, which constituted the central object of study of the work. The project aimed to structure the regular production and publication of digital videos focusing on local content, seeking to consolidate the production company’s presence on social media platforms. The project began in the second half of 2025, with an estimated temporal horizon of twelve weeks for the analyzed pilot phase.

Four professionals directly participated in the project, performing functions related to project management, creative direction, activity organization, and resource and material management. These individuals were actively involved in all stages of project planning, execution, and control. Three of these professionals were selected for the interviews, excluding the researcher, to mitigate potential biases in data collection.

Data collection was carried out through three complementary techniques: documentary research, semi-structured interviews, and participant observation. Documentary research was used to analyze the formal records of the project, allowing us to understand how the scope and timeline were defined, adjusted, and executed over time, according to the recommendations of Gil (2019), Lakatos and Marconi (2017), and Yin (2018).

Several internal project documents were analyzed, including meeting minutes, preliminary schedules, planning records, and activity organization materials. Furthermore, participant observation records prepared by the researcher were used. These documents were carefully identified, cataloged, and analyzed, as detailed in Table 1, which presents the list of consulted materials and their respective access dates.

Table 1. Analyzed documents

Document title

Document type

Access date

Observations

Minutes of the 1st Ordinary Meeting

Electronic

04/09/2025

Initial project structure

Observation Record – 1st Ordinary Meeting

Electronic

04/09/2025

Initial project structure and observer perceptions

Minutes of the 1st Extraordinary Meeting

Electronic

25/09/2025

Schedule and first recording script

Observation Record – 1st Extraordinary Meeting

Electronic

25/09/2025

Schedule and first recording script and observer insights

Recording Observation Log (09/27/2025)

Electronic

27/09/2025

Follow-up of the plan, unforeseen events, delays, time control, impact on the schedule

Minutes of the 2nd Ordinary Meeting

Electronic

02/10/2025

Splitting of videos for editing

Observation Record – 2nd Ordinary Meeting

Electronic

02/10/2025

Division of videos for editing and observer perceptions

Minutes of the 2nd Extraordinary Meeting

Electronic

16/10/2025

Definition of goals and expectations; recording schedule

Observation Record – 2nd Extraordinary Meeting

Electronic

16/10/2025

Definition of goals and expectations; recording schedule and observer perceptions

Recording Observation Log (10/18/2025)

Electronic

18/10/2025

Follow-up of the plan, unforeseen events, delays, time control, impact on the schedule

Recording Observation Log (10/19/2025)

Electronic

19/10/2025

Follow-up of the plan, unforeseen events, delays, time control, impact on the schedule

Recording Observation Log (10/25/2025)

Electronic

25/10/2025

Follow-up of the plan, unforeseen events, delays, time control, impact on the schedule

Observation Log – WhatsApp (10/30/2025 to 11/06/2025)

Electronic

30/10/2025

Operational problems, deadline adjustments, and postponement of the first video publication date

Minutes of the 3rd Extraordinary Meeting

Electronic

08/11/2025

Launch of the first video

Observation Record – 3rd Extraordinary Meeting

Electronic

08/11/2025

Launch of the first video and observer insights

Minutes of the 3rd Ordinary Meeting

Electronic

13/11/2025

Schedule of publications and editions

Observation Record – 3rd Ordinary Meeting

Electronic

13/11/2025

Schedule of publications and editions and observer perceptions

Recording Observation Log (21/11/2025)

Electronic

21/11/2025

Follow-up of the plan, unforeseen events, delays, time control, impact on the schedule

Recording Observation Log (11/22/2025)

Electronic

22/11/2025

Follow-up of the plan, unforeseen events, delays, time control, impact on the schedule

Minutes of the 4th Extraordinary Meeting

Electronic

27/11/2025

Adjustments to the publication schedule

Observation Record – 4th Extraordinary Meeting

Electronic

27/11/2025

Adjustments in publication schedule and observer perceptions

Recording Observation Log (06/12/2025)

Electronic

06/12/2025

Follow-up of the plan, unforeseen events, delays, time control, impact on the schedule

Minutes of the 4th Ordinary Meeting

Electronic

18/12/2025

Adjustments to the publication schedule

Observation Record – 4th Ordinary Meeting

Electronic

18/12/2025

Adjustments in publication schedule and observer perceptions

Recording Observation Log (12/23/2025)

Electronic

23/12/2025

Follow-up of the plan, unforeseen events, delays, time control, impact on the schedule

Minutes of the 5th Ordinary Meeting

Electronic

08/01/2026

Adjustments to the publication schedule

Observation Record – 5th Ordinary Meeting

Electronic

08/01/2026

Adjustments in publication schedule and observer perceptions

Observation Log – WhatsApp (01/16/2026)

Electronic

16/01/2026

Cancellation of recordings and adjustment of deadlines

Interview – T Partner

Electronic

06/02/2026

Interview script available in appendix at the end of this article

Interview – Partner M

Electronic

12/02/2026

Interview script available in appendix at the end of this article

Interview – Partner A

Electronic

13/02/2026

Interview script available in appendix at the end of this article

Source: Original survey data

The interviews conducted were characterized as semi-structured, combining a pre-established set of questions with the flexibility needed to delve into emerging themes. According to Vergara (2016) and Gil (2019), this type of interview is particularly indicated for understanding participants’ perceptions, experiences, and interpretations of organizational processes, providing rich and contextual data for analysis.

The three professionals interviewed, directly involved in the project, addressed topics such as schedule planning, activity duration estimates, logical sequencing, deadline control, and difficulties encountered during execution. The interviews were conducted remotely, using the “WhatsApp” application, in the first semester of 2026, and the interviewees’ statements were recorded via text messages, with the complete script available in Appendix A.

Participant observation was employed with the objective of directly observing the execution of schedule management practices, allowing the researcher to record behaviors, interactions, and decisions related to meeting deadlines. According to Lakatos and Marconi (2017) and Vergara (2016), this technique offers greater proximity to the phenomenon studied, favoring the understanding of aspects that are not always explicitly stated in documents or formal interviews.

The observation occurred in planning meetings, during recording activities, and at moments of follow-up and decision-making related to the schedule. Records were made by taking notes on a “smartphone” notepad by the researcher. Subsequently, these notes were organized and categorized according to the observed dimensions, observation contexts, aspects monitored, and recording method, allowing for a systematization of the empirical data.

Initially, data related to schedule planning were collected, which included defining the project scope and decomposing activities through the Work Breakdown Structure (WBS). Activity duration estimation and logical sequencing were also performed, following the PMBOK guidelines, to establish a solid foundation for the project’s temporal performance analysis.

Next, data regarding the project execution were collected by continuously monitoring the schedule during a pilot period. The obtained data were organized, tabulated, and analyzed, enabling a comparison between the planned schedule and the actual schedule. This process allowed for the identification of deviations and their causes, providing subsidies for understanding management dynamics.

The data from the interviews were analyzed using content analysis, following the methodology proposed by Bardin (2016). This process involved the stages of pre-analysis, material exploration, and results treatment, with thematic categorization aligned with PMBOK schedule management practices, allowing for the extraction of relevant insights from the participants’ narratives.

The final data analysis was performed through methodological triangulation, integrating the information obtained from documentary research, semi-structured interviews, and participant observation. According to Yin (2018), triangulation contributes significantly to increasing the validity and reliability of case studies, by allowing the convergence of multiple sources of evidence, strengthening the robustness of the conclusions.

To ensure the integrity and ethics of the research, rigorous confidentiality procedures were adopted. The name of the studied organization and its address were not disclosed, and the identities of the interviewed partners were preserved, being referred to only as Partner T, Partner M, and Partner A. This measure ensured the protection of sensitive information and the privacy of the participants.

3. Results and Discussion

The initial analysis of project schedule management reveals a notable evolution from an informal organizational arrangement to a more structured operational regime, although still heavily conditioned by resource availability and external uncertainties. This progression is evidenced in the meeting minutes, which initially (09/04/2025) focused on defining preliminary responsibilities and general directions. This phase, while fundamental, lacked the detailed temporal commitments that characterize mature project planning. Such an approach is common in nascent organizations or creative ventures, where flexibility is often prioritized over rigid formalization (Kerzner, 2022; PMI, 2021). However, as the project progressed, subsequent minutes, such as the one from 09/25/2025, began to explicitly detail temporal planning, including the reservation of sequential dates for recording activities. This shift represents an embryonic move towards schedule formalization, aligning with the PMBOK’s emphasis on defining and sequencing activities for improved control (PMI, 2021). The initial informality, while allowing for agility, inherently introduced a degree of ambiguity regarding precise deadlines and resource allocation, a common challenge in small-scale creative ventures, where processes often evolve organically rather than through predefined structures.

A particularly insightful finding from the minutes of 09/25/2025 is the conditional advance operational rule: “should the recordings of the 27/09 be finalized earlier, the activities of 09/28 could be advanced.” This practice, although not explicitly termed “buffer,” functions as an intuitive form of temporal protection. It acknowledges the inherent variability in creative production, such as time spent on field activities, travel, capturing, and re-shooting takes, by providing a margin for early completion or absorption of delays. This aligns directly with the literature on “buffers” in project management, which posits that protective mechanisms (margins, reserves, or buffers) are essential to prevent delays in preceding activities from contaminating the delivery chain (Ghaffari & Emsley, 2015; Zohrehvandi & Soltani, 2022). These authors emphasize that variability is an intrinsic part of project execution, and proactive measures are necessary to mitigate its effects. In this context, the allocation of two days and the conditional advance rule serve as practical, albeit informal, strategies for managing this variability, reducing the “domino effect” of delays that Xu et al. (2024) describe as a major challenge in project scheduling. The absence of formal Critical Chain Project Management (CCPM) techniques does not negate the functional equivalence of these intuitive practices, suggesting that even in less formalized environments, project teams often develop adaptive strategies to deal with uncertainty. However, the lack of explicit formalization and systematic monitoring of these buffers limits their maximum potential, as their effectiveness cannot be systematically evaluated or improved over time.

As the project matured, the documentation reflected a growing formalization of the schedule, focusing on “deliverables with dates and responsible parties.” The minutes of 11/13/2025, for example, presented a detailed publication schedule with specific dates, content titles, and assigned responsibilities for editing. This level of detail indicates an approach to structured planning practices recommended by good project management practices (PMI, 2017; Kerzner, 2022). Furthermore, the definition of recording windows on specific dates (11/21 and 11/22/2025) reinforced a pattern of “block scheduling,” where activities are grouped, typically on weekends, to optimize team and resource mobilization within a short period. While this approach can be efficient for teams with limited availability, it inherently carries greater risks. The cancellation of a single block of activities can have a direct and significant impact on subsequent deliveries, highlighting the need for more disciplined control and robust contingency planning. This observation underscores a critical tension in creative projects: the desire for flexibility and efficiency often clashes with the need for predictability and risk mitigation. Project scheduling literature frequently discusses the trade-offs between agility and control, suggesting that while adaptive approaches are valuable, they should be complemented by mechanisms to manage interdependencies and potential disruptions (Pires & Varajão, 2024; Pererva and Gruzina, 2025). The project experience demonstrates that without a robust system for managing these trade-offs, the benefits of block scheduling can be quickly eroded by unforeseen events.

Empirical evidence of this cascade effect was vividly illustrated in the participant observation records of “WhatsApp” on 01/16/2026. This record explicitly details the cancellation of a recording session planned for 01/17/2026 due to multiple factors: guest unavailability, a partner’s indisposition, and general schedule constraints. Consequently, publications scheduled for 01/19/2026 and 01/22/2026 were also canceled, with the explicit justification that “the schedule depended on these recordings.” This incident serves as a powerful illustration of the rigid dependencies within the project workflow – recording, editing, and publishing – and the absence of a content buffer to absorb such disruptions. The decision criterion for altering the schedule, “based on partner availability,” further emphasizes the reactive nature of control. This finding resonates with studies highlighting the vulnerability of creative projects to resource availability and external dependencies (Ghaffari & Emsley, 2015; Pires & Varajão, 2024; Pererva & Gruzina, 2025). These authors argue that in environments characterized by high operational uncertainty, external factors such as stakeholder availability and third-party commitments significantly amplify scheduling risks. The lack of pre-produced content or “operational reserves” meant that any disruption in the initial stages translated directly into delays in final deliverables, demonstrating a critical gap in proactive risk management and contingency planning. The project’s reliance on immediate availability, rather than a strategic resource buffer or alternative content pipelines, left it highly exposed to common operational challenges.

The interviews conducted with the project partners corroborated and enriched these findings. Partner T, for example, reported that the initial schedule was planned collectively, with activities sequenced “by consensus,” and duration estimates based on assumptions or prior experience. Crucially, Partner T also admitted the absence of a systematic comparison between planned and actual deadlines. This lack of systematic tracking is a significant limitation, as it hinders organizational learning and the refinement of future estimates. The interviewee’s recognition of the continuous need for schedule revision and the possibility of creating operational alternatives aligns with recommendations for adaptive schedule management and buffer monitoring (Zohrehvandi & Soltani, 2022; Xu et al., 2024). These authors advocate for dynamic adjustment mechanisms and continuous feedback loops to improve schedule predictability in volatile environments. Without systematic comparison, the project remains dependent on empirical, often subjective, estimates, perpetuating a cycle of unpredictability that could be mitigated through more formalized control processes. This suggests that, although the team possessed an intuitive understanding of the need for flexibility, the absence of structured feedback mechanisms prevented the accumulation of actionable knowledge for future planning.

The interview with Partner M further underscored the predominance of human resource constraints, specifically “time availability” due to external commitments such as work and studies. Additionally, Partner M highlighted the project’s reliance on third parties for content, requiring image authorization and participant availability for recordings. This external dependency was also observed in the “WhatsApp” logs from 01/16/2026, where the unavailability of guests led to cancellations. The convergence of evidence from interviews and participant observation strongly suggests that the schedule variability in this project is not solely internal but is significantly driven by external factors. This phenomenon is widely discussed in the literature on project management in highly uncertain operational environments, where external stakeholders and resource limitations are major sources of risk (Ghaffari & Emsley, 2015; Pires & Varajão, 2024; Pererva and Gruzina, 2025). The implications are profound: effective schedule management in such contexts requires not only internal coordination but also robust strategies for managing external interfaces, including clear communication, contingency planning for third-party delays, and potentially building a buffer of pre-approved or alternative content. The project experience highlights that, even with internal planning efforts, external dependencies can become critical bottlenecks if not managed with explicit strategies.

Given these converging lines of evidence, the discussion about “buffers” in this case study transcends theoretical assumption to observed practice. The documentary corpus reveals at least three clear instances of intuitive temporal protection: the reservation of sequential dates for recording (09/27-28/2025), the conditional advance rule for the second day, and the definition of a double recording window (11/21-22/2025) linked to subsequent publication schedules. These practices, although not formally labeled as “buffers,” function as time reserves to absorb operational variations, a concept widely explored in project scheduling literature (Zohrehvandi & Soltani, 2022; Xu et al., 2024). However, the corpus also clearly indicates that these intuitive buffers were insufficient. The lack of systematic measurement and comparison between planned and actual performance, as explicitly mentioned in the interviews, undermined their effectiveness. The reference by Partner M to records in minutes and shared documents, while present, did not translate into a structured procedure for variation analysis. This absence of formal control mechanisms limits organizational learning and perpetuates empirical estimation, contributing to schedule unpredictability, especially given the project’s strong reliance on third parties and schedule constraints (PMI, 2017; Kerzner, 2022). The theoretical implication here is that, while intuitive buffers may offer some protection, their maximum potential is only realized when integrated into a systematic control framework that allows for continuous monitoring, deviation analysis, and adaptive adjustments. This gap between intuitive practice and formal control represents a significant area for improvement in project management maturity.

The overall analysis of the findings demonstrates strong consistency with the established literature on project management in environments with restricted resources and external dependency. Projects operating under such conditions are indeed more prone to duration variations and frequent replanning (Ghaffari & Emsley, 2015; Zohrehvandi & Soltani, 2022; Pires & Varajão, 2024; Pererva and Gruzina, 2025). The observed “buffers” and monitoring strategies, even if intuitive, are recognized mechanisms for mitigating cascading effects. In creative contexts, an adaptive and flexible operational management style is often necessary, requiring minimal documentation but maximum operational agility. However, this flexibility, while crucial for project continuity, can compromise predictability if not balanced with systematic measurement and learning routines. Brazilian case studies on the implementation of PMBOK practices in the time/schedule dimension reinforce that gradual formalization — encompassing planning, monitoring, and analysis of temporal variables — can improve performance and reduce rework, especially when actual durations are recorded and used to refine future estimates (Filgueira et al., 2016). The project’s trajectory, therefore, serves as a practical illustration of these theoretical principles, highlighting both the necessity and the challenges of adapting formal methodologies to dynamic and real-world scenarios.

In summary, the case study highlights the presence of relevant schedule management practices, such as window planning, assignment of responsibilities for deliverables, and conditional sequencing rules. However, it also exposes structural gaps in schedule control and temporal learning, specifically the absence of systematic routines for comparing planned versus actual progress, calibrating estimates, and institutionalizing operational alternatives. The intuitive adoption of temporal protection, through reserved days and double windows, as directly evidenced in project documents, was insufficient to compensate for external dependencies and schedule constraints. This suggests that, although the team recognized the need for some form of contingency, the informal nature and lack of integration with a systematic control process limited its effectiveness. The literature on “buffer management and scheduling” emphasizes that the robustness of schedule management depends on making these mechanisms explicit and connecting them to regular control procedures, including recording actual performance, analyzing variances, and incorporating alternatives or content reserves (Xu et al., 2024). This would increase predictability without sacrificing the flexibility essential for a creative context. The project experience, therefore, provides a compelling argument for a more deliberate and integrated approach to buffer management, moving beyond mere intuition to a structured implementation.

To systematically understand how these temporal protection mechanisms related to effective schedule performance and to what extent they contributed (or not) to mitigate delays and replanning, a more in-depth analysis was conducted, distinguishing between the “planned schedule” and the “executed schedule”. For this research, the planned schedule was operationalized from the decisions recorded in the minutes, covering definitions of recording dates, publication cadence, editing responsibilities, and adjustments/replanning. The executed schedule, in turn, was operationalized through participant observation records (meetings, recordings, and deliberations via “WhatsApp”) and triangulated with semi-structured interviews. This operationalization allowed for a direct comparison between planning and execution, facilitating the identification of deviations and their causes, consistent with the methodological design (PMI, 2017; Kerzner, 2022). This dual perspective is crucial for understanding not only *what* was planned, but *how* it unfolded in practice, revealing the nuances of adaptation and deviation.

In the planned schedule, a progressive formalization of temporal decisions was observed throughout the minutes. This process began with the marking of production windows, such as planning recordings on specific dates, and evolved into a delivery regime with defined dates, responsible parties, and frameworks. This trajectory indicates a growing awareness and application of structured scheduling principles. However, in the actualized schedule, participant observation records evidenced that the effective execution was strongly conditioned by capacity variables (partner availability), external dependencies (third parties and guests), and operational variables (logistics and field conditions). These factors frequently led to replanning, content substitutions, and occasional cancellations. This dynamic corroborates the understanding that, in environments of high variability, the schedule tends to be continuously reconfigured in a more adaptive than deterministic manner, a finding consistent with the literature on “buffers” and uncertainty in schedules (Ghaffari & Emsley, 2015; Zohrehvandi & Soltani, 2022; Xu et al., 2024). The constant need for adjustments underscores the inherent unpredictability of creative projects, where external factors often dictate the pace and feasibility of planned activities.

Source: Original research results

Figure 1. Comparison between the reconstructed planned schedule and the actual schedule in the analyzed period

As illustrated in Figure 1, the comparison between the reconstructed planned schedule and the actual schedule throughout the analyzed period visually demonstrates that the gap between the planned and executed is not limited to punctual delays. Instead, it reflects recurring changes in the schedule itself throughout the project. This visual representation underscores the adaptive nature of the project timeline, where continuous adjustments were made in response to unforeseen circumstances, rather than strict adherence to an initial, immutable plan. The implications of this visual evidence are significant: it suggests that traditional, rigid scheduling models may be less effective in dynamic and creative environments. Instead, a more flexible and adaptive approach, capable of incorporating frequent replanning and adjustments, is necessary. However, as discussed earlier, this adaptability must be accompanied by robust control mechanisms to prevent it from devolving into mere reactivity, which can undermine predictability and managerial learning. The constant re-evaluation and modification of the schedule, while necessary for project continuity, also highlight the absence of a stable baseline against which performance could be consistently measured and improved. This visual evidence provides a solid foundation for understanding the project’s dynamic temporal landscape.

The presented analysis of the project’s temporal milestones, derived from the comparison between planned and actual timelines, reveals several critical insights. Initial recording windows, planned with sequential dates and a conditional advancement rule, represented an intuitive attempt at temporal protection. Execution, characterized by flexibility, allowed some leeway to accommodate variability. However, the timeline for publications and recordings in subsequent months, while demonstrating more mature planning with defined dates and responsibilities, still experienced significant adjustments during execution due to external factors and activity interdependencies. This partial realization, with necessary adjustments, points to a maturing timeline, yet still dependent on continuous rescheduling. The replanning of deliverables involved content substitution and date reassignment, demonstrating that control was primarily achieved through plan reformulation. More critically, planned publications that relied on specific recordings were ultimately canceled due to participant unavailability, leading to a cascading effect. This clearly reveals the project’s vulnerability to third-party dependencies and the absence of content reserves. These insights reinforce the notion that, while planning efforts improved over time, execution remained highly susceptible to external variables and internal resource constraints, necessitating frequent and often reactive adjustments. The project’s reliance on immediate availability, rather than a strategic buffer or alternative content pipelines, left it highly exposed to common operational challenges, underscoring the limitations of intuitive protection without systematic control.

The project operated, at various times, under a milestone and window-driven schedule model (especially for recordings), which is a typical planning strategy in constrained capacity contexts. However, execution demonstrated that the robustness of the planning depended on the existence of operational alternatives and control mechanisms capable of protecting deliveries against flow variation (Zohrehvandi & Soltani, 2022; Xu et al., 2024). The case also vividly illustrates the difference between “planning dates” and “controlling temporal performance”: while the planned schedule was documented in the meeting minutes, effective control occurred mainly through replanning and content substitution, often based on availability and external dependencies. This characteristic was consistently recognized by all partners in the interviews, reinforcing the notion that reactive adjustments were the norm, rather than proactive management. This reactive stance, while allowing the project to adapt, simultaneously hindered the development of a stable baseline for performance measurement and continuous improvement.

Based on the distinction between the planned schedule and the actual schedule, a comprehensive overview of the main deviations identified during execution and their associated causes was compiled.

Table 2. Main schedule deviations and associated causes

Identified deviation

Observed manifestation

Associated cause

Contribution to schedule analysis

Publication schedule reconfiguration

Replacement of contents and rescheduling of dates in the publication schedule.

Content adjustments and reprioritization in the project.

Indicates that schedule control occurred, in part, by re-planning the originally established plan.

Postponement of publication due to operational issues

Change of the date initially planned for the publication of the first video, with the need for adjustments before the launch.

Operational problems and team availability limitations.

Shows the vulnerability of deliveries to the project’s operational capacity.

Cascading cancellation

Cancellation of the planned recording and subsequent publications that directly depended on it.

Guest scheduling failure and team member unavailability.

Exposes rigid dependencies between recording, editing, and publishing, in addition to the absence of reserve content.

Low capacity for anticipating deviations

Adjustments made after the occurrence of problems, without a systematic routine of comparison between planned and executed.

Low formalization of temporal monitoring and absence of variation analysis routine.

Indicates structural limitation in schedule control and in learning generated from observed deviations.

Source: Original research results

Table 2 reveals that the most significant variations in the project were not limited to punctual delays but included content cancellations, substitutions, and publication schedule reconfigurations. These deviations stemmed from the strong interdependence between recording, editing, and publication stages, coupled with a low stock of ready content. For instance, “Publication schedule reconfiguration” involved content substitution and date rescheduling, indicating that control was partially achieved through the reformulation of the original plan. This highlights a flexible yet reactive approach to managing scope and schedule changes. “Postponement of publication due to operational issues” underscored the project’s vulnerability to operational capacity and team availability, suggesting that initial estimates did not adequately account for real-world constraints. More critically, “Recording cancellation with cascading effect” exposed rigid dependencies between recording, editing, and publication, exacerbated by the failure to schedule guests and the unavailability of team members, leading to a lack of backup content. This specific deviation exemplifies the critical impact of external dependencies and the absence of strategic buffers. Finally, “Low capacity for deviation anticipation” was attributed to the lack of formal temporal monitoring and systematic variance analysis routines. These findings collectively suggest that project deviations were not isolated execution failures but rather a systemic outcome of combined factors: resource constraints, external dependencies, operational challenges, and insufficient formal temporal control. The implications are clear: a more robust system for identifying, tracking, and mitigating these systemic causes is essential for improving project predictability and success.

The deviations observed in the project were not primarily due to isolated execution failures, but rather to a complex interaction of factors: resource availability constraints, external dependencies, operational issues, and a low degree of formalization of temporal control. These combined elements fostered a management pattern characterized by successive replannings, where adjustments were made *after* problems occurred, rather than through a systematic routine of monitoring variations between planned and actual performance. This reactive approach, while allowing project continuity, severely limited its predictability and the team’s ability to learn from past experiences. In the recommended logic of schedule management, control goes beyond simply updating dates; it encompasses a systematic comparison of actual performance with the plan, an assessment of impacts, and the recording of causes to refine future estimates (PMI, 2017; Kerzner, 2022). In the analyzed case, despite the rich records available (meeting minutes, participant observation, and interviews), the triangulation of these sources indicates that a systematic planned/actual comparison was not institutionalized as a routine. This significantly diminished the project schedule’s learning capacity, hindering the development of more accurate future estimates and more robust contingency plans. The absence of this feedback loop perpetuates a cycle of reactive adjustments, preventing the accumulation of structured knowledge and the development of more mature project management practices.

Regarding the work breakdown, the analysis of the meeting minutes, participant observation records, and interviews allowed for the reconstruction of the initial Project Work Breakdown Structure (WBS) of the project, as presented in Figure 2.

Source: Original research results

Figure 2. Initial Project WBS

Although this structure was not explicitly identified in the project documents as a formal and consolidated artifact, the analyzed evidence clearly indicated that the scope was organized into recurring work packages. These packages encompassed content definition, recording preparation, recording execution, editing, and material publication. Thus, the WBS (Work Breakdown Structure) shown in Figure 2 represents an analytical systematization of how the work was decomposed and operationalized throughout the project. This implicit, yet functional, decomposition into interdependent stages, with distributed responsibilities and defined production cycles, supports the observed logical sequencing of activities. This finding is consistent with literature suggesting that, in small teams or creative environments, work decomposition can occur incrementally and practically, often without formal documentation. However, Kerzner (2022) warns that when not formally structured and recorded, this approach increases the likelihood of empirical estimates and frequent replanning, as the underlying logic and dependencies are not explicitly captured for future reference or systematic improvement. The reconstruction of the WBS, therefore, serves not only to illustrate the project structure but also to highlight the potential benefits of formalizing such decomposition for greater predictability and control. Formalizing the WBS, even in a simplified manner, could provide a clearer roadmap for all team members, reduce ambiguities, and improve the basis for more accurate time and cost estimates in future projects.

In a comparative discussion with the literature, this case study reinforces three convergent points. First, it confirms that projects characterized by operational uncertainty and external dependencies tend to exhibit significant duration variations, requiring temporal protection mechanisms (Ghaffari & Emsley, 2015; Zohrehvandi & Soltani, 2022). The project’s dependence on the availability of partners and external guests exemplifies this vulnerability. Second, the study demonstrates that “buffers” can be adopted intuitively (e.g., double recording windows, reserve days, conditional operations), but their effectiveness depends on the availability of alternatives and disciplined control, especially when dependencies are rigid (Xu et al., 2024). The cancellations observed due to a single point of failure (guest unavailability) underscore this limitation. Third, it reinforces that, in creative environments, management tends to be adaptive and oriented towards delivery feasibility. While this approach can promote project continuity, it may compromise predictability in the absence of systematic measurements and temporal learning routines (Pires & Varajão, 2024; Pererva and Gruzina, 2025). The frequent replanings and content substitutions of the project exemplify this adaptive, but sometimes reactive, mode of operation. These convergences highlight the universal challenges faced by projects in dynamic environments, regardless of their scale.

Specifically, in relation to the PMBOK guidelines, the data suggest that schedule management was executed in a progressive and partially informal manner, approaching best practices but without fully institutionalizing temporal control and learning mechanisms (PMI, 2017; PMI, 2011). Regarding schedule management planning, the minutes indicate the establishment of operational rules and decisions on cadence, windows, and responsibilities (e.g., minutes of 09/25/2025 and 11/13/2025), even without a single formal baseline. In relation to activity definition, the practical decomposition of work (content planning, recording, editing, and publishing) appears consistently in the minutes and participant observation records, supporting the notion that activities were identified and organized to enable deliverables. This indicates a fundamental understanding of project structuring, even if not formally and comprehensively documented.

The most robust evidence for the sequencing of activities is the rigid dependency between recording, editing, and publishing, confirmed by execution records (participant observation of WhatsApp on 01/16/2026) and by the logic of schedule organization in deliverables with assigned responsibilities (minutes of 11/13/2025). This characteristic emphasizes the need to treat critical predecessors with temporal protection and alternatives, as the failure of an initial activity tends to generate a cascading effect on all subsequent deliverables. Figure 3 schematically illustrates the sequencing of the main project activities and the points at which the schedule required replanning due to execution impediments.

Source: Original research results

Figure 3. Project activity sequencing

Figure 3 visually represents the workflow, starting with content definition, moving through recording and editing, to final publication. Decision points, such as “Did recording occur as planned?” and “Was editing completed?”, clearly show where replanning was necessary. If a recording did not occur as planned, the entire subsequent chain — organization of captured material, editing, and publication — was affected, leading to date adjustments, content replacement, or cancellation. This flowchart effectively illustrates the rigid interdependencies and the cascading effect of delays, reinforcing the findings from documentary and observational data. The presence of these decision points and feedback loops (implicit in “Schedule replanning”) highlights the adaptive nature of the project, but also its vulnerability to disruptions at critical junctures. The visual model underscores the importance of robust contingency planning and buffer management, not just as theoretical concepts, but as practical necessities for maintaining project flow in a highly interdependent environment. The frequent need to return to “Date adjustment, replacement of content, or cancellation of recording/publication” further emphasizes the reactive nature of control.

Regarding the estimation of activity duration, interviews consistently indicated that estimates were predominantly empirical, based on experience or assumptions. This approach, while common in creative environments, reduces predictability due to the absence of historical data and calibration. The lack of systematic recording and analysis of actual durations prevents the refinement of estimation techniques, leading to the perpetuation of subjective judgments rather than data-driven predictions. This finding aligns with Kerzner (2022), who argues that empirical estimates, without adequate feedback loops, contribute to frequent replanning and a general lack of schedule stability. Practical implications include the implementation of simple time tracking for key activities and regular post-project analyses to compare estimated versus actual durations, thereby building an internal knowledge base for more accurate future estimates. This would allow the team to move from purely intuitive estimates to more data-informed projections, gradually enhancing the reliability of their schedules.

Regarding the schedule development, the project evolved from recording windows to a publication schedule with defined dates and responsible parties, as documented in the minutes of 11/13/2025. This progression aligns with the PMBOK objective of consolidating activities, dependencies, and durations into an executable plan. However, data triangulation reveals that schedule control occurred mainly through replanning and content substitution (minutes of 11/27/2025 and participant observation of WhatsApp on 01/16/2026), along with the absence of systematic comparison between planned and actual progress, as mentioned by Partner T. This suggests that the project’s main gap, in relation to PMBOK best practices, lies less in the planning itself and more in the institutionalization of a temporal control and learning mechanism capable of feeding back estimates, protecting deliverables, and reducing the cascade effect in situations of capacity constraints and external dependencies (PMI, 2017; Kerzner, 2022). The project, therefore, operated in a continuous adjustment cycle, where the “plan” was a living document constantly reshaped by execution realities, rather than a fixed benchmark for performance measurement. This adaptive approach, while pragmatic, limited the accumulation of structured knowledge about schedule performance and the effectiveness of various strategies.

The findings collectively paint a picture of a project navigating the complexities of a creative and resource-constrained environment, with a blend of intuitive practices and emergent formalization. While the team demonstrated an understanding of key scheduling concepts such as temporal buffering and activity decomposition, the lack of systematic control and learning mechanisms created vulnerabilities. The constant need for replanning, the cascading effects of disruptions, and reliance on empirical estimates point to the need for greater institutionalization of project management processes. This does not necessarily imply a rigid, bureaucratic approach, but rather the adoption of structured yet agile practices that allow for increased predictability, risk management, and continuous improvement. For similar small-scale creative projects, the practical implication is to focus on establishing simple but consistent routines for tracking actual performance, comparing it against the plan, and documenting lessons learned. This would transform reactive adjustments into proactive learning opportunities, ultimately enhancing the project’s ability to deliver on time and within scope while maintaining the flexibility inherent in creative work. The project’s journey underscores that sustainable success in dynamic environments requires a continuous feedback loop between planning, execution, and learning, moving beyond mere adaptation to strategic evolution.

Table 3. Triangulation of results

Analytical axis

Minutes

Participant observation

Interviews

Interpretive synthesis

Initial planning

Definition of responsibilities and first recording windows.

Meetings show collective construction of the schedule.

Report of planning in meeting and sequencing by consensus.

The schedule was built in a collegial manner, however, initially little formalized.

Formalization of the schedule

Definition of posting cadence, dates, and responsible parties.

Records show progressive organization of deliverables.

Interviews acknowledge the evolution of planning.

There was progressive elaboration of the schedule throughout the project.

Execution and replanning

Adjustments and substitutions recorded in minutes.

Recordings and WhatsApp show delays, postponements, and cancellations.

Interviews indicate the need for continuous review.

The control occurred mostly by replanning.

Dependencies and buffers

Date reservations and double recording windows.

Recording cancellation generated a waterfall effect on publications.

Interviews point to the need for operational alternatives.

Intuitive use of buffers occurred, but insufficient to absorb variability.

Control and learning

Records of decisions and adjustments, systematic variance analysis.

Adjustments made based on availability and contingencies.

Report of absence of systematic planned/executed comparison.

The main gap was in the low formalization of temporal control.

Source: Original research results

Table 3, which synthesizes the triangulation of results, offers a holistic view of the project schedule management. In the “Analytical Axis” of “Initial Planning”, the minutes show a definition of responsibilities and initial recording windows, while participant observation records reveal meetings that demonstrate the collective construction of the schedule. Interviews confirm a collegial planning process, based on consensus, but initially informal. This convergence suggests that the project began with a collaborative, but unstructured, approach to defining its timeline, relying heavily on informal agreements rather than formalized documentation. This initial informality, while promoting team cohesion, also laid the groundwork for potential ambiguities and lack of clarity in accountability in later stages, as noted by Kerzner (2022) regarding the risks of empirical estimates. The absence of a formal baseline at this stage meant that subsequent deviations were more difficult to quantify and analyze systematically.

Moving to “Schedule Formalization”, the minutes indicate a definition of the cadence of postings, dates, and responsible parties. Participant observation records show a progressive organization of deliverables, and interviews acknowledge the evolution of planning. This indicates a progressive maturation of schedule management throughout the project. The team gradually moved towards a more structured approach, defining specific deliverables, deadlines, and responsible parties. This shift is a positive development, aligning with PMBOK principles that advocate for increased formality as a project progresses (PMI, 2021). However, as subsequent axes reveal, this formalization was not always accompanied by equally robust control mechanisms. The “progressive maturation” referred more to the definition of *what* and *when* rather than the systematic tracking of *how* it was being achieved against a baseline, which is a critical distinction in effective project control.

For “Execution and replanning”, the minutes record adjustments and content substitutions, while participant observation records show recordings with delays, postponements, and cancellations. Interviews consistently point to the need for continuous review. The synthesis here is clear: control occurred predominantly through replanning. This highlights a reactive rather than proactive management style, where deviations were addressed by modifying the plan, rather than being prevented or mitigated through systematic monitoring. This pattern, while adaptive, can lead to a perception of instability and lack of control, as the baseline itself is constantly changing. The literature suggests that, although replanning is an inevitable part of project management, especially in dynamic environments, over-reliance on it can mask underlying issues in initial planning or risk management (Pires & Varajão, 2024). The frequent need for project adjustments underscores the importance of distinguishing between planned flexibility and reactive improvisation.

The “Dependencies and buffers” axis shows records registering date reservations and double recording windows. Participant observation records reveal that recording cancellations generated a cascading effect on publications. Interviews highlight the need for operational alternatives. The interpretation is that there was an intuitive use of buffers, but they were insufficient to absorb variability. This is a critical finding, as it suggests that, although the team instinctively understood the need for temporal protection, the informal nature and limited scope of these buffers failed to account for the full spectrum of external dependencies and internal constraints. Xu et al. (2024) emphasize that for buffers to be effective, they must be strategically placed and actively monitored, which was not systematically observed in this case. The project experience demonstrates that, even with some form of contingency, the lack of systematic integration and monitoring can render buffers ineffective against significant disruptions.

Finally, for “Control and learning”, the minutes record decisions and adjustments based on availability and contingencies. The interviews report the absence of systematic comparison between planned and actual. The synthesis points to a main gap: low formalization of schedule control. This is perhaps the most significant limitation identified, as it directly impacts the project’s ability to learn and improve. Without systematic comparison and variance analysis, the project cannot accurately assess the effectiveness of its planning and execution strategies, nor can it refine its estimation processes for future endeavors. This lack of institutionalized learning perpetuates a cycle of empirical, often inaccurate, estimates and reactive replanning, hindering the organization’s long-term project management maturity (PMI, 2017; Kerzner, 2022). The rich qualitative data collected through observation and interviews, while providing deep insights, also reveal the missed opportunity for quantitative analysis and structured feedback that could have been derived from a more formalized control system, transforming individual experiences into organizational knowledge.

4. Conclusion

It is concluded that the objective was achieved, as the schedule management practices adopted in the creation and launch project of a video production company were evaluated in light of the PMBOK guidelines. The research compared formalized planning with actual execution, identifying deviations and proposing improvements. It was found that the project demonstrated progressive maturity in schedule structuring, with the incorporation of temporal planning, definition of responsibilities, and the intuitive use of protection mechanisms, such as double recording windows and reserve days. However, the actual execution revealed a strong dependence on the availability of human and third-party resources, as well as operational problems that resulted in continuous replanning and cascading cancellations. The main gap identified was the absence of systematic and formalized schedule control, especially in the comparison between planned and actual, which limited managerial learning and predictability.

The limitations of this study include the specific temporal scope of the analyzed case, the concentration of the analysis on a single project, and the reconstructive nature of some of the temporal evidence, which required the consolidation of dispersed and non-standardized records. For future studies, it is suggested to expand the investigation to other projects in the creative sector, allowing for a more comprehensive understanding of schedule management dynamics in different contexts. It is also recommended to apply the analytical model comparatively in organizations with varying levels of project management maturity, in order to identify patterns and best practices that can be generalized. Such approaches would contribute to the continuous improvement of schedule management methodologies in dynamic and resource-constrained environments.

Bibliographic References

Instituto Brasileiro de Geografia e Estatística [IBGE]. 2024. Em 2023, 88,0% das pessoas com 10 anos ou mais utilizaram Internet. Agência de Notícias IBGE. Instituto Brasileiro de Geografia e Estatística, Rio de Janeiro, RJ, Brasil. Disponível em: <https://agenciadenoticias.ibge.gov.br/agencia-noticias/2012-agencia-de-noticias/noticias/41026-em-2023-87-2-das-pessoas-com-10-anos-ou-mais-utilizaram-internet>. Acesso em: 13 mar. 2026.

Kerzner, H. 2022. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 13. ed. John Wiley & Sons, Hoboken, NJ, USA.

Nascimento, L.

Information and Coordination Center of the .BR domain. 2025. Survey on the use of information and communication technologies in Brazilian households: TIC Domicílios 2024. Internet Steering Committee of Brazil, São Paulo, SP, Brazil.

Project Management Institute [PMI]. 2021. A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 7th ed. Project Management Institute, Newtown Square, PA, USA.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.