Risk Management of Tailings Piles in a Mining Company

Risk Management in Tailings Dams of a Mining Company

Rafael Giovanni do Nascimento; Gilberto Marassi de Loiola Leite

DOI: 10.22167/2675-6528-202601325

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

Risk management in tailings disposal structures has become central in the mining sector, especially after recent accidents that highlighted technical and governance failures. This study aimed to analyze risk management in a mining company’s tailings piles through the application of the Failure Mode and Effects Analysis (FMEA) tool, from a project management perspective. The research was characterized as applied, with a mixed approach, developed through a case study, using historical operational data, technical records, and institutional information from the analyzed company. Initially, the main failure modes associated with the geotechnical stability of the pile were identified, including slope rupture, liquefaction, internal erosion, and rising water table. Subsequently, risks were quantitatively analyzed by assigning Severity, Occurrence, and Detection indices, enabling the calculation of the Risk Priority Number (RPN) and its subsequent prioritization. The results indicated that the most critical risks were related to hydraulic control, with the water table rise and the “piping” phenomenon standing out. The integrated analysis showed that the risks stemmed from the interaction between design, operation, and monitoring factors, reinforcing the need for systemic approaches. It was concluded that the application of FMEA significantly contributed to structuring risk management, supporting decisions and the development of preventive actions. The study demonstrated that, even in systems considered safer, the adoption of formal risk management practices is essential to ensure operational safety and the sustainability of mining operations.

Keywords: Dry stacking; Geotechnical stability; FMEA; Project management; Operational safety.

1. Introduction

The global mining sector faces increasing scrutiny regarding the safety and sustainability of its operations, especially in tailings disposal. Geotechnical complexity and massive material volumes pose significant challenges, requiring robust risk management. In Brazil, the urgency of this agenda was heightened by the tailings dam failure disasters in Fundão (2015) and Brumadinho (2019). These events resulted in loss of human lives, environmental damage, and socioeconomic impacts, exposing systemic failures that included technical, organizational, and governance deficiencies (Freitas et al., 2019; Garcia, 2022; Oliveira et al., 2021). The tragedies spurred a re-evaluation of engineering and management practices, tightening regulations and seeking safer disposal technologies, such as dry stacking.

In this highly complex scenario, risk management assumes a central and strategic role, encompassing the identification, analysis, evaluation, risk treatment, and continuous monitoring of uncertainties that can affect the objectives of a project or operation (Kerzner, 2022). In large-scale engineering projects, such as mining projects, the application of systematic risk management methodologies is fundamental to strengthen decision-making, optimize resource allocation, and mitigate potential negative impacts. The Project Management Institute (PMI) (2021) emphasizes that risk management is an essential knowledge domain for the success of any project, and should be integrated from planning to closure. The absence of a structured approach can lead to project failures, operational delays, and, in the context of mining, accidents with disastrous consequences, reinforcing the imperative of integrating project management principles into risk management.

Among the tools for risk management, Failure Mode and Effects Analysis (FMEA) stands out for its systematic and preventive approach. Developed in the 1940s for the aerospace industry, its application has extended to high-criticality sectors such as mining (Stamatis, 2019). FMEA allows for the detailed identification of failure modes, their effects, causes, and existing controls. By assigning Severity, Occurrence, and Detection indices, the Risk Priority Number (RPN) is calculated, enabling objective risk prioritization and the prioritization of preventive and corrective actions (Carpinetti, 2020; Pillay and Wang, 2020). This methodology offers a robust framework for understanding risks, supporting engineering in the design of safer projects and management in the implementation of effective monitoring and control strategies.

The search for safer alternatives to conventional dams has driven the adoption of dry stacking of tailings. This technology involves the disposal of low-moisture materials, usually after filtration, forming stacks that resemble compacted soil masses. Conceptually, dry stacks exhibit distinct geotechnical behavior from dams, with a lower potential for catastrophic failure associated with liquefaction, due to the reduced presence of free water (Davies and Rice, 2021; Vick, 2020). However, the perception of increased safety does not eliminate the need for rigorous risk management. Recent events, such as the Jaguar Mining accident, demonstrate that failures can occur even in systems considered more stable, often resulting from deficiencies in design, operation, or monitoring (Almeida et al., 2021; Silva et al., 2022). Additionally, Brazil faces specific regulatory and procedural gaps for tailings stacks, creating an environment of uncertainty and increasing companies’ technical responsibility in defining safety criteria (ANM, 2023; Silva et al., 2024).

Given the complexity of mining operations, the risks associated with tailings disposal structures, the need for systematic project management approaches, and the regulatory and knowledge gaps regarding dry tailings pile risk management, the application of formal methods to identify and mitigate potential failures becomes fundamental. A deep understanding of failure modes and risk prioritization are crucial for developing effective preventive strategies, contributing to operational safety and the environmental sustainability of the sector. Thus, the present study aimed to analyze risk management in tailings piles of a mining company, through the application of the Failure Mode and Effects Analysis (FMEA) tool, from a project management perspective, aiming to improve safety practices and decision-making in the mining sector.

2. Material and Methods

This study was characterized as an applied research, of a descriptive-exploratory nature, developed through a single case study in a company in the mineral sector. Applied research aimed at generating knowledge focused on solving practical and specific problems, with potential for direct application in the analyzed organizational context (Gil, 2019). The choice of case study was justified by the need to understand, in depth and contextually, the risk management processes associated with tailings piles, preserving the real characteristics of the operational and decision-making environment, as recommended by Yin (2021) for investigations of complex and contemporary phenomena.

Regarding the methodological approach, the study adopted a mixed method, combining qualitative and quantitative elements. The qualitative approach was related to the identification, description, and analysis of failure modes, their causes, effects, and existing controls, allowing for the technical and contextual interpretation of the risks involved in tailings stacking. The quantitative approach, on the other hand, was manifested in the assignment of numerical values to the variables of severity, occurrence, and detection, enabling the calculation of the Risk Priority Number (RPN), which facilitated the objective prioritization of risks. The literature highlights that the combination of qualitative and quantitative approaches enhances analytical robustness, especially in engineering and risk management studies (Creswell and Creswell, 2018; Marconi and Lakatos, 2022).

The object of study of this work was a medium-sized Brazilian mining company, active in the iron ore exploration sector, with a consolidated trajectory in the national market. The organization develops integrated mining and mineral processing activities, with tailings generation being an inherent consequence of its production processes. During the analyzed period, the mining company adopted dry stacking through tailings piles as an alternative to conventional hydraulic containment dams. The unit of analysis focused on the risk management of these Waste and Tailings Disposal Piles (PDER).

The study period was not explicitly delimited, but the research was based on the analysis of historical operational data, technical records, and institutional information of the company. This data encompassed past occurrences, identified risk events, and recorded failures over time, reflecting practical experience and event frequency in the organization’s operational environment. Information gathering also considered the context of recent accidents in Brazilian mining, as discussed in the introduction.

There was no defined population or sample in the traditional sense, as it was a single case study. Data were collected from documentary and historical sources of the mining company itself, complemented by external references. Data sources included internal maintenance histories, operational records, and technical documents of the company, which served as the basis for identifying failure modes and assigning risk indices. The criteria for selecting information were its relevance to the physical and geotechnical stability of the PDER.

The main data collection and analysis tool was the Failure Mode and Effects Analysis (FMEA) tool, which systematically organizes the analysis of risks associated with the object of study. FMEA is a widely used systematic tool to identify potential failure modes, assess their effects, and prioritize treatment actions before unwanted events occur. Its origin dates back to the 1940s, being later incorporated by sectors with high operational criticality, such as mining, due to its essentially preventive nature (Carpinetti, 2020; Stamatis, 2019).

The construction of the FMEA framework followed a sequential and structured logic. Initially, the system to be analyzed was defined, which was the Waste and Tailings Disposal Stack (PDER), focusing on its physical and geotechnical stability. Aspects such as global and local slope stability, surface and internal drainage, behavior of the stacked material, operational conditions, and monitoring practices were considered. This choice was justified by the relevance of geotechnical stability as a critical safety factor in stacking structures (Fourie et al., 2021; Vick, 2020).

The first execution stage consisted of identifying possible failure modes, their effects, causes, and existing controls. This information was defined based on the mining company’s institutional records, including maintenance histories, operational records, and internal technical documents, ensuring adherence to the organization’s operational reality. This approach allowed for a contextualized understanding of the risks involved in tailings stacking, underpinning the initial qualitative analysis.

Next, numerical indices were assigned to the Severity (S), Occurrence (O), and Detection (D) criteria for each identified failure mode. The Occurrence and Detection indices were assigned primarily considering the company’s internal history, reflecting its practical experience and the effectiveness of existing control mechanisms. For the definition of the Severity indices, recourse was made to the support of technical and scientific literature, historical records of accidents and disasters involving waste disposal structures in Brazil, and current legislation and regulations applicable to the mineral sector (Pillay and Wang, 2020; Stamatis, 2019).

The next step involved calculating the Risk Priority Number (RPN), obtained by the product of the Severity, Occurrence, and Detection indices. The RPN, a quantitative indicator, allowed for the objective prioritization of risks, directing treatment efforts towards those considered most critical. Based on the risk prioritization, the recommended actions for each failure mode were defined, as well as the frequency of execution of these actions, aiming for continuous improvement in operational safety and the reliability of the analyzed structure (Kerzner, 2022; PMI, 2021).

The data were treated and analyzed using the FMEA framework, which favored the traceability of information and the comparison between the different identified risks. The qualitative analysis allowed for a detailed description of failure modes, their causes and effects, while the quantitative analysis, via RPN, enabled objective prioritization. This process facilitated the identification of weaknesses in existing controls, priority failure modes, and opportunities for improvement in the design, operation, and monitoring processes of the stack, contributing to decision-making.

No specific ethical procedures were declared in the original term paper. However, the methodology sought to reduce the subjectivity inherent in the assignment of indices in FMEA by combining internal empirical data and external references, such as technical literature and accident records. Although technical judgment is present in the assignment of indices, the application of NPR provided greater objectivity and comparability to the decision-making process, strengthening the reliability of the obtained results.

3. Results and Discussion

Initially, based on the company’s historical data analysis, as described in the methodology, Table 1 was elaborated. It presents the main failure modes associated with the physical and geotechnical stability of the Waste and Tailings Disposal Pile (PDER), as well as their effects, causes, and currently adopted controls. The construction of this table was based on operational records, maintenance histories, and internal technical documents, allowing for a systematized view of the most recurrent and relevant risks in the studied context. It serves as a basis for the subsequent stages of prioritization and quantitative analysis through FMEA.

Table 1. Failure mode and its effects

Item

Failure mode

Failure Effect

Cause of failure

Current control

1

Circular slope failure

Structural collapse and risk to people and roads

Overestimated resistance parameters or inadequate geometry

Stability Analyses (Limit Equilibrium)

2

Static liquefaction

Sudden rupture with large reach (“run-out”)

Material saturation and rapid load application

Piezometer monitoring

3

Internal erosion (“piping”)

Void formation and fine material loss

Failures in filters or drainage clogging

Visual inspection of drains

4

Excessive foundation settlement

Deformations and possible rupture at the base

Compressible foundation without adequate treatment

Surface marks and topographic control

5

Groundwater level rise

Reduction of massif stability

Rainfall above forecast or failure of the bottom drain

Water Level Indicators [INA]

6

Overtopping

Slope erosion and risk of rupture

Obstructed or undersized surface drainage

Post-rain inspections and device cleaning

7

Out of specification disposition

Fragile points and insufficient compaction

Error in blend or material loading

Visual control and laboratory tests

8

Tension cracks

Water infiltration and evidence of instability

Talus movement initiation

Visual and topographic monitoring

9

Excessive vibrations

Trigger for instability or liquefaction

Detonations with charge above the limit

Seismic stability analyses

10

Drainage siltation

Stack foot saturation

Sediment transport by surface erosion

Periodic cleaning of gutters and shoulders

Source: Original research results

The analysis of Table 1 shows that the identified failure modes are strongly related to classic geotechnical instability mechanisms, such as slope rupture, liquefaction, internal erosion, and excessive settlement. These mechanisms are widely discussed in the literature as critical factors in tailings disposal structures, including in dry stacking systems, which, despite presenting lower moisture content, are not exempt from failures when subjected to inadequate operational conditions or extreme events (Fourie et al., 2021; Vick, 2020). The effects associated with these failure modes range from losses of structural performance to collapse scenarios with risks to people’s physical integrity and the environment, reinforcing the high criticality of these occurrences.

The first failure mode, circular slope failure, is one of the most catastrophic, resulting in the collapse of the structure and posing an imminent risk to people and roads. Its main cause lies in overestimated soil strength parameters or inadequate slope geometry. Geotechnical literature, according to Vick (2020), emphasizes that slope stability is intrinsically linked to the correct characterization of materials and conservative geometric design. Overestimation of strength parameters can arise from insufficient geotechnical investigations or optimistic data interpretations, which is a critical error in the design phase. The practical implication is the need for robust investments in detailed geotechnical investigation campaigns, using advanced methods such as triaxial and direct shear tests, as well as numerical modeling that considers critical saturation and loading scenarios. The current practice of limit equilibrium stability analyses, although fundamental, must be complemented by probabilistic analyses and rigorous quality control during execution, ensuring that the constructed geometry conforms to the design.

Static liquefaction, the second failure mode, is characterized by a sudden rupture with large “run-out”, a particularly dangerous phenomenon in saturated granular materials subjected to rapid loading. Material saturation and rapid load application are the primary causes. This failure mode was a contributing factor in dam disasters in Brazil, such as those in Mariana and Brumadinho, even in upstream raising contexts (Freitas et al., 2019; Garcia, 2022). Although dry tailings piles are designed to have low moisture content, the occurrence of localized saturation due to poor drainage or extreme rainfall events cannot be ruled out. Piezometer monitoring is the current control, but its effectiveness depends on the density of the instrumentation network and the reading frequency. The practical implication is the need for a robust piezometric monitoring system, with automated, real-time readings, and the definition of clear “trigger levels” that trigger immediate preventive actions. Furthermore, managing tailings moisture during stacking and ensuring an efficient internal drainage system are crucial to mitigate the risk of saturation.

Internal erosion, or “piping”, represents the third failure mode, leading to the formation of voids and the loss of fine material, which can compromise the structural integrity of the stack. Failures in filters or drainage clogging are the underlying causes. Stamatis (2019) highlights that the failure of drainage components is a common problem in geotechnical structures, and its early detection is vital. Visual inspection of drains, the current control, may be insufficient to identify internal problems. The practical implication is the implementation of a more sophisticated drainage inspection program, including the use of video cameras for internal pipe inspection, periodic permeability tests, and analysis of drained water quality to identify the presence of fines. Filter design should be reviewed to ensure its long-term effectiveness, considering the granulometry of the tailings and the prevention of clogging.

Excessive foundation settlement, the fourth failure mode, results in significant deformations and potential rupture at the pile base. The main cause is a compressible foundation without adequate treatment. Vick (2020) emphasizes the importance of geotechnical characterization of the foundation as one of the pillars of the design of waste disposal structures. The absence of adequate treatment can be a reflection of failures in the investigation and design phase. Current controls, surface benchmarks, and topographic control, detect deformation after it occurs. The practical implication is the need for complementary soundings and CPTu (Cone Penetration Test with Pore Pressure Measurement) tests in the foundation, before and during construction, to adequately characterize the compressibility and strength of the soil. In cases of problematic foundations, treatments such as consolidation, piles, or gravel columns should be considered in the design phase, with continuous monitoring of deformations.

The rise in the water table, the fifth failure mode, reduces the stability of the mass, making it more susceptible to other failure modes. Rainfall above forecast or failure of the underdrain are the causes. Davies and Rice (2021) and Silva and Rocha (2022) reiterate that water control is the most critical factor for the stability of tailings piles, even those with dry stacking. Water Level Indicators (INA) are the current control, but their effectiveness depends on interpretation and responsiveness. The practical implication is the installation of automated piezometers with telemetry, allowing continuous monitoring and the definition of safety triggers to activate contingency plans. Furthermore, preventive and corrective maintenance of surface and internal drainage systems is essential, with periodic cleaning of channels and gutters, and adequate sizing for extreme rainfall events.

Galgamento (“overtopping”), the sixth failure mode, causes embankment erosion and rupture risk due to obstructed or undersized surface drainage. This failure mode, although more associated with dams, can occur in tailings piles if the surface drainage system is inadequate to handle rainwater volumes. Post-rain inspections and device cleaning are the current controls. The practical implication is the sizing of stormwater diversion channels for a Return Period (RP) of 100 years, according to best engineering practices, and lining these channels to prevent erosion. Maintenance should be intensified during the rainy season, with daily inspections and immediate cleaning of obstructions.

The out-of-specification disposition, the seventh failure mode, creates brittle points and insufficient compaction in the pile, due to errors in the blend or material loading. This is a direct operational risk. Visual inspection and laboratory tests are the current controls. Project management literature, such as PMI (2021), emphasizes the importance of quality control during execution to mitigate operational risks. The practical implication is the implementation of rigorous quality control at the discharge front, with constant supervision, use of radio communication for efficient communication between operators and supervisors, and readjustment of the blend and equipment (bulldozers and graders) to ensure adequate compaction. Field tests, such as the in-situ density test, should be performed frequently to verify the compliance of the piled material.

Tension cracks, the eighth failure mode, indicate water infiltration and signs of instability, caused by the initial movement of the slope. Visual and topographic monitoring is the current control. Tension cracks are often precursors to mass movements and ruptures, and their early detection is fundamental (Vick, 2020). The practical implication is the implementation of an automated topographic monitoring system, such as robotic total stations or laser scanning, which allows for the detection of millimeter-scale deformations. Furthermore, immediate sealing of cracks with compacted material, as soon as they are detected, is an essential corrective action to prevent water infiltration and the progression of instability.

Excessive vibrations, the ninth failure mode, can act as a trigger for instability or liquefaction, being caused by detonations with loads above the limit. Although dry tailings piles are more seismically and dynamically stable than hydraulic dams, intense vibrations can compromise their integrity. Seismic stability analyses are the current control. The practical implication is the implementation of continuous seismographic monitoring in the pile area, with the definition of vibration limits and a plan to adjust the mine’s firing plan to ensure that detonations do not exceed safety limits. Coordination between the mining and geotechnical teams is crucial to manage this risk.

Finally, drainage silting, the tenth failure mode, leads to pile toe saturation due to sediment transport by surface erosion. This failure mode is intrinsically linked to water control and maintenance. Periodic cleaning of gutters and berms is the current control. The practical implication is the installation of sedimentation basins before the main drainage network to retain sediments and reduce silting. The frequency of gutter and berm cleaning should be reviewed and, if necessary, increased, especially after intense rainfall events, to ensure the continuous functionality of the drainage system.

It is also observed that a significant portion of the causes pointed out in Table 1 is associated with design, execution, or operation deficiencies, such as overestimated geotechnical parameters, insufficient drainage, failures in compaction control, and limitations in the management of the disposed material. The literature highlights that such factors reflect not only technical aspects but also weaknesses in planning and control processes, typical of complex projects when there is inadequate integration between engineering, operation, and risk management (PMI, 2021; Kerzner, 2022). In this sense, the results reinforce the need for systematic approaches that transcend specific analyses, incorporating structured project management practices throughout the pile’s lifecycle.

Regarding the controls currently adopted, Table 1 demonstrates a predominance of measures of a technical-operational nature, such as stability analyses, monitoring by geotechnical instruments, and periodic visual inspections. Although these practices are widely recommended by literature and technical standards, recent studies indicate that, when applied in isolation, they may present limitations in anticipating complex or progressively evolving failures (Silva and Rocha, 2022; Stamatis, 2019). Thus, the results suggest that the effectiveness of existing controls depends not only on their adoption but also on their integration into a formal system for risk assessment and prioritization.

In general, the findings presented in Table 1 are aligned with evidence reported on accidents and incidents in tailings disposal structures, in which failures associated with drainage, groundwater level control, and slope stability are among the main causes of critical events (Freitas et al., 2019; Garcia, 2022). A detailed understanding of these failure modes and their interrelationships is the starting point for building a robust risk management system, which is not limited to reactivity, but promotes proactivity and operational resilience.

From the identification and characterization of the failure modes presented in Table 1, it was possible to advance to a quantitative analysis stage, with the objective of objectively and comparably prioritizing the identified risks. To this end, the Severity, Occurrence, and Detection indices were assigned to each failure mode, according to the criteria defined in the methodology, considering both the company’s internal history and the support of technical and regulatory literature. The product of these indices resulted in the Risk Priority Number (NPR), presented in Table 2, which allows for the identification of the most critical failure modes and guides the definition of preventive and corrective actions, in line with good risk management and project management practices.

Table 2. NPR Index

Item

Severity

Occurrence

Detection

NPR

1

5

2

3

30

2

5

1

4

20

3

4

2

5

40

4

4

3

3

36

5

5

5

2

50

6

4

3

2

24

7

3

5

2

30

8

5

4

2

40

9

4

3

3

36

10

3

5

1

15

Source: Original research results

The RPN presented in Table 2 enabled the objective prioritization of the identified failure modes, according to the classic FMEA approach described by Stamatis (2019). In the context of tailings disposal structures, this prioritization is particularly relevant, as geotechnical failures can present disproportionate consequences in terms of safety, environment, and operational continuity (Fourie et al., 2021; Vick, 2020). The analysis of the RPN values reveals crucial insights into the criticality of each failure mode and the perceived effectiveness of existing controls.

The highest NPR values observed are concentrated in failures related to the pile’s water regime, especially groundwater level rise (NPR 50) and internal erosion (“piping”) (NPR 40). The literature is consistent in pointing out the presence and inadequate control of water as one of the main factors of instability in geotechnical structures, even in dry stacking systems (Davies and Rice, 2021; Silva and Rocha, 2022). The high NPR for groundwater level rise (Item 5) reflects a combination of high severity (5), high occurrence (5), and limited detection (2), indicating that, despite existing controls (INA), the ability to anticipate or mitigate this event is challenging. This underscores the need to improve monitoring systems and response strategies for extreme rainfall events.

Internal erosion (“piping”) (Item 3), with NPR 40, also demonstrates high severity (4) and limited detection (5), although with intermediate occurrence (2). This result suggests that, once initiated, the piping process is difficult to detect early and can lead to serious consequences. Studies on recent accidents in Brazilian mining indicate that failures in drainage control and piezometric monitoring are among the main triggers for progressive failures and structural collapses, which corroborates the high NPR values attributed to these failure modes in this study (Freitas et al., 2019; Garcia, 2022). The practical implication is that water management, both surface and underground, must be the top priority, with investments in robust drainage infrastructure and continuous, integrated monitoring.

Failures associated with global stability, such as circular slope failure (NPR 30) and excessive foundation settlement (NPR 36), also presented high NPRs, reflecting the combination of high severity and limitations in early detection. Circular slope failure (Item 1), with severity 5 and occurrence 2, but detection 3, indicates that, although not the most frequent event, its impact is devastating and the detection capability is not ideal. Excessive foundation settlement (Item 4), with severity 4 and occurrence 3, but detection 3, points to design and soil characterization problems that may manifest late. According to Vick (2020), problems related to geotechnical characterization of the foundation, overestimated strength parameters, and inadequate slope geometries are among the main causes of instability in tailings piles. From a project management perspective, Kerzner (2022) highlights that such failures are often associated with deficiencies in the planning and design phases, whose impacts tend to manifest critically during operation. This reinforces the need for rigorous quality control at all project stages, from geotechnical investigation to execution.

Failure modes of a predominantly operational nature, such as the disposition of out-of-specification material (NPR 30) and the silting of the drainage system (NPR 15), presented intermediate NPR values, though not negligible. The literature highlights that these operational risks are cumulative and, when neglected, can indirectly contribute to the occurrence of more severe structural failures (Silva et al., 2023; Stamatis, 2019). In this sense, although individually they present a lower immediate catastrophic potential, their recurrence increases the probability of progressive degradation of the pile’s safety over time. The low NPR for drainage silting (Item 10) (NPR 15) is notable, with severity 3, occurrence 5, but detection 1. The low detection (1) suggests that, although it is a frequent event, current controls (periodic cleaning) are effective in identifying and mitigating it before it becomes critical. However, the high occurrence (5) indicates that this is a persistent problem that demands continuous attention to prevent progression to more severe failures.

Finally, the NPR analysis shows that, even with the existence of consolidated technical controls, the early detection capacity for certain failures remains limited, directly influencing the obtained values. Pillay and Wang (2020) highlight that detection is often the most sensitive criterion of FMEA, as it depends not only on the available instrumentation but on the integration between monitoring, data interpretation, and decision-making processes. Thus, the results reinforce the need to incorporate FMEA into a structured risk management system aligned with PMI (2021) best practices, in which prioritized risks are continuously monitored, with defined responsibilities and clearly established preventive actions.

Based on the NPR values obtained, the final stage of the FMEA was concluded, in which the recommended actions for each failure mode were defined, as well as the frequency of execution of these actions. The results can be observed in Table 3.

Table 3. Recommended actions

Item

Recommended actions

Attendance

1

Perform back analysis of existing slopes with conservative parameters and triaxial tests.

Monthly

2

Install automated piezometers and define safety triggers (“Trigger Levels”).

Weekly (reading)

3

Installation of flow meters with turbidity monitoring.

Daily (reading)

4

Perform complementary soundings and CPTu tests on the foundation.

Semestral (essays)

5

Cleaning and maintenance of stormwater diversion channels.

Weekly (rainy season)

6

Channel lining and sizing for 100-year flood.

Monthly

7

Strict inspection at the discharge front with radio communication and blend readjustment using tractors (crawler and grader).

Daily

8

Immediate sealing of cracks with compacted material to prevent infiltration.

Immediate (if detected)

9

Seismographic monitoring and adjustment of the mine’s blast plan.

Per event (Detonation)

10

Installation of sedimentation basins before the main network.

Per event

Source: Original research results

Table 3 shows that the recommended actions were defined coherently with the fundamental principle of FMEA, which consists of prioritizing interventions proportional to the criticality of the risks identified through the NPR. The literature highlights that the effectiveness of FMEA is not limited to the identification and prioritization of failure modes, but directly depends on the ability to convert the results into clearly defined, measurable, and executable preventive and corrective actions (Carpinetti, 2020; Stamatis, 2019). In this sense, it is observed that the proposed actions encompass measures of an investigative, preventive, and corrective nature, aligned with good practices in Risk Management for geotechnical structures.

The actions associated with the highest NPR failure modes focus predominantly on controlling the water regime and the geotechnical stability of the pile, through frequent monitoring, automated instrumentation, and direct interventions in drainage and slopes. For example, for the rise in the water table (Item 5, NPR 50), the recommended action is the installation of automated piezometers and the definition of safety triggers with weekly readings. This measure aims to improve detection capacity (which had an index of 2) and reduce the occurrence of critical events. For internal erosion (“piping”) (Item 3, NPR 40), the installation of flow meters with turbidity monitoring and daily readings is proposed, complementing visual inspection and seeking earlier detection of fine material loss. The literature indicates that continuous monitoring of water levels, flows, and deformations is one of the pillars of safety management for tailings disposal structures, being essential for early detection of critical conditions and for the activation of response plans (Davies and Rice, 2021; Vick, 2020). The definition of high frequencies for inspection and instrumental readings, such as daily, weekly, or immediate actions, reflects the need for permanent vigilance over rapidly evolving risks, widely discussed in studies on recent mining failures.

For structural stability risks, such as circular slope failure (Item 1, NPR 30) and foundation settlement (Item 4, NPR 36), recommended actions include performing slope retroanalyses with conservative parameters and triaxial tests (monthly), and complementary soundings and CPTu tests on the foundation (semiannually). These actions are investigative and preventive in nature, aiming to enhance geotechnical knowledge and validate design parameters, mitigating the causes of failure related to design deficiencies. The frequency of these actions, although not daily, is continuous and systematic, ensuring the updating and robustness of stability analyses.

Operational and organizational actions, such as rigorous inspection at the discharge front (Item 7, NPR 30) with daily frequency, adjustment of the mine fire plan (Item 9, NPR 36) per event, and definition of immediate responses to anomaly identification (Item 8, NPR 40) like crack sealing, reinforce the importance of integrating technical and management aspects. Kerzner (2022) and PMI (2021) highlight that risk management in complex projects requires clear definition of responsibilities, monitoring routines, and action periodicity, to ensure the effectiveness of controls over time. Thus, Table 3 demonstrates that the recommended actions and their respective frequencies not only mitigate specific risks but also contribute to the consolidation of a structured risk management system, aligned with good project management practices and the continuous improvement of PDER’s operational safety. The implementation of these actions, with the proposed frequencies, represents a continuous effort to transform risk analysis into an improvement cycle, where early detection and rapid response are prioritized.

Integrated analysis of the results

From the individual analysis of failure modes, prioritization through the NPR, and the definition of recommended actions, it becomes possible to move towards an integrated reading of the results, with the objective of identifying patterns, interrelationships between risks, and systemic implications for PDER management. This integrated approach is fundamental in complex contexts, where risks do not act in isolation, but interdependently, influencing the overall behavior of the system (Kerzner, 2022; PMI, 2021). The results can be observed in Table 4.

Table 4. Integrated synthesis of failure modes and their predominant characteristics

Risk category

Associated failure modes

Dominant critical factor

Nature of the risk

Predominant impact

Water regime

Groundwater level rise, “piping”, “overtopping”

Presence and control of water

Geotechnical-operational

Instability and rupture

Structural stability

Slope failure, foundation settlement

Geotechnical parameters

Project/engineering

Structural collapse

Operational

Improper disposal, silting

Operational execution and control

Operational

Progressive degradation

Monitoring

Cracks, vibrations

Detection limit

Control/management

Unexpected failures

Source: Original research results

The integrated analysis evidenced in Table 4 highlights that the identified risks are not randomly distributed, but are concentrated in four major structural axes: water regime, geotechnical stability, operation, and monitoring. Among these, the predominance of risks associated with water control stands out, appearing both as a direct cause and as an aggravating factor in different failure modes. The water regime, with failure modes such as phreatic level rise, “piping”, and “overtopping”, is categorized as geotechnical-operational and its predominant impact is instability and rupture. This corroborates the literature that points to water as the main destabilizing agent in tailings disposal structures, even in dry stacking systems (Davies and Rice, 2021; Vick, 2020). More than that, the results suggest that water control should not be treated as an isolated project element, but as a transversal component that directly impacts the overall stability of the structure. Failure to manage water effectively can trigger a cascade of events, transforming a localized problem into a large-scale structural failure.

Additionally, it is observed that a relevant part of the risks classified as critical originates in phases prior to operation, especially in the planning and design stages. Structural stability failures, such as slope rupture and foundation settlement, are categorized as “Design/engineering” and have “Geotechnical parameters” as the dominant critical factor. Failures such as overestimated geotechnical parameters and inadequate design of drainage systems indicate gaps in the project’s conception phase. From a project management perspective, this result reinforces the premise that risks poorly managed in planning tend to materialize with greater severity in subsequent phases, increasing costs and impacts (Kerzner, 2022; PMI, 2021). The absence of an integrated approach between the disciplines of geotechnical engineering, hydrology, and project management in the initial phase can compromise the structure’s safety throughout its entire useful life.

Another relevant aspect refers to the limitation of detection systems. The “Monitoring” axis, with failure modes such as cracks and vibrations, is characterized by “Detection Limitation” as the dominant critical factor and has “Unforeseen Failures” as its predominant impact. Even in the presence of consolidated monitoring instruments and practices, some risks presented high NPR values due to low early identification capacity. This result highlights a gap between monitoring and interpretation, indicating that the effectiveness of controls depends not only on data collection but on the integration of this data into decision-making processes (Pillay and Wang, 2020). Simple data collection without critical, real-time analysis with well-defined action triggers does not guarantee safety. The implication is the need for intelligent monitoring systems that integrate different data sources (piezometers, topographic benchmarks, seismographs) and use algorithms to identify patterns and anomalies, alerting managers proactively.

Thus, the integrated analysis allows us to conclude that the most critical risks do not arise exclusively from isolated technical failures, but from the interaction between design, operation, and governance factors, reinforcing the need for systemic and integrated risk management approaches. The complexity of tailings piles requires risk management to be seen as a continuous and multidisciplinary process, where design decisions affect operation, and monitoring practices inform mitigation strategies.

Based on the integrated analysis of the results and the prioritization obtained through the NPR, it is possible to consolidate the prioritization of risks, highlighting those that demand greater attention in the decision-making process. This prioritization is fundamental for the efficient allocation of resources and for defining mitigation strategies proportional to the criticality of the identified risks (PMI, 2021; Stamatis, 2019). The results are presented in Table 5.

Table 5. Prioritization of failure modes based on NPR

priority

Failure Mode

NPR

Category

Origin type

1

Groundwater level rise

50

Water regime

Operational/monitoring

2

Internal erosion (“piping”)

40

Water regime

Project/operation

3

Tension cracks

40

Monitoring

Detection

4

Foundation settlement

36

Structural

Project

5

Excessive vibrations

36

Monitoring

Operational

6

Slope failure

30

Structural

Project

7

Out of specification disposition

30

Operational

Execution

Source: Original research results

The prioritization of risks shows that the most critical failure modes are strongly concentrated in factors related to the water regime, particularly the rise in the water table (NPR 50) and internal erosion (“piping”) (NPR 40). This result not only confirms trends widely discussed in the literature but also reinforces the centrality of water control as a critical element of operational safety, even in technologies considered safer, such as dry stacking (Fourie et al., 2021). The rise in the water table, classified as operational/monitoring origin, requires constant vigilance and improvement of drainage and piezometric monitoring systems. Internal erosion, of design/operation origin, demands a critical review of the filter and drain design, as well as rigorous maintenance to prevent clogging.

Furthermore, it is observed that risks associated with detection, such as tensile cracks (NPR 40), occupy high positions in prioritization, indicating that the inability to identify certain phenomena early can be as critical as their occurrence. Tensile cracks, classified as originating from monitoring/detection, highlight the need to invest in more sensitive and real-time deformation monitoring technologies, such as automated topographic monitoring systems and fiber optic sensors. This finding expands the traditional FMEA discussion by evidencing that risk management should not be limited to reducing the probability of failures, but also to improving response and detection capabilities (Pillay and Wang, 2020). Late detection of a crack can mean the loss of precious time to implement corrective actions before the failure worsens.

Another relevant point refers to the presence of risks originating in the design phase among the most critical, such as foundation settlement (NPR 36) and slope failure (NPR 30). Both are classified as structural/design origin. This result indicates a structural fragility in the planning stage, reinforcing the importance of integration between geotechnical studies, modeling, and technical validations before implementation. As highlighted by Kerzner (2022), decisions made in the initial phases of the project have a multiplier effect on risks throughout the life cycle. The practical implication is the need for a robust design review process, with the participation of independent specialists and the use of advanced modeling software to simulate different load and saturation scenarios.

Finally, the presence of operational risks in prioritization, such as out-of-specification disposition (NPR 30) and excessive vibrations (NPR 36), demonstrates that stack safety does not depend exclusively on engineering solutions, but also on the quality of execution and control of field activities. The out-of-specification disposition, of operational/execution origin, requires rigorous quality control at the discharge front. Excessive vibrations, of monitoring/operational origin, demand effective coordination between mining operations and stack management. Thus, the prioritization obtained in this study highlights the need for an integrated approach between engineering, operation, and management, aligned with good project management practices. The safety of a PDER is a continuous effort that requires the collaboration of all teams involved, from design to operation and monitoring.

Based on the results presented and discussed throughout this section, it is possible to consolidate the main evidence obtained, highlighting its implications for the risk management of tailings piles and its contribution to the field of project management applied to geotechnical structures. In general, the results showed that the risks associated with the Waste Rock and Tailings Disposal Pile are predominantly concentrated in factors related to the water regime, geotechnical stability, and limitations of monitoring systems. The application of FMEA made it possible not only to systematically identify failure modes but also to objectively rank them, evidencing which risks are most critical and require priority actions.

The analysis developed throughout the chapter allows us to state that the most critical risks do not arise exclusively from isolated technical failures, but from the interaction between design, operation, and management aspects. In this sense, the results reinforce the need for integration between disciplines and project phases, as inadequate decisions in planning tend to amplify risks during operation. Furthermore, the application of FMEA demonstrated significant potential as a decision support tool, by transforming historical and operational data into structured information for risk prioritization. This result confirms the tool’s adherence to PMI (2021) best practices, especially regarding the identification, analysis, and planning of risk responses. Finally, the findings of this study contribute to the advancement of risk management practices in tailings disposal structures, by highlighting that the adoption of safer technologies, such as dry stacking, does not eliminate the need for formal and integrated management systems. On the contrary, it reinforces the importance of structured, continuous, and evidence-based approaches capable of supporting decision-making in environments of high complexity and criticality.

4. Conclusion

It is concluded that the objective was achieved, as the study successfully analyzed risk management in tailings piles of a mining company, applying the Failure Mode and Effects Analysis (FMEA) tool from a project management perspective. The application of FMEA allowed for the objective identification, analysis, and prioritization of failure modes, highlighting the predominance of risks related to the water regime, geotechnical stability, and limitations of monitoring systems. The results reinforced that the most critical risks do not arise from isolated technical failures, but from the complex interaction between design, operation, and governance factors, underscoring the need for systemic and integrated approaches to operational safety and decision-making in the mining sector.

This study, however, has limitations inherent to its nature as a single case study, which restricts the direct generalization of results to other mining companies or contexts. Furthermore, the assignment of Severity, Occurrence, and Detection indices in the FMEA, although based on historical data and literature, involved technical judgment, introducing a degree of subjectivity. For future studies, it is suggested to apply FMEA to multiple companies for validation and comparison, to evaluate the effectiveness of recommended actions after their implementation, and to develop more advanced monitoring systems that integrate real-time data and artificial intelligence for early detection. It is also recommended to deepen research on the regulatory gap for dry tailings piles in Brazil, proposing specific guidelines for the sector.

Bibliographic References

Agência Nacional De Mineração [ANM]. 2023. Agenda regulatória da ANM 2023–2025. Brasília, DF, Brasil.

Almeida, M.R.; Lima, H.M.; Silva, D.F. 2021. Risk management practices applied to mine waste disposal structures. Journal of Sustainable Mining 20(4): 220-232.

Carpinetti, L.C.R. 2020. Gestão da qualidade: conceitos e técnicas. 3ed. Atlas, São Paulo, SP, Brasil.

Creswell, J.W.; Creswell, J.D. 2018. Research design: qualitative, quantitative, and mixed methods approaches. 5ed. Sage Publications, Thousand Oaks, CA, EUA.

Davies, M.P.; Rice, S. 2021. An alternative to conventional tailings management – filtered tailings. In: Tailings And Mine Waste Conference. University of British Columbia, Vancouver, Canadá.

Fourie, A.; Davies, M.; Martin, T. 2021. Tailings management after recent failures: lessons learned and future directions. Soils and Rocks 44(2): 139-153.

Freitas, C.M.; Barcellos, C.; Asmus, C.I.R.F.; Silva, M.A.; Xavier, D.R. 2019. O desastre na barragem de mineração da Samarco: fragilidades institucionais e impactos à saúde coletiva. Ciência & Saúde Coletiva 24(10): 3705-3716.

Garcia, L.P. 2022. Desastres de mineração no Brasil: lições de Mariana e Brumadinho. Revista Brasileira de Epidemiologia 25: e220002.

Gil, A.C. 2019. Métodos e técnicas de pesquisa social. 7ed. Atlas, São Paulo, SP, Brasil.

Kerzner, H. 2022. Project management best practices: achieving global excellence. 5ed. John Wiley & Sons, Hoboken, NJ, EUA.

Marconi, M.A.; Lakatos, E.M. 2022. Fundamentos de metodologia científica. 9ed. Atlas, São Paulo, SP, Brasil.

Oliveira, M.L. Wanderley, L.J.M.; Milanez, B.; Zucarelli, M.C. 2021. Environmental disaster in Brumadinho, Brazil: impacts, risks and governance failures. Ambiente & Sociedade 24: e01191.

Pillay, A.; Wang, Ji. 2020. Modified failure mode and effects analysis using approximate reasoning. Reliability Engineering & System Safety 79: 69-85.

Project Management Institute [PMI]. 2021. A guide to the Project Management Body of Knowledge (PMBOK® Guide). 7ed. Project Management Institute, Newtown Square, PA, EUA.

Silva, D.R.; Rocha, H.C. 2022. Descomissionamento de barragens de rejeitos no Brasil: aspectos técnicos e regulatórios. Revista Brasileira de Engenharia Geotécnica 12(2): 55-70.

Silva, L.A.; Costa, J.M.; Pereira, F.R. 2023. Regulatory gaps in dry stacking tailings management. Journal of Environmental Management 332.

Stamatis, D.H. 2019. Failure mode and effect analysis: FMEA from theory to execution. 3ed. ASQ Quality Press, Milwaukee, EUA.

Vick, S.G. 2020. Planning, design, and analysis of tailings dams. 2.d. ASCE Press, Reston, Virginia, EUA.

Yin, R.K. 2021. Case study research and applications: design and methods. 6ed. Sage Publications, Thousand Oaks, CA, EUA.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving the independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated the automated reading of files, the organization of curves into current-potential matrices, the generation of the potential map, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed by device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of the results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and enhance the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used for the definition and identification of the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.