Management of Simultaneous Operations Risk in Petroleum Production Development Projects
Marina Barroso Alves; Fabrício Martins Lacerda
DOI: 10.22167/2675-6528-202601199
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
Simultaneous Operations (SIMOPs) represent an inherent risk in the deployment phase of offshore oil production development projects, characterized by activities occurring in the same period and area, with the potential to generate conflicts and negative impacts. The study aimed to analyze the approach adopted for managing the risk of offshore SIMOPs and evaluate its effectiveness in achieving the expected project outcomes. To this end, a qualitative and exploratory case study was employed, conducted in a Brazilian oil and gas company, with data collection through documentary analysis, participant observation, and the application of a questionnaire to ten specialists involved in the project. The results indicated that the integrated approach, based on project management best practices (PMI) in the domains of risks, schedule, and stakeholders, was effective. Alignment was found between the employed approach and the theoretical framework, which enabled the mitigation of SIMOPs risk. The project achieved the FPSO start-up on time, with optimized production increase, and the simultaneous operations carried out followed safety measures, without accidents or additional costs. It was concluded that adapting project management best practices is a sound strategy for managing SIMOPs risk, even in the absence of specific organizational standards, contributing to project success.
Keywords: Project Management; Risk Management; Offshore; Simultaneous Operations; Oil.
1. Introduction
The oil and gas (O&G) industry plays a strategic role in the Brazilian and global economy. Brazil is the eighth largest oil producer in the world (IBP, 2025), with the domestic energy supply (OIE) in 2024 being 34% from oil and derivatives and 9.6% from natural gas (BEN, 2025). The oil sector contributes 17% to Brazil’s industrial GDP (IBP, 2025). Most of this production, 97.6% of oil and 85.3% of natural gas, originates from offshore fields (ANP, 2025), with 79.4% of Brazilian offshore production coming from pre-salt fields (ANP, 2025).
The development of oil and gas production in marine environments, especially offshore, involves megaprojects. These ventures are complex and high-cost, frequently exceeding one billion dollars (Flyvbjerg, 2014). Such projects range from the definition of reservoir drainage grids and well construction, to the interconnection and installation of subsea equipment, as well as the construction, assembly, and commissioning of platforms. They require the involvement of diverse stakeholders (Freeman, 1984) and are subject to strict regulations, such as environmental licensing (CONAMA Resolution No. 237/1997, Brazil, 1997).
In this scenario of high complexity and multiple actors, one of the inherent risks in the implementation phase of offshore oil production development projects is simultaneous operations, known as SIMOPs. This concept refers to activities that occur in the same period and in the same area in offshore environments (IMCA, 2010). For each type of operation, there are specific spatial restrictions that determine the occurrence of SIMOPs, and the safest strategy to mitigate this risk is preferably to avoid it through the temporal decoupling of activities.
SIMOPs represent potential conflicts between two or more vessels or operational units, requiring rigorous management to prevent environmental and operational safety risks. The coexistence of simultaneous operations is considered a last resort, being recommended only after all possibilities of avoiding concomitance have been exhausted. The materialization of these risks can lead to significant financial impacts, such as payment for vessel waiting time and millionaire losses resulting from collisions or impacts (Stuart et al., 2015). In addition to physical and financial damages, effective SIMOPs management is crucial to keep the schedules of different operations within the planned timeframe.
Considering the relevance of simultaneous operations management for the success of oil production development projects, this study aligns with good project management practices. Three performance domains from the Project Management Institute (PMI, 2025) were selected as focus: Risks, Schedule, and Stakeholders. The Risks domain is fundamental for anticipating and adapting to uncertainties, ensuring project continuity (PMI, 2024). The Schedule is essential for planning the delivery of results (PMI, 2025), intrinsically linked to SIMOPs by the concurrency of activities. The Stakeholders domain acts as a tool for risk management and facilitates monitoring and control, ensuring the engagement of involved parties (Rajhans, 2018).
Despite international and Brazilian regulations governing SIMOPs, the central problem of this work lies in the need to establish an integrated approach for the management of simultaneous operations risk, which goes beyond regulatory compliance and incorporates project management best practices. The complexity of offshore projects, with their multiple activities and stakeholders, demands efficient coordination to mitigate SIMOPs, avoiding negative impacts on schedule and cost. The justification for this research lies in the importance of evaluating the effectiveness of an approach that coordinates activities such as subsea engineering, well construction, seismic data acquisition, offloading, and commissioning, seeking to avoid simultaneities and manage risks when coexistence is inevitable. Given this scenario, the objective of this study is to analyze the approach adopted for the management of offshore simultaneous operations risk and its effectiveness in achieving the expected project results.
2. Material and Methods
The methodology employed in this study was characterized as a single type case study, according to the guidelines of Gil (2017). The research adopted a qualitative approach and had an exploratory nature, seeking to deepen the understanding of the relationship between project management domains and the mitigation of the risk of simultaneous operations. The empirical object was a project for the development of oil production in its implementation phase, located in a field in ultra-deep waters in Brazil, within a Brazilian company in the oil and gas industry.
The study participants were ten specialists directly involved in the practices and routines related to the management of simultaneous operations (SIMOPs) in the analyzed project. The selection of these individuals occurred due to their active participation and in-depth knowledge of risk management, schedule, and stakeholder management activities and processes, which are central elements for understanding the approach adopted in the context of SIMOPs.
Data collection was carried out through a triangulation of sources, using documentary analysis, participant observation, and the application of a structured questionnaire. This combination of instruments aimed to obtain a comprehensive and rigorous understanding of the procedures and the effectiveness of the SIMOPs management approach, as recommended for case studies (Gil, 2017).
In the documentary analysis, several project records were examined. Twelve meeting minutes, covering the period from November 2024 to February 2025, and four PowerPoint presentations intended for management level, held between July 2024 and October 2025, were collected. Additionally, spreadsheets with project integration room records, emails, schedules created in Primavera and Excel software, in PDF format, and conversation logs from Teams groups were analyzed.
Participant observation was a fundamental technique, as the author of this study integrated the project team, allowing for direct monitoring of SIMOPs management routines and practices. Complementarily, organizational portals, software, and applications were consulted, serving as additional data sources, providing information on workflow and team interaction.
The questionnaire applied to the ten specialists was composed of 20 questions, distributed in five thematic blocks. The first block was dedicated to identifying the respondents’ profile. The subsequent blocks, from two to five, contained statements related to the domains of Project Risk Management, Schedule Management, Stakeholder Management, and Project Communication, respectively. For these statements, a 5-point Likert scale was used, ranging from “Strongly disagree” to “Strongly agree”.
In addition to Likert scale issues, the questionnaire included an optional open-ended question, which asked respondents for their general perceptions of managing the risk of simultaneous operations in the project. The questionnaire structure aimed to collect data on the application of project management best practices in the domains of risks, schedule, and stakeholders, according to the recommendations of the Project Management Institute (PMI, 2025).
For risk management, tools such as an internal corporate portal for risk registration and classification, market software for quantitative analysis, and Power BI dashboards for executive and internal monitoring were used. In schedule management, Primavera P6 was employed for the master schedule, Excel spreadsheets for short-term detailing, a web application for drillship schedules, and a georeferenced corporate software to spatially identify SIMOPs. For stakeholder management, Microsoft Teams, Word, and Outlook were used for communication and deliberation recording.
The analysis of the collected data followed the steps of coding, establishment of analytical categories, and data display, according to the methodology of Gil (2017). Coding consisted of assigning meaning to the emergent concepts from the data sources, allowing their organization into categories. The establishment of analytical categories was derived from the patterns identified during coding, seeking similarity between the data. Subsequently, the data were organized to enable comparison with the theoretical framework.
3. Results and Discussion
The analysis of the approach to managing the risk of simultaneous operations (SIMOPs) in an offshore oil production development project revealed an integrated and multifaceted strategy. This study sought to understand how project management best practices, focused on the domains of risks, schedule, and stakeholders, were applied to mitigate the challenges inherent in SIMOPs and contribute to the project’s success. The findings demonstrate that the ability to adapt to dynamic offshore environmental conditions, such as wind, waves, and currents, is fundamental for the effective planning of activities, which are naturally permeated by uncertainties.
The identification of potential simultaneity of operations as a critical risk occurred early in the project implementation phase, highlighting the importance of a proactive approach. The main recommendation for SIMOPs management is the temporal decoupling of activities, aiming to avoid the coexistence of two maritime units at distances less than those established by authorities and organizational rules. Only after exhausting all temporal separation alternatives is a detailed Preliminary Risk Analysis (PRA) conducted to assess the safety of coexistence, as advocated by good risk management practices.
Performance Domain of Risks
In the domain of risk performance, the last quantitative analysis performed before the platform’s production start identified the “Risk of Simultaneous Operations between pre-mooring, probe operations (drilling and completion) and FPSO arrival”. This risk was estimated with a 20% probability and a potential impact of 0 to 6 days delay, directly associated with the pre-mooring activity. The management of this risk demanded careful planning and execution of responses, aligned with the project management methodology.
Other relevant risks related to SIMOPs were recorded in the corporate portal. These included the risk of vessel conflicts with other platform operations during anchoring, start-up, and ramp-up, with the potential for schedule slippage due to boat idle periods and impact on production. Additionally, the risk of delayed well tie-in due to simultaneity with offloading operations was identified, which could result in delayed ramp-up. The categorization and recording of these risks were crucial for defining mitigation strategies.
The predominant response to the identified SIMOPs risks was mitigation, which involved establishing specific actions to reduce the probability of their occurrence. Continuous monitoring of risks and their actions was carried out by a designated project manager, using support tools such as risk dashboards and the corporate portal. The monthly review of the probability and impact of risks, as well as the update of their status (active, completed, canceled), provided essential subsidies for the project panel, ensuring visibility and effective control.
The mitigation actions recorded on the portal included adjusting the line launch sequence based on rig operations and planning the riser tie-in to allow the dive to occur during pumping. Through participant observation, the creation of a SIMOPs forum and periodic verification of interferences between vessels were identified, in addition to the analysis of the schedule and subsea layout to identify potential simultaneities. These actions demonstrate a coordinated effort to anticipate and resolve conflicts, minimizing negative impacts.
The planning and monitoring of offshore activities via the project’s War Room, as well as the evaluation of interfaces and risks in specific workshops with the participation of the organization and supplier companies, were crucial. These processes demonstrate the application of good risk management practices, which include consideration of technical, social, political, market, and economic contexts, according to PMI (2024) guidelines. The project team demonstrated proactivity in exploring and responding to uncertainties, aligning risk responses with the project’s budget, schedule, and performance constraints.
The tools used for risk management were diverse and integrated. The internal corporate portal allowed for the registration and qualitative classification of risks, the description of response strategies, and mitigation actions. A market software was employed for quantitative risk analysis, while Power BI dashboards were used for managerial presentations and internal monitoring, indicating the status of risks and the expiration of actions. An Excel spreadsheet, developed based on lessons learned from previous projects, monitored offshore activities, wind forecasting, and wave height, optimizing vigilance over SIMOPs.
Schedule Performance Domain
The schedule management plan for the project was already established by organizational standards and project office procedures, covering the monthly update of the physical and financial schedule, the review of dates, the status of activities, and the recording of progress. The integrated schedule, or master, was developed before the implementation phase, and with the start of field operations, the short-term schedules, known as “look ahead”, with a horizon of two weeks to two months, began to be provided by the contracted companies for offshore operations.
The master schedule monitoring was performed weekly, based on short-term schedules, to identify simultaneities, update projections, and check for new risks. This practice allowed for the proactive identification of SIMOPs, which became one of the main risk response actions, especially through the combined analysis of schedule and subsea arrangement. Participation in inter-project meetings, such as those for allocating critical resources for well activities, was essential to identify SIMOPs involving field operations, such as seismic acquisition.
The concomitant operations identified included well construction, platform anchoring, well tie-in, subsea equipment installation, well commissioning, offloading operations, and seismic acquisition. To manage these complexities, it was crucial to integrate the subsea layout into a georeferenced software. This software allowed for the visualization on a single map of the wells, the project’s subsea pipelines and their respective restriction areas, as well as all adjacent FPSOs in operation and in the design phase, with their registered layouts.
The capability of the georeferenced software to assign schedules to the subsea arrangement and hatch the occurrence locations of SIMOPs, indicating the overlap periods, was a valuable tool. Although only the construction of wells, subsea interconnections, and installation of some subsea equipment were in the master schedule, most of the other activities required the development of complementary schedules in Excel, and in some cases, new activities were created in the master schedule to increase the level of detail and accuracy in identifying SIMOPs.
The schedule management processes were met, with schedule management planning being developed by the PMO and applied to multiple projects. The master schedule development occurred in previous stages, but complementary schedules were elaborated for greater detail of the SIMOPs. Evidence of the implementation of these processes was found in Primavera P6, daily tracking spreadsheets, SIMOPs identification spreadsheets in georeferenced software, monthly guidance emails, and group chats on Teams.
Schedule monitoring and control followed the frequency established by project governance, with on-demand updates to anticipate and predict SIMOPs. A dashboard was used to track SIMOPs with automated updates from the probe schedules and the master schedule. All PMBOK processes for schedule planning and monitoring and control were adopted, demonstrating adherence to best practices. Verified outputs included the Schedule Management Plan, the schedule baseline, its updates, the project schedule, and activity attributes.
The schedule documentation was considered complete, using software for development, monitoring, and control. Duration estimating techniques, such as expert judgment and historical data from similar activities, were employed for the detailed schedules. The project approach was predominantly predictive, suitable for megaprojects with defined deliverables and safety requirements, but a hybrid approach was used for short-term offshore activities, considering weather conditions and vessel availability. The project was represented holistically, with float calculated based on quantitative risk analyses.
Stakeholder Performance Domain
The identification of stakeholders, both internal and external to the project, was a fundamental step to establish communications, initiate stakeholder management, enable schedule analyses, monitor risks, and decide on solutions for potential conflicts. Internally, the project directly related to four management areas: implementation of subsea projects, well construction, platform operation, and integrated project management. The managers of these areas were the initial focal points, and from them, technical professionals were consulted for concurrency analyses.
Externally, stakeholders included the contractor company for subsea Engineering, Procurement, Construction, and Installation (EPCI), the company responsible for platform operation, the organization’s seismic team, and the external company contracted for seismic acquisition. The mapping of these stakeholders was detailed for the main categories of simultaneities, such as SIMOPs between well construction and subsea EPCI, seismic and subsea EPCI, and seismic with interconnections and FPSO diving activities. For each scenario, the managers and professionals involved were identified, including supervisors on vessels and reservoir focal points.
The structuring of routines and the dynamics of meetings were established to pace the analysis of spatial and temporal constraints. Three types of forums were instituted for discussions and decisions on simultaneities, given the dynamic nature of SIMOPs. The update frequency for offshore activities of the subsea EPCI and seismic surveys was weekly, while the drilling rig schedule was bi-weekly. Thus, a weekly frequency was defined for the analysis of schedule inputs, with the objective of proactively identifying simultaneities.
The initial analysis of activities was carried out individually by the integrated project planner, considering the dependence on meteoceanographic and operational conditions of the boats, which introduce uncertainties into the schedules. This approach allowed for the identification not only of overlapping periods but also of possible simultaneities, considering delays or anticipations in operations. After this individual analysis, potential conflicts were brought to a discussion forum, with the participation of technical representatives from each involved area and the integrated project planner.
Area managers were kept updated on the meeting agenda, the analyzed SIMOPs, and the solutions found through chats. All members had access to the documents and could collaborate on the analyses. During meetings, alternatives to avoid SIMOPs were discussed, prioritizing the most likely ones. Daily monitoring of some activities was necessary to verify the effective occurrence of SIMOPs. Solutions included replanning the schedule or conducting APRs for coexistence, even in situations of doubt about the realization of simultaneity.
Stakeholder management was essential to engage competent professionals in the analysis of the various schedules, seeking the best integrated replanning and considering organizational impacts. Although there was no formal stakeholder engagement plan, the intention to keep them informed about risks, schedule changes, and listen to their perceptions to find solutions was evident. The weekly frequency of meetings and centralized communication about general updates and discussions served as an informal communication plan.
Communication channels included group chats on Microsoft Teams for urgent and important communications, and emails for disseminating agendas and meeting follow-ups, especially for management not directly participating in the project. No formal stakeholder satisfaction surveys were conducted, but the questionnaire applied in this study revealed positive recognition of stakeholder management and communications, with averages of 4.0 and 4.4, respectively, on a 5-point Likert scale. Engagement monitoring occurred tacitly through constant and representative participation in meetings.
Stakeholder assessment on SIMOPs management
The questionnaire applied to ten specialists involved in SIMOPs management practices revealed a positive evaluation of the approach used. The sample, composed of 90% men and 10% women, all with complete higher education and half with postgraduate degrees, ensured the representativeness of the organization’s areas involved in the analyses. All evaluated dimensions – risks, schedule, stakeholders, and communication – obtained averages equal to or higher than 4.0 on the Likert scale, indicating a general agreement with the good management practices employed.
Specifically, the Schedule domain obtained the highest average, with 4.5, followed by Risks and Communication, both with 4.4, and Stakeholders with 4.0. The statements with the lowest averages (4.0, 3.8, and 3.5) referred to the existence of formal processes in the organization for managing risks, schedule, and stakeholders, respectively. It was observed that the areas directly linked to projects assigned higher scores to these statements, which is expected, as these areas have greater familiarity with the standards inherent in their routine activities.
On the other hand, the statements with the highest averages (4.6, 4.7, and 4.8) highlighted the interviewees’ recognition that the risk of SIMOPs was identified, recorded, and monitored throughout the project. There was also a strong recognition of the contribution of schedule management to the mitigation of SIMOPs risk and to the management of overall project risks. These perceptions reinforce the effectiveness of the adopted approach, even in the absence of formalized organizational standards for SIMOPs.
The answers to the optional open-ended question of the questionnaire complemented these findings, pointing to the absence and the need for the creation of specific organizational standards and processes for the management of simultaneous operations. Another highlighted challenge was the alignment of the diverse interests of stakeholders and the contractual issues of each operation. However, swift and judicious decision-making, with scenario analysis, was mentioned as a positive point. These results indicate that, despite the formal gaps, the integrated approach was successful in practice.
In summary, the research demonstrated that the integrated approach to SIMOPs risk management, based on project management best practices in the domains of risks, schedule, and stakeholders, was effective. Consistent alignment was found between the practices employed and the PMI theoretical framework, which enabled the mitigation of SIMOPs risk. The project achieved the start-up of the FPSO within the planned timeframe, with optimized production increase, and the simultaneous operations that occurred followed safety measures, without accidents, incidents, or additional costs. Proactive schedule management and stakeholder engagement were crucial to de-escalate SIMOPs and support replanning decisions, ensuring risk mitigation.
4. Conclusion
This study sought to analyze the approach adopted for the management of simultaneous operations (SIMOPs) risk offshore and its effectiveness in achieving the expected project results. It was found that the integrated strategy, based on good project management practices in the domains of risks, schedule, and stakeholders, proved to be effective. A consistent alignment was observed between the practices employed and the theoretical framework of the Project Management Institute (PMI), which enabled the mitigation of SIMOPs risk. The project achieved the start-up of the FPSO within the planned timeframe, with an optimized production increase, reaching the platform’s production peak more than two months ahead of schedule. The simultaneous operations that materialized strictly followed safety measures, with no record of accidents, incidents, or additional costs. Proactive schedule management and stakeholder engagement were crucial for decoupling SIMOPs and supporting replanning decisions, ensuring risk mitigation.
The main contribution of this work lies in demonstrating that the adaptation of project management best practices is a sound strategy for managing SIMOPs risk, even in the absence of specific organizational standards, directly contributing to project success. However, the study has limitations due to being a single case, qualitative in nature, and restricted to a development project in a Brazilian pre-salt field. For future studies, it is suggested to evaluate the applicability and effectiveness of this approach in mature fields in Brazil, such as in oil production revitalization projects, and in production development projects in other parts of the world, in order to broaden the generalization of the findings.
Bibliographic References
Agência Nacional do Petróleo, Gás Natural e Biocombustíveis (ANP). Agosto, 2025. Boletim Da Produção De Petróleo E Gás Natural. Boletim Mensal. Número 180.
Brasil. Conselho Nacional do Meio Ambiente (CONAMA). 1997. Resolução n° 237, de 19 de dezembro de 1997. Dispõe sobre a revisão e complementação dos procedimentos e critérios utilizados para o licenciamento ambiental. Diário Oficial da União: seção 1, Brasília, DF, n. 247, p. 30.829–30.830, 22 dez. 1997.
Empresa de Pesquisa Energética (EPE). 2025. Balanço Energético Nacional (BEN).
Flyvbjerg, B. 2014. What you should know about megaprojects and why: an overview. Project Management Journal, 45(2), 6–19.
Freeman, E. 1984. Strategic Management: A Stakeholder Approach. Pitman. Boston, EUA.
Gil, A. C. 2017. Como Elaborar Projetos de Pesquisa. Atlas, São Paulo, SP. Brasil.
International Marine Contractors Association (IMCA). 2010. Guidance on Simultaneous Operations (SIMOPS).
Project Management Institute [PMI]. 2024. Risk Management in Portfolios, Programs and Projects: A Practice Guide. Newtown Square, PA, EUA.
Project Management Institute [PMI]. 2025. Padrão de Gerenciamento de Projetos e Guia do conhecimento em gerenciamento de projetos (Guia PMBOK). 8ed. Newtown Square, PA, EUA.
Rajhans, K. 2018. Effective Communication Management: A Key to Stakeholder Relationship Management in Project-Based Organizations
Stuart, D.; Pemberton, G.; Strater, L. 2015. Managing Simultaneous Operations During Seismic Acquisition in Offshore Fields. World Oil. (236): 53-55.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq