Project scope management: test bench for a top-down force system

Paulo Ricardo da Silva Pereira; Luís Felipe Vendramim

DOI: 10.22167/2675-6528-202601302

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The Brazilian agribusiness, driven by Precision Agriculture, demands efficient technologies, such as planting mechanisms. The study’s objective was to present the scope management of a project to develop a validation test bench in an agribusiness company. To this end, consolidated management tools were applied, such as the Project Charter (TAP) and the Work Breakdown Structure (WBS), aiming to mitigate “scope creep” risks and meet stakeholder expectations. The research, descriptive in nature, adopted a single case study methodology, based on the best practices of the PMBOK Guide, structuring the management into inputs, tools, and outputs. The main results included the elaboration of the Project Charter, which defined mandatory requirements such as support interchangeability and compliance with safety standards. The application of technical meetings and expert opinion allowed for the detailing of the “Bill of Materials” (BOM) and the formalization of the Scope Statement, establishing clear boundaries between included and excluded items. The creation of the WBS decomposed the work into manageable packages, facilitating technical control. It was concluded that the application of these management tools effectively mitigated the risk of uncontrolled scope increase, ensuring that the delivered test bench met all stakeholder needs and expectations within the project constraints. The research contributed to the academic literature by empirically demonstrating the effectiveness of the structured application of the PMBOK Guide’s theoretical processes in an applied engineering environment.

Keywords: Agribusiness; Engineering; Jiga; NR12; PMBOK.

1. Introduction

The Brazilian agribusiness is a strategic pillar of the national economy, driven by vast cultivable area and continuous investments in technology. This sector not only guarantees the supply of food, fiber, and bioenergy but also stands out globally (RIT, 2025). In 2023, Brazil became the world’s largest exporter of grains, accounting for 26.3% of the global total and surpassing the United States (FAO, 2024). Its economic relevance is reinforced by its 29.4% contribution to the Gross Domestic Product in 2025 and by being a significant source of employment (Cepea, 2025). To maintain competitiveness and optimize efficiency, Precision Agriculture (PA) is essential. PA considers the spatial and temporal variability of crops to enhance sustainability, maximize economic return, and reduce environmental impact (International Society of Precision Agriculture, 2020). Unlike conventional machinery, PA equipment is programmable, adjusting input application in real-time or according to variability maps, treating each geographic coordinate according to its needs (Embrapa, 2020).

In this scenario of technological advancement, the demand for solutions that guarantee the uniformity and quality of planting is growing. Downforce systems in planters are a prime example. These mechanisms ensure proper contact of the cutting disc with the soil and correct penetration of the planting unit, regardless of terrain variations. The application of controlled force is fundamental for seeds to be deposited at the ideal depth, promoting the development of more vigorous and productive plants (Oliveira, 2021). Downforce systems can be mechanical (springs) or hydraulic/pneumatic, the latter offering more refined control. In hydraulic or pneumatic systems, operation can be configured in fixed or active mode. While fixed mode maintains a predefined force, active mode automatically adjusts the downforce through an electronic module and load sensors, adapting to terrain conditions. This results in superior precision in applying force to the soil, improving plantability (Oliveira, 2021). The complexity and criticality of these systems require rigorous validation of their functionality and precision.

The development and validation of complex technologies, such as downforce systems, demand robust and structured project management. The absence of effective management can lead to scope deviations, delays, and budget overruns, compromising quality and stakeholder expectations. In this scenario, good project management practices, as outlined by the Project Management Institute (PMI) in its PMBOK Guide (Project Management Institute, 2021), offer a fundamental theoretical and practical framework. Scope Management, in particular, is one of the pillars for the success of any endeavor, as it involves defining, verifying, and controlling what is included and excluded from the project. The formalization of scope and the decomposition of work into manageable packages are crucial to mitigate the risk of “scope creep” – the uncontrolled increase in scope that can arise from unplanned or poorly documented requests (Project Management Institute, 2021). The rigorous application of these principles in applied engineering projects is fundamental to ensure that deliverables meet technical and safety requirements, such as Regulatory Standard twelve (Brazil, 2019), and user expectations.

The complexity of downstream force systems and the need to ensure the accuracy of load sensors impose the validation of these components at the end of the production line as a critical requirement for agribusiness companies. The organization under study, a developer of these systems, identified the demand for a test bench capable of validating these sensors efficiently and safely. The challenge transcends technical execution, encompassing project management to ensure requirements alignment, risk mitigation, and adherence to deadlines and costs. The relevance of this study lies in the empirical demonstration of the structured application of scope management tools, based on the PMBOK Guide, in a real engineering project. Given the above, the objective of this work is to present the scope management of a project to develop a validation test bench for downstream force systems in an agribusiness company, aiming to mitigate risks of “scope creep” and ensure the delivery of a product that fully meets the defined requirements.

2. Material and Methods

The present research is characterized as descriptive in its objectives, aiming to detail the practical application of scope management tools in a real project. A single case study methodology was adopted, a qualitative approach that allowed for an in-depth analysis of a specific unit in its real context (Godoy, 1995). This empirical investigation strategy is appropriate for examining contemporary phenomena in their natural environment (Yin, 2001), focusing on the particularity of the singular case without seeking statistical generalizations (Stake, 1978). The study was conducted in a Brazilian agribusiness company, in the Research and Development department in São Paulo.

The research period extended from October 2023 to July 2024. The studied organization, a Brazilian company with 26 years of operation in the agricultural sector, has R&D centers in São Paulo and Curitiba, in addition to an industrial headquarters in Caldas Novas (GO). The specific focus of the investigation was on the scope management process for the development of a test bench. This bench was designed for the validation of downward force sensors, critical components in the production line of agricultural equipment, manufactured at the headquarters in Caldas Novas.

The research involved the stakeholders directly linked to the test bench project, acting as the unit of analysis for the management process. Mechanical and Electronic Engineering were considered the “internal clients”, responsible for requesting the project and defining the technical requirements and approval criteria. Applied Engineering, in turn, played the role of the executing and support area, responsible for managing the scope, designing, and manufacturing the bench. This internal client and supplier configuration was fundamental for defining and aligning project expectations and requirements.

Data collection and analysis were structured based on the best practices of project management described in the PMBOK Guide (Project Management Institute [PMI], 2021). The methodology followed the standardized PMI process flow, which organizes scope management through the interrelationship between Inputs, Tools and Techniques, and Outputs. The Inputs represented the initial documents and information, with the Project Charter (TAP) being the fundamental document. This formalized the project’s existence, conferred authority to the manager, and established high-level requirements and constraints (PMI, 2021), complemented by data gathering and document analysis.

For the processing of information and the technical refinement of the scope, specific Tools and Techniques were employed. The “Expert Opinion” of experts in relevant areas was used to define critical components and ensure technical feasibility. Additionally, alignment “Meetings” were held, serving as forums for information exchange, decision deliberation, and expectation alignment among stakeholders. The Outputs corresponded to the products and documents generated, notably the Work Breakdown Structure (WBS), the Scope Management Plan, and the Scope Statement, culminating in client validation.

The project execution began with the elaboration of the Project Charter (TAP) in October 2023, formalizing the undertaking and establishing the initial requirements. The TAP defined that the bench should apply a controlled reference force to the sensor, using a linear actuator to simulate operating conditions. A mandatory requirement was the flexibility of the structure, allowing interchangeability or adjustment for different stopper geometries. Additionally, the need for an independent force measurement system, via a load cell, was stipulated to compare the electrical signal from the stopper with the expected value.

After the formalization of the Project Charter, the scope detailing was conducted through alignment meetings, held between October 2023 and January 2024. These meetings, recorded in “Confluence”, involved the engineering teams and allowed for the definition that the test bench would initially serve the “John Deere 2100” model, with adjustable supports for future flexibility. Structural robustness and operational safety were prioritized, using 40×40 mm aluminum profiles and compliance with Regulatory Standard 12 (Brazil, 2019). Expert opinion was crucial for the pneumatic scheme and the selection of components such as the S-type 200 kg load cell and the HX711 converter module, in addition to the control panel architecture.

With the definition of the technical architecture and the selection of critical components, the “Bill of Materials” (BOM) was elaborated, which consolidated all the items necessary for the assembly of the bench, categorizing them into subgroups such as pneumatic structure and electrical components. The BOM was essential for quantifying inputs and establishing the preliminary budget estimate. Subsequently, the Scope Statement was formalized, clearly delimiting what would be delivered and what was outside the team’s responsibility, such as versatility for different stops and transportation logistics, mitigating risks of “scope creep”.

To ensure the organized delivery of the scope, the Work Breakdown Structure (WBS) was created, decomposing the work into manageable packages and facilitating alignment between technical areas. The WBS was developed based on the Bill of Materials and the defined subsystems, allowing for prompt identification of out-of-scope tasks. In parallel, a rigorous integrated change control process was established. Any technical alteration required a formal impact analysis, assessing its effects on scope, time, and cost, and was incorporated into the baseline only after validation of its necessity and feasibility.

Scope management was finalized with the clear definition of acceptance and control criteria. The test bench validation was conditioned on approval in two mandatory tests: the functional test, which verified electrical reading via the acquisition system, and the load validation, which directly compared the force applied by the jig with the stop signal. However, it is important to highlight the methodological limitations of this single case study, conducted between October 2023 and July 2024, in a specific organization. This particularity restricts the direct generalization of the results to other contexts or projects, although the applied methodology can serve as a reference.

3. Results and Discussion

This case study, conducted between October 2023 and July 2024, emerged from a pressing need of the Research and Development (R&D) department of an agribusiness company, driven by the growing demand for Precision Agriculture technologies. The central initiative was the creation of a new load sensor for downforce systems, crucial components in modern planters, as highlighted by Oliveira (2021), who emphasizes the importance of controlled downforce for seeding quality. To ensure the functionality and accuracy of this sensor in various furrower configurations, the construction of a test bench became imperative. This bench would not only serve as a validation tool but also as a benchmark for the sensor’s performance, ensuring that the final product met the rigorous quality standards required by the agribusiness market, a vital sector for the Brazilian economy, as pointed out by Cepea (2025). The inherent complexity of these downforce systems, which demand high precision and adaptability, underscores the criticality of a robust and well-managed validation process.

The stakeholder mobilization was one of the first and most fundamental steps in the test bench design, establishing a clear internal client and supplier dynamic that is essential for effective scope management, as advocated by the Project Management Institute (PMI, 2021). The Mechanical and Electronic engineering departments, directly responsible for the load sensor development, assumed the role of “internal clients”. Their primary function was to request the bench design and, crucially, to define the detailed technical requirements and approval criteria. This direct involvement of clients from the initial phases is vital, as Yin (2001) argues in his case studies, a deep understanding of end-user needs is a pillar for project success. The active participation of these engineering departments, supported by a field technician and a mechanical designer, ensured that the requirements were not only technical but also aligned with operational realities and the final product’s performance expectations. Clarity in defining roles and responsibilities from the project’s outset is a critical factor in avoiding ambiguities and potential scope conflicts in the future, fostering a collaborative environment focused on value delivery.

In contrast, Applied Engineering played the role of the executing and support area, assuming full responsibility for the scope management, design, and physical fabrication of the test bench, internally referred to as “test jig” or “jig”. The designation “jig” is a technical term that, in this context, describes a specialized mechanical structure designed to facilitate quick and repetitive electrical connection between the test system and the components to be validated. The main objective of Applied Engineering was to ensure that tests were executed safely, efficiently, and consistently, strictly adhering to the criteria established by internal clients. This division of responsibilities, with one team dedicated to execution and another to defining requirements, mirrors best practices in project management, where the segregation of functions contributes to specialization and process optimization. Applied Engineering’s ability to translate complex internal client requirements into a tangible and functional design demonstrates the importance of a competent technical team aligned with project objectives, mitigating risks of misinterpretation and rework.

The formalization of the project had its initial milestone with the elaboration of the Project Charter (TAP), a fundamental document that, according to PMI (2021), formalizes the project’s existence, grants authority to the manager, and establishes high-level requirements and constraints. In this study, the TAP consolidated the initial needs of the requesting engineering departments, defining the scope as the development of equipment for testing the force sensors of the “downforce” system on the production line. The clarity and formality of the TAP are crucial for aligning expectations and preventing scope creep, a common problem in complex projects.

As detailed in Figure 1, the Project Charter established mandatory technical requirements that would be the basis for the success of the validation. Firstly, the test bench should apply a controlled reference force to the sensor, using a linear actuator (electric or pneumatic) capable of simulating real operating conditions. This requirement is vital to accurately replicate field conditions, ensuring that the tests are representative of the sensor’s actual use. Secondly, a critical requirement was the flexibility of the structure, which would need to be interchangeable or adjustable to accommodate various stopper geometries. This flexibility not only ensures the equipment’s longevity in the face of future products and updates but also optimizes investment, allowing the same test bench to be used for a wider range of sensors, an aspect of great practical value for the company. Finally, the Project Charter stipulated the need for an independent force measurement system in the jig, via a load cell, to compare the read electrical signal with the expected stopper value. This measurement redundancy is fundamental for cross-validation and for ensuring the accuracy of the results, a pillar of test engineering. The preliminary deadline for initial planning and development was set for October 2023, establishing an initial timeline for the project.

Source: Original research results

Figure 1. Project charter and initial requirements

The development of the Project Charter (TAP), with its well-defined requirements, serves as an internal contract, aligning expectations among stakeholders and providing a solid foundation for all subsequent project phases. The absence of a formal document like the Project Charter (TAP) can lead to ambiguities, misunderstandings, and consequently, rework and delays, as warned by several authors in project management literature (Kerzner, 2017). The formalization of the initial scope is a preventive step against “scope creep”, where additional requirements are inserted without control, compromising the budget and schedule. The inclusion of an estimated budget of R$ 15,000.00 and a planned deadline until October 2024 in the Project Charter (TAP), although not explicitly in Figure 1, but in the context of the Project Charter (TAP) discussion on page 7, reinforces the importance of establishing clear constraints from the outset, allowing for more realistic planning and more effective financial and temporal control.

After the formalization of the Project Charter, the scope detailing process was intensified through alignment meetings, held between October 2023 and January 2024. These meetings, meticulously recorded in “Confluence” – a collaborative tool from Atlassian that served as a central repository for knowledge organization and management – were crucial for enriching the project’s database and information. The practice of documenting all discussions, decisions, and technical diagrams on a centralized platform is a differentiator, as Godoy (1995) and Stake (1978) point out for qualitative research, the richness of contextual data is fundamental for a deep understanding of the phenomenon. In the context of projects, this robust documentation minimizes information loss and ensures that all stakeholders have access to the most up-to-date versions of documents, promoting transparency and continuous alignment.

The weekly meetings between the Applied Engineering team (technicians, engineers, and supervisor) and internal clients were a cornerstone for the project’s success. The central objective of these encounters was to foster collaboration and constant communication, essential for the completion of the work, especially given the technical complexity involved. Regular and structured communication is one of the critical success factors in projects, according to PMI (2021), as it allows for early identification of inconsistencies, problem-solving, and proactive risk mitigation. Through these meetings, it was defined that the test bench would initially serve the “John Deere 2100” model, the best-selling model at the time, but with the flexibility of adjustable supports for future models. This strategic decision reflects the company’s long-term vision and its ability to adapt the project to future market needs, a crucial aspect in the dynamic agribusiness sector, which demands constant innovation and adaptability (Embrapa, 2020).

Beyond functional definitions, such as adjusting excitation force via Programmable Logic Controller (PLC) to replicate field conditions, structural robustness and operational safety were prioritized. The use of 40×40 mm aluminum profiles and the rigorous implementation of safety items in accordance with Regulatory Standard 12 (NR12) (Brazil, 2019) were established. NR12 is an occupational safety standard that sets minimum requirements for the prevention of accidents and work-related illnesses in machinery and equipment, and its observance is mandatory. The decision to use 40×40 mm aluminum profiles, instead of the initially considered 45×45 mm, demonstrates resource optimization without compromising robustness, an example of value engineering. The installation of a protective cage, a dual-actuation system, and an emergency button became mandatory, elements that ensure operator safety and legal compliance. The chronological synthesis of these deliberations and the evolution of requirements, including detailed guidelines and definitions, are presented in Table 1.

Table 1. Meeting history and requirement definitions

Meeting with the client:

Eng. Meeting: Applied:

Participants

16/10/2023

Weekly (Monday)

Suppliers;

23/10/2023

Client (Eng.: Development)

30/10/2023

Applied Engineering

06/11/2023

13/11/2023

20/11/2023

11/12/2023

15/01/2024

Agendas and Definitions

Action items (Applied Eng.)

Apply a reference force to the force sensor; Geometries Alignment: Essential discussion to ensure the interchangeability of supports, allowing the same bench to serve different models, starting with the John Deere 2100 line; Test Cycle Definition: Meetings to define how the excitation force will be adjusted manually or via PLC, ensuring that the force diagram applied to the jig replicates real field conditions; Electrical Panel Review: Meetings to validate the panel layout, confirming the use of switching power supplies (12V/24V) and protection via 6A bipolar circuit breakers, as detailed in your data files

Jig with vibration stop; Jig with user protection cage; Safety system (sensors / dual activation); HMI development via software; PLC programming; 45×45 aluminum profile structure (robust); Jig with emergency button according to NR12;

Final considerations

Aluminum profile structure 40×40 (will meet the demand, without the need to use 45 profile); 1500 N linear actuator to ensure the system’s compression force; Defined the need for a load cell module to convert mechanical deformation into a digital signal; User protection must be guaranteed at all stages of the process; Jig transport logistics.

Source: Original research results

Table 1 illustrates the density and depth of the discussions held, from the application of reference force to the alignment of geometries and the definition of the test cycle. Each agenda item reflects a critical step in translating the TAP’s high-level requirements into detailed technical specifications. For example, the discussion on the interchangeability of supports for different stopper geometries is a direct reflection of the flexibility requirement established in the TAP. The definition of the test cycle, in turn, addresses the test bench operation methodology, whether manual or via PLC, ensuring that the force simulation replicates real field conditions. The review of the electrical panel, with the validation of the layout and the selection of components such as switching power supplies and circuit breakers, demonstrates attention to detail and concern for the safety and functionality of the electrical system. The final considerations, such as the choice of the 1500 N linear actuator and the need for a load cell module, solidify the technical and operational decisions, reinforcing the project’s systematic and iterative approach.

To ensure technical feasibility and define the critical components of the pneumatic system, expert opinion from support areas was sought. This tool, according to PMI (2021), is fundamental for decision-making in areas where the project team may not have all the necessary knowledge. Based on these consultations, the initial pneumatic technical diagram for force simulation was developed, as detailed in Figure 2.

Source: Original research results

Figure 2. First draft of the complete system (Compressor/Piston)

The designed system integrates a compressor as the power source, connected to a proportional valve responsible for fine-tuning the inlet pressure. Motion control is managed by a directional valve that actuates the piston, ensuring the application of the necessary load on the stopper. This pneumatic arrangement is an example of how precision engineering is applied to simulate the downward forces acting on planters, as described by Oliveira (2021). The choice of components such as the S-type load cell of 200kg and the HX711 converter module, which allows for precise digitization of mechanical deformation, is crucial for measurement accuracy. The control panel architecture, responsible for managing sensor connections and operating logic, complements the system, consolidating the pneumatic and electrical subsystems. The integration of these components, from the compressor to the control panel, is a testament to the project’s complexity and sophistication, aiming for maximum precision and reliability in testing.

Following the definition of the technical architecture and the selection of critical components, the “List of Materials”, also known as “Bill of Materials” (BOM), was elaborated. This artifact consolidated all the items necessary for the assembly of the bench, categorizing them into subgroups such as pneumatic structure, sheet metal, machining, and electrical components. Although Table 5, which details the BOM, is not included here to adhere to the table limit, its importance to the project is undeniable. The elaboration of the BOM allowed for the quantification of inputs, identification of potential suppliers, and establishment of the project’s preliminary budget estimate. This process is a vital component of scope and cost planning, as, according to PMI (2021), the decomposition of work into manageable components and resource estimation are essential for project control. The BOM, by detailing each item, from the type of aluminum profile to the electronic components, provided a concrete basis for procurement planning and financial control, mitigating the risk of budget overrun.

The formalization of the Scope Statement was a decisive step to clearly delimit what would be delivered and what was outside the team’s responsibility, mitigating risks of “scope creep”. This document, according to PMI (2021), is a detailed description of the project scope and main deliverables, serving as a baseline for future decisions. The bench, for example, was designed to be versatile and accept different geometries of stops, not being restricted only to the pilot line. Furthermore, the logistics of transport to the factory floor was defined as the responsibility of Applied Engineering. These boundaries, presented in Table 2, were essential to align expectations with the client and avoid change requests outside the planned scope.

Table 2. Scope Statement: Inclusions and Exclusions

Classification

Deliverable description

Included Items (In Scope)

1. Interchangeable Mechanical Structure: Base manufactured from 40x40mm aluminum profiles (guaranteeing robustness) and a modular structure allowing for the replacement of supports to accommodate other John Deere line stop geometries, ensuring the versatility required in the Project Charter.
2. Safety: Full compliance with NR12, including a protective cage
3. Actuation System: Supply and installation of the power unit composed of an ISO 6431 Ø100×200 cylinder, 5/3-way solenoid valves, and flow regulators to ensure the application of the reference force of 1500N.
3. Control Panel and Logic: Assembly of the electrical panel containing the WEG Clic-02 PLC for cycle automation, switching power supplies (12V/24V), and interface relays for signal management
4. Measurement Instrumentation: Integration of the data acquisition system composed of an S-type load cell (200kg), converter module, and magnetic limit switches for electrical reading validation, HMI interface via software.
5. Logistics and Transport: Planning and execution of all jig transport logistics from the development area to the installation site at the factory, under the full responsibility of Applied Engineering.
6. Documentation: Electrical and pneumatic diagrams, and manuals.

Excluded Items (Out of Scope)

1. Utilities Infrastructure: The project does not include the installation of the factory’s compressed air network (waiting point is the responsibility of Building Maintenance).
2. Sensor Development: The scope is limited to the test equipment; internal calibration or correction of failures in the tested “downforce” sensors (product) are not part of this project.
3. Post-Delivery Maintenance: Corrective or predictive maintenance services after formal acceptance (technical delivery).

Source: Original research results

Table 2 is a clear example of how the explicit definition of inclusions and exclusions can “shield” a project. Included items, such as the interchangeable mechanical structure and compliance with NR12, reinforce the mandatory requirements of the Project charter. The detailed description of the actuation system, control panel, measurement instrumentation, logistics, and documentation provides a comprehensive overview of the deliverables. On the other hand, the list of excluded items, such as the factory utilities infrastructure and post-delivery maintenance, is equally crucial. By stating that the project does not include the installation of the compressed air network or the internal calibration of tested sensors, the team established clear boundaries, preventing additional responsibilities from being assigned without planning. This practice is fundamental for managing expectations and protecting the project’s scope, time, and cost. The Scope Statement, therefore, is not just a descriptive document but a strategic tool for project control and governance, ensuring that the focus remains on the agreed-upon deliverables.

To ensure the organized delivery of the scope, the Work Breakdown Structure (WBS) was created, a hierarchical decomposition of the total work to be performed by the project team to accomplish the project objectives and create the required deliverables (PMI, 2021). The WBS was developed based on the Bill of Materials (BOM) and the subsystems (mechanical, pneumatic, and electrical) defined in the alignment meetings, culminating in the detailed visual representation in Figure 3.

Source: Original research results

Figure 3. Project breakdown structure

Figure 3 demonstrates the granularity with which the project was planned. The decomposition of the work into manageable packages, such as “Project Management”, “Mechanical Structure and Safety”, “Pneumatic System”, “Electrical System and Control”, and “Delivery and Validation”, facilitated alignment between the different technical areas. Each work package, such as “Interchangeable stop supports” or “Data acquisition (load cell + HX711)”, represents a specific and measurable deliverable. This structuring allowed for prompt identification of out-of-scope tasks, as any new task that did not fit into these packages would be immediately identified as “out of scope”. The WBS (Work Breakdown Structure) is not just a planning tool, but also a communication tool, clearly visualizing the scope for all stakeholders. Its practical application in this project reinforces the theory that a well-elaborated WBS is one of the pillars for effective scope management, preventing the disorderly growth of tasks and ensuring that the team’s effort is directed towards what was approved in the baseline.

The second stage of the scope management plan established a rigorous integrated change control process. It was defined that any technical alteration, such as the replacement of already acquired components or changes in the PLC logic, could not be executed based solely on verbal requests. For each request, a formal impact analysis was required, which verified whether the alteration would compromise the triple constraint (scope, time, and cost). This proactive approach is fundamental to project management, as, according to PMI (2021), change control is a continuous process aimed at systematically managing project changes. The impact analysis assessed whether the change would increase costs beyond the budget approved in the BOM, require unavailable resources, or affect the final delivery schedule (October 2024). Only after validation that the change was technically necessary and feasible within the constraints was it incorporated into the scope baseline. This change control process is an effective barrier against “scope creep”, preventing small “simple” changes from accumulating and compromising the final delivery. The formalization of this process ensures that all decisions are made in an informed manner and aligned with the project’s strategic objectives, protecting the budget and schedule.

The practical application of these three steps – scope statement, integrated change control, and WBS – was what allowed the project to be shielded against the disordered growth of tasks, a common challenge in engineering projects. The prevention of “scope creep” occurred by acting on three main fronts. Firstly, the definition of clear boundaries, formalized in Table 2, established what was included and, crucially, what was excluded from the scope, such as future maintenance. This “contractual barrier” gave the team the necessary security to deny informal requests that deviated from the initial objective, avoiding the waste of resources on unplanned activities. This practice is in line with project management literature, which emphasizes the importance of a well-defined scope for project success (Kerzner, 2017).

Secondly, change control, with its formal impact analysis, prevented any technical alteration from entering the project without a prior assessment of cost and schedule. This avoided small, seemingly “simple” modifications, such as swapping a component due to personal preference, causing delays and budget overruns that would compromise the final delivery in October 2024. The discipline of a formal change control process is a pillar for project stability, ensuring that decisions are based on data and analysis, rather than on impulses or individual preferences.

Finally, the total visibility provided by the WBS, with the work visually divided into packages, allowed any new task that arose and did not fit into the structure to be immediately identified as a deviation. The WBS, by breaking down the work into manageable components, offers a clear view of what needs to be done, facilitating the identification of any element that is not part of the original plan. In summary, the Scope Management plan transformed vague expectations into controlled deliverables, ensuring that the team’s effort was directed only towards what was approved in the baseline. This systematic and integrated approach to Scope Management not only protected the project against deviations but also promoted efficiency, transparency, and accountability among all stakeholders.

The scope management process was finalized with the clear definition of acceptance and control criteria, a crucial step for validating deliverables. It was established that the validation of the test bench would be conditioned on approval in two mandatory tests. The first was the functional test, which verified electrical reading via the acquisition system, ensuring that the test bench’s electronic system was operating correctly and providing accurate data. The second test was the load validation, which directly compared the force applied by the jig with the stop signal, ensuring that the test bench faithfully replicated the expected downward force conditions. These well-defined and measurable acceptance criteria are essential to ensure that the final product meets the needs and expectations of internal clients, as recommended by the PMI (2021) in the Scope Validation phase. Clarity in acceptance criteria minimizes ambiguities and potential disputes at the time of delivery, ensuring that the test bench is considered successful only when it unequivocally demonstrates its functionality and accuracy. The application of these mandatory tests is the final proof of the effectiveness of scope management, confirming that all requirements have been met and that the test bench is ready for its purpose of validating downward force sensors.

4. Conclusion

It is concluded that the objective was achieved by presenting the scope management of a project to develop a downstream power systems validation test bench in an agribusiness company. The structured application of tools such as the Project Charter (TAP), the Scope Statement, and the Work Breakdown Structure (WBS) proved effective in mitigating “scope creep” risks. This rigorous planning ensured that the test bench was delivered fully meeting the defined requirements, within the established cost and time constraints. The formalization of requirements and integrated change control were crucial to ensure the visibility of activities and the protection of the project budget and schedule, promoting efficiency and transparency among stakeholders.

However, this case study has limitations inherent to its nature, being restricted to a single organization and a specific period (October 2023 to July 2024). This particularity prevents the direct generalization of results to other contexts or companies. For future studies, it is suggested to replicate this scope management methodology in projects of different sizes and in various organizations, in order to validate its applicability in broader scenarios. Additionally, it is recommended to include new variables in the analysis, such as management focused on risks and acquisitions, to deepen the understanding of project management in applied engineering environments.

Bibliographic References

Brasil. 2019. Portaria nº 916, de 30 de julho de 2019. Altera a Norma Regulamentadora nº 12 – Segurança no Trabalho em Máquinas e Equipamentos. Diário Oficial da União, Brasília, 31 jul. 2019. Seção 1, p. 104.

Centro de Estudo Avançados em Economia Aplicada [CEPEA]. 2025. PIB do Agronegócio Brasileiro. Disponível em: <https://www.cepea.org.br/br/pib-do-agronegocio-brasileiro.aspx#:~:text=Segundo%20pesquisadores%20do%20Cepea/CNA,de%20significativos%208%2C5%25.> Acesso em: 23 jan. 2026.

Food and Agriculture Organization of the United Nations [FAO]. 2024. FAOSTAT. Disponível em: <https://www.fao.org/faostat/en/#data/QCL>. Acesso em: 13 out. 2025.

Franchini, J. C.; Grego, C. R.; Inamasu, R. Y.; Jorge, L. A. de C.; Luchiari Júnior, A.; Rabello, L. M.; Rodrigues, G. C.; Rodrigues, C. A. G.; Ronquim, C. C; Speranza, E. A.; Vendrusculo, L. G.; Vaz, C. M. P.; Zolin, C. A. 2020. Tecnologias desenvolvidas em Agricultura de Precisão. 166-191. In: Empresa Brasileira de Pesquisa Agropecuária [EMBRAPA]. 2020. Brasília, DF, Brasil. Disponível em: <https://www.embrapa.br/busca-de-publicacoes/-/publicacao/1126264/tecnologias-desenvolvidas-em-agricultura-de-precisao>. Acesso em: 13 out. 2025.

Godoy, A. S. 1995. Pesquisa qualitativa: tipos fundamentais. Revista de Administração de Empresas [ERA], 35(3): 20-29.

International Society of Precision Agriculture [ISPA]. 2025. Disponível em: <https://ispag.org>. Acesso em: 20 out. 2025.

Kerzner, 2017 [Referência completa não encontrada no documento original]

Oliveira, L. P. 2021. Qualidade da semeadura das culturas do algodão, milho e soja sob a ação de forças descendentes em linha. Tese de doutorado em Pós-Graduação em Agronomia – FCAV. Universidade Estadual Paulista [Unesp], São Paulo, SP. Brasil Disponível em: <https://repositorio.unesp.br/entities/publication/a1da3cfa-4d66-4e44-8b78-b05a1cac8bfb>. Acesso em: 15 out. 2025.

Project Management Institute [PMI]. 2021. Um Guia do Conhecimento em Gerenciamento de Projetos (Guia PMBOK). 7ed. Project Management Institute, Newtown Square, PA, EUA. Disponível em: <https://www.academiaplaorc.com.br/wp-content/uploads/2024/07/Guia-PMBOK-7a-Edicao.pdf>. Acesso em: 14 out. 2025.

Revista Inovação Tecnológica [RIT]. 2025. O impacto do agronegócio na balança comercial brasileira: uma análise Narrativa. Disponível em: <https://www.rit.openjournalsolutions.com.br/index.php/rit/article/view/173/75>. Acesso em: 22 out. 2025.

Stake, R. 1978. The Case study method in social inquiry. Educational Researcher, 7(2): 5-8.

Yin, R. K. 2001. Estudo de caso: planejamento e métodos. Bookman, Porto Alegre, RS, Brasil.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving the independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated the automated reading of files, the organization of curves into current-potential matrices, the generation of the potential map, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed by device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of the results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and enhance the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used for the definition and identification of the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.