Schedule Management in Aerospace Industrial Projects: Case Study of an Annealing Furnace

Loane Santana Gonçalves Santos; Lorena Hernández Mastrapa

DOI: 10.22167/2675-6528-202601078

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

Schedule management is a central element for the success of industrial projects, especially in sectors of high technological complexity, such as aerospace. The study aimed to analyze the application of schedule management in the execution of an industrial project for the implementation of a annealing furnace for aerospace application, aiming to reduce delays, risks, and rework. The research was characterized as a case study of an applied nature, with a qualitative approach and descriptive objective, based on PMBOK practices and using Microsoft Project as a tool to support the planning, sequencing, monitoring, and control of activities. The application of the methodology allowed for the structuring of the Work Breakdown Structure (WBS), sequencing of activities, estimation of their durations, identification of the critical path, and establishment of the schedule baseline. The results showed the concentration of critical activities in the manufacturing, installation, and acceptance testing phases. A delay of approximately two weeks was observed in the manufacturing phase, due to technical revisions. However, the early identification of this deviation, associated with the use of an incorporated logistic buffer, allowed for its mitigation without impacting the project’s final deadline. It was concluded that the structured application of schedule management contributes to greater predictability, better deadline control, and support for decision-making in industrial projects of high complexity. The research reinforces the importance of adopting management tools and methodologies in complex and highly regulated industrial environments, contributing to the academic discussion on efficiency in project execution.

Keywords: Deadline analysis; Critical path; Technological complexity; Operational planning; Predictability.

1. Introduction

Project management (GPRO) is widely recognized as a fundamental strategic discipline for organizational success. In a dynamic and competitive global landscape, the ability to plan, execute, and control complex initiatives within time, cost, and quality constraints has become a differentiator (Project Management Institute, 2021; Kerzner, 2022). The adoption of structured GPRO practices, based on references such as the *Project Management Body of Knowledge* (PMBOK), is essential to increase the predictability of deliverables, optimize resource allocation, and support decision-making (Müller; Turner, 2021). Among the knowledge areas of GPRO, schedule management assumes a role of particular relevance, focusing on controlling the time required for activity execution, involving planning, sequencing, duration estimation, monitoring, and control (PMI, 2017). Failure to effectively manage the schedule can lead to significant delays, costly rework, and increased costs, negatively impacting project viability, especially in engineering and infrastructure ventures (Vargas, 2018). Organizations that implement formal project management methodologies consistently achieve better results in their strategic initiatives.

In the industrial context, project complexity is amplified by factors such as the high volume of investments, specialized equipment, and rigorous technical certifications. Such projects involve the coordination of multiple agents, from suppliers to internal teams, throughout an extensive and interdependent production process (Project Management Institute, 2021; Kerzner, 2022). The coordinated execution of activities depends on detailed planning and continuous monitoring of interdependencies between tasks. This precision is further accentuated in the aerospace sector, an environment characterized by extremely strict technical and regulatory requirements. Standards such as Aerospace Material Specification (AMS2750), which governs heat treatment processes, and the accreditation requirements of the National Aerospace and Defense Contractors Accreditation Program (NADCAP) (SAE International, 2020; PRI, 2023), impose a level of control and traceability over processes and deadlines that transcends the usual. In aerospace projects, a delay in a single activity can generate a cascading effect throughout the schedule, compromising contractual deadlines, increasing costs, and affecting operational reliability and the safety of the final product. The criticality of these projects therefore demands a robust and systematic approach to schedule management.

Despite the literature’s recognition of the importance of time management for project success, gaps persist in understanding the systematic application of these practices in complex industrial projects, particularly in environments highly regulated by rigorous technical standards. Recent studies (Elqasaby et al., 2023) suggest that the integration of digital planning and monitoring tools can increase schedule predictability and mitigate deviations in engineering projects. However, the transposition of these approaches to the practical scenario of implementing specific industrial equipment, such as annealing furnaces for aerospace applications, still lacks in-depth analyses demonstrating their effectiveness and inherent challenges. Practical experience frequently reveals that, even with theoretical relevance, complex industrial projects continue to face recurring difficulties in deadline control, driven by intrinsic technical and logistical dependencies. Technical reviews, component delivery delays, and alignment challenges among multiple stakeholders are examples of common deviations that can compromise project performance.

Given the inherent complexity of industrial projects, especially in the aerospace sector with its regulatory and technical demands, and the persistence of challenges in schedule control, it becomes essential to investigate the application of structured schedule management methodologies. The relevance of this study lies in its contribution to academic and practical discussion, by analyzing how the systematic application of such practices can optimize project execution in high-complexity and regulated environments. Thus, this work aims to analyze the application of schedule management in the execution of an industrial project for the implementation of a heat treatment furnace for aerospace application, aiming to reduce delays, risks, and rework.

2. Material and Methods

The present research was characterized as a case study, according to Gil’s (2017) methodology, which allows for an in-depth investigation of a phenomenon in its real context of occurrence. This approach was selected to deeply analyze schedule management practices in complex industrial projects, providing a detailed understanding of the phenomenon. The applied nature of the study sought to generate useful knowledge for practice, while the descriptive objective aimed to detail the application of schedule management. A qualitative approach was adopted to explore the nuances and complexity of the subject.

The study was developed in the context of a specific industrial project, conducted in a multinational company in the aerospace sector located in France. The object of analysis corresponded to the implementation of an industrial annealing furnace, intended for the processing of titanium leading edges (flaps), critical components in heat treatment processes. The identity of the organization was not mentioned in the work, in accordance with academic standards and ethical research principles. The unit of analysis was the furnace implementation project itself, followed throughout its various phases.

The central unit of analysis for this study was the implementation project of a heat treatment furnace for aerospace application, characterized as a unique case. There was no population or sample in the statistical sense, but rather the intentional selection of this specific project due to its complexity and relevance to the sector. Selection criteria included the industrial and aerospace nature of the project, the criticality of the equipment (heat treatment furnace for titanium flaps), and the need for compliance with rigorous standards, such as the Aerospace Material Specification (AMS2750) and the requirements of the National Aerospace and Defense Contractors Accreditation Program (NADCAP).

Data collection was carried out through a combination of documentary analysis and direct observation of the project. These approaches allowed for the capture of comprehensive and detailed information throughout the different phases of equipment implementation. The documentary analysis provided a structured information base, while direct observation complemented it with *insights* into interactions and operational dynamics. Data were systematically collected to ensure a complete view of schedule management in the studied context, covering from initial planning to testing and validation stages.

The primary data included project tracking records and direct observations of interactions among project managers, process engineers, quality teams, and involved suppliers. Complementarily, secondary data were used, such as the Specifications Notebook (CDC), detailed execution schedules, minutes of tracking meetings, technical reports, and internal records related to project development. Data collection occurred at relevant timeline milestones, encompassing the completion of equipment manufacturing, the end of assembly, the execution of acceptance tests, and intermediate validations, ensuring the capture of information at critical execution points.

For the study’s conduction and the application of schedule management, the practices described in the PMBOK Guide (PMI, 2017), specifically those related to time management, were adopted as reference. The Microsoft Project software was employed as an essential support tool for the planning, monitoring, and control of the project schedule. This choice allowed for the systematic structuring of activities, visualization of dependencies, and real-time progress monitoring, aligning execution with industry best practices and facilitating the identification of deviations and decision-making.

The application of the methodology was structured in sequential steps, starting with the structuring of the Work Breakdown Structure (WBS). This was developed from the Specifications Booklet (CDC), allowing the decomposition of the project into phases and activities necessary for its execution. Subsequently, the definition and sequencing of project activities were carried out, considering the dependency relationships between tasks. The phases covered included planning, procurement, manufacturing, transportation, installation, commissioning, and factory acceptance tests (FAT) and site acceptance tests (SAT), with a predominance of finish-to-start relationships.

Next, the duration of the activities was estimated, considering technical project information, contractual deadlines, and operational dependencies between stages. Based on these estimates, the project’s critical path was identified, composed of activities that directly impact the final deadline. Resources, milestones, and deadlines were inserted into the schedule using Microsoft Project to organize and visualize the planning. Finally, the schedule baseline was defined, which served as the approved reference for continuous monitoring of activity progress throughout the project execution.

The monitoring of the actual progress of activities was carried out periodically, comparing the planned schedule with the executed one. Performance reports were issued to identify schedule deviations and propose corrective actions, aiming to minimize impacts on the schedule. Additionally, an impact analysis of delays on critical activities was conducted, qualitatively assessing the potential risks associated with each stage. This analysis considered the position of activities on the critical path, the absence of total float, and technical, logistical, and regulatory constraints. Mitigation strategies, including the incorporation of a two-week logistical *buffer*, were defined to increase schedule robustness.

The data analysis was conducted in two complementary stages for an in-depth understanding of schedule management. In the first stage, a detailed comparative analysis was performed between the planned schedule, established as the baseline, and the effectively executed schedule. This procedure allowed for the identification of schedule deviations, changes in the critical path, and the resulting impacts on project milestones. The systematic comparison provided an empirical basis for evaluating the project’s adherence to the initial plan and understanding the variations that occurred during its execution, highlighting the areas of greatest sensitivity.

In the second stage of the analysis, the observed results were confronted with the specialized literature on project management, including the practices described in the PMBOK (PMI, 2017) and studies by Gil (2017) and Vargas (2018). This comparison aimed to identify adherence to best practices, as well as limitations and opportunities for improvement in schedule management applied to the studied project. This methodological approach made it possible to evaluate how structured schedule management contributes to reducing delays, rework, and risks in highly complex industrial projects, especially in environments regulated by strict technical standards, according to the central objective of the work.

Regarding the ethical aspects, the identity of the organization where the study was conducted was not mentioned in the paper, in accordance with academic norms and ethical research principles, ensuring the confidentiality of data and the company. As for methodological limitations, it is acknowledged that, due to it being a single case study, the results obtained cannot be generalized to other contexts or projects. This inherent characteristic of the case study restricts the direct applicability of the conclusions, although it provides an in-depth understanding of the phenomenon in the specific scenario analyzed, contributing to future research.

3. Results and Discussion

The Results and Discussion section details the empirical findings of the case study on schedule management in the implementation of a annealing furnace for aerospace application, confronting them with the specialized literature and exploring their practical implications. The analysis was conducted in sequential steps, according to the proposed methodology, allowing for an in-depth understanding of the adopted practices and their impacts on the project.

The first stage of the methodological application consisted of the elaboration of the Project Work Breakdown Structure (WBS), a fundamental element for the organization and decomposition of the scope. The WBS was developed from the equipment’s Specifications Booklet (CDC), which allowed the segmentation of the project into distinct and manageable phases, including planning, acquisition, manufacturing, transportation, installation, commissioning, and factory acceptance tests (FAT) and field acceptance tests (SAT). This initial approach is widely recognized in the literature as a pillar for effective scope and time management, as advocated by the Project Management Institute (PMI, 2017, 2021). The hierarchical decomposition of work facilitated the visualization of necessary activities, the allocation of responsibilities, and the estimation of resources and deadlines, corroborating Kerzner’s (2017) view of the WBS as an essential tool for project lifecycle control.

During the structuring of the WBS (Work Breakdown Structure), the need was observed to refine some activities that, initially, had been foreseen in a more aggregated manner. This detailing was particularly relevant in the manufacturing and installation phases of the equipment, where the technical complexity and operational interdependencies demanded greater granularity. Such behavior reflects the dynamic and iterative nature of planning in complex industrial projects, where the initial technical documentation, although robust, does not always capture all the nuances of the operational reality. Project management literature frequently highlights that the WBS is not a static document, but a living tool that must be adjusted as the understanding of the project matures (PMI, 2021). The ability to adapt the WBS in response to new information and constraints is an indicator of a mature and flexible planning process, crucial for risk mitigation and ensuring schedule accuracy.

The need for WBS refinement, as observed in this study, underscores the importance of a collaborative and multidisciplinary approach to planning. The interaction between project managers, process engineers, quality teams, and suppliers, mentioned in the methodology, is vital for translating the technical requirements of the CDC into concrete and sequential activities. Without this collaboration, the WBS would risk being a merely theoretical document, disconnected from execution realities. Kerzner (2022) emphasizes that the WBS is the backbone of planning and that its accuracy directly impacts the quality of time and cost estimates. The project experience demonstrated that the WBS, by being detailed and refined, not only organized the activities but also provided a deeper understanding of technical interdependencies, reducing ambiguities and facilitating communication among teams.

Source: Original research results

Figure 1. Work Breakdown Structure (WBS)

As presented in Figure 1, the Work Breakdown Structure (WBS) developed for the annealing furnace implementation project illustrates the hierarchical decomposition of deliverables. This visual representation is fundamental for all project stakeholders to understand the scope of work and the main phases. The clarity provided by the WBS is a critical factor for success, as it minimizes the probability of scope creep and facilitates the identification of planning gaps. Adherence to this practice, as per the PMBOK Guide (PMI, 2017), is a differentiator in complex projects, especially in the aerospace sector, where precision and compliance are non-negotiable requirements. The WBS served as a detailed map, guiding the teams through the complex stages of manufacturing, certification, and installation, ensuring that each component of the annealing furnace was considered in the overall planning.

The step following the WBS (Work Breakdown Structure) structuring was the definition and sequencing of project activities. Using Microsoft Project software, the activities were organized considering the dependency relationships between tasks and the technical constraints inherent to the different phases of equipment implementation. The predominance of Finish-to-Start (FS) relationships observed is a reflection of the sequential and interdependent nature of the industrial processes involved, where one activity must be completed before the next can begin. This precedence logic is a central principle of schedule management, as described by PMI (2017), and its correct application is vital for building a realistic and executable schedule. The visualization of these often complex interdependencies is facilitated by tools such as the Gantt chart, which allows for a clear understanding of the distribution of activities over time.

The schedule analysis revealed a high level of interdependence between the manufacturing, transportation, installation, and testing phases. In practice, this means that a delay in any of these steps can generate a cascading effect, directly impacting subsequent phases and, consequently, the project’s final deadline. This interconnection reinforces the need for continuous coordination and rigorous monitoring, especially in highly complex projects like the one studied. The identification of the critical path, composed of activities that have no total float and determine the total project duration, became a central focus. The manufacturing of the furnace, international logistics, equipment installation, and the Factory Acceptance Test (FAT) and Site Acceptance Test (SAT) were identified as critical components, requiring priority attention and management. This finding is in line with the literature, which points to the critical path as the main determinant of the project deadline and an essential target for control (Vargas, 2018).

The sequencing of activities also highlighted technical and operational constraints that were not fully clear in the initial planning. The need to align theoretical dependencies with real execution conditions is a common challenge in industrial projects. For example, the availability of specialized teams, coordination with international suppliers, and certification requirements (AMS2750, NADCAP) impose constraints that need to be carefully managed. The project experience demonstrated that defining dependencies is not just an exercise in logic, but a continuous negotiation and alignment with stakeholders and operational capabilities. Müller and Turner (2021) emphasize that effective communication and collaboration between teams are crucial to overcome these challenges and ensure that the schedule reflects project reality.

The estimation of activity durations, based on the sequenced activities, was a crucial step for schedule construction. This estimation considered detailed technical project information, established contractual deadlines, and operational dependencies between stages. The accuracy of these estimates is fundamental, as they form the basis for identifying the critical path and forecasting the project’s final deadline. In aerospace industrial projects, technical complexity and the need for compliance with rigorous standards (SAE International, 2020; PRI, 2023) make duration estimation a challenging process, requiring expertise and reliable data. The use of Microsoft Project as a support tool was essential for consolidating this information and generating a clear visual representation of the schedule.

The identification of the critical path, as synthesized in Figure 2, directed the team’s attention to the activities most sensitive to delays. The oven manufacturing, equipment transportation, installation, and acceptance testing (FAT and SAT) activities were confirmed as integral parts of the critical path. Any deviation in these activities would have a direct and immediate impact on the project’s final deadline. This clarity allowed the management team to allocate resources more strategically and implement more intensive monitoring of these stages. Kerzner (2017) argues that critical path analysis is one of the most powerful tools for schedule control, as it allows managers to focus their efforts where they will have the greatest impact.

Source: Original research results

Figure 2. Schedule synthesis and critical path identification

According to Figure 2, the total estimated duration for the project execution was 40 weeks. This timeframe not only encompassed the manufacturing and installation phases but also included the CE certification process, conducted by an independent body, and the preparation to meet NADCAP qualification requirements. The inclusion of these regulatory steps in the critical path highlights the project’s complexity and criticality, where regulatory compliance is as important as technical execution. Furthermore, a proactive risk management strategy was implemented with the incorporation of a two-week logistical *buffer* between the transport and installation stages. This safety margin was designed to absorb potential delays arising from logistical processes, technical inspections, and other external variables beyond the direct control of the project team. The adoption of contingency margins is a recommended practice by the PMI (2017) to increase schedule robustness and reduce sensitivity to deviations, especially in environments with high uncertainty.

The impact analysis of delays in critical activities was a fundamental step for proactive risk management. After identifying the critical path, a qualitative assessment of the risks associated with each critical activity was performed, considering its position on the path, the absence of total float, and technical, logistical, and regulatory constraints. This assessment allowed for the identification of the stages most sensitive to delays and their potential impacts on the project’s final deadline. Figure 3 illustrates this analysis, consolidating the main risks identified, their potential impacts on the schedule, and the mitigation strategies adopted. Transparency and anticipation of these risks are crucial for the development of effective contingency plans, minimizing surprises and allowing for a rapid response to adverse events.

Source: Original research results

Figure 3. Analysis of the impact of delays on critical project activities

Figure 3 shows that the manufacturing, certification, and transportation phases of the equipment concentrate the points of greatest schedule sensitivity. Manufacturing, for example, presented a “High impact on the final deadline” due to “Technical complexity and engineering adjustments”, with the mitigation strategy focused on “Monitoring manufacturing milestones”. This reflects the reality of high-tech industrial projects, where innovation and customization can lead to unforeseen challenges during production. Dependence on suppliers and regulatory requirements, such as CE and NADCAP certifications, add layers of complexity and risk, as they involve external entities and bureaucratic processes that can be difficult to control. Elqasaby et al. (2023) emphasize that risk management in engineering projects is intrinsically linked to the ability to predict and mitigate technical and logistical uncertainties.

The defined mitigation strategies, such as close monitoring of manufacturing milestones, advance planning of documentary requirements, and the inclusion of logistical *buffers*, proved essential in reducing exposure to delay risks and making the schedule more robust. The “Logistical buffer (risk margin)”, for example, was a proactive measure to deal with “Logistical and customs procedures” that could “Delay installation”, with the strategy of “Inclusion of logistical buffer”. This proactive approach aligns with best practices in risk management, which emphasize the importance of identifying, analyzing, and planning responses to risks before they materialize (PMI, 2017). The ability to anticipate and plan for contingencies is a differentiator in large-scale projects, where the costs of delays and rework can be substantial.

The insertion of resources, milestones, and deadlines into the schedule was a crucial step in transforming the planning into a concrete and monitorable action plan. The main project milestones, such as the completion of furnace manufacturing, equipment delivery, Factory Acceptance Tests (FAT), and final validation after Site Acceptance Tests (SAT), were established as key control points. These milestones are not just dates on a calendar, but represent key events that signal the completion of important deliverables and the transition between project phases. The clear definition of these milestones, as presented in Figure 6 (Main project milestones and planned weeks), facilitated progress tracking and the identification of potential deviations, serving as performance indicators for the team and stakeholders.

The importance of milestones lies in their ability to provide visibility and accountability. Each milestone, with its description and planned week, acts as a mini-objective, allowing the team to celebrate achievements and, more importantly, quickly identify if the project is going off course. The “Completion of furnace manufacturing” in Week 24, for example, is a critical point that, if delayed, would directly impact subsequent phases. This practice aligns with literature highlighting the importance of milestones for project control, as they offer tangible checkpoints that help keep the project on track and communicate progress effectively (PMI, 2021). In a complex project like the implementation of an aerospace industrial furnace, where multiple suppliers and teams are involved, milestones are essential for coordinating efforts and ensuring alignment.

The definition of the schedule baseline represented the approved version of the detailed project plan, serving as a reference for continuous performance monitoring. The baseline, as illustrated in Figure 7 (Project schedule baseline), corresponds to the set of planned start and end dates for activities. Although, in this case, the baseline coincided with the initial schedule, its formalization is a critical step in project management. It establishes an internal “contract” that allows for systematic comparison between what was planned and what is being executed, facilitating the identification of schedule deviations and corrective decision-making. The baseline is, therefore, a dynamic management tool, not a mere static record of the plan, as emphasized by the PMI (2017).

The relevance of the baseline is particularly accentuated in projects of high complexity and long duration, where the probability of deviations is greater. By having a fixed reference, the project team can objectively evaluate progress, communicate status to stakeholders, and justify any corrective actions or change requests. Without a clear baseline, the project runs the risk of becoming a “moving target”, making performance evaluation and accountability difficult. The practice of establishing a robust baseline is a pillar of project management and contributes significantly to predictability and control, as reinforced by Vargas (2018) in his practical manual. The schedule baseline for the annealing furnace allowed for more structured and transparent management, essential for a regulated environment like aerospace.

The monitoring of the progress of activities was carried out periodically, using Microsoft Project to compare the planned schedule (baseline) with the effectively executed schedule. This continuous monitoring revealed schedule deviations, mainly related to technical project reviews and delays in the delivery of critical components. One of the most significant findings was a delay of approximately two weeks in the equipment manufacturing phase, resulting from technical adjustments to the thermal system. This deviation, although punctual, represented a potential risk to the project’s final deadline, given the criticality of the activity.

The ability to identify this deviation in advance was crucial. Thanks to continuous monitoring and critical path analysis, the team managed to reschedule subsequent activities and, more importantly, utilize the two-week logistical *buffer* previously incorporated into the schedule. As shown in Figure 4 (Comparison between the planned schedule (baseline) and the executed one), the logistical *buffer*, which had a planned duration of 2 weeks, was used in 1 week, partially absorbing the manufacturing delay and resulting in an identified deviation of -1 week for the *buffer* itself, but without impacting the final project deadline. This demonstrates the effectiveness of a proactive risk management approach and the importance of including schedule reserves in complex schedules (PMI, 2017).

Source: Original research results

Figure 4. Comparison between the planned schedule (baseline) and the executed one

Figure 4 clearly illustrates that, despite a two-week delay in “Furnace Fabrication” (extending from 18 to 20 weeks), the overall project deadline was not compromised. The “Schedule Impact” for fabrication was classified as “High Potential Impact,” but the “Logistics Buffer” acted as a mitigator, resulting in “Partial Delay Absorption” and keeping other activities, including “Equipment Installation,” “FAT,” “SAT,” and “Final Commissioning,” unaffected by the schedule. This practical outcome reinforces the importance of structured schedule management in complex industrial projects. The inclusion of schedule reserves, coupled with continuous monitoring of critical activities, contributes to reducing the impact of uncertainties and increasing execution predictability, as highlighted by Kerzner (2017) and Elqasaby et al. (2023).

The schedule performance analysis, based on the comparison between planned and executed, confirmed that the schedule is not just an initial plan, but an active management tool. The early identification of the deviation in manufacturing allowed the team to take corrective actions and use the logistical *buffer* strategically, avoiding a more significant impact on the final deadline. This type of real-time adjustment is a testament to the flexibility and adaptability that well-implemented schedule management can offer. Furthermore, continuous monitoring of dependencies between activities helped anticipate potential problems in critical stages, such as transportation, installation, and technical adjustments, reducing the need for rework and optimizing resource utilization.

The effectiveness of this process, however, depends directly on the constant updating of information and the active involvement of the responsible teams. Without continuous alignment and effective communication, the schedule may lose its function as a control instrument and become obsolete. Müller and Turner (2021) emphasize that project success is based not only on tools and methodologies but also on organizational culture and the teams’ ability to collaborate. The experience of this case study reinforces that schedule management, when applied in a structured manner and with the support of tools like Microsoft Project, contributes significantly to the organization of planning, clarity of interdependencies, visibility of critical steps, and consistent progress monitoring.

In summary, the results demonstrate that the application of schedule management practices, according to the PMBOK Guide (PMI, 2017), was fundamental to the success of the annealing furnace implementation project. The structuring of the WBS (Work Breakdown Structure), activity sequencing, duration estimation, critical path identification, baseline definition, and continuous monitoring were interconnected processes that allowed for proactive management. The ability to identify and mitigate a significant delay in the manufacturing phase, without compromising the project’s final deadline, is clear evidence of the value added by these practices. This aligns with literature that advocates for structured schedule management increasing predictability, improving deadline control, and supporting decision-making in highly complex industrial projects, especially in environments regulated by strict technical standards such as the aerospace sector.

4. Conclusion

It is concluded that the objective was achieved, as this work successfully analyzed the application of schedule management in the execution of an industrial project for the implementation of a annealing furnace intended for aerospace application. The structured methodology, based on PMBOK practices and supported by Microsoft Project, allowed for detailed planning organization, clear identification of interdependencies between activities, and visibility of critical stages. The development of the Work Breakdown Structure (WBS), activity sequencing, duration estimation, and baseline definition were crucial. Continuous monitoring demonstrated the effectiveness of these practices by allowing for the early identification of a two-week delay in the manufacturing phase, which was mitigated by the strategic use of a logistical *buffer*, without compromising the project’s final deadline. This reinforces the capacity of structured management to reduce delays, risks, and rework, increasing predictability and control in highly complex environments.

However, it is important to acknowledge the limitations of this study, which focused on a single case project. This approach restricts the generalization of results to other industrial contexts, although it provides an in-depth analysis of the specific scenario. For future studies, it is suggested to expand the research to explore the application of these practices in different industrial sectors, with varying levels of complexity and regulation. Additionally, it is recommended to incorporate more advanced performance analysis methods, such as Earned Value Management (EVM) indicators, for an even more robust evaluation of project efficiency and progress. Such investigations could enrich the understanding of the adaptability and impact of schedule management across a broader range of projects.

Bibliographic References

Elqasaby, A.; Alqahtani, F.; Alheyf, M. (2023). Automated schedule and cost control using 3D sensing technologies. Journal of Construction Engineering and Management, v.149, n.3, art. 04022179.

Gil, A. C. (2017). Como elaborar projetos de pesquisa. 6. ed. São Paulo: Atlas.

Kerzner, H. (2022). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 13. ed. Hoboken: Wiley.

Müller, R.; Turner, J.R. (2021). An assessment of the factors impacting project success in the engineering sector. International Journal of Project Management, v.39, n.4, p.278–292.

Performance Review Institute (PRI). (2023). NADCAP Program Overview. Warrendale: PRI.

Project Management Institute (PMI). (2017). Um guia do conhecimento em gerenciamento de projetos (PMBOK Guide). 6. ed. Newtown Square: PMI.

Project Management Institute (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK Guide). 7. ed. Newtown Square: PMI.

SAE International. (2020). AMS2750: Pyrometry. Warrendale: SAE International.

Vargas, R.V. (2018). Manual prático do plano de projeto: utilizando o PMBOK Guide. 2. ed. Rio de Janeiro: Brasport.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.