Schedule Management in Wind Projects

Marceli Carolina Rocha; Aline Gisele Zanão Benatto

DOI: 10.22167/2675-6528-202601165

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

Schedule management in wind power generation projects has assumed a strategic role due to the high operational complexity, logistical constraints, and contractual requirements that characterize these ventures. The recurrence of delays in critical activities highlighted the need for more robust planning and control practices, capable of increasing predictability and reducing impacts on the final deadline. This work aimed to propose and analyze a structured model for managing the mobilization schedule in wind projects, focusing on increasing predictability and reducing schedule deviations. To this end, an action research, descriptive in nature and with a qualitative approach, was adopted, developed in a large company in the wind sector. Data collection occurred through direct observation and documentary analysis of schedules, monitoring reports, and physical progress records. The results showed a high rate of completion of critical activities within the revised deadline, partial mitigation of delays due to external restrictions, and a relevant reduction in costs during the mobilization phase. It was concluded that the structured application of schedule management practices contributed to strengthening project governance, increasing transparency in decision-making, and expanding predictability in highly complex ventures, although its effectiveness was partially conditioned by external factors.

Keywords: Deadline control; Wind energy; Project management; Project mobilization; Operational planning.

1. Introduction

Wind energy has been consolidating itself as one of the main sources of renewable energy, standing out for its lower environmental impacts. In Brazil, data from the Brazilian Wind Energy Association and New Technologies (ABEEólica, 2023) reveal significant growth in installed capacity, increasing from 4.05 GW in 2022 (with 109 new wind farms) to 4.8 GW in 2023 (with 123 new wind farms). Although there was a slowdown in 2024, with an additional 3.3 GW, the country currently counts 1,103 wind farms in operation, totaling 33.7 GW of power. This represents about 14% of the national electricity matrix, placing Brazil among the main global producers.

This scenario intensified the pressure for operational efficiency, especially in companies responsible for the assembly and lifting of wind components. In these organizations, cost control and compliance with contractual deadlines became critical competitiveness factors.

In this context, schedule management holds a central position in project management, organizing activities over time for the delivery of planned results. This function becomes even more critical during the mobilization phase, which involves the preparation and availability of essential resources, such as labor, equipment, materials, and support structures. According to the Project Management Institute (PMI, 2021), schedule planning must reflect the sequence of activities and the feasibility of their execution considering resource constraints and operational conditions.

The mobilization schedule plays a strategic role, as it establishes the foundations for efficient project execution. An adequate structure allows for anticipating needs, aligning suppliers, organizing work fronts, and reducing risks associated with the start of activities. As highlighted by Kerzner (2022), the integration between planning and resource availability is a key factor for the success of complex projects, especially in environments with multiple interfaces and high logistical dependency.

However, resource mobilization in wind projects presents specific challenges. Equipment transportation, obtaining permits, and coordination among suppliers make the process highly sensitive to delays and restrictions. Recent studies indicate that mobilization logistics directly influence schedule performance, being a critical factor for meeting deadlines (Chamier-Gliszczynski, 2024). Supply chain decisions, such as route selection and equipment availability, directly impact activity sequencing and the critical path. Inadequate mobilization can compromise subsequent schedule performance in “offshore” and “onshore” environments (“Logistic Decisions in the Installation of Offshore Wind Farms”, 2024).

Thus, the management of the mobilization schedule requires a structured approach, integrating planning, control, and performance monitoring. Its effectiveness, however, depends on the quality of the initial planning and the consistency of the information. Large infrastructure projects often face weaknesses in the planning phase, such as underestimation of constraints and overestimation of execution capacity. According to Flyvbjerg and Gardner (2023), these biases contribute to the recurrence of delays and reinforce the need for more realistic and structured practices, particularly in the initial stages, such as mobilization.

Given this context, it was observed that the company under study adopted a predominantly operational approach, focused on the execution of activities. The structured planning of the mobilization schedule received less attention. This practice resulted in recurring delays, additional costs, and emergency mobilizations. Thus, the mobilization phase represented a critical moment, in which planning maturity was tested.

In this scenario, the problem of this study consists of analyzing how to structure the resource mobilization schedule in wind projects, aiming to reduce delays and increase the predictability of deliveries, considering the high logistical complexity, the dependence on external factors, and the inherent limitations of planning in environments of high uncertainty. Thus, this work is justified by the need to develop more robust practices in a critical sector, and its objective is to propose and analyze a structured model for managing the mobilization schedule in wind projects, integrating planning, monitoring, and control practices, with a focus on increasing the predictability of deliveries and reducing schedule deviations.

2. Material and Methods

This study was characterized as an action research, of qualitative nature and descriptive character. The choice for this methodological approach was justified by the need to integrate the practical application of schedule management tools with the critical analysis of their effects in the real project context. This allowed for observation and intervention in the studied phenomenon, as advocated by Thiollent (2011) for empirical social investigations.

From a qualitative perspective, the research focused on a deep understanding of the planning, monitoring, and schedule control processes. Managerial interactions, decisions, and organizational dynamics that influenced the project’s temporal performance were analyzed. According to Creswell and Poth (2018), the qualitative approach is indicated for interpreting meanings attributed by individuals or groups to social or organizational problems.

Regarding the descriptive nature, the study sought to record, analyze, and interpret the practices effectively adopted in schedule management, without deliberate manipulation of independent variables. According to Gil (2019), descriptive research has the main objective of describing characteristics of a given phenomenon, contributing to the improvement of applied knowledge.

Action research developed in iterative cycles of diagnosis, intervention planning, action implementation, effects observation, and critical reflection. This dynamic followed the classic conception proposed by Lewin (1946), later consolidated in the methodological literature, allowing decisions related to the schedule to be continuously evaluated and adjusted.

The researcher’s direct participation in the analyzed context, acting as a project analyst, favored in-depth access to information and project dynamics. To mitigate the potential interpretation bias arising from this participation, data triangulation was adopted. This technique combined direct observation and documentary analysis, seeking to increase the reliability and consistency of the evidence obtained (Flick, 2009).

The object of study was a large organization operating in the wind energy sector, with over three decades of experience in executing energy infrastructure projects nationwide. The company has a predominant presence in strategic regions of Brazil, such as the Northeast, South, and Center-West, and operates with a matrix structure, composed of specialized areas such as planning, engineering, and procurement.

The company’s organizational culture is strongly oriented towards operational safety, regulatory compliance, and fulfillment of contractual deadlines. The organization maintains its own multidisciplinary teams and mobilizes outsourced professionals according to the needs of each project, adopting rigorous Health, Safety, Environment, and Quality (HSEQ) standards.

The analyzed project referred to the mobilization phase of a wind farm, starting on July 1, 2025, and ending on January 8, 2026. The scope included detailed planning of work fronts, logistical organization, resource definition, and structuring of the executive schedule until the start of assembly and lifting activities.

The team directly involved in conducting the project was composed of three professionals, two project managers and one project analyst. Indirectly, approximately thirty professionals participated, distributed among the areas of engineering, planning, procurement, safety, quality, and operations, in addition to suppliers and service providers linked to mobilization and assembly activities.

Data collection was carried out through direct observation and documentary analysis. Direct observation occurred due to the author’s active participation in the project, acting as a project analyst responsible for planning and monitoring the schedule. This condition allowed continuous access to strategic information, follow-up meetings, and decisions related to adjustments (Gil, 2019).

Concurrently, documentary analysis was performed based on the organization’s internal records. Schedules created in MS Project software, periodic progress reports, physical progress records, meeting minutes, mobilization controls, contractual documents, and rescheduling records were examined. Documentary analysis is a relevant technique in organizational research, allowing the exploration of previously produced data (Cellard, 2008).

To structure the project planning, the Work Breakdown Structure (WBS) was used, a tool that allowed the scope to be decomposed into hierarchically organized work packages. The WBS constitutes a hierarchical decomposition oriented towards the deliverables of the work to be executed, being fundamental to ensure that the entire scope is identified and adequately planned (PMI, 2021; Kerzner, 2017).

Based on the WBS (Work Breakdown Structure), the schedule was developed using MS Project software. This tool enabled the logical sequencing of activities, the definition of predecessors and successors, duration estimation, critical path identification, and tracking of physical progress during execution (Heldman, 2018). The software also facilitated scenario simulation and visualization of interdependencies between critical activities.

Additionally, the RACI matrix was employed as a tool to support responsibility management. This tool was used to define, in a structured manner, who was responsible, who had final authority, who should be consulted, and who should be informed at each relevant stage of the schedule (Meredith, Shafer, and Mantel, 2017).

The integrated use of the WBS (Work Breakdown Structure), MS Project, and the RACI matrix structured the schedule planning and control system adopted in the project. These tools, based on good project management practices, allowed for organizing the scope, sequencing activities, monitoring temporal performance, and ensuring alignment between teams.

The analysis of the collected data, in turn, sought to record, analyze, and interpret the practices effectively adopted in schedule management. The schedule’s performance was examined comprehensively, integrating empirical evidence, formal records, and the practical experience gained during project execution, without deliberate manipulation of independent variables.

3. Results and Discussion

The results obtained from the application of the methodology show that the structuring of the schedule planning contributed significantly to the increase in project predictability and to the improvement of critical activity control. The organization of the stages allowed for a clear relationship to be established between the practices adopted and the impacts observed during execution, especially regarding the control of critical activities and the mitigation of delays, as per the central objective of this study.

The first stage of the project consisted of diagnosing the organizational and contractual context, with the objective of identifying premises, restrictions, and obligations that would impact the schedule planning. From this diagnosis, the planning process began with the construction of the Work Breakdown Structure (WBS), used as an instrument to organize the deliverables and activities necessary for mobilization. The use of this tool contributed to increasing planning clarity, supporting deadline control, and facilitating the monitoring of activity progress.

The WBS (Work Breakdown Structure) was structured in two levels, according to the guidelines of the Project Management Institute (PMI, 2021) Guide, which contributed to greater clarity in the scope decomposition and facilitated the control of activities throughout the execution. At the first level, the main project activity groups were defined, such as mobilization, infrastructure, and documentation. At the second level, these groups were broken down into specific tasks, allowing for greater detail of the necessary actions. This decomposition enabled the construction of a more consistent schedule aligned with the project deliverables.

Subsequently, the detailed planning of the mobilization schedule was developed, with the objective of transforming the decomposed scope into a structured temporal plan. In this stage, the logical sequencing of activities, duration estimates, identification of dependencies, and determination of the critical path were defined. This process promoted greater integration between the involved areas, such as planning, logistics, and infrastructure, and enabled the identification of the most sensitive phases of the project, allowing for the prioritization of preventive actions.

The identification of the critical path is essential for effective schedule control, as these activities directly impact the project’s final deadline, as highlighted by Kerzner (2017). The schedule was developed using project management software, which allowed for the organization of activities, establishment of logical links (start-to-start, finish-to-start, and finish-to-finish), calculation of float, and automatic identification of the project’s critical path.

The mobilization planning presented a total duration of 135 days, covering from contractual analysis to the start of assembly and lifting activities. The mobilization planning phase stood out as one of the most relevant, with a duration of 80 days, concentrating critical activities related to labor, equipment, and logistics, considered determinants for meeting the contractual milestone of starting assembly.

The use of the software contributed to greater visibility of available slack, allowing the project team to anticipate strategic decisions and adopt preventive measures before significant deviations occur. This systematization strengthened the alignment between planning and execution, creating a consistent technical basis for the subsequent stage of schedule monitoring and control.

The analysis allowed the identification of the project’s critical path, highlighting the sequence of activities without float that directly impact the final mobilization deadline. The activities with the longest duration and greatest impact on the contractual milestone for the start of assembly were the labor admission and documentation process, with 35 days, and the equipment transportation logistics, with 45 days. Both were classified as critical.

It was observed that activities such as defining the onboarding schedule for collaborators and defining the necessary equipment were positioned sequentially, reinforcing the interdependence between human resources planning and logistical planning. This structure demonstrated that any delays in preliminary stages could directly impact subsequent activities, compromising the project’s final deadline.

The visual identification of the critical path allowed the team to prioritize the monitoring of these tasks during execution. The concentration of control over activities without total float favored the adoption of preventive measures, such as anticipating admissions, scheduling preventive maintenance, and intensive monitoring of document release. The breakdown revealed that, although the total schedule presented a duration of 135 days, a large part of the temporal risk was concentrated in a reduced subset of strategic activities, reinforcing the importance of directing managerial efforts to critical tasks.

With the structured schedule and critical paths duly identified, the RACI Matrix was developed with the objective of clarifying the responsibilities of those involved in the mobilization phase. The tool was used to support management and communication between areas, especially considering that not all stakeholders had direct access to the detailed schedule. From the RACI Matrix, the Responsible for executing activities, the Accountable for approving, the parties to be Consulted, and those to be Informed were identified, reducing ambiguities regarding assignments and contributing to the continuous monitoring of the status of activities among the involved areas.

The clear definition of roles and responsibilities is a determining factor for the effectiveness of planning and for reducing communication failures in projects, according to Kerzner (2017). It was verified that all activities in the mobilization phase had formally designated responsible parties and a record of progress monitoring, achieving 100% completion by the end of the analyzed period. This clarity contributed to reducing ambiguities, strengthening governance, and supporting systematic schedule monitoring.

After the consolidation of the structured schedule planning and the identification of critical activities, the implementation phase of the mobilization began. This phase aimed to ensure that the activities planned in the schedule were executed as planned, guaranteeing alignment between the involved areas and anticipation of possible deviations. In the first stage of the project, a detailed analysis of the contract signed with the client was carried out, focusing on the established deadlines, contractual milestones, penalties for delay, and mandatory technical requirements for the commencement of field activities.

This analysis was conducted in conjunction with the commercial sector and the project manager, allowing for alignment between contractual expectations and the organization’s operational capacity. In parallel, the main stakeholders involved in the project were identified, considering both internal areas and external agents. This identification made it possible to map preliminary responsibilities and understand the critical interfaces that would influence the schedule, especially in the stages related to the mobilization of labor, equipment, and mandatory documentation.

At the end of this initial stage, the consolidated information was presented at the project’s “kick-off” meeting, ensuring that the involved areas had a shared vision of the scope, deadlines, and initial responsibilities. This formalization marked the transition to the next stage, corresponding to the detailed planning of the mobilization schedule. In the planning and mobilization stage, the main restrictions and critical factors to be considered were consolidated.

The main restrictions identified included the fixed deadline for the start of assembly and lifting, which generated schedule compression of intermediate deadlines; the deadline for recruitment, hiring, and mandatory training of labor, with a risk of delay in team release; the need for preventive maintenance of equipment before mobilization, impacting availability for transport; the approval of documentation on the client’s platform, with external dependency and risk of rescheduling; and the release of licenses for crane movement, with possible interruption of critical activities.

The analysis of these constraints highlighted factors that directly impact the execution of the most sensitive activities in the schedule, especially those with greater dependence on contractual deadlines, critical resources, and external approvals. It was possible to correlate these constraints with the activities belonging to the project’s critical path, emphasizing those with the greatest potential impact on the start of the assembly milestone.

The critical path activities, with their respective initial risk levels, were the admission and documentation of labor, with a planned duration of 35 days and high impact on the assembly milestone, classified as high risk. The logistics of equipment transportation, with 45 planned days, also presented high impact and high risk. The development of the Rigging plan, with 30 days, had medium impact and moderate risk. Finally, the documentary release on the client’s platform, of variable duration, showed high impact and high risk.

Structured planning, associated with the analysis of constraints and the identification of critical activities, enabled the establishment of intermediate milestones and control mechanisms for each group of activities. Additionally, it facilitated scenario simulations, evaluating the impacts of potential delays and identifying possibilities for parallelization of non-critical tasks, which is fundamental for proactive risk management and integration between schedule and resources (PMI, 2021).

Historically, the admission process presents risks of delay due to recruitment, documentation, onboarding, and mandatory training stages. Similarly, equipment mobilization involves risks associated with mechanical failures, demands for corrective maintenance, and logistical challenges related to transportation and availability within the planned deadlines.

Due to these risks, preventive measures were adopted with the objective of mitigating impacts on the schedule. Regarding equipment, preventive maintenance was scheduled prior to mobilization, in addition to monitoring the displacement by maintenance teams, aiming to increase operational reliability during transport and assembly. As for labor, hiring was anticipated for the beginning of the programming, and mandatory training was planned in an integrated manner with other activities, reducing the risk of delays in releasing teams for the start of operations.

Within the scope of Health, Safety, and Environment (HSE), the necessary documents for the project’s mobilization and execution were developed and aligned, such as the HSE Plan and Preliminary Risk Analyses (PRA). Although this phase was originally planned for a later stage, it was identified that it needed to be conducted in parallel with other activities, due to the deadlines involved for the development, approval, and release of the documentation.

This anticipation contributed to mitigating risks related to the release of teams and field activities, favoring the continuity of the schedule and compliance with legal and contractual requirements. With the defined schedule and the estimate of the number of collaborators and established deadlines, it was possible to structure the planning of the necessary infrastructure to meet the project demands.

In conjunction with the purchasing department, a mapping of suppliers and resources was carried out, considering items such as accommodation, transportation, food, and other support structures. This approach enabled greater predictability of deadlines and opened an adequate window for negotiation with suppliers and internal areas, favoring more strategic decisions related to costs, deadlines, and contractual conditions, without compromising the schedule’s progress.

The documentation submission stage on the client’s platform was recognized, based on the history of previous projects, as one of the phases with the greatest potential to generate delays. Therefore, a strategy of continuous monitoring and advance preparation of documents was adopted, with the objective of reducing rework and minimizing impacts on the schedule.

The next phase corresponded to the effective start of the project mobilization, a moment when the planned activities began to be executed in an integrated manner. At this point, continuous monitoring was carried out until the project reached the field, ensuring that all planned activities were completed or in adequate condition for the start of assembly and lifting operations. The monitoring focused on verifying compliance with deadlines, resource availability, release of mandatory documentation, installed infrastructure, and mobilization of personnel and equipment.

This control contributed to the early identification of deviations and the implementation of timely adjustments to the schedule whenever necessary, helping the operational activities to start as per the established plan. This project phase proved to be strategic, as it enabled the identification of demands, reducing the need for emergency actions and increasing the time available for negotiations with suppliers, optimizing costs and ensuring the availability of resources within the planned deadlines.

Regarding project governance, daily meetings were held between the project managers and the analyst responsible for planning, focusing on monitoring critical activities and resolving operational impediments. Additionally, weekly meetings were held with the involved areas, aiming to review deadlines, validate deliverables, and promote integration between planning, logistics, infrastructure, security, and human resources.

This follow-up dynamic was structured with daily technical follow-up meetings, involving project managers and the analyst, for monitoring critical activities and resolving impediments. Weekly operational alignment meetings, with all involved areas, focused on reviewing deadlines, risks, and deliverables. Additionally, contractual validation meetings, as needed, with sales and project management, aimed at adjusting and aligning contractual obligations.

The implemented governance structure enabled continuous monitoring of activities, facilitating early identification of deviations and timely corrective decision-making. Nevertheless, it was observed that not all risks could be fully mitigated, especially those related to external factors, such as the release of licenses and documentary approvals. Despite these limitations, the implementation phase was completed with all activities executed, enabling the transition to the operational stage of assembly and lifting.

Given this scenario, it became necessary to intensify monitoring practices, initiating the schedule monitoring and controlling phase, with the objective of comparing the actual performance of activities with the established plan and identifying deviations that could compromise the project’s final deadline. As part of this process, systematic control of activity progress was implemented.

The analysis of the progress control of critical activities demonstrated that, although all activities were completed, some presented variations in relation to the planned deadline. The admission and documentation of labor activity, planned for 35 days, was carried out in 38 days. The equipment transportation logistics were completed within the planned deadline of 45 days, as was the elaboration of the Rigging plan, in 30 days. Document release on the client’s platform, of variable duration, was completed with a three-day delay. Infrastructure planning was completed within the 15-day deadline.

The extension of the labor admission process and delays associated with document release stood out, factors that contributed to the final deviation from the schedule. Despite these variations, the implementation phase was completed with the full execution of activities, which demonstrates the adaptive capacity of the adopted management model, albeit with limitations in the face of uncontrollable external factors.

Considering the observed deviations, the overall schedule performance was evaluated at the end of the mobilization phase. The project began on July 1, 2025, and ended on January 8, 2026, fully encompassing the mobilization phase and the start of assembly and lifting activities. Although all activities were completed, a final delay of eight days was observed compared to the originally planned deadline.

The schedule performance analysis, based on the evaluation of activities belonging to the critical path and the comparison between planned and actual dates, revealed that 100% of the analyzed critical activities were completed. Of this total, 85% were completed within the revised deadline, and 15% were delayed. The final project delay was eight days, with the activity with the greatest individual deviation being document release, with three additional days, representing 37.5% of the total deviation.

The data demonstrated high adherence to the structured plan and reinforced the effectiveness of continuous schedule monitoring, as recommended by the Project Management Institute (PMI, 2021), which highlights the importance of systematic variation control for project success. However, deviations occurred in activities integral to the critical path, making total absorption impossible through the parallelization of non-critical tasks.

The main factors associated with deviations were, for the most part, external variables and processes with high documentary dependence, indicating that, although structured planning increases predictability, its effectiveness is partially limited by factors beyond the direct control of project management. Although strategies for anticipating non-critical activities were adopted, such as prior organization of equipment logistics and infrastructure preparation, the impacts on activities belonging to the critical path resulted in the consolidated final delay.

In addition to temporal performance, the impact of structured planning on mobilization costs was evaluated. The comparison with a previous project of similar characteristics showed relevant financial gains. There was a 19% reduction in infrastructure costs and an average global reduction of 15% in mobilization costs. The main savings identified were in vehicles, generators, and fuel.

The reduction of approximately 19% in infrastructure costs shows that the structured schedule planning not only contributed to temporal control but also to the optimization of financial resources, demonstrating the interdependence between time and cost in project management. The global average reduction of 15% in the mobilization phase showed that structured planning generated not only temporal but also financial benefits.

Additionally, it was estimated that the corrective actions implemented during monitoring reduced the risk of further delays by approximately 20%, as they allowed for timely responses to identified impediments. The consolidation of the project’s key performance indicators revealed 85% adherence to the revised schedule, a final consolidated deviation of eight days, a 19% reduction in infrastructure costs, and an overall average reduction of 15% in costs. The governance model included daily and weekly meetings, and 100% of activities had formally assigned responsibilities.

The analysis of the results allows us to infer that the structured model adopted presented consistent adherence to good project management practices, especially regarding scope decomposition, critical path identification, and systematic activity monitoring. These findings corroborate the guidelines of the Project Management Institute (PMI, 2021), which highlight the importance of integration between planning and control for schedule success.

However, the results also highlight the model’s limitations when facing uncontrollable external variables, such as licensing processes and documentary approvals. This aspect reinforces the literature that points to the influence of exogenous factors on the predictability of infrastructure projects, indicating that, even with structured planning, deviations may be inevitable, according to Flyvbjerg and Gardner (2023).

These findings reinforced the relevance of the systematic application of project management tools in highly complex wind ventures and provided an empirical basis for critical discussion. The structured application of schedule management practices contributed significantly to project predictability and control, even though it did not entirely eliminate schedule deviations.

The completion of 85% of critical activities within the revised deadline demonstrated satisfactory adherence to the adjusted plan, corroborating the premise that systematic monitoring favors timely interventions and reduction of accumulated impacts. The identification and tracking of the critical path proved to be decisive for prioritizing managerial actions, as highlighted by Kerzner (2017), who emphasizes that controlling activities without float is a central element for maintaining the project’s final deadline.

In the present study, it was found that delays occurred precisely in activities belonging to the critical path, confirming the relevance of this approach for directing monitoring efforts. The adoption of a formal governance model, with daily and weekly meetings, also proved consistent with the specialized literature, which points to structured communication and clear definition of responsibilities as critical success factors in complex projects (Meredith et al., 2017).

The formalization of assignments through the RACI matrix reduced ambiguities and favored integration between the involved areas, strengthening the information flow and decision-making. Despite the application of recommended best practices, the project experienced a final delay of eight days, mainly due to external factors and unforeseen restrictions in the initial planning, such as the non-release of the crane movement license during the recess period.

This result confirms the argumentation of Flyvbjerg and Gardner (2023), according to whom infrastructure projects frequently face external variables that challenge initial predictability, requiring adaptive capacity from the management team. However, even in the face of these restrictions, partial mitigation of impacts was observed through the parallel execution of non-critical activities and logistical anticipation, a strategy that proved consistent with the recommendations for proactive risk management and integration between schedule and resources (PMI, 2021).

The financial gains achieved, with a reduction of approximately 19% in infrastructure costs and 15% in total mobilization costs, demonstrated that structured planning produced benefits beyond the temporal dimension, increasing the project’s overall efficiency. The systematic application of project management tools in the wind context contributed to increased predictability, strengthened governance, and cost optimization, even though external restrictions limited the total elimination of delays.

The empirical analysis reinforced the importance of integration between scope, time, resources, and communication, as advocated by contemporary literature in the field. The results obtained reinforce that, in projects of high complexity, the structured application of schedule management tools is a necessary, but not sufficient, condition, with the ability to adapt to external factors being indispensable.

Thus, the findings of this study not only confirm the literature guidelines but also demonstrate, in practice, the challenges and limitations of schedule management in wind projects, especially in contexts subject to high uncertainty and dependence on external factors. The structured model adopted in schedule management showed satisfactory performance, demonstrating the ability to control and adapt to critical variables, and providing relevant subsidies for the improvement of management practices in highly complex wind projects.

In summary, the implementation of a structured model for managing the mobilization schedule in wind projects proved effective in increasing the predictability and control of critical activities, as per the objective of this study. Although challenges such as external factors and documentation dependency caused a final delay of eight days, the research showed that 85% of critical activities were completed within the revised deadline and that there were significant cost reductions, of 19% in infrastructure and 15% overall. These results reinforce the importance of integrating detailed planning, continuous monitoring, and robust governance, while also highlighting the need for adaptive management capacity in the face of uncertainties inherent in complex projects.

4. Conclusion

The present study aimed to propose and analyze a structured model for managing the mobilization schedule in wind projects, seeking to increase delivery predictability and reduce schedule deviations. It was found that the application of practices such as the Work Breakdown Structure (WBS), the use of management software, and the RACI Matrix contributed significantly to increased predictability and control of critical activities. It was observed that 85% of critical activities were completed within the revised deadline, and there was a 19% reduction in infrastructure costs and an overall average decrease of 15% in mobilization costs. These findings reinforced project governance, transparency in decision-making, and resource optimization. However, the project experienced a final delay of eight days, mainly due to external factors such as documentation release and the non-issuance of permits for crane movement, demonstrating that the effectiveness of structured planning is partially conditioned by variables outside the direct control of management.

Among the limitations of this work, we highlight the restricted access to strategic data and the impossibility of full disclosure of financial information, in addition to the analysis being based on a single project, which restricts the generalization of the results. For future studies, it is recommended to apply the model in different operational contexts, aiming to broaden its robustness and external validity. It is also suggested to incorporate more robust quantitative methods for risk analysis and scenario simulation, as well as integration with advanced predictive analysis tools. It is concluded that the structured schedule management model demonstrated relevant capacity to increase predictability, strengthen governance, and optimize resources, even though it does not entirely eliminate schedule deviations, underscoring the need for adaptive management capacity in the face of uncertainties inherent in complex projects.

Bibliographic References

ABEEólica. 2023. Boletim Anual de Geração Eólica 2023.

Chamier-Gliszczynski, N. 2024. Logistics processes in the construction of wind farms. Energies. 17(3): 1-18.

Creswell, J. W.; Poth, C. N. 2018. Qualitative Inquiry and Research

Flyvbjerg, B.; Gardner, D. 2023. How Big Things Get Done: The Surprising Factors That Determine the Fate of Every Project, from Home Renovations to Space Exploration and Everything in Between. 1. ed. Crown Currency, New York, NY, Estados Unidos.

Kerzner, H. 2022. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 13. ed. John Wiley & Sons, Hoboken, NJ, Estados Unidos.

Logistic Decisions In The Installation Of Offshore Wind Farms. 2024. Logistic decisions in the installation of offshore wind farms. Energies. 17(5): 1-22.

Project Management Institute [PMI]. 2021. A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 7. ed. Project Management Institute, Newtown Square, PA, Estados Unidos.

Thiollent, M. 2011. Metodologia da Pesquisa-Ação. 18. ed. Cortez, São Paulo, SP, Brasil.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.