Schedule management of the footwear development project of a footwear industry
Schedule Management of the Footwear Development Project of a Footwear Industry
Wendell Zague Soares; Emilio Antonio Amstalden
DOI: 10.22167/2675-6528-202602434
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
Schedule management is a central element for project success, especially in industrial contexts with multiple dependencies. In the footwear sector, the complexity of product development and the need to meet collection deadlines make time control a critical factor for coordinating activities and making decisions. In this context, schedule management practices in product development in a footwear industry were analyzed, identifying operational challenges and improvement opportunities. To this end, a qualitative case study was conducted, using documentary research, semi-structured interviews with product development, merchandising, and factory professionals, and participant observation. The data were analyzed by triangulation between the different sources of evidence. The results showed that, although a formal schedule existed as a reference for sequencing activities, its application was predominantly operational and reactive. Updates were motivated by execution deviations, dependence on punctual communications, and limitations in integration between areas. It was concluded that strengthening structured practices for monitoring, communication, and schedule integration can contribute to increasing predictability and efficiency in the management of product development projects in the footwear industry.
Keywords: Deadline control; Product development; Project time management; Project planning; Industrial processes.
1. Introduction
The growing complexity of corporate environments has reinforced the importance of project management as a central discipline to ensure alignment between organizational strategies and delivered results. The increase in competitiveness and the speed of changes demand the adoption of structured models for planning, execution, and control, capable of transforming demands into consistent deliverables aligned with strategic objectives (Kerzner, 2017). In this context, project management has assumed a strategic role in organizations, contributing to improved decision-making, activity control, and value generation throughout the product and service development cycle.
In the Brazilian context, the footwear industry holds a prominent economic and social position. Brazil is the fourth largest producer of footwear in the world, with 929.5 million pairs produced in 2024, representing approximately 4% of global production. The sector generates around 300,000 direct jobs and concentrates its main production hubs in the states of Rio Grande do Sul, Minas Gerais, São Paulo, Ceará, and Bahia (ABICALÇADOS, 2025). This scenario reinforces the relevance of modern management practices to ensure competitiveness in a sector characterized by long development cycles, intense pressure for deadlines, and multiple actors involved in production processes.
Project management is presented as a mechanism for continuous improvement, fundamental for constant adaptation in the business environment (Camargo, 2015). The growing demand for innovation reinforces the importance of project management as support for the creation of new products and solutions. In industrial sectors, the ability to coordinate activities and monitor deadlines directly influences results. Rozenfeld et al. (2006) highlight that structured development processes depend on the integration between areas and the efficient coordination of stages, ensuring the fulfillment of planned deadlines and contributing to greater operational efficiency. The Project Management Institute (PMI, 2017) emphasizes that the adoption of structured practices, aligned with internationally recognized methodologies, contributes to process standardization and uncertainty reduction, making project execution more predictable.
National literature has widely discussed the application of structured practices for planning and monitoring activities in product development. Studies show integration failures and delays in product development (Silva and Kaminski, 2012), difficulties in sequencing and controlling activities (Rozenfeld et al., 2006), limitations in the use of manual tools and communication problems between areas (Costa and Figueiredo, 2010), in addition to the low application of schedule management practices provided for in the PMBOK (Miranda and Amaral, 2004). These factors indicate that challenges related to time control are recurrent in both product development and the practical application of these methodological guidelines, reinforcing the importance of investigating how schedule management is conducted in different organizational contexts, especially in sectors with long cycles and strong dependence on multiple sectors, such as the footwear industry.
Despite the relevance of schedule management for footwear development, it is observed that the company under study faces difficulties in coordinating the stages, updating information, and integrating the involved sectors. This occurs due to the use of manual and poorly collaborative tools, which has generated delays, rework, communication errors, and low visibility of the progress of activities, compromising project performance. Given this scenario, it becomes necessary to investigate how the schedule has been planned, controlled, and communicated in product development.
Understanding these practices is fundamental to identifying improvement opportunities and strengthening project management, especially regarding predictability and efficiency. The objective of this research is to analyze the schedule management practices in the footwear development project of a multinational company in the footwear sector, headquartered in São Paulo, SP, identifying limitations and improvement opportunities in the planning, updating, and deadline control processes. It also seeks to propose recommendations that contribute to the enhancement of schedule management and greater integration among those involved in the project.
2. Material and Methods
The research was characterized as a case study, a modality selected for the in-depth investigation of contemporary phenomena in their real context, as advocated by Yin (2015). Regarding its nature, it was an exploratory and descriptive investigation, seeking to gather information about existing practices and describe their characteristics, aligning with the approaches of Gil (2017) and Lakatos and Marconi (2017). The methodological approach adopted was qualitative, allowing for the understanding of perceptions and organizational processes related to schedule management.
The study was developed in a Brazilian subsidiary of a Japanese multinational company in the footwear sector, founded in 1949, with a consolidated presence in several international markets. In Brazil, the organization has maintained its own operations for 18 years and has approximately 140 employees distributed among the areas of product development, design, quality, planning, sales, and corporate support. The company has a dedicated structure for the development of sports footwear and maintains partnerships with local factories for project implementation.
The empirical object of the research was a development project for a children’s “running” shoe, belonging to the autumn/winter 2026 collection. The project’s development cycle took place between March 2025 and January 2026, with a planned launch in July 2026. A product developer, a merchandising professional, representatives from the partner factory responsible for production, as well as the quality and planning teams that monitor specific stages of the process, participated in this project.
The methodological procedures involved data collection through three main sources: documentary research, semi-structured interviews, and participant observation. This data triangulation was employed to integrate information and allow for a more comprehensive analysis of schedule management practices in the footwear development project.
The documentary research focused on the analysis of formal records used by the company for project monitoring. Initially, the original project schedule, developed in a spreadsheet (Excel), was analyzed, serving as the main instrument for monitoring the stages. From this document, patterns of completion, duration estimates for activities, sequence of phases, and the level of information update were identified.
In addition to the schedule, the weekly project progress minutes and formal communications via corporate emails between the teams involved were examined. These documents were used as complementary sources to record information related to the progress of the stages, technical feedback, and definitions of next activities. The analysis of these records aimed to understand how the information related to the schedule was formalized, updated, and communicated among the areas involved in the project.
Three semi-structured interviews were conducted, involving a professional from the partner factory, a member of the merchandising area, and a product development professional. The interviews, composed of approximately 10 to 12 open-ended questions, were conducted via videoconference, according to participant availability, and were previously scheduled. Information was recorded through detailed manual notes, aiming to preserve the fidelity of the content of the answers provided by the participants, without recording due to technical limitations.
Participant observation occurred throughout the product development stages, allowing for an understanding of the schedule’s application in the organization’s daily life and how communication flows between areas influenced the progress of activities. Key moments of each project stage were recorded, through phase monitoring reports, as well as defined deadlines, deliveries made, and adjustments made during the process. Situations where the schedule directly influenced the progress of activities, interactions, and information exchanges between the involved areas were also noted.
The collected data were qualitatively analyzed through thematic categorization, following the assumptions of content analysis proposed by Bardin (2011). This procedure involved the organization, coding, and interpretation of information, allowing for a comparison of findings from documents, interviews, and participant observation. The analysis was guided by the schedule management processes established in the PMBOK, such as activity definition, sequencing, duration estimation, schedule development, and control.
Regarding ethical considerations, this work falls under Article 1, sole paragraph, of CONEP/CNS Resolution n.510/2016, with no need for submission to the Research Ethics Committee via Plataforma Brasil. However, participants in this research were offered the Free and Informed Consent Agreement, which was accepted before the data collection instruments were applied.
3. Results and Discussion
The analysis of schedule management practices in the development of footwear for a shoe industry revealed a complex scenario, characterized by the coexistence of formal planning with predominantly operational and reactive execution. The findings, derived from documentary research, semi-structured interviews, and participant observation, converged to highlight both the relevance of the schedule as a guiding instrument and the inherent limitations of its application in the daily project routine. This data triangulation allowed for an in-depth understanding of the challenges and opportunities for improvement in Time Management, as outlined by the study’s objective.
The documentary research initially focused on the project schedule, developed in a spreadsheet (Excel), which served as the main reference for sequencing activities and monitoring the development stages of an infant “running” category shoe for the Fall/Winter 2026 collection. This document detailed the project phases, with planned start and end dates, and crucial intermediate milestones. For example, the “Merchandising Briefing” was scheduled for March 21st, the “1st Design” for April 18th, the “Feedback on Prototype Sample” for June 6th, and the “Launch” for July 2026. The schedule’s structure, although functional, did not explicitly include a precedence diagram or formal representation of activity dependencies, which is a recommended practice in project management.
In addition to the schedule, the weekly project follow-up minutes were analyzed, proving to be a recurring tool for recording the progress of stages, technical decisions, deadline adjustments, and operational definitions. These minutes highlighted informal schedule management practices, such as continuous activity monitoring and recording deviations from the initial plan. Replanning of stages to mitigate delays was also observed, functioning as an alignment mechanism between the involved areas. The documentation of discussions and actions in these weekly meetings reinforced the role of the minutes as a communication and information-sharing tool, detailing how schedule control was conducted in practice.
E-mail communications were also examined, being used to formalize the closing of phases, align deadlines, request technical corrections, and communicate changes in the schedule. These records demonstrated the interaction dynamics between the product development, merchandising, quality, planning, and factory areas. However, the analysis revealed that schedule updates occurred in a punctual and decentralized manner, depending on the sending of specific messages to communicate adjustments. This practice resulted in the dispersion of relevant information, making it difficult to consolidate an integrated view of the project’s progress and limiting the overall visibility of the schedule.
Documentary research did not identify formal records related to a schedule management plan, project breakdown structure (WBS), scope plan, risk mapping, or structured lessons learned documents. This indicates that, although the company used tools for schedule monitoring, the process lacked a formal management structure, being limited to an operational record of activities and decisions. This absence of formalization contrasts with the PMBOK guidelines (PMI, 2017), which emphasize the need for structured processes for effective schedule control.
The results obtained through semi-structured interviews deepened the understanding of schedule management practices, complementing the documentary findings. The perceptions of professionals from the product development, merchandising, and factory areas revealed different levels of involvement and understanding regarding the schedule. There was convergence regarding the clarity of the schedule for professionals directly involved in planning and execution, such as those in development and factory, who considered it clear and complete, covering all stages.
However, the merchandising professional indicated limitations in understanding the initial phases and in visualizing the complete project flow, suggesting that the schedule more effectively serves the technical areas than the commercial interface areas. This difference in perception points to a lesser clarity of the schedule in areas with more strategic involvement, indicating misalignments in understanding between sectors. The absence of standardization in the way information is updated and shared contributes to distinct interpretations among professionals, generating operational misalignments throughout the project cycle.
The schedule update, according to the interviewees, occurs recurrently throughout product development, driven by internal and external interferences, such as supplier delays, global approvals, and technical adjustments. This perception was corroborated by documentary analysis, which showed frequent deadline changes and stage redefinitions in weekly progress reports and email communications. However, the communication of these updates is punctual and not systematized, focusing on weekly records and specific messages at the end of phases, without uniform dissemination to all involved areas.
Regarding the realism of deadlines, the interviewees agreed that the initial planning is structured and includes safety margins. However, external factors, especially related to suppliers and manual processes, compromise adherence to the original schedule, requiring frequent adjustments and deadline recovery strategies. This vulnerability to external factors demands continuous replanning, which, although expected in complex projects, indicates a significant dependence on reactive actions to keep the project on track, as also observed in the literature by Rozenfeld et al. (2006).
Communication between areas emerged as one of the main critical points of the schedule management process. Interviews highlighted difficulties in aligning expectations and priorities, excessive reliance on emails, and the absence of formal mechanisms for real-time alerts and updates. This dynamic directly impacts schedule control and decision-making. Document analysis, with the predominant use of weekly minutes and email communications, corroborates this perception, indicating that communication does not occur in a standardized manner, which negatively affects project alignment and predictability.
Schedule delays frequently require mitigation strategies, such as the need to skip or adapt project phases. Respondents reported that these delays have a direct impact on commercial presentations and sales results, highlighting the centrality of the schedule to overall project performance. The reliance on replanning to recover lost dates reinforces the reactive nature of management, where the schedule, although central, is constantly adjusted in response to deviations, rather than proactively.
The tool used, the Excel schedule, was recognized as simple, accessible, and functional. However, its limitation regarding collaboration and shared updates was highlighted, especially by the merchandising area. This perception reinforces that the tool meets basic control needs but does not favor integration among the various project stakeholders, limiting traceability and collaboration. The lack of a more robust and integrated tool contributes to information fragmentation and hinders activity tracking, as pointed out by Costa and Figueiredo (2010).
The improvement opportunities pointed out by the interviewees converged on the need for greater standardization of the schedule management process, with the adoption of a single and integrated schedule, greater transparency of information, and systematic recording of planned and actual dates. The importance of strengthening interfunctional communication was also highlighted. These suggestions indicate a path for improving schedule management, especially regarding integration between areas and process maturity, aligning with Kerzner’s (2017) recommendations on the integration between planning, monitoring, and continuous communication.
Participant observation, carried out throughout the product development stages, corroborated the documentary and interview findings, evidencing the practical application of the schedule in the organizational routine. It was verified that the schedule plays a central role in organizing activities, serving as a reference for defining deadlines, prioritizing demands, and monitoring deliveries. However, its use is predominantly operational, focused on updating dates and meeting immediate demands, especially in the face of supplier delays and technical adjustments.
Communication of schedule changes during the observation period primarily occurred through specific formal channels, such as emails and dedicated meetings, directed at restricted groups. This dynamic reinforces information fragmentation and the difficulty of alignment between areas like product development, merchandising, quality, and manufacturing, limiting integrated visibility of project progress. Schedule replanning was observed as a reactive process, driven by external events or operational unforeseen issues, such as delays in material release or scope revisions, with decisions based on experience and informal negotiations rather than systematic impact analysis.
The systematization of participant observation records reinforces that, although the schedule is widely used as a guiding instrument, its application is predominantly operational and reactive, with limitations in standardizing procedures and integrated communication between areas. The adoption of a formal schedule is evident, but the recurring need for adaptations during execution demonstrates a poorly standardized and inconsistent update process. There is fragmentation of information and a lack of systematic dissemination, resulting in an imbalance in schedule visibility among the involved areas, which suggests fragility in the initial planning and dependence on continuous adjustments.
In summary, schedule management in the studied company’s footwear development project is carried out through formal planning that guides the sequencing of activities. However, its application is predominantly operational and reactive, with updates driven by technical adjustments, supplier delays, and other process dependencies. Although the schedule is a widely used reference, there are significant limitations related to the standardization of update processes, integrated communication between areas, and the systematic dissemination of information about deadline changes. These findings indicate that schedule management meets immediate operational needs, but there is considerable room for improvement in time management, especially regarding the formalization of processes, cross-functional integration, and more strategic use of the schedule throughout product development, contributing to greater predictability and efficiency.
4. Conclusion
This study analyzed the schedule management practices in the footwear development project of a shoe industry, seeking to identify its limitations and opportunities for improvement in the planning, updating, and deadline control processes. It was found that, although the company used a formal schedule as a reference for activity sequencing, its application was predominantly operational and reactive. The findings showed that schedule updates were motivated by execution deviations and depended on punctual communications, resulting in fragmented visibility of project progress. The absence of structured control and integrated communication processes was identified, which limited the effectiveness of the schedule as a management tool. The tool used, an electronic spreadsheet, proved functional for basic control but deficient in terms of collaboration and systematic dissemination of information among the product development, merchandising, and factory areas. This analysis contributes to the understanding of the challenges faced in time management in complex projects and offers subsidies for improving predictability and operational efficiency in the sector.
As limitations of the research, it is noteworthy that the study was conducted in a single project and a single organization, which restricts the generalization of the results. There was also an impossibility of access to detailed historical records on the evolution of the schedule in previous development cycles. Additionally, difficulties were encountered in collecting and systematizing data from different sources, as well as in reconciling the author’s professional activities with the research development stages. For future studies, it is suggested to expand the analysis to other projects and organizations in the footwear sector, investigating the application of digital schedule management tools and more integrated project management practices. To improve schedule management, it is recommended to define a baseline, conduct periodic reviews of activities, systematically record deadline deviations, strengthen cross-functional communication, and use collaborative tools that enhance project information visibility.
Bibliographic References
Abicalçados. (2025). Relatório da Industria de Calçados no Brasil. Disponível em: http://abicalcados.com.br/. Acesso em: 15 set.2025.
Bardin, L. (2011). Análise de conteúdo. Lisboa, Portugal: Edições 70.
Camargo, M. R. (2015). Gerenciamento de Projetos: fundamentos e prática integrada. 2. ed. São Paulo: Atlas.
Costa, J. M.; Figueiredo, K. F. (2010). Atrasos no desenvolvimento de novos produtos: um estudo em empresas industriais brasileiras. Encontro Nacional de Engenharia de Produção ENEGEP, Brasil.
Gil, A. C. (2017). Como elaborar projetos de pesquisa. 6. ed. São Paulo: Atlas.
Kerzner, H. (2017). Gerenciamento de projetos: uma abordagem sistêmica para planejamento, programação e controle. 11. ed. São Paulo: Blucher.
Lakatos, E. M.; Marconi, M. A. (2017). Fundamentos de metodologia científica. 8. ed. São Paulo: Atlas.
Miranda, R. M.; Amaral, D. C. (2004). Gerenciamento de prazos em projetos: um estudo sobre a aplicação das práticas recomendadas pelo PMBOK. Encontro Nacional de Engenharia de Produção, ENEGEP, Brasil.
PMI, Project Management Institute. (2017). Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK®). 6. ed. Newtown Square, PA: Project Management Institute.
Rozenfeld, H.; Forcellini, F. A.; Amaral, D. C.; Toledo, J. C.; Scalice, R. K.; Silva, S. L. (2006). Gestão de desenvolvimento de produtos: uma referência para a melhoria do processo. São Paulo: Saraiva.
Silva, C. L.; Kaminski, P. C. (2012). Modelos de referência para o processo de desenvolvimento de produtos: um estudo de caso em uma indústria brasileira. Revista Produção Online, UFSC, Brasil.
Yin, R. K. (2015). Estudo de caso: planejamento e métodos. 5. ed. Porto Alegre, RS: Bookman.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq