Integration Management in the Implementation of New Explosive Emulsion Technology in Mining

Integration Management in the Implementation of New Explosive Emulsion Technology in Mining

Wesley Bazílio de Andrade; Daniel Luis Garrido Monaro

DOI: 10.22167/2675-6528-202602437

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

Pioneering projects in complex industrial environments demanded high coordination capacity, especially when the project manager’s formal authority was limited. It was analyzed how integration management tools and practices were used, until April 21, 2026, in a project to implement new explosive emulsion technology in mining. The study identified the coordination mechanisms employed, the main challenges faced, and, based on the findings, proposed a minimum set of integration mechanisms for similar projects. The research adopted a single case study, of an applied nature, with a qualitative approach and descriptive objective, based on documentary analysis of the project’s own records. The results showed that integration was sustained by the combination of authorization to proceed, project breakdown structure, integrated schedule, weekly meeting routine, shared document repository, and coordination between regional and global leaderships. It was found that the main outcome of integration management was the progressive construction of project system readiness, preserving coherence between technical, commercial, logistical, and operational fronts. It was concluded that the analysis supported a managerial proposition applicable to pioneering projects in weak matrix structures, indicating that the anticipation of minimum integration mechanisms benefits projects with similar characteristics.

Keywords: Coordination; Schedule; Case study; Matrix governance; Stakeholders.

1. Introduction

Integration Management occupies a central position in project literature as it is the dimension responsible for articulating decisions, resources, information, and deliverables throughout the entire lifecycle of an undertaking (PMI, 2021; Kerzner, 2022). Within the Project Management Institute framework, this logic is treated systemically, with an emphasis on principles, performance domains, context adaptation, and value generation. This reinforces the understanding that a project should not be conducted as a set of isolated parts, but as a temporary organizational system that needs to maintain coherence between strategy, governance, and execution (PMI, 2021; Kerzner, 2022).

From this perspective, integrating does not mean merely consolidating schedules or documents. It means, above all, ensuring alignment between objectives, managerial choices, technical interfaces, and stakeholder expectations (PMI, 2021; Kerzner, 2022). The relevance of this discussion becomes even greater in complex projects, where the multiplicity of involved areas, the interdependence between activities, and the diversity of stakeholders amplify the need for continuous coordination (Kerzner, 2022).

Previous studies have shown that the best performance of project management practices is associated with project success, which reinforces the importance of managerial mechanisms capable of connecting planning, execution, and control (Mir and Pinnington, 2014). In environments marked by intensive interfaces, overlapping responsibilities, and operational uncertainty, integration between teams also favors conflict resolution, decision-making, and execution fluidity (Franz and Olopade, 2024). Thus, integration is understood as an essential managerial capability to sustain project unity in more demanding organizational contexts.

In the mineral sector, this need for integration proves particularly critical. The value chain brings together engineering, operation, safety, logistics, supplies, regulatory compliance, and commercial relationships in the same decision and delivery flow. In this context, coordination failures tend to generate chain effects on technical, operational, and economic performance. From the perspective of mineral production, the literature indicates that the blasting stage directly influences the subsequent crushing and grinding stages, which is why the fragmentation generated by detonation is treated as a relevant variable in the “mine-to-mill” logic (Nikkhah et al., 2022; Figueiredo et al., 2023). This implies that decisions made during mining can affect the regularity of plant feed, energy consumption, and the overall efficiency of mineral processing.

It was in this environment that the project analyzed in this work was inserted, focused on the implementation of a new pumped explosive emulsion technology, using a loading equipment substantially different from the standard fleet. The project was developed in an open-pit copper mine located in the Pavlodar region, in northern Kazakhstan, with an installed processing capacity of approximately 30 million tons of ore per year.

The complexity of the case stemmed from simultaneous factors, such as the first application of the technology across the “Europe, Middle East and Africa” [EMEA] region. Furthermore, the project was conducted within a weak matrix structure, where the project manager acted primarily as a coordinator with low formal authority over resources. The execution involved stakeholders distributed across local, regional, and global levels, and the work’s conduct depended on unprecedented imports, regulatory requirements, multilingual training, and technical adaptations for extreme climatic conditions.

In this scenario, the research problem that guided this study emerged: how were integration management tools and practices applied, in practice, to coordinate a multidisciplinary technological implementation project in mining in a context of high organizational and operational complexity?

The justification for investigating this issue lies in the fact that projects of this nature require not only technical mastery of the implemented solution but also coordination capacity between areas with distinct priorities, high dependency between deliverables, and limitations of formal authority. Although the literature recognizes the importance of integration management for project success (PMI, 2021; Kerzner, 2022; Mir and Pinnington, 2014), it is still relevant to broaden the understanding of how these practices materialize in applied and high-complexity contexts, such as mining. Therefore, the objective of this work is to analyze how integration management tools and practices were used, until April 21, 2026, in a project to implement new technology in mining, identifying the coordination mechanisms employed, the main challenges faced, and, based on the case findings, proposing a minimum set of integration mechanisms applicable to similar projects.

2. Material and Methods

The research adopted a single case study design, of an applied nature, with a qualitative approach and descriptive objective. The choice of case study proved pertinent for examining a contemporary phenomenon in its real context (Yin, 2017), with learning potential for similar organizational contexts. The qualitative approach was considered the most appropriate, as the central interest focused on coordination practices, integration routines, managerial decisions, and interfaces between the involved areas, rather than on the statistical measurement of variables (Creswell and Creswell, 2022).

The unit of analysis corresponded to a corporate project for the implementation of new pumped emulsion explosive technology in an open-pit copper mining operation in northern Kazakhstan. The temporal scope of the analysis covered the period from March 2024 to April 21, 2026. The choice of a single case was justified by the unique nature of the project, being the first application of the technology in the “Europe, Middle East and Africa” [EMEA] region, in a context of weak matrix structure and multiple technical interfaces (Yin, 2017). As of the cutoff date, the physical implementation phase of the product at the client’s site had not yet begun.

The data collection technique employed was documentary research, based on pre-existing institutional records, produced in the normal flow of the project, without the generation of primary data through interviews, questionnaires, or direct observation (Bowen, 2009). The documentary corpus consisted of textual documents, spreadsheets, presentations, and visual evidence, made available by the author, and provided evidence of planning, monitoring, governance, communication, and definition of responsibilities.

The analyzed documents included the research project, preliminary results, description of the operation and governance, project schedule, “stakeholders” matrix, and the project breakdown structure [EAP]/”work breakdown structure” [WBS]. The minutes of the general project meeting and the documentary record of the authorization to proceed [ATP], along with the phase 1 “project charter” template, were also examined.

The organization and analysis of the data were developed in stages. Initially, a complete reading of the documents was carried out to understand the general project linkage and identify convergent or discrepant information. Subsequently, data related to milestones, deliverables, responsibilities, “stakeholders”, communication routines, constraints, relevant changes, and managerial responses observed in the analyzed period were extracted.

In the subsequent stage, this information was organized into synthetic tables, allowing for the comparison of distinct sources and the verification of dependency relationships, internal coherence, and critical points. The interpretation of the material was based on content analysis from a thematic perspective, following the steps of pre-analysis, material exploration, and results treatment proposed by Bardin (2016). Four analytical categories guided the reading: operational context of the case; governance and “stakeholders”; integration tools and routines; and managerial changes, constraints, and responses. Triangulation between sources, through documents with distinct functions, favored interpretive consistency (Yin, 2017; Bowen, 2009).

Due to the corporate nature of the documents analyzed, the final text omitted company names, brands, clients, and individual participants, preserving the information essential to understanding the phenomenon studied. Primary data collection with human participants was not used, ensuring confidentiality and anonymity of the parties involved.

As a limitation, it was considered that the research portrayed a project still in progress until the adopted cutoff date, preventing the measurement of final operational results or definitive benefits perceived by the client. The analysis focused exclusively on documentary evidence, restricting direct observation of informal coordination perceptions and dynamics. As it is a single case study, the work did not seek statistical generalization, but offered analytical generalization and learning applicable to projects with similar characteristics (Yin, 2017).

3. Results and Discussion

The analysis of the implementation project of the new explosive emulsion technology in mining revealed a complex panorama of challenges and integration strategies, especially in an environment of weak matrix governance and geographical dispersion of stakeholders. The findings indicated that, although there was no formal integration management plan in the analyzed period, the project developed a robust set of coordination mechanisms that allowed for the progressive construction of system readiness. The research focused on identifying how these practices materialized, the obstacles overcome, and, from this understanding, proposing a managerial model applicable to similar contexts, according to the central objective of the study.

The initial results highlighted the importance of integration to maintain coherence among the various project fronts, including technical, commercial, logistical, and operational aspects. This need for continuous articulation was amplified by the pioneering nature of the technology in the EMEA region and the organizational structure that limited the project manager’s formal authority. The discussion of the findings will be presented in subtopics, following the analytical logic of the original work, which addressed the operational context, governance and communication, integrating tools, and finally, managerial changes and responses, culminating in the proposal of an integration model.

Operational context of the case and initiation milestone

The project was developed in an open-pit copper mine in northern Kazakhstan, with an estimated lifespan of approximately 40 years, where drilling, blasting, loading, and hauling operations are integrated with two processing plants. The technical justification for the new explosive emulsion technology was based on the expectation of more controlled ore fragmentation, which would positively impact the regularity of crushing, the stability of mill feed, and the efficiency of the mineral circuit. This logic aligned directly with the “mine-to-mill” concept, which emphasizes the influence of blast fragmentation on productivity and energy consumption throughout the mineral value chain (Nikkhah et al., 2022; Zhang et al., 2022). From a business perspective, the initiative aimed for operational gains for the client and a foundation for a longer-term contract.

The project initiation had a hybrid character, with the authorization to proceed (ATP) functioning as the formal start mark, even before the consolidation of a complete “project charter” for phase 1. The documentary record of the ATP, dated March 2024, showed that the mobilization and initial alignment of the project occurred from the client’s acceptance. This initiation pattern, where effectiveness precedes the complete formalization of the charter, is compatible with literature highlighting the decisive role of the “front-end” in organizing governance and reducing ambiguities in complex projects (PMI, 2021; Brunet et al., 2023). The existence of documentary evidence to support the decision and initial mobilization was crucial for the project’s advancement.

Governance, “stakeholders” and communication

The project governance reflected a weak matrix structure, in which the project manager’s formal authority was limited, acting more as a coordinator and facilitator. Resources remained tied to their original functional areas. Coordination was reinforced by the presence of two project managers, one at a regional scale and another global, in addition to sponsors with high formal power. This weak matrix configuration required integration to occur predominantly through lateral negotiation, recurrent follow-up, and interface management, rather than direct hierarchical command (PMI, 2021; Kerzner, 2022), corroborating the centrality of coordination in complex organizations (Zani, Denicol, and Broyd, 2024).

The distribution of the project’s 59 internal “stakeholders”, covering 12 functional areas, reinforced the complexity of coordination. The Explosives and Automation, Marketing, and Engineering and Maintenance areas concentrated 24 participants, representing 40.7% of the total, highlighting the criticality of the interfaces between technology, market development, and engineering. In terms of geographical scale, 27 “stakeholders” (45.8%) operated locally, 17 (28.8%) at the EMEA level, and 15 (25.4%) at the global level. The predominance of a neutral stance among participants, followed by supporters and few opponents, indicated an environment that demanded continuous persuasion and alignment, as pointed out by studies on stakeholder management in contexts of multiple interests (Klaus-Rosińska and Iwko, 2021; Cvijović, Obradović and Todorović, 2021).

The communication routine played a central role in integration. The project established a weekly routine of integrative meetings, which included a 60-minute general meeting, open to all participants, and 30-minute specific meetings for critical fronts such as Commercial, Technical Services, Marketing, Engineering and Maintenance, Logistics and Supplies, Training and Development, and Safety, Health, Environment and Sustainability (SHES). These meetings, held on different days of the week, served as spaces for alignment and handling of critical interfaces. Although there was no formal communication plan, this routine, combined with the use of minutes, email, Microsoft Teams, and SharePoint, contributed to reducing information dispersion and creating documentary stability, mitigating the challenges of time zones and linguistic diversity.

The observed communicational discipline was fundamental for multinational and cross-functional teams, which tend to rely on explicit routines to mitigate loss of meaning, low participation, and noise in knowledge processing (Tenzer, Pudelko, and Zellmer-Bruhn, 2021). The structuring of these routines allowed the project to maintain a continuous flow of information and decisions, essential for coordination in a highly complex environment with geographically dispersed “stakeholders”. The ability to consistently record and share information was a pillar for maintaining decision-making coherence and managing the expectations of the parties involved.

Integrating tools, schedule, and front readiness

Despite the absence of a formal integration management plan, the project utilized a recognizable set of integrating tools. The Project Breakdown Structure (PBS), or “work breakdown structure” (WBS), was one of these tools, organizing the scope into macro-areas such as global and regional support, commercial relationship, mobile asset (truck), product, production plant, site preparation, people and training, and product implementation at the site. This scope decomposition not only detailed the deliverables but also provided a common language for the various areas, making the interfaces between deliverables visible and organizing the logical sequence between technical, operational, and commercial fronts. The PBS, in this sense, functioned as an artifact that made the project intelligible as an integrated system, rather than a mere aggregate of independent tasks (PMI, 2021; Kerzner, 2022).

The central document repository in SharePoint also proved to be a crucial integrative tool. It mitigated the risk of discontinuity during leadership changes, as occurred in the Engineering and Maintenance area, ensuring that documents, approvals, and histories remained accessible to new managers. This reinforced the role of documentary memory in projects with high interface turnover, ensuring knowledge continuity and traceability of decisions over time. Maintaining an organized collection of information was vital for project stability in a dynamic environment with multiple stakeholders.

In terms of time, the integration was evidenced by the consolidated schedule, which by April 21, 2026, listed critical milestones concentrated between June and September 2026. The main milestones included the authorization to start the project (March 2024), the acceptance of the technical/commercial proposal for demonstration (June 11, 2026), the production of the new formulation at the plant (June 12, 2026), the assembly and testing of the loading equipment (June 12, 2026), the phase 1 “project charter” with the client (June 25, 2026), the local team training (July 15, 2026), the commissioning and calibration of the equipment at the mine (August 19, 2026), and the product certification (September 14, 2026). This concentration of milestones indicated that the schedule was oriented towards building technical, regulatory, commercial, and operational readiness, rather than the immediate delivery of the solution to the client. The schedule, therefore, operated as a readiness architecture, sequencing essential dependencies before the start of the field phase, which is consistent with the literature on complex project governance (PMI, 2021; Brunet et al., 2023).

The analysis of the progress percentages of the macro-fronts on April 21, 2026, revealed uneven progress, but consistent with the project’s preparatory phase. Resource readiness was already 100% complete, while commercial readiness (73%), charging equipment readiness (75%), and mine site adequacies (71%) showed advanced stages. Other fronts, such as product readiness (67%), production plant adequacies (51%), training readiness (47%), and operational readiness (43%), also showed significant progress. In contrast, the phase 1 “project charter” and implementation with wet commissioning were still at 0%, as they belonged to a later window in the schedule. This scenario confirmed that the main outcome of the integration at that time was the construction of project system readiness, rather than the generation of final benefits for the client.

The draft of the general meeting of April 13, 2026, corroborated this interpretation, registering the delay in imports as the main critical problem and indicating that the next steps involved regulatory approvals, remote training, and the issuance of the commercial proposal to the client. This demonstrated that the project was not stagnant, but rather in an intensive phase of preparing the conditions for implementation. The integration, therefore, focused on ensuring that all fronts were aligned and ready for the next stage, guaranteeing coherence among the various project components before going live.

Managerial changes, restrictions, and responses

The integration was particularly demanding due to the high technical, regulatory, and logistical uncertainty that permeated the project. Although there was no formal change control system with an autonomous approval flow during the analyzed period, relevant changes were discussed and recorded in the minutes of the follow-up meetings. Among the observed adjustments, the following stood out: the revision of the customer value calculation logic, with a deepening of the “mine-to-mill” approach, the inclusion of specific spare parts for the new truck, the expansion of the “champions” team from two to six members, the incorporation of initially unforeseen government licenses, the creation of contingency for international training resources, the adaptations of the truck and formulation to extreme weather conditions, and the need to include a generator for the storage tank on site. These adjustments demonstrated that the integrating discipline existed, operating predominantly relationally and incrementally, rather than relying on a formal “change control” system from initiation (PMI, 2021; Kerzner, 2022).

The challenges faced by the project were not limited to an isolated technical domain, but crossed diverse areas such as engineering, procurement, training, regulation, operation, and customer relationship. The prolonged wait for the truck after customer approval, the conversion of technical value into perceived economic value, the coordination of 59 globally distributed “stakeholders”, the weak matrix structure, linguistic barriers, and regulatory and logistical constraints were some of the critical problems. Integrated managerial responses included conditioning the purchase investment on customer approval, deepening the value model with the “mine-to-mill” approach, defining two project managers (regional and global) supported by SharePoint and meeting routines, and adapting the truck and formulation to extreme climate.

The ability to rearticulate fronts in the face of concrete problems was the most relevant managerial response, demonstrating that integration did not depend on a single tool, but on the combined articulation of artifacts, meetings, replanning, and escalation. This finding converges with the literature indicating that partially integrated teams can achieve good performance when they maintain a common focus and collaborative working relationships (Franz and Olopade, 2024). Flexibility and adaptability were essential for the project’s continuity in a high-uncertainty environment.

However, the results also pointed to weaknesses, such as the absence of a formal communication plan, a structured change log, and a complete “charter” from initiation. These gaps increased the dependence on key people and monitoring routines to maintain decision-making coherence. For similar projects, the findings suggested anticipating a minimum integration package, composed of a preliminary “charter”, formal change log, explicit responsibilities for critical interfaces, and readiness indicators by macro-area. This proposition, derived from the case interpretation, aims to reduce initial ambiguity, align mobilization, and create a common reference for subsequent decisions, in addition to providing traceability for emerging adaptations and avoiding replanning without managerial memory.

Managerial proposition for similar projects

Based on the convergence of case findings, a managerial proposition was developed for pioneering projects in weak matrix structures, with high geographical dispersion of “stakeholders”, multiple technical interfaces, and strong dependence on lateral coordination. This proposition was not configured as a universal prescriptive model, but as an applied managerial artifact, derived directly from the observed empirical evidence. Its construction started from five recurring weaknesses identified in the case: ambiguity in initiation, diffusion of responsibilities among critical interfaces, informational dispersion, absence of formal traceability for relevant changes, and unequal maturity among macro-fronts on the eve of implementation. Added to these weaknesses was the need to reduce linguistic barriers and expand knowledge transfer to the local team, an indispensable condition for entering the field.

The minimum operating model for integration proposed for pioneering projects in weak matrix structures was organized in a logical sequence of interdependent mechanisms. The model’s input would occur at initiation, with the authorization to proceed (ATP) and a preliminary charter, recognizing that project mobilization may precede the consolidation of the formal charter. Subsequently, the explicit definition of responsibilities for critical interfaces would be necessary to avoid decision-making gaps, given the weak matrix structure and the multiplicity of globally distributed stakeholders. Structured communication, with a fixed calendar of integrative meetings, standard minutes, follow-up trail, and a single document repository, would assume a central role in synchronizing fronts and preserving decision-making memory.

In the fourth stage, the simplified registration of critical changes, with impact, responsible party, deadline, dependencies, and forwarding, would be essential to provide traceability to emerging adaptations and avoid replanning without managerial memory. The fifth stage proposes a consolidated readiness dashboard by macro-area, with milestones, progress percentages, critical pending issues, and release criteria, aiming to prevent premature implementation start and make critical dependencies between areas visible. Finally, training and knowledge would be addressed through a structured strategy of local “champions”, a minimum training and translation track, to reduce linguistic noise and enhance knowledge transfer.

The concrete managerial utility of the model lies in offering an objective reference for structuring the preparatory phase of pioneering projects before entering the field. Instead of relying exclusively on the project manager’s relational capacity or the spontaneous maturity of the areas involved, the proposition was structured to offer a minimum core of verifiable mechanisms that tend to reduce rework, anticipate escalations, improve visibility of dependencies, and preserve coherence between technical, commercial, logistical, and operational fronts. Its practical contribution does not replace managerial judgment, but supports decision-making with greater clarity, traceability, and integration discipline in contexts of high complexity, aligning with literature that associates project performance with the articulation between governance, roles, communication, interface coordination, and integration mechanisms throughout the venture’s cycle (PMI, 2021; Kerzner, 2022; Brunet et al., 2023).

In summary, integration management in the analyzed project was a decisive factor for its execution, even without an initial formal plan. Integration was manifested through a combination of authorization to proceed, project breakdown structure, integrated schedule, meeting routines, shared document repository, and coordination between regional and global leadership. This arrangement allowed for alignment between technical, commercial, logistical, and operational fronts, building system readiness in a context of high organizational complexity. Challenges, such as technical and regulatory uncertainty, were overcome by adaptive and relational managerial responses, which underpinned the proposal of a minimum integration model for similar projects, aiming to anticipate and mitigate common weaknesses in weak matrix structures.

4. Conclusion

The study sought to analyze how integration management tools and practices were used in a pioneering project to implement new explosive emulsion technology in mining, identifying the coordination mechanisms employed, the challenges faced, and, based on the findings, proposing a minimum set of integration mechanisms for similar projects. It was found that integration was sustained by a combination of authorization to proceed, project breakdown structure, integrated schedule, weekly meeting routines, shared document repository, and coordination between regional and global leadership. The main outcome of this management was the progressive construction of the project system’s readiness, preserving coherence between the technical, commercial, logistical, and operational fronts, even in a context of high organizational and operational complexity. The research showed that challenges, such as technical, regulatory, and logistical uncertainty, were overcome by adaptive and relational managerial responses. As a managerial contribution, the study supported the proposal of a minimum operational integration model, applicable to pioneering projects in weak matrix structures, which aims to reduce initial ambiguity, align mobilization, and create a common reference for subsequent decisions, supporting decision-making with greater clarity and traceability.

However, the study presented important limitations, such as the fact that it portrayed a project still in progress until the cut-off date of April 21, 2026, which prevented the measurement of the final operational results of the implementation and the definitive benefits perceived by the client. Furthermore, the analysis focused on a single case and relied exclusively on documentary evidence, restricting direct observation of participants’ perceptions and informal coordination dynamics. For future studies, it is recommended to follow the subsequent phase of implementation and operation of the solution, in order to verify how the integration influenced the technical, commercial, and organizational results at the end of the project. It is also suggested to conduct comparative studies with other innovation projects in mining and to incorporate interviews with stakeholders at different levels, to deepen the understanding of governance, decision-making, and knowledge transfer in matrix and multicultural environments.

Bibliographic References

Bardin, L. 2016. Análise de conteúdo. Edições 70, São Paulo, SP, Brasil.

Bowen, G. A. 2009. Document analysis as a qualitative research method. Qualitative Research Journal 9(2): 27-40.

Brunet, M.; Petit, M.-C.; Romero-Torres, A. 2023. Interorganizational design for collaborative governance in co-owned major projects: An engaged scholarship approach. Project Management Journal 55(5).

Creswell, J. W.; Creswell, J. D. 2022. Research design: qualitative, quantitative, and mixed methods approaches. 6. ed. Sage, Thousand Oaks, CA, USA.

Cvijović, J.; Obradović, V.; Todorović, M. 2021. Stakeholder management and project sustainability: A throw of the dice. Sustainability 13(17): 9513.

Figueiredo, J.; Torres, V.; Cruz, R.; Moreira, D. 2023. Blasting fragmentation study using 3D image analysis of a hard rock mine. Applied Sciences 13(12): 7090.

Franz, B. W.; Olopade, J. 2024. Exploring pathways to project success through project delivery team integration: A qualitative comparative analysis. Construction Management and Economics 42(6): 564-581.

Kerzner, H. 2022. Project management: A systems approach to planning, scheduling, and controlling. 13. ed. Wiley, Hoboken, NJ, USA.

Klaus-Rosińska, A.; Iwko, J. 2021. Stakeholder management: One of the clues of sustainable project management as an underestimated factor of project success in small construction companies. Sustainability 13(17): 9877.

Mir, F. A.; Pinnington, A. H. 2014. Exploring the value of project management: Linking project management performance and project success. International Journal of Project Management 32(2): 202-217.

Nikkhah, A.; Vakylabad, A. B.; Hassanzadeh, A.; Niedoba, T.; Surowiak, A. 2022. An evaluation on the impact of ore fragmented by blasting on mining performance. Minerals 12(2): 258.

Project Management Institute [PMI]. 2021. A guide to the project management body of knowledge (PMBOK guide). 7. ed. Project Management Institute, Newtown Square, PA, USA.

Tenzer, H.; Pudelko, M.; Zellmer-Bruhn, M. 2021. The impact of language barriers on knowledge processing in multinational teams. Journal of World Business 56(2): 101184.

Yin, R. K. 2017. Case study research and applications: Design and methods. 6. ed. Sage, Thousand Oaks, CA, USA.

Zani, C. M.; Denicol, J.; Broyd, T. 2024. The four coordination roles of clients when designing megaproject organizations. Project Management Journal 55(5): 558-579.

Zhang, Z.-X.; Sanchidrián, J. A.; Ouchterlony, F.; Luukkanen, S. 2022. Reduction of fragment size from mining to mineral processing: A review. Rock Mechanics and Rock Engineering 56: 747-778.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.