Critical paths as a support tool in project management

Jesse Andrei Nietzscher Nascimento; Luís Felipe Vendramim

DOI: 10.22167/2675-6528-202600940

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Abstract

Efficient project management is crucial for the productive utilization of business resources, with time being one of the most valuable and challenging to manage. In this context, schedule management, using methods such as Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM), is fundamental for the successful delivery of projects. The study aimed to present a methodology capable of assertively estimating the duration of each activity, identifying critical paths, and proposing contour measures to strengthen processes and minimize delivery delays. An explanatory case study was conducted, evaluating six projects for the installation of electronic surveillance systems in assets of a company in the metropolitan region of Recife, Pernambuco. Initially, three projects (A, B, C) were analyzed without the proposed methodology, revealing significant delays totaling 136 business days. Subsequently, three new projects (D, E, F) were implemented and managed with the application of three-point estimation and PERT/CPM analysis, allowing for the construction of activity networks and daily monitoring. The results showed an expressive difference: project D had a minimum delay of 4 days, while projects E and F were completed 3 and 8 days ahead of schedule, respectively. The methodology optimized processes, increased predictability, and reduced delays, demonstrating that schedule management with structured techniques provides a competitive and strategic advantage for efficiency and reliability in project delivery.

Keywords: Efficiency; Three-point method; Optimization; PERT; Predictability.

1. Introduction

Project management constitutes a fundamental strategic pillar for global economic development and business innovation. The Project Management Institute (PMI, 2017) estimates that approximately 20% of the Gross Domestic Product (GDP) worldwide is directed towards projects, which is equivalent to about twelve trillion dollars annually invested in the creation and enhancement of value. In this scenario of high demand for results, the efficient allocation of resources becomes imperative. Among the various resources managed, time emerges as one of the most critical and challenging, whose precise management is a pressing need in the execution of any undertaking (Kenar et al., 2023). The ability to complete projects within the established deadline not only optimizes costs and resources but also strengthens the reputation and competitiveness of organizations.

A project, as defined by Santos (2023), is a set of interdependent activities, executed in a logical sequence, with the purpose of achieving unique and satisfactory results. Gonçalves (2024) and Nunes (2022) complement that efficient project management, characterized by well-defined stages of initiation, planning, execution, monitoring, and closure, is crucial for delivering optimal results within agreed deadlines. In highly complex sectors, such as the electrical sector, often associated with the development of infrastructure and systems projects, managing multiple criteria and objectives demands meticulous attention to technical and economic feasibility, as well as to the detailing that ensures execution as planned. The absence of rigorous planning and adequate control tools can lead to significant deviations, compromising the integrity and success of the project.

Within a project’s lifecycle, schedule management is an invaluable step, directly influencing the perception of success or failure. The PMI (2021) describes the schedule as a detailed model for executing activities, encompassing durations, dependencies, and other planning information. Schedule planning can follow predictive approaches, which involve decomposing the scope into specific activities, logical sequencing, estimating efforts and durations, allocating resources, and finally, adjusting estimates until a consensual schedule is achieved. The assertive execution of each of these steps is vital for project managers to meet stakeholder expectations, even in the face of complex challenges.

To optimize schedule management, methodologies such as the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM) are widely employed. PERT aims to organize project activities, identifying their dependencies and logical sequence, while CPM, known as the critical path method, allows for the determination of the sequence of activities that defines the minimum total project duration. Kenar et al. (2023) highlight the efficiency of these methods in project management and in simplifying execution time. Carvalho (2018) explains that the critical path method uses programming logic to determine the earliest start and latest finish dates for all activities, facilitating the analysis of float and critical activities. The combination of PERT and CPM allows for the determination of an optimal project completion time, as well as the identification of opportunities to accelerate completion, considering additional costs (Suharni and Lily, 2023).

The duration estimate of activities is a critical component for schedule accuracy. The three-point estimation method, intrinsic to PERT, addresses the inherent uncertainty in estimates by considering three scenarios: optimistic (to), representing the best possible scenario with minimal interference; most likely (tM), a realistic forecast based on expected resources and productivity; and pessimistic (tP), considering the worst-case scenario with maximum interference or delays. From these estimates, the expected duration of the activity is calculated, offering a more robust and realistic view of the time required for each task. This approach contrasts with single-point estimation methods, which often underestimate the complexity and risks associated with project execution.

The absence of structured methodologies for schedule management, such as three-point estimation and PERT/CPM analysis, has been consistently associated with significant delays, resource waste, and failure to deliver value. Preliminary observations in the context of electronic surveillance system installation projects, for example, frequently reveal that a lack of predictability and the inability to proactively identify bottlenecks result in accumulated delays that can total hundreds of working days. Such deficiencies compromise not only operational efficiency but also the reliability of deliveries and stakeholder satisfaction. Given this scenario, the present study aims to present and evaluate a methodology capable of assertively estimating the duration of each activity, identifying critical paths, and proposing contour measures to strengthen processes and minimize project delivery delays, thereby conferring greater predictability and efficiency.

2. Material and Methods

The present study was designed as an explanatory case study, seeking to deepen the understanding of the application of schedule management methodologies in projects. The research adopted a qualitative approach, which allowed for an interpretive analysis of the dynamics and underlying factors of the recurring delays observed in electronic surveillance system installation projects. This approach was essential to identify the causes and propose robust solutions, aligned with the objective of optimizing the predictability and efficiency of deliveries, according to the need for more assertive project management.

The research was conducted in a Company located in the metropolitan region of the city of Recife, in the State of Pernambuco, focusing on electronic surveillance system installation projects. The analysis period covered the execution of six projects, with three historical projects (A, B, and C) evaluated retrospectively and three new projects (D, E, and F) implemented and managed under the proposed methodology. The unit of analysis consisted of these six installation projects, allowing for a comparison between previous practices and the application of schedule management techniques. The projects were executed by a team of ten employees from a outsourced company.

The study sample comprised six electronic surveillance system installation projects, all executed at the Company in Recife. Initially, three completed projects (A, B, and C) were selected for a retrospective analysis of their schedules and performance. Subsequently, three new projects (D, E, and F) were actively implemented and managed, applying the methodology in question. The selection of projects D, E, and F was based on the similarity of their characteristics, activities, and resources to projects A, B, and C, ensuring comparability between the groups. The projects were categorized into subgroups according to the number of installed equipment.

Data collection began with the documentary analysis of projects A, B, and C, where the S-curves of actual and planned physical progress were examined, allowing for the identification of historical delays. For projects D, E, and F, the first stage consisted of the detailed identification of all involved activities, as well as the establishment of their precedence and dependency relationships. These activities, which were similar across the projects, were organized and presented in a standardized structure. This initial survey was crucial for building the database necessary for applying scheduling estimation and analysis techniques.

Table 1. Activities involved in the CCTV installation project

Activities

Description

A

Basic Project

B

Inspection

C

Executive project

D

Excavations

And

Material Handling

F

Installation of Buried Infrastructure

G

Visible Infrastructure Assembly

H

Cable Pass-through

I

Equipment Installation

J

Settings and Tests

K

Pre-commissioning

L

Commissioning

M

Final Project Documentation Delivery

Source: Original survey data

The duration estimate for activities in projects D, E, and F was performed using the three-point method, intrinsic to the PERT technique. This method considered three scenarios for each activity: optimistic (to), representing the minimum duration under ideal conditions; most likely (tM), a realistic estimate based on normal conditions; and pessimistic (tP), predicting the maximum duration in case of unforeseen events. From these estimates, the expected duration (tE) of each activity was calculated using triangular and Beta-PERT distributions. Subsequently, the activity network was constructed, graphically representing the interconnections and dependencies between project tasks.

For the determination of the critical path, the Earliest Start Date (ESD) and Latest Start Date (LSD) were calculated for each activity, according to Cukierman (2009) formulations. The ESD represents the earliest date an activity can begin, considering its predecessors, while the LSD indicates the latest date to start an activity without delaying the project. Additionally, to refine duration estimates, base execution times were defined for each activity, considering optimistic, probable, and pessimistic scenarios, and multipliers based on project size were applied, categorized by equipment subgroups.

The research execution was divided into distinct stages. Firstly, an analysis of the three historical projects (A, B, and C) was carried out to diagnose delay patterns and schedule management deficiencies. Subsequently, for projects D, E, and F, the proposed methodology was implemented. The initial phase of this implementation consisted of an exhaustive identification of all activities that make up the electronic surveillance system installation projects. These activities, which are common to the studied projects, were detailed and organized, establishing their interdependencies and logical sequences, as presented in Table 1.

In the subsequent stage, the durations of activities for projects D, E, and F were estimated using the three-point method (optimistic, most likely, and pessimistic) for each task. The expected durations were calculated using triangular and Beta-PERT distributions, incorporating the inherent uncertainty in the estimates. Based on these durations and the established precedences, the activity network was constructed for each project, standardizing the format to include duration, float, and early and late start and finish dates. This network representation was fundamental for identifying critical paths and determining the total estimated project durations.

After identifying the critical paths in projects D, E, and F, daily monitoring and control routines were implemented. These routines included fifteen-minute status updates (PS), held twice a day, at 8:30 AM and 5:00 PM, in collaboration with the service provider company (EPS). During these meetings, activities to be executed that day were described and organized, feedback on progress was collected, and problems were identified. The objective was to outline real-time workaround measures, minimizing delays and ensuring process robustness, unlike the previous weekly monitoring of projects A, B, and C.

The treatment and analysis of the data were centered on the application of the Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) techniques. These methodologies were employed to organize project activities, identify their dependencies, and determine the logical sequence of execution. Network analysis allowed for the visualization of activity interconnections, facilitating the identification of the critical path and existing float. The critical path, which represents the sequence of activities with the longest total duration, was determined for each project, being crucial for time planning and control, as described by Carvalho (2018).

The estimated duration of the activities was analyzed using the three-point method, which considers the inherent uncertainty in projects by providing optimistic, most likely, and pessimistic scenarios. The expected duration of each activity was calculated from these estimates, offering a more solid basis for planning. To identify the critical path, the earliest start date (ES) and latest finish date (LF) for each activity were calculated using Cukierman’s (2009) equations. The comparison between planned and actual durations, especially in projects D, E, and F, was fundamental to evaluating the effectiveness of the implemented methodology.

3. Results and Discussion

The analysis of the results and the subsequent discussion reveal crucial insights into the effectiveness of schedule management methodologies in electronic surveillance system installation projects. Initially, the study focused on the retrospective evaluation of three historical projects (A, B, and C), which were executed without the structured application of Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) techniques. As detailed, these projects experienced significant delays: 42 business days for Project A, 20 business days for Project B, and 74 business days for Project C. Such temporal deviations, illustrated by the S-curves of actual and planned physical progress, as observed in Figure 1 for Project A, demonstrate a substantial gap between planning and execution.

Figure 1. S-curve for Project A

Source: Original survey data

The discrepancy between the planned percentage and the actual percentage, visible in the S-curves of historical projects, not only indicates delays but also reflects reactive and, at times, ineffective schedule management. The absence of a robust methodology for estimating activity durations and identifying the critical path resulted in an inability to proactively anticipate and mitigate risks. This scenario corroborates the literature that emphasizes schedule management as a fundamental pillar for project success (PMI, 2021). The lack of clarity in dependencies and duration estimation based on fixed methods, without considering inherent uncertainty, contributed to the observed culture of delays. The practical implications of these delays are multifaceted, ranging from increased operational costs due to the extended work period to customer dissatisfaction and potential loss of company credibility. In a competitive market, predictability and on-time delivery are strategic differentiators, and failure to achieve them can compromise business sustainability.

In contrast to the approach of the historical projects, the second phase of the study implemented a structured methodology for projects D, E, and F, with similar characteristics in terms of activities and resources. The first crucial step in applying this methodology was the detailed identification of all activities involved in the electronic surveillance system installation projects, as well as the establishment of their precedence and dependency relationships. Although Table 1, which lists these activities, was presented in the Materials and Methods section, its relevance to the discussion lies in the fact that a clear decomposition of the scope into specific activities is the foundation for any effective schedule planning (PMI, 2021). Without this foundation, the estimation of durations and the identification of critical paths would be inaccurate, and consequently, control measures would be ineffective. The standardization of these activities, common to the studied projects, allowed for a consistent basis for applying estimation and schedule analysis techniques.

The duration estimate for activities in projects D, E, and F was performed using the three-point method, a technique intrinsic to PERT that considers optimistic (to), most likely (tM), and pessimistic (tP) scenarios. This approach, which acknowledges and quantifies the inherent uncertainty of each task, represents a significant advancement over the fixed duration used in projects A, B, and C. The expected duration (tE) of each activity was calculated using triangular and Beta-PERT distributions, according to equations (1) and (2) presented in the methodology. Table 2 details the base execution times for each activity, providing a clear overview of the optimistic, expected, and pessimistic estimates.

Table 2. Project activities’ schedule baseline execution time

Activities

Optimistic

Expected

Pessimist

A

1

2

3

B

1

1

1

C

2

3

4

D

5

7

10

And

10

15

20

F

3

5

7

G

2

3

4

H

3

5

7

I

5

7

10

J

3

5

7

K

1

2

3

L

1

1

1

M

6

8

10

Source: Original research results

The inclusion of optimistic and pessimistic scenarios, in addition to the most likely estimate, allows for a more realistic assessment of deadlines and better management of associated risks. Kenar et al. (2023) highlight that the PERT method, by incorporating uncertainty, offers a more robust tool for project management, especially in environments with high variability. The expected duration, calculated from these three estimates, provides a more solid basis for planning, enabling project managers to make more informed decisions. The practice of considering the temporal variability of each activity is crucial to avoid the unrealistic optimism often associated with point estimates, which can lead to delays and budget overruns. The application of this technique to projects D, E, and F represents a fundamental step towards building more resilient and reliable schedules.

Additionally, the methodology incorporated project size multipliers for activities whose durations vary according to the number of installed equipment. Projects were categorized into three subgroups: up to 5 equipment (subgroup 1, multiplier 1), between 6 and 10 equipment (subgroup 2, multiplier 1.3), and above 10 equipment (subgroup 3, multiplier 1.6). Table 3, although not included here to maintain the table limit, details how these durations vary by subgroup and scenario. This differentiation is vital, as it recognizes that the complexity and effort of certain activities are not linear and increase with project scale. Ignoring this variability, as likely occurred in historical projects, would lead to inaccurate estimates and, consequently, delays. The use of multipliers, based on historical data and expert opinions, allows for schedule adaptation to the reality of each project, making predictions more assertive and aligned with performance expectations. This modular and scalable approach is an example of how schedule management can be refined to meet the specificities of different projects within the same portfolio.

After estimating the durations, the activity network was constructed for projects D, E, and F, as illustrated in Figures 4, 5, and 6. These networks graphically represent the interconnections and dependencies between tasks, facilitating the identification of the critical path.

Figure 2. Project D activity network

Source: Original research results

Figure 3. Activity network project E

Source: Original research results

Figure 4. Activity network project F

Source: Original research results

The critical path, which is the sequence of activities with the longest total duration, was determined for each project, being crucial for time planning and control (Carvalho, 2018). The identification of the critical path is one of the pillars of CPM and PERT, as it allows managers to focus their efforts and resources on activities that, if delayed, will directly impact the project completion date. Vergara et al. (2016) reinforce that any delay in a critical activity has a direct impact on the planned completion date. The methodology employed calculated the Early Start Date (ESD) and the Late Start Date (LSD) for each activity, according to Cukierman’s (2009) formulations, allowing for the visualization of float and the prioritization of tasks. The construction of these activity networks and the identification of the critical path not only provide a clear visual representation of the project but also empower managers to perform “what-if” analyses, exploring different scenarios and strategies to optimize the schedule and mitigate risks. The ability to visualize dependencies and workflow is fundamental for proactive management, allowing for interventions before problems become critical.

One of the most significant differentials in the management of projects D, E, and F was the implementation of daily monitoring and control routines. Unlike the weekly monitoring of historical projects A, B, and C, the new projects featured fifteen-minute status updates (SUs), held twice a day (at 8:30 AM and 5:00 PM), in collaboration with the service provider company (SPC). This change in monitoring frequency represents a transition from a reactive to a proactive approach. Daily communication allowed for the description and organization of activities to be executed, immediate feedback collection on progress, and real-time problem identification. The ability to quickly devise mitigation measures minimized delays and ensured process robustness. This practice aligns with agile management principles, which value frequent communication and continuous adaptation to respond to changes and unforeseen events (PMI, 2021). The practical implication is the drastic reduction in response time to deviations, transforming potential significant delays into small daily adjustments. This not only improves operational efficiency but also fosters a culture of accountability and collaboration among the team.

The comparative results between historical projects and new projects are expressive and demonstrate the effectiveness of the implemented methodology. Table 3 presents a summary of the planned and actual durations, as well as the delay or anticipation in business days for each project.

Table 3. Project delay/advancement

Project

Estimated duration (d.u.)

Actual Duration (d.u.)

Lag/lead time

A

47

89

42

B

51

71

20

C

47

121

74

D

44

48

4

And

56

53

-3

F

64

56

-8

Source: Original research results

According to Table 3, historical projects A, B, and C, which did not use the PERT/CPM methodology with three-point estimation, presented considerable delays: 42 business days for Project A, 20 business days for Project B, and 74 business days for Project C. In contrast, Project D, managed with the new methodology, had a delay of only 4 business days. Most notably, Projects E and F were completed 3 and 8 business days ahead of schedule, respectively. This difference in results is significant and corroborates the premise that the application of structured schedule management methodologies can transform the predictability and efficiency of deliveries. The total reduction of over 130 days of delay, when comparing historical projects with the new ones, is a testament to the robustness of the approach.

The anticipation of deadlines in projects E and F, in particular, highlights the methodology’s potential not only to avoid delays but also to optimize execution and free up resources earlier. This finding is in line with Suharni and Lily (2023), who state that the combination of PERT and CPM allows for determining an optimal completion time and even accelerating the finalization of activities. The ability to anticipate project completion has direct financial implications, such as reducing indirect costs and the possibility of starting new projects or reallocating teams more quickly. Furthermore, improved predictability contributes to greater stakeholder satisfaction and strengthens the company’s reputation. The transition from a culture of delays to one of punctuality and, in some cases, anticipation, demonstrates a maturation in the organization’s project management.

The optimization of processes, financial predictability, and compliance with regulatory deadlines, as evidenced by the results, position schedule management as a competitive and strategic differentiator. In an increasingly dynamic and demanding business scenario, the ability to deliver projects on time and within budget is a critical success factor. The PERT/CPM methodology, combined with three-point estimation and daily monitoring, has proven to be an effective tool for achieving these objectives. Project management is not just about completing tasks, but about doing so efficiently, maximizing resource utilization and minimizing waste. Kenar et al. (2023) emphasize that time is the most precious resource, and its efficient management is a necessity for any business.

Despite the limitations inherent in a case study with a restricted number of projects, the results are consistent and provide a solid foundation for future research and applications. Replicating this methodology in different contexts and with a larger number of projects could further solidify its conclusions. The ability to identify the critical path and manage activity float allows for smarter resource allocation and more agile decision-making. The proposed methodology not only solved a chronic problem of delays but also established a new standard of excellence in the execution of electronic surveillance system installation projects, transforming the perception of project success and the organizational culture regarding time management.

4. Conclusion

It is concluded that the objective was achieved, presenting and evaluating an effective methodology to assertively estimate activity durations, identify critical paths, and propose contour measures, strengthening processes and minimizing delays in the installation of electronic surveillance systems projects. The application of PERT/CPM techniques, combined with three-point estimation and daily monitoring, demonstrated a significant transformation in schedule management. While historical projects (A, B, and C) accumulated substantial delays, projects managed with the new methodology (D, E, and F) showed a drastic reduction in delays, with projects E and F being completed ahead of schedule. This approach not only provided greater predictability and efficiency but also optimized execution and resource allocation, evidencing the capacity to transition from a culture of delays to one of punctuality and anticipation.

Despite the inherent limitation of a case study with a restricted number of six projects, in a single context, the results were consistent and reinforce the validity of the proposed methodology. For future studies, it is recommended to replicate this methodology in different contexts and with a larger number of projects, covering diverse complexities. This would further solidify the conclusions and deepen the understanding of the critical path behavior under various execution scenarios, contributing to the continuous improvement of project management and the reliability of deliverables in different sectors.

Bibliographic References

Carvalho, M. M.; Rabechini, R. 2018. Fundamentos em Gestão de Projetos – Construindo Competências para Gerenciar Projetos. Rio Janeiro –RJ: Grupo GEN.

Cukierman, Z. S. 2009. O Modelo Pert/CPM aplicado a gerenciamento de projetos, LTC – Livros técnicos científicos.

Gonçalves, L. P. 2024. Diagnóstico das boas práticas em gestão de projetos: um estudo de caso em uma empresa do setor elétrico. Trabalho de Conclusão de Curso (Graduação em Administração) – Instituto Federal de Educação da Paraíba, Unidade Acadêmica de Gestão e Negócios, 73p.

Kenar, E.; İpek, M.; Düğenci, M.; Korkmaz, Ö. 2023. A. Applying the Fuzzy PERT Method in Project Management: A Real-Life Case Study. International Journal of Computational and Experimental Science and Engineering, v. 9, n. 2, p. 123-132.

Nunes, P. A. M. 2022. Gestão de projetos de instalações elétricas: uma proposta baseada em metodologias ágeis. Trabalho de Conclusão de Curso (Graduação em Engenharia Elétrica) – Universidade Estadual Paulista, Faculdade de Engenharia de Ilha Solteira, Ilha Solteira. 66p.

Project Management Institute [PMI]. 2017. The PMI guide to business analysis. Primeira edição. Project Management Institute. Newtown Square, Pennsylvania, EUA.

Project Management Institute [PMI]. 2021. Padrão de gerenciamento de projetos e Guia do conhecimento em gerenciamento de projetos (Guia PMBOK). Sétima edição. Project Management Institute. Newtown Square, Pennsylvania, EUA.

Santos, P. E. C. D. 2023. Metodologia para gerenciamento das incertezas do cronograma do projeto por indicadores de sensibilidade. Trabalho de Conclusão de Curso (Graduação em Engenharia de Produção) – Universidade Federal de Pernambuco, Centro de Tecnologia e Geociências, Recife. 68p.

Suharni, M. A.; Lily, E. 2024. Endang. Project scheduling analysis using the CPM and PERT: A case study. Journal of Mathematical Sciences and Optimization, v. 1, n. 1, p. 25-36.

Vergara, w. R. H.; teixeira, r. T.; yamanari, j. S. 2016. Risk analysis in engineering projects: use of PERT/CPM with simulation. Exacta – EP, São Paulo, v. 15, n. 1, p. 75-88.

Article originating from the Final Course Work of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.