Critical path as support for deadline control in projects
Luiz Oracy Carvalho de Oliveira; Luís Felipe Vendramim
DOI: 10.22167/2675-6528-202601134
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
Schedule management is fundamental to project success, and the critical path is an essential tool for prioritizing activities and controlling deadlines. The impact of visual identification of the critical path on stakeholders’ interpretation of schedules was evaluated. A quantitative and applied experimental design was adopted, in which volunteers were randomly assigned to a control group, which analyzed a conventional schedule without visual highlighting of criticality, and an experimental group, which used a schedule with the critical path graphically highlighted. Data collection occurred through a structured technical evaluation instrument on a digital platform, focusing on the ability to identify priority activities and understand the impact of delays. The results showed that the group with visual support achieved a 16.7% gain in assertiveness on schedule analysis questions (P3 and P8), although there was a 16.7% retraction in another question (P5). The overall average of correct answers was 2.8% higher for the model with visual highlighting. It was concluded that highlighting the critical path acted as an effective communication artifact, facilitating the identification of priorities and the perception of deadlines, despite suggesting the need for complementary analytical support for more detailed interpretations. The tool contributed to a more agile interpretation of information, fulfilling the objectives of decision support in project environments.
Keywords: Schedule management; CPM Method; Stakeholders; Decision making; Data visualization.
1. Introduction
Project management, in its essence, constitutes a fundamental pillar for the success and competitiveness of organizations in the contemporary scenario. The growing complexity of undertakings, allied to market volatility, demands a structured approach to the planning, execution, and control of activities. In this context, schedule management emerges as a critical area, as meeting deadlines is often one of the most sensitive indicators of a project’s performance. The Project Management Institute (PMI, 2021) emphasizes that the schedule transcends the mere listing of dates, configuring itself as a strategic tool for analysis and decision-making. The inability to effectively manage time can lead to significant delays, cost increases, and, ultimately, project failure, as widely documented in management literature. Kerzner (2009) corroborates this perspective, highlighting that proficiency in deadline control is intrinsically linked to understanding the interdependencies between activities and identifying the elements that exert the greatest influence on the total duration.
One of the most powerful and widely recognized tools for schedule management is the Critical Path Method (CPM). This method allows for the identification of the sequence of activities that determines the minimum project duration, known as the critical path, whose activities have no float. Any delay in a critical activity directly results in an equivalent delay in the project completion date (PMI, 2021). The precise identification of the critical path is crucial, as it directs managers’ attention to the most sensitive activities, enabling optimized resource allocation and prioritization of monitoring efforts, thereby mitigating temporal risks (Meredith and Mantel, 2009). However, the effectiveness of CPM depends not only on its technical application but also on the ability to communicate its information clearly and unequivocally to all stakeholders.
The effective communication of schedule information is a complex challenge, especially considering the diversity of stakeholder profiles involved in projects. These individuals may have different levels of familiarity with management techniques, and therefore, the way data is visually presented can significantly impact their interpretation and the quality of subsequent decisions (Amaral et al., 2011; Vargas, 2009). Recent literature has explored data visualization as a strategic tool to improve the understanding of complex information in project environments. Bar charts and network diagrams, when well-crafted, can act as cognitive facilitators, transforming raw data into actionable insights and supporting decision-making (Monageng et al., 2025; Barbosa et al., 2018). Killen et al. (2020) and Eberhard (2021) reinforce that the use of visualizations can improve the speed and comprehension of information, positively impacting decision quality. Despite the theoretical relevance and practical potential of the critical path and data visualization, it is observed that, in many organizational contexts, the explicit highlighting of the critical path in schedules is not always a consolidated practice. The absence of this visual clarity can lead to homogeneous activity control, without proper distinction between critical and non-critical tasks, resulting in late interventions and rework (Kerzner, 2009).
In light of this scenario, it becomes imperative to investigate how the visual identification of the critical path can enhance the interpretation of schedules by different stakeholders. The adoption of an experimental design, as advocated by Gil (2008), allows for the comparison of controlled conditions and the observation of the impact of a specific stimulus, such as visual highlighting, on the comprehension of project information. Thus, the justification for this study lies in the need to fill a gap in the understanding of the effectiveness of visual communication of critical schedule information for *stakeholders* with varying levels of experience, aiming to optimize decision-making and, consequently, project success. The objective of this work is to evaluate the impact of visual identification of the critical path on the interpretation of schedules by stakeholders, seeking to verify whether this approach facilitates the understanding of activity prioritization and the perception of deadlines in project environments.
2. Material and Methods
The present study adopted an experimental design, characterizing itself as a quantitative approach and applied research. This methodological choice allowed for controlled comparison between different conditions, aiming to observe the impact of a specific stimulus on the interpretation of schedules. The experimental design is fundamental for establishing cause-and-effect relationships, as advocated by Gil (2008), by manipulating independent variables and measuring their effects on dependent variables. The applied nature of the research sought to generate useful knowledge for project management practice, optimizing the communication of critical information and improving decision-making in organizational environments.
The research context involved the simulation of typical project management scenarios, where the interpretation of schedules is crucial for effective decision-making. There was no specific physical location for conducting the experiment, as data collection was carried out digitally, allowing for remote participation of volunteers. The study execution period was not explicitly detailed in the original TCC, but data collection occurred at a specific and controlled moment. The unit of analysis consisted of the individual’s capacity to interpret schedules, assessing their understanding of activity prioritization and deadline perception.
The study’s target population consisted of volunteer adults representing the diversity of stakeholder profiles frequently found in organizational environments. This broad scope aimed to capture different levels of familiarity with project planning and management tools, reflecting the reality of multidisciplinary teams. The effective sample for the experiment totaled twelve participants, who were randomly and equally distributed into two distinct groups. The selection criteria established that there would be no restrictions regarding academic background or prior project experience, ensuring the representativeness of a heterogeneous audience for the proposed evaluation.
For data collection, two schedule models were developed for the same hypothetical project, both structured as network diagrams. These schedules contained detailed information about activities, their respective durations, and the precedence relationships between them. Schedule A presented this information in a standard format, without any visual emphasis on task criticality. In contrast, Schedule B applied the Critical Path Method (CPM), graphically identifying activities with zero float and displaying early and late dates. This distinction allowed for direct visualization of the tasks that constrain the project’s total deadline, serving as the main experimental stimulus.
The additional data collection instrument consisted of a technical assessment questionnaire, designed and structured on the Google Forms platform, as detailed in Appendix A of the original work. This questionnaire was distributed digitally to participants immediately after the schedule analysis. The instrument’s objective was to assess respondents’ ability to identify priority activities, understand dependency relationships, and perceive the impact of delays on project final deadlines. The questions were formulated objectively to measure technical performance in interpreting the information presented in each schedule model, focusing on the understanding of activity prioritization and deadline perception.
The research execution began with the meticulous development of two schedule models, A and B, which represented the hypothetical project with and without the visual highlighting of the critical path, respectively. Subsequently, for participant distribution and to ensure randomness, an external redirection platform was used. This tool randomly directed each respondent to analyze one of the two schedules, ensuring equality in the composition of the experimental groups. After analyzing the assigned schedule, participants proceeded to complete the technical evaluation instrument, made available via Google Forms, recording their responses in a standardized manner.
The responses collected through Google Forms were automatically recorded and organized in an electronic spreadsheet for subsequent processing and analysis. The comparison between the results obtained by Groups A and B was performed using simple descriptive statistics, focusing on the participants’ technical performance. This approach allowed for an evaluation of assertiveness in interpreting project constraints, including the ability to identify priority activities, understand dependency relationships, and anticipate the impact of delays on deadlines. The analysis sought to observe the effectiveness of highlighting the critical path as a tool to support activity prioritization and deadline control.
The study participants were voluntary adults, and participation occurred spontaneously, without any form of coercion or compensation. Although the original TCC does not detail formal ethical procedures, the voluntary nature of participation ensured respect for the autonomy of the individuals involved in the experiment. No explicit mentions of approvals by research ethics committees or free and informed consent terms were identified in the original TCC in the methodology section. The methodological limitations inherent to the study, such as sample size and the punctual nature of the experiment, were addressed in the conclusion section of the work, acknowledging their potential impact on the generalization of the findings.
3. Results and Discussion
The quantitative results obtained from the experiment, which involved 12 participants equally distributed into two groups, provide valuable insights into the effectiveness of the Critical Path Method (CPM) visual highlighting in schedule interpretation. The study compared a conventional schedule model (Group A) with a model that applied CPM visual highlighting (Group B), seeking to measure the accuracy in the technical understanding of crucial information for project management. Initial data analysis revealed that Group B, which used the schedule with visual support, achieved an overall average accuracy 2.8 percentage points higher than Group A. Although this difference may seem marginal at first glance, it suggests a positive trend in the communication capability of the visually enhanced schedule, especially considering the inherent complexity of project interpretation. This initial finding, though modest, aligns with the premise that visual clarity can optimize understanding, as advocated by Monageng et al. (2025) and Barbosa et al. (2018), who emphasize the importance of data visualization as a strategic facilitator for decision-making in project environments.
Table 1 details the percentage of correct answers per question for each group, allowing for a granular comparison of performance in executing the proposed analysis tasks.
Table 1. Assertiveness Comparison by Group (%)
|
Assessment Block |
Question |
Group A (Expected Answers) |
Group B (Expected Answers) |
|
Block 2: Schedule Analysis |
P3 |
50,00% |
66,70% |
|
Block 2: Schedule Analysis |
P4 |
33,30% |
33,30% |
|
Block 2: Schedule Analysis |
P5 |
50,00% |
33,30% |
|
Block 2: Schedule Analysis |
P6 |
100,00% |
100,00% |
|
Block 2: Schedule Analysis |
P7 |
50,00% |
50,00% |
|
Block 2: Schedule Analysis |
P8 |
50,00% |
66,70% |
|
Block 2 Overview |
Mean |
55,50% |
58,30% |
|
General |
Source: Original research results
The analysis of Table 1 reveals varied performance patterns among the questions. It was observed that, in some questions, such as P4, P6, and P7, the performance was identical between the two groups, indicating that the visual highlighting of the critical path did not influence assertiveness for these specific types of information or task. This may suggest that certain information in the schedule is inherently easier to interpret, regardless of the presence of visual aids, or that the questions formulated for these items did not sufficiently explore the nuances that CPM highlighting could offer. On the other hand, questions P3, P5, and P8 showed notable variations in assertiveness, indicating that the impact of CPM visual highlighting is not uniform across all dimensions of schedule interpretation. This heterogeneity in results is a crucial point for discussion, as it suggests that, while visualization can be highly beneficial for certain aspects of understanding, it may have a neutral or even counterproductive effect on others, depending on the nature of the information and the cognitive task involved.
For a deeper understanding of performance fluctuations, Figure 1 illustrates the percentage variance of hits from Group B in relation to Group A.
Source: Original research results
Figure 1. Performance variance of the survey (Group B vs. Group A) obtained after the application of the questionnaires
As evidenced in Figure 1, questions P3 and P8 registered a 16.7% increase in assertiveness for the group that used the schedule with visual highlighting. Question P3, which likely refers to the identification of activities that directly impact the project’s final completion date, and question P8, which addresses the identification of the activity with the highest risk for meeting the final deadline, are intrinsically linked to the concept of the critical path. The significant increase in correct answers to these questions strongly corroborates the hypothesis that the visual highlighting of the CPM facilitates the identification of priorities and the perception of temporal risks. This 16.7% gain is substantial and demonstrates the effectiveness of the visual artifact in directing participants’ attention to the most critical elements of the project, a central objective of schedule management, as emphasized by Kerzner (2009) and PMI (2021). The ability to quickly identify critical path activities is fundamental for proactive decision-making and efficient resource allocation, minimizing the risk of delays and rework.
In contrast, question P5, which likely referred to prioritizing activities to avoid delays, registered a 16.7% retraction in assertiveness for Group B. This drop in performance is a counterintuitive finding and deserves detailed analysis. The retraction in P5 may indicate that, although visual highlighting helps identify the critical path, it may, in certain circumstances, lead to oversimplification or misinterpretation of other schedule nuances, such as the total or free float of non-critical activities. It might be that the excessive focus on the critical path diverted participants’ attention from other relevant information for prioritization, or that question P5 required a deeper understanding of interdependencies and floats that the visual highlighting, by itself, could not effectively convey. Lu et al. (2017) point out that the interpretation of floats and the mastery of concepts like total “float” require analytical competence that is not fully supplied by the visual interface. This result suggests an important limitation of the visual model: it may be excellent for highlighting what is critical, but it may not be sufficient for understanding more complex scenarios involving float management and the prioritization of activities with some room for maneuver.
The other questions (P4, P6, and P7) maintained performance neutrality between the two schedule models, reinforcing the idea that the impact of visual highlighting is selective. These questions may have addressed aspects of the schedule that are more universal in their interpretation, or that are not directly influenced by the identification of the critical path. For example, if a question referred to a direct dependency between two non-critical activities, the presence or absence of critical path highlighting would likely not alter the participant’s response. The neutrality in these questions suggests that visual highlighting does not impair the understanding of basic schedule information, but it also does not offer an additional benefit for it.
The schedules used as experimental stimulus are presented in Figures 2 and 3. Figure 2 illustrates Schedule A, the conventional model without visual highlighting of the critical path.
Source: Original research results
Figure 2. Project schedule without critical path highlighting
In contrast, Figure 3 presents Schedule B, which incorporates the visual highlighting of the critical path, graphically identifying activities with zero float and displaying early and late dates.
Source: Original research results
Figure 3. Project schedule highlighting the critical path
The fundamental difference between Schedule A and Schedule B lies in the application of the Critical Path Method (CPM) in the latter, which allows for direct visualization of the tasks that constrain the total project deadline. This visual distinction was the main experimental stimulus, and the results discussed above reflect the impact of this intervention. Schedule B, by highlighting the critical path, aims to improve the communication of critical information and decision-making, as proposed by Vargas (2009), who emphasizes the importance of the proper use of the critical path to guide control focus.
The interpretation of the results demonstrates that the application of visual techniques in schedule management transcends the mere organization of tasks, consolidating itself as a critical facilitator in the Performance Domain of Planning. As advocated by the PMBOK Guide (PMI, 2021), the effectiveness of a planning artifact lies not only in its mathematical precision but in its ability to communicate information in a way that stakeholders make decisions that generate value for the project. In this context, information visualization emerges as a strategic tool, as bar charts and network diagrams are perceived as clear formats for decision support (Monageng et al., 2025; Barbosa et al., 2018). The ability to translate complex data into intuitive visual representations is a competitive advantage, allowing managers and teams to quickly understand project status and identify potential deviations. The literature reinforces that clarity in communication is a pillar for project success, and visual tools are essential to achieve this clarity, especially in environments with stakeholders of varying levels of familiarity with management techniques (Amaral et al., 2011).
The critical path as a communication artifact and cognitive support
The obtained data indicate that the visual highlighting of the Critical Path Method (CPM) fulfilled the premise of reducing the cognitive load of those involved. The 16.7% increase in technical assertiveness observed in questions P3 and P8 corroborates the thesis that signaling activities with zero float creates a “shared visual language” (Chao, 2025). This visual language allows participants, even with little experience in project management, to quickly identify deviations that impact the final delivery. The literature widely validates the use of CPM to increase clarity on priorities, helping stakeholders focus attention on what is truly critical to avoid delay risks (Zakia and Febrianti, 2021; Deepika et al., 2024). The ability of a schedule to unequivocally communicate which activities are critical and which are not is a determining factor for the effectiveness of planning and control. Without this clarity, efforts can be dispersed on non-critical activities, leading to unnecessary delays and inefficient resource utilization. Visual highlighting acts as a cognitive filter, directing attention where it is most needed, which is particularly beneficial in complex projects with many interdependencies.
Group B’s superior performance in systemic vision tasks reflects what Killen et al. (2020) describe as the positive relationship between the use of visualizations and decision quality. By highlighting logical sequencing and interdependencies, the visual schedule acts as an intuitive support that improves the speed and understanding of complex information (Eberhard, 2021; Ke et al., 2023). This approach aligns with the “Tailoring” principle of PMBOK 7th Edition, suggesting that the success of deadline control depends on the suitability of tools to stakeholders’ competencies (Couto et al., 2022). In other words, a schedule that is visually tailored to highlight the critical path not only informs but also educates and empowers users to make more informed decisions. The reduction of cognitive load allows stakeholders to focus on strategic analysis, rather than spending excessive time decoding information. This is especially relevant in dynamic project environments, where decision-making agility is a critical success factor. The visualization of the critical path, therefore, is not just a data representation, but an active tool for supporting business intelligence and risk management.
Limitations of the visual model and cognitive load factors
Despite the gains in criticality, the 16.7% retraction in the assertiveness of question P5 reveals inherent limitations in the exclusive use of visual stimuli. The interpretation of float and the mastery of concepts such as total “float” continue to demand analytical competence that is not fully supplied by the visual interface (Lu et al., 2017). Float, which represents the amount of time an activity can be delayed without impacting the project’s final deadline or the start date of a successor activity, is a more abstract concept and requires a deeper understanding of interdependencies and date calculations. The visual highlighting of the critical path, by its nature, focuses on activities with zero float, which can inadvertently lead users to neglect the importance of activities with float, which, although not critical, still need to be managed and can become critical if delays exceed their float.
As pointed out by Ke et al. (2023), “dashboards” and visual artifacts are sensitive to information load; a design that excessively highlights the critical path may inadvertently lead the observer to neglect non-critical activities or induce a perception of superior complexity when dealing with mathematical calculations of float. Visual information overload, even if well-intentioned, can have the opposite effect than desired, confusing the user or directing their attention inappropriately. In a schedule, the distinction between critical and non-critical activities is fundamental, but effective project management requires understanding both. The retraction in question P5 suggests that, for tasks requiring a more nuanced analysis of float and schedule flexibility, pure visual highlighting may not be sufficient and may even obscure the information necessary for an optimal decision.
This phenomenon suggests that, although tools that automatically calculate and visualize the critical path make control more systematic and agile (Raihan and Sidabalok, 2025; Soe and Htike, 2018), they can generate overconfidence or interpretative bias depending on the user’s profile (Eberhard, 2021). A less experienced user, upon seeing the critical path highlighted, may assume that only these activities matter, ignoring proactive management of other tasks that, although not critical at the moment, may become future bottlenecks. Therefore, the effectiveness of “Schedule B” proved high for monitoring final deadlines, but demonstrated the need for additional instructional support for fine-grained control of resources and tolerable delay windows. This implies that visualization should be complemented by training, clear guidelines, and possibly interactive tools that allow users to explore different scenarios and understand the implications of delays in non-critical activities. The mere visual presentation, however clear, does not replace the need for knowledge and experience for truly effective project management.
Practical implications and convergence with the literature
The convergence between the findings of this research and the literature of the last five years reinforces that visual techniques applied to CPM transform the schedule into an active decision-making tool. The marginal gain of 2.8% in the overall average assertiveness, although modest, indicates that the tool alone functions as valuable support, but does not replace the need for alignment between the artifact’s design and the team’s analytical capacity. Recent studies emphasize that visual methods have a positive effect on communication and alignment of project constraints, especially for less experienced participants (Barbosa et al., 2018; Chao, 2025). For project managers, this means that the implementation of schedules with visual emphasis on the critical path is not just an aesthetic improvement, but a functional strategy to enhance communication and understanding within their teams and with external stakeholders. The ability to quickly identify and communicate critical activities can accelerate decision-making, reduce misunderstandings, and promote more effective alignment around project objectives.
The most evident practical implication is the recommendation for organizations to adopt schedules that incorporate the visual highlighting of the critical path as a standard practice. This is particularly relevant in environments where the project team and stakeholders have different levels of familiarity with project management techniques. The “shared visual language” created by CPM highlighting can level the playing field, allowing everyone involved to intuitively understand priorities and deadline risks. However, it is crucial that this adoption is accompanied by training and clear guidelines on how to interpret not only the critical path but also activities with float. The retraction observed in question P5 underscores the importance of educating users on float management and the complexity of interdependencies, ensuring that visual highlighting does not lead to oversimplification or neglect of important schedule aspects.
Furthermore, the research suggests that the development of project management tools should focus not only on the automation of critical path calculation but also on optimizing its visual representation for different user profiles. The ability to customize the visualization, perhaps with different levels of detail or with the option to highlight other aspects of the schedule (such as activities with limited float), can mitigate the observed limitations. The integration of interactive elements that allow users to explore the consequences of delays in different activities, both critical and non-critical, could further enhance decision-making capabilities. This aligns with Eberhard’s (2021) view, which highlights the importance of visualization for judgment and decision-making, but also warns about potential biases.
In summary, the results confirm that the critical path is a practical management tool that reduces the dispersion of answers about activities influencing the total deadline. Even with limited sampling, it was observed that the presence of visual highlighting provided greater security in understanding priorities. Thus, the schedule management objectives are met by demonstrating that adequate visualization is an essential component for agility and assertiveness in decision-making in contemporary project environments. The research reinforces the idea that effective visual communication is a pillar for project success, but also points to the need for more holistic approaches that combine visual clarity with analytical and instructional support for a complete and nuanced understanding of the project schedule. The ability to manage deadlines effectively is a competitive advantage, and visualizing the critical path is a powerful tool in this arsenal, provided it is used with discernment and complemented by a deep understanding of project management principles.
4. Conclusion
It is concluded that the objective was achieved when evaluating the impact of the visual identification of the critical path on the interpretation of schedules by stakeholders. The results demonstrated that this approach facilitates the understanding of activity prioritization and the perception of deadlines in project environments. There was a notable gain of 16.7% in accuracy on issues directly related to the identification of the critical path, confirming that visual highlighting acts as effective cognitive support. Although the overall average of correct answers was marginally higher in the group with visual support, the reduction in the dispersion of responses regarding activities influencing the total deadline showed greater confidence in understanding priorities. This validates the critical path as a practical management tool that enhances communication and supports decision-making.
However, the study presented important limitations, such as the small sample size and the punctual nature of the experiment. It was also observed that, for issues involving the interpretation of float and more complex concepts, visual highlighting, by itself, was not sufficient, and could even lead to a retraction in assertiveness. This suggests that visualization, although powerful, may require complementary analytical support for more detailed interpretations and to avoid biases. For future research, it is recommended to expand the sample base and investigate different visual representation models, as well as explore approaches that combine visual highlighting with training and interactive tools for a more holistic understanding of the schedule. Thus, adequate visualization of the critical path is an essential component for agility and assertiveness in decision-making in contemporary projects, but its full effectiveness depends on a context of support and education.
Bibliographic References
Amaral, D.C.; Conforto, E.C.; Benassi, J.L.G.; Araujo, C.A.S. 2011. Gerenciamento Ágil de Projetos: Aplicação em Produtos Inovadores. Saraiva, São Paulo, Brasil.
Barbosa, F.; Souza França, R.; Rodrigues, R.; Parreiras, F. 2018. Visualização da informação e métodos visuais como ferramentas estratégicas para o gerenciamento de projetos. Revista de Gestão e Projetos 9(1): 102-114.
Chao, J. 2025. Research on the development and application of science and technology project management platform based on data visualization. Academic Journal of Computing & Information Science 8(7): 080714.
Couto, J.; Kroll, J.; Ruiz, D.; Prikladnicki, R. 2022. Extending the project management body of knowledge (PMBOK) for data visualization in software project management. SN Computer Science 3: 236.
Deepika, S.; Gomathi, S.; Maheswaran, S.; Indhumathi, N.; Murugesan, G.; Duraisamy, P. 2024. A comparative analysis for optimal project completion utilizing critical path method and precedence diagram method for efficient solar power plant installation. In: International Conference on Computing Communication and Networking Technologies, 15., 2024. Anais… p. 1-10.
Eberhard, K. 2021. The effects of visualization on judgment and decision-making: a systematic literature review. Management Review Quarterly 73: 167-214.
Gil, A.C. 2008. Métodos e Técnicas de Pesquisa Social. 6ed. Atlas, São Paulo, Brasil.
Ke, J.; Liao, P.; Li, J.; Luo, X. 2023. Effect of information load and cognitive style on cognitive load of visualized dashboards for construction-related activities. Automation in Construction 156: 105029.
Kerzner, H. 2009. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 10ed. John Wiley & Sons, Hoboken, NJ, EUA.
Killen, C.; Geraldi, J.; Kock, A. 2020. The role of decision makers’ use of visualizations in project portfolio decision making. International Journal of Project Management 38(5): 267-277.
Lu, M.; Liu, J.; Ji, W. 2017. Formalizing a path-float-based approach to determine and interpret total float in project scheduling analysis. International Journal of Construction Management 17(4): 251-263.
Meredith, J.R.; Mantel, S.J. 2009. Project Management: A Managerial Approach. John Wiley & Sons, New Jersey, NJ, EUA.
Monageng, K.; Marnewick, A.; Marnewick, C. 2025. Visualisation of project data for informed decision-making. In: Hope for a Sustainable Future: Blending AI&IT, ESG, and Capital Projects, 2025. Anais… p. 1-15.
Project Management Institute [PMI]. 2021. Padrão de Gerenciamento de Projetos e Guia do Conhecimento em Gerenciamento de Projetos (Guia PMBOK). 7ed. Project Management Institute, Newtown Square, PA, EUA.
Raihan, M.; Sidabalok, A. 2025. Design and build project scheduling applications using the critical path method. Bigint Computing Journal 3(2): 1255.
Soe, P.; Htike, T. 2018. Critical path analysis programming method without network diagram. MATEC Web of Conferences 192: 01027.
Vargas, R.V. 2009. Manual Prático do Plano de Projeto: Utilizando o PMBOK Guide. 4ed. Brasport, Rio de Janeiro, Brasil.
Zakia, S.; Febrianti, D. 2021. The critical path method in construction project rescheduling. IOP Conference Series: Earth and Environmental Science 832: 012009.