Financial assessment for an operational expansion project in the railway sector
Financial Assessment for an Operational Expansion Project in the Railway Sector
Wallas Madureira; Rafael Confetti Gatsios
DOI: 10.22167/2675-6528-202602433
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The evaluation of investment projects is essential in capital-intensive sectors, where expansion decisions involve high financial commitment and long-term return. The study aimed to financially evaluate an operational expansion project in the railway sector for serving fuel transport customers. To this end, the initial investment was dimensioned commercially and operationally, the incremental cash flow was constructed, the discount rate was defined, and the net present value (NPV) and payback criteria were applied, complemented by sensitivity analysis. The research was characterized as applied and quantitative, structured from the simulation of a project with plausible operational and financial assumptions. The results indicated a positive NPV of R$ 258,010,536.27, a simple payback of 6.01 years, and a discounted payback of 7.09 years, evidencing the economic-financial attractiveness of the investment. The sensitivity analysis demonstrated that the project maintained economic feasibility even under moderate variations in the main assumptions, indicating relative robustness. It was concluded that the analyzed expansion presents potential for value generation and recovery of invested capital within a timeframe compatible with the sector, highlighting the importance of financial analysis as a tool to support managerial decision-making.
Keywords: investment analysis; cash flow; net present value.
1. Introduction
The economic-financial analysis of investment projects represents a fundamental element in sectors that demand high capital intensity. In these contexts, resource contributions involve long-maturing assets, characterized by low reversibility and strong dependence on future results. This scenario requires investment decisions to be supported by robust technical and financial criteria, overcoming mere growth expectations or subjective strategic perceptions.
In the railway sector, this need is widely recognized, given the complexity and volume of capital involved. Previous studies, such as Benini (2012), which analyzed Brazilian concessionaires after privatization, and Santos, Barrueco Filho, and Ribas (2023), which demonstrated the economic feasibility of an important railway, reinforce the importance of financial evaluation. These studies indicate that railway projects can generate medium-term returns, provided that the evaluation considers the sustainability of the concessionaires and the feasibility of new infrastructure investments.
The corporate finance literature corroborates this perspective, highlighting that methods such as discounted cash flow, Net Present Value (NPV), and complementary return indicators are consistent instruments for capital allocation (Assaf Neto, 2020; Ross, Westerfield, and Jaffe, 2015). In infrastructure projects, this approach is even more relevant, as investments demand large volumes of immobilized capital, long maturation cycles, and high exposure to technical, economic, and financial risks. Tools such as the Weighted Average Cost of Capital (WACC) are essential for relating operational assumptions with return requirements.
Economic attractiveness in the railway sector depends on factors such as operational efficiency, dilution of fixed costs, utilization of installed capacity, and demand stability. However, in long-term projects, small variations in assumptions can significantly alter the results, demanding transparency and technical justification. Despite this, analyses that are not very detailed are still common, especially in complex projects like railway ones, where attractiveness depends on the interaction between technical and financial variables. Expansion decisions are often limited to logistical justifications, without a proper demonstration that the expected gains adequately remunerate the invested capital.
It is in this context that the present study is inserted, seeking to analyze operational expansion not only as an increase in capacity or logistical gain, but as an investment decision that must be financially validated. The research contributes by proposing an explicit modeling of the economic components of a railway expansion project. Thus, the justification for this study lies in the need to transform a potentially intuitive decision into an analysis based on return, risk, deadline, and value creation. The objective is to evaluate the attractiveness of a railway expansion project aimed at fuel transportation, using detailed modeling of the initial investment, incremental cash flow projection, definition of the discount rate, and application of NPV and payback criteria, complemented by sensitivity analysis and from the perspective of controlling and finance.
2. Material and Methods
This study was characterized as an applied research, with a quantitative approach, for descriptive and analytical purposes. The methodological design adopted was based on the logic of engineering economics and corporate finance, with emphasis on discounted cash flow modeling as a support tool for investment decision-making (Assaf Neto, 2020; Ross, Westerfield, & Jaffe, 2015).
The unit of analysis corresponded to a railway operational expansion project, modeled from plausible technical and financial premises. This project was designed to represent a typical situation of logistics capacity expansion and operational efficiency gain, being structured as an applied study based on simulated data, consistent with the economic reality of the sector, without identifying a specific company. The temporal horizon adopted for the analysis was 10 years, and the cash flows were modeled in nominal terms.
The operational premises considered the railway operation as a closed-loop process, with tank cars circulating in fixed batches. The current fleet of the company under study is approximately 1,200 wagons, each with a capacity of 98 tons and a constant availability of 80%. The possibility of moving batches of 90 wagons, instead of the current 75, would imply an additional investment of R$ 15 million per batch for track and traction adaptation.
The commercial premises included the transportation of petroleum derivatives and biofuels in both directions, with contracts for monthly volumes of linear cadence. The volume projection was carried out based on a compound annual growth rate (CAGR) of 1% for derivatives and 9% for biofuels until year 7, resulting in an expansion opportunity of 15 million tons in 10 years, from a current scenario of 60 million tons.
The project evaluation was conducted by constructing the incremental free cash flow, considering only the economic effects directly attributable to the expansion and excluding sunk costs. The initial investment totaled R$ 620,455,471.69, covering the acquisition of rolling stock (wagons) and operational adjustments works. The investment composition was 62.3% for wagons and 37.7% for works and adjustments.
The discount rate used was the Weighted Average Cost of Capital (WACC), calculated according to ANTT Resolution nº 6035/2024. The cost of equity (Ke) was estimated by the CAPM model, using a sector beta of 0.4, a risk-free rate (Rf) of 13% (NTN-B), and an expected market return (Rm) of 20% (Damodaran, 2024). The capital structure was defined with 60% equity and 40% debt, with a cost of debt of 10% per year, resulting in a WACC of approximately 12.1%.
The need for initial working capital was calculated considering gross revenue, variable costs, average customer payment period (PMR) and average supplier payment period (PMP). For the logistics sector, a PMR and PMP of 60 days were considered. The incremental free cash flow incorporated annual incremental revenue, incremental operating costs, asset depreciation, taxable operating income, income tax, working capital requirement, and residual value.
At the end of the analysis horizon, a residual value estimated at R$ 193,391,298.11 was considered, as the assets maintain economic generation capacity after the tenth year. The accounting useful life of the railway wagons is 20 years, with an annual depreciation rate of 5%, according to ANTT regulations (Brazil, ANTT, 2021; Brazil, ANTT, Resolution No. 5,946/2021). A residual value of 50% of the initial investment was considered, reflecting that the asset is not fully depreciated.
The project’s attractiveness was evaluated through the Net Present Value (NPV) and the simple Payback and discounted Payback indicators. Sensitivity analysis was performed to assess the robustness of the results against variations in key assumptions, such as the discount rate (WACC), incremental revenue, and operational cost reduction, defining pessimistic, base, and optimistic scenarios.
3. Results and Discussion
The economic-financial assessment of the operational expansion project in the railway sector revealed the attractiveness of the investment, with results indicating potential for value generation and capital recovery within timeframes compatible with the sector’s nature. The main findings showed a positive Net Present Value (NPV) of R$ 258,010,536.27, a simple payback of 6.01 years, and a discounted payback of 7.09 years. These indicators, obtained from detailed modeling, provide a robust basis for managerial decision-making, aligning with the recommendations of corporate finance literature for capital-intensive projects.
The structuring of the financial model’s premises was carried out rigorously, seeking a balance between operational plausibility and financial consistency, according to the logic of expansion in a capital-intensive sector. The model was developed for a ten-year horizon, using nominal terms and focusing on incremental cash generation. The central premises included a total investment of R$ 620,455,471.69, an economic life compatible with long-term assets, a tax rate of 34%, linear depreciation of assets, and a discount rate of 12% per year, defined by the Weighted Average Cost of Capital (WACC).
Additionally, the model considered the need for working capital at the beginning of the expanded operation and a residual value at the end of the projected period, crucial elements for the faithful representation of the project’s financial reality. The adopted approach was conservative, avoiding overestimations of operational gains and strengthening the credibility of the analysis. This stance reduces dependence on overly optimistic hypotheses, aligning the study with the investment appraisal guidelines proposed by authors such as Assaf Neto (2020) and Souza and Clemente (2008).
The project investment detailing, known as CAPEX, was segmented into two main groups of expenditures. The first group comprised the acquisition of rolling stock, specifically wagons, and the second, operational adjustments, implementation, and other complementary expenses. The investment need for the purchase of new wagons was sized considering the increase in transport volume over the ten years of the project. Initially, the current fleet of 1,200 wagons was sufficient, but the expansion of demand required the acquisition of 553 additional wagons throughout the period, totaling a CAPEX of R$ 386,782,596.22 for this item.
The modeling for the acquisition of wagons considered that each unit costs about R$ 700,000, according to recent projects by the manufacturer Greenbrier Maxion. The constant availability of the fleet was estimated at 80%, an important factor for sizing operational capacity. The need for wagons increased progressively, from 893 in Year 0 to 1,402 in Year 10, resulting in an investment concentrated in the early years, with R$ 60.2 million annually between Year 1 and Year 7, and R$ 8.0 million in the last three years.
The second group of investments, related to operational adjustments, aimed to increase the capacity of train sets from 75 to 90 wagons. This operational adjustment required an additional investment of R$ 15 million for each fixed set implemented, intended for the adaptation of the permanent way and the increase of locomotive traction. The CAPEX for operational adjustments totaled R$ 233,672,875.47, with an initial contribution of R$ 160.2 million in Year 1, followed by R$ 11.5 million annually until Year 7, and R$ 1.5 million in the last three years. The total composition of the project’s investment, R$ 620,455,471.69, showed the predominance of wagon acquisition (62.3%) and works/adjustments (37.7%), confirming the capital-intensive profile of the railway project.
The investment structure, with its predominance of fixed assets and physical adaptations, is an inherent characteristic of railway projects for operational expansion. This configuration reinforces the need for a rigorous economic-financial evaluation, as decisions of this nature imply low reversibility and a high commitment of resources in the initial period. The detailed analysis of these CAPEX components is fundamental to ensure that all expenditures necessary for the operationalization of the expansion are duly considered in the financial modeling.
The detailing of the Working Capital Requirement (WCR) was crucial to sustain the project’s operational cycle from the beginning. The WCR calculation considered gross revenue, variable costs, the average customer payment period (APP), and the average supplier payment period (APP). WCR represents the difference between operating current assets and operating current liabilities, serving as an indicator of the demand for own resources to finance operations until receipts occur. For the logistics sector, an APP of 60 days was considered for the calculation of accounts receivable and payable.
Initial working capital was estimated at R$ 6,521,143.00 in the first year, progressively growing to R$ 49,562,400.00 by the tenth year, reflecting the increase in operational activity. Incremental gross revenue totaled R$ 3,339,547,200.00 over the ten years, while incremental variable costs amounted to R$ 1,375,358,400.00. This working capital requirement is an essential component of the total investment, ensuring the project has sufficient liquidity to operate and expand without interruption, as demand and transported volumes increase.
The structure of the incremental free cash flow (FCF) was designed to capture exclusively the additional economic effects attributable to operational expansion. Several dimensions were incorporated, including annual incremental revenue, incremental operating costs, asset depreciation, taxable operating income, income tax, working capital requirement, and residual value at the end of the analysis horizon. This approach is in line with the classic corporate finance literature, which favors the cash generation effectively attributable to the investment as the basis for viability assessment (Ross, Westerfield, and Jaffe, 2015).
Depreciation and residual value were important elements in the modeling. At the end of the analysis horizon, the total estimated depreciation was R$ 120,509,103.13, and the estimated residual value was R$ 193,391,298.11. This procedure was adopted because the assets associated with operational expansion maintain economic generation capacity after the tenth year, avoiding the underestimation of the project’s financial value. Railway cars, according to ANTT (Brazil, ANTT, 2021), have a useful accounting life of 20 years, with an annual depreciation rate of 5%, and the consideration of a residual value of 50% of the initial investment reflects that the asset is not fully depreciated, maintaining economic value at the end of its useful life.
The inclusion of residual value is particularly relevant in railway investments, where the economic life of assets frequently exceeds the conventional evaluation horizon. This practice contributes to greater economic realism in modeling and prevents an artificially conservative reading of the investment’s economic feasibility. The project’s free cash flow, after considering all these elements, showed a negative balance in the initial years, reflecting the initial CAPEX, but became positive from the third year onwards, culminating in a positive discounted cumulative cash flow at the end of the period.
The discount rate used in the modeling was 12.0% per year, defined based on the Weighted Average Cost of Capital (WACC), compatible with the risk profile of an operational expansion project in a capital-intensive sector. The WACC calculation considered a capital structure of 60% equity and 40% debt, with a cost of debt of 10% per year. The cost of equity (Ke) was estimated by the CAPM (Capital Asset Pricing Model), using a risk-free rate (Rf) of 13%, a systematic risk coefficient (beta) of 0.4, and an expected market return (Rm) of 20%.
The sector beta of 0.4, according to ANTT resolution no. 6035/2024, reflects the specific risk of the railway infrastructure sector, adjusted to consider low liquidity, regulatory risks, and the demand for logistics transport, in addition to long-term contracts with guaranteed revenues. The risk-free rate of 13% was based on NTN-B (IPCA + 6%), a parameter corresponding to the real yield of National Treasury bonds, considered risk-free. The expected market return of 20% reflects the high risk premium associated with the Brazilian market, in line with Damodaran (2024), who points to high risk premiums in emerging markets.
The inclusion of debt, taking advantage of the tax benefit and the relatively lower cost compared to equity, contributed to reducing the project’s weighted average cost of capital to 12.1%. This means that projects with returns above this threshold tend to generate value for shareholders, while lower returns can destroy value. The adequate definition of the capital structure is, therefore, crucial for balancing cost and financial risk, and the discount rate of 12% allowed future cash flows to be brought to present value based on a minimum economically plausible return requirement for the type of investment analyzed.
The evaluation of the project’s economic feasibility was carried out using three main indicators: Net Present Value (NPV), simple payback, and discounted payback. The NPV, obtained from the sum of the present values of the projected cash flows, discounted at a rate of 12% per year, and deducting the initial investment, resulted in R$ 258,010,536.27. A positive NPV indicates that the project is economically viable and generates net value for the company, exceeding the minimum return required by the cost of capital. This result represents the main financial argument in favor of the investment’s viability, demonstrating that the project not only recovers the committed capital but also generates additional economic value.
The simple payback period, which corresponds to the time needed to recover the initial investment without considering the time value of money, was 6.01 years. This indicator suggests that, in nominal terms, the project presents a return within a timeframe relatively compatible with the nature of the investment, especially considering it is a railway operational expansion. The accumulated free cash flow showed that the nominal recovery of the investment occurs between the sixth and seventh year, with a negative balance of R$ 1.4 million at the end of the sixth year and a positive balance of R$ 107.3 million at the end of the seventh year.
The discounted payback period, which considers the time value of money and is calculated based on cash flows discounted at the WACC rate, was 7.09 years. The difference between the simple and discounted payback, of approximately one year, confirms the effect of the cost of capital on the perception of investment attractiveness, reinforcing the importance of not relying solely on nominal return metrics. The investment recovery in discounted terms occurs between the seventh and eighth year, with a negative balance of R$ 6.7 million at the end of the seventh year and a positive balance of R$ 66.6 million at the end of the eighth year.
Sensitivity analysis was performed to assess the robustness of the results against variations in the main model assumptions, such as the discount rate (WACC), incremental revenue, and operating costs. The alternative scenarios (pessimistic, base, and optimistic) allowed us to observe the impact of these variations on the NPV and the investment payback period. In the base scenario, with a WACC of 12%, the NPV was R$ 258,010,536.27 and the discounted payback was 7 years. In a scenario with a WACC reduced to 10%, the NPV increased to R$ 318,338,458.33, and the discounted payback was between 6 and 7 years.
Even in a scenario of higher return requirement, with a WACC of 14%, the Net Present Value (NPV) remained positive at R$ 207,411,963.61, and the discounted payback extended to 7 to 8 years, indicating that the project maintains economic feasibility, although with a reduction in added value. The sensitivity analysis showed that the project is more sensitive to variations in operational and revenue parameters than to the cost of capital. A 15% reduction in incremental revenue resulted in an NPV of R$ 151,631,093.77 and a discounted payback between 8 and 9 years, while a 10% increase in operational costs resulted in an NPV of R$ 214,206,311.10 and a discounted payback between 7 and 8 years.
This sensitivity to operational and revenue parameters highlights that the project’s attractiveness fundamentally depends on operational efficiency and sales stability, classic characteristics of the railway sector. The sensitivity analysis reinforces that the project’s attractiveness is not based exclusively on a rigid base scenario, remaining financially positive even under moderate variations in the main assumptions. This result is relevant from a managerial perspective, as it indicates that the investment presents relative resilience in the face of reasonable changes in the cost of capital, operating revenue, and efficiency gains.
The results obtained converge with the classic literature of corporate finance, which emphasizes the analysis of capital-intensive projects from the perspective of cash flow generation and economic value creation (Assaf Neto, 2020; Ross, Westerfield, and Jaffe, 2015). The positive NPV, even with a high initial investment, confirms the usefulness of discounted cash flow as the main decision criterion. The difference between the simple and discounted payback clearly illustrates the impact of the cost of capital on the perception of return, reinforcing the need for an integrated interpretation of the indicators, according to Gitman (2010).
The importance of sensitivity analysis, as highlighted by Bruni and Famá (2012), was also confirmed, demonstrating that the robustness of an investment decision does not depend solely on a good base-case result, but on the project’s ability to maintain attractiveness under reasonable variations of assumptions. The operational expansion analyzed demonstrates not only financial feasibility, but also relative consistency in the face of changes in the model’s central variables. This finding strengthens the consistency of the analysis and directly addresses the requirement to test the stability of the results, a crucial aspect for decision governance.
The main managerial contribution of the analysis lies in demonstrating that the decision to expand the railway operation can be treated in a financially structured manner, instead of relying solely on operational expectations or generic strategic perceptions. By transforming expansion hypotheses into cash flow, cost of capital, NPV, and sensitivity analysis, the study offers a more rational basis for the investment decision. The results suggest that the project has approval potential from an economic-financial perspective, provided that the operational and financial assumptions adopted are effectively sustained in execution.
In other words, the observed attractiveness should not be interpreted as an automatic guarantee of success, but as evidence that, under reasonable conditions, expansion is financially defensible. Thus, the analysis reinforces the role of controlling and corporate finance as central decision-support functions in operational expansion projects. In capital-intensive sectors, such as the railway industry, the quality of the decision directly depends on the ability to transform complex investments into technical evaluation criteria, highlighting the practical utility of financial analysis as an instrument of economic governance for expansion.
In summary, the financial evaluation of the operational expansion project in the railway sector demonstrated its economic feasibility and value-generating capacity. The indicators of positive NPV, simple payback, and discounted payback, along with the robustness evidenced by the sensitivity analysis, confirm that the investment is attractive and aligned with the sector’s return expectations. The detailed modeling of assumptions, CAPEX, NWC, and cash flow, together with the rigorous definition of the discount rate, provides a solid framework for decision-making, responding to the objective of evaluating the project’s attractiveness under consistent technical and financial criteria.
4. Conclusion
The present study aimed to evaluate the economic-financial attractiveness of an operational expansion project in the railway sector, focused on fuel transportation. To this end, the initial investment was dimensioned, the incremental cash flow was constructed, the discount rate was defined, and the Net Present Value (NPV) and payback criteria were applied, complemented by sensitivity analysis. A positive NPV of R$ 258,010,536.27 was verified, indicating the generation of net value for the company. A simple payback of 6.01 years and a discounted payback of 7.09 years were observed, periods considered compatible with the nature of long-term investments in the sector. The detailed modeling of CAPEX, which totaled R$ 620,455,471.69, and the working capital requirement, along with the definition of a 12% annual discount rate based on the Weighted Average Cost of Capital (WACC), underpinned the analysis. The sensitivity analysis showed that the project maintains its economic feasibility even under moderate variations in revenue and operational cost assumptions, demonstrating its relative robustness.
The main contribution of this work lies in demonstrating that the decision to expand railway operations can be approached in a financially structured manner, overcoming merely generic logistical or strategic justifications. By transforming expansion hypotheses into a cash flow model, cost of capital, and feasibility indicators, the study offers a rational basis for investment decision-making. The results obtained converge with the corporate finance literature, which emphasizes the analysis of capital-intensive projects from the perspective of cash flow generation and economic value creation. The project’s attractiveness, supported by consistent technical and financial criteria, reinforces the role of controlling and corporate finance as essential management support functions in infrastructure sectors, highlighting the practical utility of financial analysis as an instrument of economic governance for expansion.
Bibliographic References
Benini, 2012
Citações Identificadas no Resumo:
Processamento e Cruzamento:
—
ANTT, 2024
Assaf Neto, 2020
Benini, 2012
Brasil, ANTT, 2021
Brasil, ANTT, Resolução n° 5.946/2021 (Ano implícito: 2021)
Bruni e Famá, 2012
Busca por “Benini” e ano “2012”.
Damodaran, 2024
Encontrado: Benini, R. A. C. 2012. Avaliação econômico-financeira das concessionárias de ferrovia no Brasil: uma análise de precificação de
Gitman, 2010
Para gerar a lista bibliográfica final, vamos cruzar as citações com as referências do PDF, aplicando as regras de paridade e correspondência flexível.
Ross, Westerfield e Jaffe, 2015
Ross, Westerfield, & Jaffe, 2015
Santos, Barrueco Filho e Ribas, 2023
Souza and Clemente, 2008
Article originating from the Final Course Work of the Specialization in Finance and Controllership of the MBA USP/Esalq