Analyses on the managerial aspects of communication and “stakeholders” in Master Plans

Marcelo Duarte Borges Caixeta; Josué Marcos de Moura Cardoso

DOI: 10.22167/2675-6528-202601168

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The Master Plan (PD) constitutes a central instrument of Brazilian urban policy; however, digital transparency in its elaboration did not ensure citizen understanding or effective social participation. This study analyzed the failures in external communication and their impacts on stakeholders in PD processes, from a project management perspective. A qualitative and descriptive field survey was conducted, with the application of questionnaires to nine urban planning specialists, and the data were subjected to content analysis. The results showed that the absence of structured institutional feedback mechanisms compromised the traceability of social contributions, mainly in the Diagnosis and Draft Law stages. It was observed that the excessive technicality of the documentary artifacts hindered understanding by non-specialized audiences, and the institutional portals functioned as fragmented repositories, with low usability and limited information retrieval capacity. To mitigate these gaps, three matrices were proposed: Opportunities, Stakeholders, and Communication, which suggested actions such as content simplification, use of visual technologies, channel integration, audience segmentation, and engagement strategies. It was concluded that the implementation of these tools can strengthen active transparency, broaden social engagement, and contribute to the legitimacy of urban planning and the effective dissemination of PDs.

Keywords: External communication; Project management; PMBOK Guide; Stakeholders; Digital transparency.

1. Introduction

The Master Plan (PD) represents a fundamental instrument of urban development and expansion policy in Brazil. Its relevance is formalized by the Federal Constitution of 1988 (Brazil, 1988) and detailed in the Statute of the City (Federal Law 10.257/2001) (Brazil, 2001). This legal framework establishes the PD as a set of essential guidelines and norms for the territorial ordering of municipalities, aiming to promote balanced urban development, protect the environment, and, crucially, ensure the right to the city and the social function of property.

The elaboration and review of the Master Plan must be participatory and democratic processes, involving civil society, popular movements, and representative associations. Popular participation is mandatory in all phases (Brazil, 2021), requiring channels for dialogue and clear rules for conflict mediation. The quality of this process, according to Pereira (2017), depends on political will, adequate institutional design, and technical commitment to democratic principles.

Although the publicity of documents and information is a constitutional principle (Brasil, 1988) and a requirement of the City Statute (Brasil, 2001), mere disclosure does not guarantee effective transparency. A significant portion of this information is often not understood by the public (Uhlir, 2006). Prediger and Allebrandt (2014) point out that transparency requires data to be adapted and presented in an accessible way to the public, which does not always happen in practice.

Communication barriers are diverse, encompassing technical and semantic obstacles (Chaves et al., 2014). Complex institutional portals and the technical language of documents hinder effective information processing. Lack of standardization and inadequate formats on digital platforms limit effective transparency, as Jambreiro et al. (2009) observe. Abstract and difficult-to-understand content compromises popular mobilization (Bueno and Freitas, 2018), and technical language can exclude citizens from the decision-making process (Nassif, 2020).

The inequality in understanding the PD contents reduces dialogue, favoring the capture of participation by groups with real estate interests (Bueno and Freitas, 2018). The insufficient disclosure of public hearings compromises social participation (Santos and Silva, 2021). This discrepancy between norm and practice reveals gaps in external communication management, manifested by fragile digital channels, fragmented information, and the absence of structured “feedback” mechanisms with the population.

An efficient management of communication and stakeholders is fundamental to the effectiveness of Master Plans (Bueno and Freitas, 2018). The Project Management Book of Knowledge [PMBOK] Guide (PMI, 2017; PMI, 2021) offers a framework of tools and best practices applicable to the public sphere. Communications Management ensures the correct and timely distribution of information, and Stakeholder Management requires the systematic identification of the information requirements of the various actors, analyzing their interests, influence, and impact (PMI, 2017).

The failure to engage civil society and ensure understanding of published content constitutes a managerial gap, making communication ineffective and hindering functional transparency. The absence of an efficient and timely communication plan, with defined methods, formats, and timing for each audience, contributes to accessibility and clarity failures (PMI, 2017; PMI, 2021). Thus, improving institutional communication and stakeholder management is paramount for the legitimacy and effectiveness of urban planning.

Given this scenario, the present research is justified by the need to deepen the understanding of the barriers that impede active transparency. This work aimed to diagnose external communication failures in the processes of elaboration and dissemination of Master Plans from the perspective of project management. It was evaluated how limitations in documentary artifacts, weaknesses in identifying and recording stakeholder needs, and the absence of feedback mechanisms to the population compromised transparency and effectiveness. Based on this diagnosis, the study proposed management tools to improve active transparency and social engagement.

2. Material and Methods

This study was characterized as a qualitative and descriptive field survey. The qualitative approach favored the interpretation of professionals’ perceptions and experiences regarding communication and stakeholder management processes in Master Plans, seeking to understand social phenomena through the interpretive analysis of the obtained information (Creswell, 2014).

The descriptive research aimed to identify and systematize characteristics of the investigated phenomenon, describing perceptions and practices related to digital transparency and communication management in urban planning processes (Gil, 2008). For this purpose, a field survey, or “survey”, was employed as a strategy to collect information from participants through structured instruments (Fowler, 2014).

The study population was composed of nine professionals with experience in the elaboration and management of Master Plans, selected by non-probabilistic and convenience sampling (Ponto, 2015). The participants had senior and multidisciplinary profiles, including municipal managers and private consultants, aiming to access qualified knowledge to identify procedural flaws and support the diagnosis.

The main data collection instrument was a structured questionnaire, developed based on the Project Management Book of Knowledge [PMBOK] Guide (PMI, 2017; PMI, 2021). The questionnaire was divided into four blocks: Characterization, Artifacts, Stakeholders, and Opportunities, each focusing on specific aspects of project management.

The questionnaire application occurred online and asynchronously, between January and February 2026, with open, short, and objective questions. The data analysis, of a qualitative nature, was carried out using the content analysis technique, according to the guidelines of Bardin (2011; 2016). The collected material was organized and read exploratorily in the pre-analysis, followed by thematic coding with previously defined categories.

The Unit of Record (UR) was defined as the theme, to identify the core meanings in the specialists’ responses about managerial failures. The Unit of Context (UC) was the complete response of each participant, ensuring adequate interpretation. The frequency enumeration rule quantified the recurrence of themes. Data categorization followed a deductive approach, with categories established before analysis, guided by theoretical assumptions (Bardin, 2016).

The analytical categories corresponded to the processes of Communications Management and Stakeholder Management, as structured in the PMBOK® Guide (PMI, 2017). A synoptic framework synthesized the problems and related them to project management principles, guiding the interpretation of data from a managerial perspective.

Regarding the ethical aspects, anonymity and data confidentiality were guaranteed, used exclusively for academic purposes. The research was exempted from submission to the Research Ethics Committee (CEP), according to Resolutions of the National Health Council [CNS] numbers 466/2012 and 510/2016, and the questionnaire was initiated after the confirmation of Free and Informed Consent [FIC]. Generative Artificial Intelligence tools were used as technical support to improve readability and revise language, with the author assuming full responsibility for the final content.

Based on the analysis, management tools were proposed to enhance active transparency and social engagement. Three matrices were structured: the Opportunities Matrix, the Stakeholder Matrix, and the Communication Matrix. These matrices were designed to systematize the diagnostic findings and relate them to improvement actions, based on project management best practices, aiming to strengthen institutional communication and the management of the actors involved.

3. Results and Discussion

The results of this study offer an in-depth diagnosis of external communication failures and stakeholder management in the processes of elaboration and disclosure of Master Plans (PDs), from the perspective of project management. The research, qualitative and descriptive in nature, was based on the perceptions of nine specialists with extensive experience in urban planning, whose contributions allowed for the identification of operational gaps and the proposal of management tools to enhance active transparency and social engagement. The data analysis was structured into categories aligned with the Communications Management and Stakeholder Management processes of the PMBOK Guide (PMI, 2017; PMI, 2021), ensuring a technical framework for the interpretation of the findings.

The sample consulted was composed of nine specialists with high technical and academic qualifications, predominantly architects and urban planners, many with postgraduate training in related areas, such as Geography and Built Environment. The group also included professionals from Social Sciences and Law, providing a multidisciplinary view of the challenges analyzed. The respondents’ experience ranged from three to over 20 years of direct involvement in PD processes at different scales, from capitals to small municipalities. This seniority and diversity of practice reinforced the consistency of the collected data, providing a precise technical diagnosis of the bottlenecks in contemporary urban planning.

Omission of “feedback” and return to the population in the context of Master Plans

The investigation revealed that the omission of institutional “feedback” is a systemic failure in the bidirectional communication of PD processes, compromising the interactivity and traceability of social contributions. Experts pointed out that this gap is most intensely manifested in the Diagnosis and Draft Law stages, both cited by three respondents. In the Diagnosis, the absence of return discouraged the initial engagement of the population, while in the Draft Law, institutional silence prevented stakeholders from understanding how their expectations were addressed, generating a perception of exclusion from the decision-making process.

This failure was not restricted to isolated moments, also being mentioned in relation to the Municipal Guidelines and the plan’s Monitoring, each cited by a respondent. This pattern of omission of feedback, especially at the extremes of the project life cycle (gathering expectations and formalization of the final product), breaks the traceability of social participation. From the perspective of the Communications Management of the PMBOK Guide (PMI, 2017; PMI, 2021), the absence of an effective Communications Management Plan is evident, transforming participation into a passive data collection ritual, without the closure of the communication cycle essential for social validation and democratic legitimacy.

Failures in the management of “websites”

The analysis of the responses indicated recurring problems in the management of institutional portals used for the dissemination of information about PDs. The difficulty in locating documents and content was mentioned by three respondents, evidencing flaws in the navigation structure and search mechanisms. Furthermore, the use of technical language in the available content was pointed out by two respondents as a barrier to comprehension for audiences not specialized in urban planning, limiting information accessibility.

Issues related to the updating and disclosure of information were also cited by two respondents, indicating the absence of institutional routines for the continuous maintenance and communication of the stages of the PD elaboration process. Other aspects, such as the limitation of interactivity and visualization resources, and difficulties with accessibility or digital infrastructure, were mentioned by one respondent each. These findings, from the perspective of Communications Management (PMI, 2017; PMI, 2021), reveal flaws in the information distribution process, where portals function as static and disorganized repositories, with low query and retrieval capacity, limiting transparency to mere legal compliance.

Format and language inconsistency

Experts identified significant inconsistencies in the language and level of detail of the artifacts produced during the development of the PDs, hindering public comprehension. The Diagnosis was the most cited document, by six respondents, as presenting barriers to understanding due to excessive technical jargon. Draft Laws and Guidelines and Proposals were mentioned by two respondents each, indicating that the legal and technical language in these documents also made it difficult to interpret the rules and territorial impacts.

The Technical Report, cited by a respondent, was also pointed out as containing technical language inadequate for institutional disclosure. The presence of technical terminology, complex tables, and specialized descriptions limited understanding by audiences without specific training. From the perspective of Communications Management (PMI, 2017; PMI, 2021), this hermetic jargon and low data spatialization generate noise, preventing effective decoding of the message by the citizen. Semantic barriers discourage Stakeholder Engagement, as the population cannot relate technical indicators to real impacts, compromising the communication flow between the technical team and society, and excluding the citizen from the decision-making process, as discussed by Bueno and Freitas (2018) and Nassif (2020).

Fragility in the identification and documentation of needs

The research revealed vulnerabilities in maintaining the integrity of popular demands, especially in the transition between data collection and the formulation of guidelines. The Diagnosis phase and the initial steps were cited by three respondents as the most fragile moments in identifying and documenting social needs. Proposals/Conflicts, Public Hearings and Workshops, Prognosis, Zoning Maps, and Underrepresented Groups were cited by one respondent each, indicating gaps in the registration and treatment of contributions and in the translation of social demands into technical planning instruments.

This fragility is concentrated in the project’s initiation and diagnosis, resulting in the loss of information integrity as the process migrates to the final proposals and the confrontation of conflicts. The absence of formal feedback mechanisms compromised the traceability of contributions, as the population’s suggestions in the initial stages did not have their treatment communicated in the following phases, breaking the chain between public consultation and normative consolidation. Studies on participatory urban planning, such as those by Pereira (2017) and Lima et al. (2023), corroborate that organized groups tend to have greater representation, while vulnerable populations and traditional communities are under-represented, creating gaps in the identification of stakeholders and limiting the incorporation of diverse territorial demands.

Critical information and advertising gaps

The analysis of the responses to the question about critical information neglected by institutional advertising in the PDs indicated a deficit in “accountability” and governance. Respondents reported that the publication of documents did not guarantee access to relevant information for the oversight of urbanistic decisions. The Update and Implementation Monitoring were cited by three respondents, evidencing the absence of information on the follow-up of the PD measures after their approval.

Zoning Parameters and Rules, as well as Collective Costs and Burdens, were mentioned by two respondents each, indicating gaps in data disclosure that would allow for the assessment of economic and territorial impacts. Public Hearings and Rituals, Conflicts of Interest, and Traceability of Suggestions were cited by one respondent each, revealing the absence of institutional mechanisms to monitor the treatment of popular contributions and the mediation of divergent interests. This omission of data on monitoring, social costs, and conflicts of interest limits civil society’s ability to follow urban policies, compromising the link between social participation, decision-making, and plan implementation, as pointed out by Bueno and Freitas (2018) and Prediger and Allebrandt (2024).

Effectiveness of communication for lay stakeholders

Limitations were identified in institutional communication directed at the general public, characterized by the gap between technical content and the population’s comprehension capacity. Four respondents cited communication as protocolary or ineffective, indicating that the dissemination focused on fulfilling legal advertising requirements, without concern for understanding the content. Noise or Technical Language was mentioned by three respondents, highlighting the presence of specialized terms and documentary structures that hindered reading and interpretation by audiences without technical training.

Other elements, such as problems related to information updating and disclosure, digital exclusion (lack of traditional channels), territorial limitation of communication actions’ reach, and the need for greater engagement from internal teams, were cited by one respondent each. The interpretation of these results, from the perspective of Communications Management (PMI, 2017; PMI, 2021), pointed to the non-existence of a Strategic Communication Plan. The predominance of a protocol-based communication indicates that the project focuses on legal rites (passive transparency), failing to generate real engagement and understanding from stakeholders, which reduces the population’s capacity for informed participation and weakens social control over urbanistic decisions (Bueno and Freitas, 2018; Pereira, 2017).

Opportunities for improvement in methods and tools

Participants suggested several alternatives to improve institutional communication and expand the population’s access to urban planning content. Social Networks and the use of messaging applications, such as WhatsApp, were cited by four respondents as effective tools for information circulation and mobilization. Workshops and in-person meetings were mentioned by three respondents, highlighting the importance of direct interaction between technicians and the community. The coordination of multiple communication channels, cited by two respondents, reinforced the need for articulation between different dissemination media.

Innovation and visual methods, such as WebGIS, and the use of didactic language and booklets were mentioned by two respondents each, aiming at the didactization of technical content. Audience segmentation and the use of analog methods, such as radio and loudspeaker trucks, were cited by one respondent each, indicating the need to adapt communication strategies to the social and territorial characteristics of the groups, including those with less access to digital technologies. These improvement opportunities point to an enhancement of the Plan Communications process, focusing on the coordination of digital and analog channels, the use of visual technologies, and content didactization to reduce the decoding effort of stakeholders.

Quality of communications and the city’s statute

The investigation into the quality of communications and its relationship with the City Statute (Brazil, 2001) revealed the need for an evolution from passive advertising to effective transparency. Two respondents highlighted the importance of didactic and accessible language in documents and disclosure materials, indicating that the current technical language limits the population’s understanding. Continuous monitoring and transparency of the actions foreseen in the plan were cited by two respondents, evidencing the demand for public information on the implementation of urbanistic measures after the legislation’s approval.

Social participation associated with the treatment of territorial conflicts was also mentioned by two respondents, reflecting concern with the registration and mediation of divergent interests. Representativeness and quorum in participation spaces, stakeholder training, and the use of communication channels linked to schools or educational institutions were cited by one respondent each. These proposals for quality requirements aim to institutionalize the quality of communications, ensuring that didactics and active validation transform participation into a technical criterion for the approval of stages, and that the understanding of information and public monitoring are conditions for social control over the use of territory (Bueno and Freitas, 2018; Pereira, 2017).

Urgent managerial skills for transparency

The research identified crucial managerial skills for transforming passive advertising into functional transparency, focusing on the public manager’s profile as a transformative agent. Process and Time Management was the most cited skill, by three respondents, emphasizing the need to synchronize technical timelines with the communities’ absorption capacity. This implies that the manager must adjust the project’s pace to meet not only legal milestones but also the information requirements of Stakeholders (PMI, 2017; PMI, 2021).

Technical, Legal, and Social Vision, and Strategic Communication and Translation were mentioned by two respondents each, indicating the need for leadership capable of decoding technicalities into usable and understandable information. Direct Interaction Channels and Synthesis Capacity were cited by one respondent each, reinforcing the importance of integrating multidisciplinary knowledge. The most urgent managerial skill is, therefore, the capacity for integrative leadership, which acts as an interpreter of impacts, transforming complex processes into understandable and usable information, essential for social legitimacy and informed participation (Bueno and Freitas, 2018).

Opportunities Matrix Proposal: strategies for effective transparency in PPs

The Opportunities Matrix, developed based on the PMBOK Guide (PMI, 2017) and the results of the field survey, systematized the diagnostic findings into managerial dimensions and proposed improvement actions. In the Communications axis, the didacticization and synthesis of information were identified as opportunities, with the recommendation to translate the Diagnosis into accessible formats, such as booklets and videos, to reduce semantic barriers and technical jargon. Multichannel communication and accessibility were also highlighted, suggesting the integration of social networks, messaging applications, and analog media, in addition to improving search engines on portals, aiming to expand reach and facilitate information retrieval.

In the Stakeholders field, the matrix highlighted the need for segmentation and active listening, proposing specific methods per audience profile, such as local workshops, to favor representativeness and mitigate the influence of hegemonic groups. Monitoring and “accountability” were another opportunity, with the recommendation of continuous publication of data on the plan’s implementation to ensure transparency throughout the entire project cycle. In the Timeline axis, time synchronization was proposed to adjust the project’s technical milestones to the communities’ absorption capacity, seeking greater democratic legitimacy. Finally, in the Leadership axis, integrative leadership was identified as essential, with the recommendation to train managers in conflict mediation and technical translation, strengthening governance and the construction of territorial consensus.

Proposals for a “Stakeholders” Matrix and Communication Matrix to enhance active transparency in PDs

The “Stakeholders” Matrix organized the main actors involved in the PD development processes, relating their interests, influence levels, impacts, risks, and engagement strategies, according to the best practices of the PMBOK Guide (PMI, 2017). Managers and Technicians, as internal actors with high influence and critical impact, are interested in legal compliance and legitimacy, but present a risk of excessively bureaucratic action, which demands integrative leadership and technical translation. Technical Consulting, external, with medium influence and high impact, focuses on methodological rigor, but runs the risk of producing excessively technical content, requiring guidelines for synthesis and didacticization.

Civil Society, external, with medium to high influence and high impact, seeks social control and monitoring, but faces the risk of low traceability and data dispersion, requiring “feedback” and “accountability” mechanisms. Vulnerable and Traditional Populations, external, with low influence but critical impact, are interested in the right to the city and social function, and run the risk of digital and semantic exclusion, which demands strategies for time synchronization and multichannel communication. The Real Estate Sector, external, with high influence and high impact, focuses on zoning and territorial valorization, presenting a risk of capture of participation, demanding transparency about burdens and interests.

The Communication Matrix, also based on the PMBOK Guide (PMI, 2017), structured the informational flows of the PD elaboration process for different target audiences. For Senior Management, the objective is decision-making and “status”, with information on risks, milestones, and legal compliance, communicated through meetings and visual dashboards, monthly or per milestone, under the responsibility of the coordination, aiming for recorded decisions. For Technical Consulting, the objective is technical quality, with acceptance criteria and didactic materials, via email and terms of reference, per deliverable, under the responsibility of the technical coordination, seeking didactic artifacts.

For Civil Society, the objective is oversight and validation, with information on conflicts, burdens, and traceability, continuously (cross-sectionally) disclosed on an official portal with effective search, under the responsibility of the project manager, aiming for “accountability”. For Vulnerable Populations, the objective is inclusion and rights, with information on local impacts and territorial diagnosis, via radio, booklets, and local workshops, in time synchronization, under the responsibility of communication and technical staff, seeking real participation. For the Lay Public, the objective is access and engagement, with information on “what changes” and access to WebGIS, via WhatsApp, social media, and WebGIS, daily or by project milestones, under the responsibility of social communication, aiming for feedback on suggestions.

In summary, the study diagnosed that external communication in Master Plans is marked by the absence of institutional feedback, excessive technicality of documents, fragility of digital portals, and gaps in the identification and documentation of stakeholder needs. These failures compromise the traceability of social contributions and citizen understanding, limiting transparency to legal compliance. The proposed matrices – of Opportunities, of Stakeholders, and of Communication – offer a managerial framework to mitigate these gaps, promoting the didactization of content, integration of channels, segmentation of audiences, and synchronization between technical and social timelines, aiming to strengthen active transparency and social engagement in urban planning processes.

4. Conclusion

This study investigated external communication failures in the processes of developing and disseminating Master Plans, from the perspective of project management. It was found that the absence of structured institutional feedback mechanisms compromised the traceability of social contributions, especially in the Diagnosis and Draft Law stages, generating a perception of exclusion. It was identified that the excessive technicality of documentary artifacts, such as the Diagnosis, hindered comprehension by non-specialized audiences, while institutional portals functioned as fragmented repositories with low usability and limited information retrieval capacity. Furthermore, a fragility was observed in the identification and documentation of stakeholder needs in the initial phases, which resulted in the loss of integrity of popular demands. Institutional communication, predominantly procedural, focused on meeting legal advertising requirements, neglecting critical information about monitoring, social costs, and conflicts of interest, which limited transparency to mere compliance and reduced social engagement.

To mitigate these gaps, the study proposed a managerial framework composed of three matrices: Opportunities, Stakeholders, and Communication. These tools suggest actions such as the didacticization of technical content into accessible formats, the integration of multiple communication channels (digital and analog), the segmentation of audiences for active listening, and the synchronization between the project’s technical timelines and the communities’ absorption capacity. The implementation of these matrices can strengthen active transparency, broaden social engagement, and contribute to the legitimacy of urban planning, transforming advertising into an auditable process of social value delivery. However, the study’s limitations include the small sample size of experts, which restricts the generalization of results, and the focus on professional perception, without directly capturing citizens’ experiences. For future studies, it is suggested to expand the research to include the perception of citizens and public managers, as well as to conduct case studies that apply and evaluate the practical impact of the proposed matrices in real contexts of Master Plans.

Bibliographic References

Brasil. 1988. Constituição da República Federativa do Brasil. Diário Oficial da União, Brasília, 5 out. 1988.

Brasil. 2001. Lei nº 10.257, de 10 de julho de 2001. Regulamenta os artigos 182 e 183 da Constituição Federal, estabelece diretrizes gerais da política urbana e dá outras providências. Diário Oficial da União, Brasília, 10 jul. 2001.

Brasil. 2021. Guia para Elaboração e Revisão de Planos Diretores. Projeto ANDUS (Apoio à Agenda Nacional de Desenvolvimento Urbano Sustentável no Brasil). Brasília, DF, Brasil. Disponível em: <https://www.gov.br/cidades/pt-br/acesso-a-informacao/acoes-e-programas/desenvolvimento-urbano-e-metropolitano/projeto-andus/GuiaparaElaboraoeRevisodePlanosDiretores_compressed.pdf>. Acesso em: 27 dez. 2025.

Pereira, E.M. 2017. Como anda a participação? As condições para a elaboração de planos diretores participativos. Revista Brasileira de Estudos Urbanos e Regionais, Paraná, 19(2): 235-250. Disponível em: <https://www.scielo.br/

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.