Analysis and proposal for process optimization using BPMN

Analysis and Proposal for Process Optimization Using Bpmn

Marcos Viliam Grawer; Aline Gisele Zanão Benatto

DOI: 10.22167/2675-6528-202603244

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

Inefficient project management can significantly compromise value delivery and organizational sustainability. The present study addressed the problem of operational inefficiencies in the engineering department of a company specializing in synthetic turf works in Rio de Janeiro, where a lack of standardization and clear communication resulted in rework, delays, and high costs. The main objective was to analyze the current (AS-IS) project management process, from the input of project characteristics to the final delivery of the field, and propose an optimized (TO-BE) process using process management tools. The methodology employed was qualitative, exploratory, and descriptive, characterized as a case study, with data collection through semi-structured interviews with engineers and direct observation. The results revealed critical bottlenecks in information flow and inter-team coordination. The TO-BE proposal, based on a centralized BPM system and standardized project kickoff meetings, showed potential to significantly reduce rework, improve outcome quality, optimize costs, and increase operational agility. It was concluded that the objectives were fully achieved, providing a clear path for the company to improve its project management and ensure greater efficiency and customer satisfaction.

Keywords: BPMN; Engineering; Synthetic Grass; Project Management; Process Optimization.

1. Introduction

Project management has consolidated itself as a fundamental pillar for the success and competitiveness of organizations in an increasingly dynamic and demanding market scenario. The application of methodologies and good practices, as advocated by the Project Management Institute (PMI, 2017), is essential to ensure that projects are delivered within scope, time, and budget. In this context, Business Process Management (BPM) emerges as a strategic discipline, focused on improving the efficiency and effectiveness of operations.

The importance of process reengineering to achieve substantial performance gains, emphasizing the need to fundamentally rethink how work is done, was already highlighted by Hammer and Champy (1994). Davenport (1994) complements this perspective by associating process reengineering with the strategic use of information technology as an enabler of structural changes in organizations, an argument that underpins the proposal for a centralized BPM system presented later in this work.

However, many companies still face significant challenges in executing their projects due to poorly defined processes, lack of communication, and absence of standardization. These issues can significantly compromise value delivery and organizational sustainability.

The organization studied, an engineering company specializing in the construction of synthetic turf fields, with a strong presence in Rio de Janeiro and other states, is no exception to this scenario. The engineering department, responsible for transforming the characteristics and scope of the works into executable plans, has been dealing with inefficiencies that result in rework, delays in material and team delivery, and consequently, increased costs and customer dissatisfaction. The way information about the works, such as entry and exit dates and field characteristics, arrives and is processed by engineers lacks a clear and standardized flow, generating ambiguities and reactive decisions made at the wrong time.

Given this scenario of operational inefficiencies and the need to improve project management, the realization of this study is justified. The main objective of this work was to analyze in detail the current (AS-IS) process of construction management in the company’s engineering department and to propose an optimized (TO-BE) process capable of addressing the identified bottlenecks and creating an optimized and well-founded work model for construction management.

2. Material and Methods

This research was designed with a qualitative approach and applied nature, seeking to investigate contemporary phenomena in their real context, as advocated by Yin (2015). The case study focused on the Engineering Department of a company specialized in the construction of synthetic grass fields, based in Rio de Janeiro, identified as “the studied organization” to preserve the confidentiality of sensitive data. The study assumed a participatory character, with the researcher acting as a consultant in the process restructuring project, approaching action research (Thiollent, 2011; Coughlan and Coghlan, 2002).

Regarding the objectives, the research was classified as exploratory and descriptive. It was exploratory for identifying bottlenecks in a specific workflow and descriptive for detailing the current state (AS-IS) and the desired state (TO-BE) of the engineering processes. The research problem lay in the fragmentation of information and the lack of standardization in the data input flow.

Data collection was structured in three complementary fronts to ensure information triangulation. Semi-structured interviews were conducted with two senior engineers from the engineering department, who had approximately a decade of experience and a broad view of the processes. The script focused on the workflow of construction projects, definition of dates, and obstacles in material and team management.

Complementarily, the researcher performed direct observation of the department’s routine, verifying the internal communication flow and interaction with the teams, which allowed for the identification of discrepancies between the formal process and the actual execution. The documentary analysis examined material control spreadsheets, construction schedules, progress reports, and final delivery checklists, providing a historical basis for understanding the recurrence of technical and logistical problems.

For the operationalization of the research and process modeling, specific tools were used. The BPMN (Business Process Model and Notation) version 2.0 notation (OMG, 2011) was employed to ensure a comprehensible visual language of workflows. The Lucidchart software built the AS-IS and TO-BE flowcharts, facilitating the visualization of decision points and bottlenecks. Checklists and spreadsheets were used as models for quality verification and resource allocation.

The data analysis followed the logic of process reengineering (Hammer and Champy, 1994), divided into four stages. The AS-IS Mapping represented the current construction management process. The Critical Analysis focused on identifying non-value-adding activities, redundancies, and communication failures. The TO-BE Modeling proposed a new optimized workflow, incorporating project kickoff meetings for technical and logistical alignment. Finally, the Validation contrasted the TO-BE proposal with the needs of the interviewed engineers to ensure its feasibility.

The research strictly adhered to ethical precepts, ensuring the anonymity of professionals and the confidentiality of the company’s strategic data. All information collected was used exclusively for academic purposes, with voluntary participation of collaborators after prior clarification on the study’s objectives.

The restructuring project, which encompassed all methodological stages, lasted approximately six months. During this period, the company’s management, the construction and engineering departments, the commercial and purchasing areas, and the operational team of the logistics warehouse were involved, configuring a cross-cutting initiative across multiple sectors.

3. Results and Discussion

The study revealed a scenario of significant operational inefficiencies in the company’s engineering department, characterized by a fragmented and non-standardized construction management process. The current workflow, termed AS-IS, begins with the informal receipt of project characteristics, without the use of standardized forms, allowing information to be entered through multiple channels, such as email, phone, and messages. This decentralized and unstructured approach often results in data inconsistencies and the need for rework, compromising the effectiveness of subsequent project stages.

The document analysis and semi-structured interviews with the organization’s senior engineers allowed for the identification of six critical characteristics of the AS-IS process. Firstly, project initiation was manual and lacked standardization, creating an unstable foundation for planning. Secondly, the process involved multiple hierarchical approval levels, reaching up to four distinct approvers, which introduced complexity and slowness in decision-making. These approval steps lacked clear technical criteria, contributing to ambiguity and overall workflow inefficiency.

Complementarily, communication in the AS-IS process was notably decentralized and fragmented, with information dispersed across various channels and without a centralized point of record. This absence of a unified system resulted in a severe lack of information traceability, making it difficult to track the status of requests and retrieve previous decisions. Material and labor planning was conducted through disconnected spreadsheets, which prevented an integrated view and generated coordination issues between teams. Finally, quality assessment was performed only upon final delivery, without the use of a structured checklist, compromising the early detection of non-conformities.

These characteristics of the AS-IS process were identified as activities that do not add value, or “muda”, according to the terminology of Hammer and Champy (1994), resulting in significant waste of time and resources. The lack of standardization, in particular, was pointed out as a critical factor that directly impacts the quality, costs, and delivery times of projects, a concern widely recognized by the Project Management Institute (PMI, 2021) in the context of civil construction. The BPMN flowchart of the current process clearly illustrates this sequence of manual activities and the multiple approval levels, distributed among the Commercial, Engineering, Procurement, and Field areas.

The in-depth critical analysis allowed for the identification of the main operational bottlenecks that compromised the efficiency of the engineering department in six fundamental dimensions. It was found that standardization was low, automation was non-existent, traceability was null, agility was reduced, quality was average with frequent rework, and communication was fragmented. These points of inefficiency represent the central challenges the company faced in managing its synthetic grass projects, directly impacting productivity and value delivery, as detailed in the comparison between the AS-IS and TO-BE processes.

Given the identified bottlenecks, the research proposed an optimized process, named TO-BE, which incorporates principles of process reengineering and project management to establish a standardized, automated, and traceable flow. This model aims to transform construction management, eliminating inefficiencies and promoting greater integration between the areas involved. The proposal was developed based on the best practices of BPMN and the guidelines of the PMI, seeking a robust and sustainable solution for the organization’s operational challenges.

The proposed improvements in the TO-BE process begin with standardization, through the implementation of a digital form for collecting project characteristics. This form would include mandatory fields and automatic validation, ensuring that all essential information is captured consistently and completely from the project’s inception. Additionally, the proposal includes the formalization of a Project Kick-off Meeting, a structured encounter between the commercial, engineering, and operations teams. The objective is to ensure technical, logistical, and financial alignment, preventing future inconsistencies and rework.

The automation of approvals constitutes another core improvement, with the implementation of an automatic workflow that reduces approval levels from four to two, with clear and predefined rules. This optimization aims to accelerate the decision-making process and eliminate bureaucratic bottlenecks. In parallel, the centralization of communication is a fundamental pillar, with the use of a single Business Process Management (BPM) system for all project-related interactions. This measure eliminates communication fragmentation, ensuring that all stakeholders have access to the most up-to-date and relevant information in a single environment.

To enhance governance and transparency, the TO-BE proposal provides for total traceability, recording all steps, decisions, and changes in a centralized system. This allows for effective audits and a complete historical analysis of projects, facilitating organizational learning. Finally, quality is reinforced by the implementation of a structured checklist for the final delivery of the work, which assesses technical and logistical compliance. This checklist ensures that quality standards are consistently met before project completion, minimizing rework and customer dissatisfaction.

The TO-BE process BPMN flowchart, which replaces manual activities with automated and centralized steps on an integrated platform, illustrates the proposed transformation. This model visualizes a more efficient workflow, from the submission of the request in the BPM system to the final delivery of the work with automatic feedback and warranty management. The graphical representation highlights the transition from a fragmented environment to a cohesive and interconnected system, where decisions are made based on centralized and validated data.

The comparison between the AS-IS process and the TO-BE proposal reveals significant efficiency gains in all analyzed dimensions. In standardization, an 85% improvement is expected, moving from a low situation (without forms) to a high one (with digital forms). Automation, which was non-existent, projects a 70% improvement with the implementation of automatic approvals. Traceability, previously null, would reach 100% with a centralized system, while agility in the schedule would be optimized by 65%, reducing the cycle time from 15-20 days to 5-7 days.

Regarding quality, the expectation is a 40% improvement through the introduction of a structured checklist, mitigating the frequent rework observed in the current scenario. Communication, which was fragmented and occurred through multiple channels, would be centralized in a single system, resulting in an expected improvement of 90%. These data, although indicative estimates from a qualitative case study, demonstrate the transformative potential of the TO-BE proposal. The graphical representation of these comparisons visually reinforces the substantial efficiency gain projected for the engineering department.

The analysis of the expected benefits from the implementation of the TO-BE process was structured into six critical dimensions, detailing the projected impacts. The standardization of incomplete information, for example, is expected to reduce rework by 25%. Quality improvement, guaranteed by the structured checklist, projects a 20% increase in compliance. The optimization of materials and labor, resulting from greater clarity and coordination, aims for a 30% cost reduction.

Additionally, the centralized system proposed for traceability promises a 100% increase in the capacity for auditing and monitoring project stages. Schedule agility, driven by reduced approvals and efficient communication, anticipates a 65% decrease in total execution time. Finally, delivery within the deadline and with the expected quality would result in a 40% increase in customer satisfaction. These expected impacts, although projections, indicate a clear path towards continuous improvement and operational excellence.

The research revealed that the engineering department of the studied organization faces significant operational inefficiencies, mainly due to information fragmentation, lack of standardization, and decentralized communication. The AS-IS process mapping showed that the current flow contained non-value-adding activities, resulting in rework in approximately 30% of the projects. Furthermore, fragmented communication generated delays of 5 to 10 days in the schedule and high operational costs, according to the convergent perception of senior engineers and documentary analysis.

It is important to emphasize that these rework and delay percentages should be interpreted as indicative estimates, not precise statistical measurements, given the qualitative and exploratory nature of the case study. The interviewed engineers corroborated that the lack of standardization was the main cause of rework, due to incomplete or inconsistent information. Clear visualization of these bottlenecks, facilitated by tools like BPMN, is crucial for identifying improvement opportunities, as highlighted by Rother and Shook (2003) and OMG (2011).

The TO-BE proposal was submitted for validation by the two senior engineers interviewed, who recognized the feasibility of its implementation. Both highlighted that process standardization and information centralization would be effective solutions for the main bottlenecks identified in the current process. The construction kickoff meeting, although already an informal practice in some projects, would be formalized and, together with the implementation of a BPM system, would ensure consistency and traceability in all works, promoting more effective alignment between teams.

The comparison of cycle time, in days, for each process stage between the AS-IS and TO-BE scenarios concretely illustrates the gains in agility. In initiation, the time would be reduced from 5 to 2 days; in approvals, from 8 to 3 days; in planning, from 6 to 4 days; in execution, from 15 to 12 days; in monitoring, from 4 to 2 days; and in closure, from 3 to 1 day. This substantial reduction, from 15-20 days to 5-7 days in the total approval cycle, combined with the elimination of rework and improved traceability, represents a significant gain in efficiency and competitiveness for the organization.

The validation of the proposal with senior engineers confirmed the technical and operational feasibility of the TO-BE model, which aligns with the PMI (2021) recommendations on the integration between planning and execution as a critical success factor in civil construction projects. The proposed improvements address the bottlenecks identified in the AS-IS mapping, offering a clear path for optimizing synthetic grass construction management processes. The implementation of this model has the potential to significantly transform the efficiency of the engineering department, promoting greater agility and customer satisfaction.

In summary, the research results showed that the AS-IS process of construction management in the studied company was characterized by fragmentation, lack of standardization, and inefficient communication, leading to rework, delays, and high costs. The TO-BE proposal, based on BPMN and project management guidelines, offers an optimized model that, through the standardization of forms, automation of approvals, centralization of communication, and implementation of quality checklists, projects substantial improvements in agility, traceability, and quality. These findings directly address the objective of analyzing the current process and proposing an optimized flow, providing a practical roadmap for improving the organization’s project management.

4. Conclusion

The present study aimed to analyze the current (AS-IS) construction management process in the engineering department of a company specializing in synthetic grass and to propose an optimized (TO-BE) process. It was found that the AS-IS process was characterized by information fragmentation, lack of standardization, and decentralized communication, which resulted in rework, schedule delays, and high operational costs. It was identified that manual project initiation, multiple approval levels, and lack of traceability compromised the efficiency and quality of deliverables. The TO-BE proposal outlined a model with standardized digital forms, structured construction kick-off meetings, approval automation, and centralized communication via a BPM system. It was observed that this optimized model projects substantial improvements in standardization, automation, traceability, agility, quality, and communication, with the potential to significantly reduce rework and project cycle time. The main contribution of this work lies in offering a practical and replicable model to improve project management in the civil construction sector, promoting greater agility and customer satisfaction.

However, it is important to recognize the limitations inherent in this case study. The research was conducted in a single organization, which restricts the generalization of findings to other companies in the sector. Furthermore, the validation of the TO-BE proposal occurred through interviews with the same senior engineers who contributed to the AS-IS diagnosis, without external triangulation at this stage. The percentage improvements presented are indicative estimates, not measurements of actual results, as the proposal was not implemented in practice. For future studies, it is recommended to pilot the TO-BE model in a set of selected works, with monitoring of performance metrics, and to expand the research to other companies in the sector. It is also suggested to develop a customized BPM system, preceded by an economic feasibility analysis, and to develop a change management plan to support the adoption of the new flow by the teams, in addition to investigating the impact on customer satisfaction and company reputation.

Bibliographic References

COUGHLAN, P.; COGHLAN, D. 2002. Action research for operations management. International Journal of Operations & Production Management, 22(2), 220-240.

DAVENPORT, T.H. 1994. Reengenharia de Processos: Inovação em Negócios por meio da Tecnologia da Informação. 1. ed. Campus, Rio de Janeiro, RJ, Brasil.

HAMMER, M.; CHAMPY, J. 1994. Reengenharia: a revolução no gerenciamento. 1. ed. Campus, Rio de Janeiro, RJ, Brasil.

OMG. 2011. Business Process Model and Notation (BPMN) Version 2.0. 1. ed. Object Management Group, Needham, MA, EUA.

PMI. 2017. Um Guia do Conhecimento em Gerenciamento de Projetos (Guia PMBOK). 6. ed. Project Management Institute, Newtown Square, PA, EUA.

PMI. 2021. Um Guia do Conhecimento em Gerenciamento de Projetos (Guia PMBOK). 7. ed. Project Management Institute, Newtown Square, PA, EUA.

ROTHER, M.; SHOOK, J. 2003. Aprendendo a Enxergar: Mapeamento do Fluxo de Valor para Agregar Valor e Eliminar o Muda. 1. ed. Lean Institute Brasil, São Paulo, SP, Brasil.

THIOLLENT, M. 2011. Metodologia da Pesquisa-Ação. 18. ed. Cortez, São Paulo, SP, Brasil.

YIN, R.K. 2015. Estudo de Caso: Planejamento e Métodos. 5. ed. Bookman, Porto Alegre, RS, Brasil.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.