Lean Construction in Procurement Management in Sanitation
Tatiane Cristina Cardoso Zuculoto; Daniel Luis Garrido Monaro
Summary prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Project management has consolidated itself as an essential practice in both academic and corporate environments, based on methodologies that seek to increase the efficiency and effectiveness of organizational processes. Historically, the concepts of project management gained momentum in the 1960s, initially in the engineering sector, and expanded significantly with the founding of the Project Management Institute in 1969 (Bicalho, 2015). Within this vast field, procurement management stands out as one of the most critical knowledge areas, encompassing the processes necessary to purchase or acquire products, services, or results external to the project team. According to the guidelines established by the Project Management Institute (2013), procurement management is responsible for the rigorous planning and contracting of inputs and services demanded for execution, always aiming to meet scope, deadline, cost, and quality. This activity becomes a competitive differentiator by adding value to the organization and reducing operational costs through a strategic approach to identifying potential suppliers.
The systematic application of procurement management aids in risk mitigation and the improvement of purchasing strategies, allowing for the filtering of qualified suppliers and ensuring the availability of essential inputs. When risks are managed proactively, they generate benefits that can be replicated in future projects (Baraldi, 2010). One of the primary phases in this cycle is the planning of contracts, the moment when premises related to products and services are formalized. As pointed out by Xavier (2013), this planning culminates in the identification of the best commercial partners in terms of logistics, cost, and deadline, resulting in the elaboration of detailed contracts. Such legal instruments must contain careful clauses that define responsibilities and indicate potential risks, ensuring that acquisitions are aligned with the times and movements of the construction schedule. In the civil construction sector, the implementation of parameterized procedures directly reflects in cost control and the achievement of more favorable negotiation margins, promoting secure and high-quality contracting.
In this scenario, the philosophy of lean construction emerges as an adaptation of lean production principles to the complex environment of construction sites. The initial lack of academic research on the topic motivated the creation of a concept that adapted industrial characteristics to civil construction (Koskela, 1992). The model proposes a paradigm shift, where production is seen as a set of transformation processes that must, obligatorily, add value to the final product. For Formoso (2002), value creation is intrinsically linked to customer satisfaction and quality, not limited to mere bureaucratic procedure compliance. A process only generates real value if the means employed transform inputs into the products specifically required by customers, eliminating waste and activities that do not contribute to the final outcome.
The theoretical foundation of lean construction is based on eleven fundamental principles that serve as work tools for process management. Among these principles, the reduction of the portion of activities that do not add value, the increase of product value through the systematic consideration of customer needs, and the reduction of variability stand out (Koskela, 1992). In civil construction, where changes and uncertainties are frequent, the standardization of processes and effective verification become risk mitigation mechanisms. Furthermore, the reduction of cycle time—which includes transport, waiting, processing, and inspection—stimulates faster and more efficient delivery. The transparency of the process and the focus on global control, rather than just local control, allow procurement and production management to operate in synergy, ensuring that the flow of materials and services supports the planned pace for the execution of the sanitation infrastructure.
The methodology adopted for the analysis of the application of these concepts consisted of a detailed case study, according to the propositions of Kauark (2010), focusing on the construction of a Sewage Treatment Plant in the interior of the state of Rio de Janeiro. The research was based on documentary survey, analysis of operational information, and direct observation of procurement planning and control processes over a period of 12 months. The case study method allowed the identification of concrete evidence on the effectiveness of management tools in a real scenario, generating debates about the integration between supply and engineering teams. The company object of the study has more than 50 years of experience in the infrastructure market and holds ISO 9001 certification, which ensures the existence of structured procedures and well-defined departments for conducting activities.
The operational procurement process in the organization is divided between the supply departments, responsible for purchasing inputs, and engineering, focused on contracting service providers. Requisitions can originate from various departments, such as production, administration, or QSMS (Quality, Safety, Environment, and Health), and must respect established workflows and deadlines. A central concept applied in the analysis was lead time, which comprises the total period for processing an order, including waiting, processing, inspection, and transportation times (Tubino, 2017). To ensure competitive advantage, the company seeks to dimension these times in order to reduce waiting time and increase customer satisfaction (Ballestero and María, 2019). The variation in deadlines according to the type of product or service required constant monitoring to avoid interruptions in the sanitation work schedule.
Procurement management was structured into three main processes: planning, execution, and control. In planning, potential suppliers were identified and proposals were technically and commercially evaluated, aiming for the best cost-benefit. In the execution stage, after acceptance of the conditions, registration, documentary qualification, and contractual formalization proceeded. Procurement control involved continuous monitoring of compliance with contractual clauses, management of amendments, and verification of the conformity of qualifying documentation. This entire workflow was centralized in the integrated Globaltec system, which allowed financial management by cost centers, automatically linking contracts to the work budget. Monthly, the engineering department performed measurements of the executed services, which, after approval, were entered into the system for payment control and budget monitoring.
Supplier qualification represented a critical stage, requiring the presentation of legal documents such as permits, articles of incorporation, and operating licenses. This information, stored in the cloud, ensured that only qualified partners operated on the project. In the context of civil construction, where material costs are increasing exponentially, rigorous planning of what and when to buy has become a vital tool to increase negotiation power and reduce waste. The integration between procurement management and the Lean Management philosophy allowed the company to identify movement and waiting stages that could be mitigated, optimizing material handling on the construction site and increasing the overall productivity of the Sewage Treatment Plant.
The analyzed Sewage Treatment Plant is a complex infrastructure, composed of collection and treatment systems fragmented into collection points and a processing center. The main objective of the unit is to meet the demand for basic sanitation in the region, promoting significant environmental improvements. The treatment process is divided into liquid and solid phases. In the liquid phase, the effluent undergoes coarse screening for the removal of bulky solids, followed by pumping stations that convey the sewage to fine screening and grit chambers for the removal of sand and smaller debris. Subsequently, the material proceeds to anaerobic reactors, where organic matter is decomposed by bacteria, and to aeration tanks, where microorganisms are stimulated by the addition of air to form biological sludge and reduce the pollutant load.
After settling, the treated effluent undergoes ultraviolet disinfection for bacterial sterilization before being discharged into water bodies. In the solid phase, the resulting sludge is sent to thickeners and dewatering and drying processes, aiming to reduce the volume of waste for transport to the sanitary landfill. The complexity of this operation requires that the procurement of specialized equipment, such as air blowers, UV lamps, and pumping systems, be planned well in advance. During the initial phase of the research, problems were identified in the execution of services and team allocation, often resulting from failures in the logistics of material procurement and the hiring of outsourced labor. The initial analysis revealed unsatisfactory performance indicators in criteria such as schedule planning and site management, with weights of 20% each in the overall evaluation.
To reverse this situation, an action plan based on Lean Construction was implemented, focusing on productivity, quality, and planning. Starting in January 2024, weekly planning sessions with short-term goals were established, involving the engineering and production teams. The use of a weekly constraint spreadsheet allowed obstacles to be identified and removed before they impacted the workflow. Monitoring was carried out through the Completed Packages Percentage indicator, which measures execution efficiency relative to the plan. In week 30, for example, the index reached only 30%, but with process maturity and improved procurement management, results evolved to 100% in subsequent weeks, such as weeks 31 and 32.
The Bioreactor, being the largest asset of the Sewage Treatment Plant, received special attention due to its long execution time. Weekly progress monitoring in this structure showed that dividing services into sequential stages reduced idleness and execution errors. Supply logistics were adjusted to ensure that material supply and weekly production auditing occurred in parallel. The evolution of indicators between January and May 2024 showed that the application of lean construction not only reduced deadlines but also raised the execution standard of the technical team. The transparency generated by weekly meetings allowed behavioral flaws and lack of knowledge of technical processes to be corrected through periodic training.
The discussion of the results indicates that the integration between project management knowledge areas is fundamental for the success of infrastructure works. The use of the Globaltec system combined with Lean principles provided rigorous control over costs and the quality of inputs. It was observed that the prevention of material waste, encouraged by the methodology, contributed to environmental awareness on the construction site. However, the research also revealed limitations, such as the difficulty in finding qualified labor and suppliers that met all the documentary requirements. The synergy between the local community, suppliers, and collaborators is pointed out as an essential factor for the sustainability of civil construction projects (Lopes, 2013).
Another relevant point discussed was the need for more effective oversight by public bodies. The lack of rigorous monitoring can lead to negative impacts, such as environmental damage and structural failures, compromising safety and public trust in management. The study demonstrated that, regardless of the organization’s size, continuous planning and efficient procurement management can generate significant productivity gains. The maturity achieved by the team over the 12 months of study allowed the work to be completed within the stipulated schedule, ensuring the delivery of a final product that meets the technical and quality standards required for basic sanitation.
The analysis of quantitative data reinforces the importance of indicators such as the performance index, which assigned weights for the evaluation of the system, tools, teams, schedule, and construction site layout. Initial imprecision in the logistics of acquiring services and products was overcome by adopting a more assertive and collaborative work model. The experience gained suggests that future research should focus on identifying specific approaches for small and medium-sized organizations, as well as analyzing the role of the most relevant stakeholders in urban infrastructure projects. The application of Lean Construction has therefore proven to be an effective strategy for mitigating the risks inherent in the civil construction sector and for optimizing the management of financial and material resources.
It is concluded that the objective was achieved, as the application of the Lean Construction methodology in the procurement management of the Sewage Treatment Plant proved effective in increasing productivity and ensuring schedule compliance. The integration between weekly planning, rigorous supplier control via the Globaltec system, and the elimination of value-adding activities resulted in a smoother execution and a significant reduction in waste. The study proved that the standardization of processes and the documentary qualification of partners are indispensable pillars for risk mitigation in sanitation infrastructure works, providing gains in quality and efficiency that overcome the sector’s logistical and labor challenges.
Bibliographic References:
Ballestero Alvarez, María E. 2019. Gestão de Qualidade, Produção e Operações. São Paulo: Atlas, Disponível em: https://bityli.com/JeGlINuu.
Baraldi, Paulo. 2010. Gerenciamento de Riscos. 3ª ed. Rio de Janeiro: Campus.
Bicalho, Eduardo Gaino Caram. 2015. Gestão de projetos: importância nas organizações Fundação Educacional do Município de Assis – Fema – Assis.
Formoso, Carlos T. Lean Construction: princípios básicos e exemplos. Boletim Técnico, Norie, Universidade Federal do Rio Grande do Sul, v. 14, 2002. Disponível em: <http://www.construtoracastelobranco.com.br/aempresa/ps-37/files/LeanConstru.pdf>.
Kauark, F. Manhães, F. C.; Medeiros, C. H. 2010. Metodologia da Pesquisa: Guia Prático. Via Litterarum, Itabuna, BA, Brasil.
Koskela, L. 1992. Application of the new production philosophy to construction. Center for Integrated Facility Engineering – CIFE, Stanford University, Stanford – EUA, Technical Report n. 72.
Lopes, A. A. 2013. Construção Sustentável: Medidas Construtivas Sustentáveis que Buscam Aumentar a Eficiência no Uso dos Recursos e Minimizar os Impactos ao Meio Ambiente. Dissertação (Mestrado em Engenharia Ambiental) – Escola Politécnica, Universidade Federal do Rio de Janeiro, Rio de Janeiro.
Project Management Instituto. 2013. Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK). 4ª ed. Four Campus Boulevard, Newton Square, PA 19073-3299 EUA.
Tubino, Dalvio F. 2017. Planejamento e Controle da Produção – Teoria e Prática, 3ª edição. São Paulo: Atlas. Disponível em: https://bityli.com/BKanlEwi.
Xavier, C. M. S.; Weikersheimer, D.; Linhares Júnior, J. G.; Diniz, L. J. 2013. Gerenciamento de Aquisições em Projetos. Fundação Getúlio Vargas, Rio de Janeiro, RJ, Brasil.
Executive summary from the Final Course Work of the Specialization in Project Management of the MBA USP/Esalq