Invisible stakeholder: A case study on biodiversity as an indirect stakeholder in infrastructure project management

Invisible Stakeholder: A Case Study on Biodiversity as an Indirect Stakeholder in Infrastructure Project Management

Paula Dias Ho; Bruno Henrique Sanches

DOI: 10.22167/2675-6528-202603334

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

Infrastructure projects play a relevant role in economic and social development, but they imply significant dependence on natural resources and strong interface with ecosystems, generating risks of environmental degradation and biodiversity loss. Despite this, biodiversity has generally been treated from the perspective of legal compliance, without structured integration into project management. This study aimed to analyze how biodiversity is considered in stakeholder management in infrastructure projects, in light of PMBOK best practices. To this end, a case study of an electric power transmission line implementation project in Brazil was conducted, based on documentary analysis of technical and environmental reports. A structured analysis framework was developed in four dimensions: identification, analysis, engagement planning, and monitoring. The results indicated that, although biodiversity has been widely considered in environmental studies, its integration into stakeholder management occurred in a limited and predominantly reactive manner, mediated by regulatory bodies and focused on meeting legal requirements. It was concluded that the absence of recognition of biodiversity as an indirect stakeholder reduced the potential for risk anticipation and improvement of project performance. The study contributed by proposing its structured incorporation into stakeholder management, as well as raising reflections on the limits of institutional representation of ecological interests.

Keywords: Risk Management; Environmental Impact; Stakeholders; PMBOK.

1. Introduction

Infrastructure projects play a central role in economic and social development, covering sectors such as energy, transportation, and sanitation. The feasibility and operation of these ventures depend, directly or indirectly, on natural resources and ecological processes, establishing a strong interface with ecosystems. In the electricity sector, for example, the generation, transmission, and distribution of energy are intrinsically linked to water availability and the environmental quality of the implementation areas, as well as to relationships with communities and regulatory bodies.

In this context, environmental degradation and biodiversity loss constitute significant risks for the execution of these projects. Neglecting environmental aspects, especially those related to biodiversity, can lead to delays in licensing, work stoppages, increased costs, and conflicts with stakeholders, compromising the overall performance of the ventures. The intensification of this process in recent decades is driven by factors such as deforestation, agricultural expansion, urbanization, and climate change.

Data from the Global Assessment Report on Biodiversity and Ecosystem Services (IPBES, 2019) indicate that approximately 75% of the terrestrial environment and 66% of the marine environment have already been significantly altered by human activities, compromising the ability of ecosystems to provide essential services such as climate regulation and pollination. The accelerated loss of biodiversity, with an average reduction of 69% in vertebrate populations between 1970 and 2018 (WWF, 2022), exposes organizations to increasingly relevant operational, regulatory, and reputational risks, configuring a systemic risk for the economy and business (WEF, 2020).

In this scenario, project management assumes a strategic role in mitigating socio-environmental risks associated with infrastructure ventures. Good project management practices, as systematized by the Project Management Body of Knowledge (PMBOK) Guide, recognize stakeholder management as one of the critical success factors. Socio-environmental aspects tend to be incorporated indirectly, mediated by human stakeholders and institutions such as regulatory bodies, local communities, civil society organizations, and investors, primarily framed from the perspective of legal compliance, risk management, and organizational reputation.

However, this approach presents limitations when treating biodiversity exclusively as an object of impact or as a risk variable, without recognizing it as an indirect stakeholder with its own, diffuse, and long-term interests. Biodiversity, defined as the set of all life forms, including plants, animals, fungi, microorganisms, and the ecological environments of which they are a part (WWF, 2026; CBD, 2006), although directly impacted by infrastructure projects, is rarely treated in a structured manner as a stakeholder in the management process, often being considered only from the perspective of meeting legal requirements and environmental licensing criteria.

This gap highlights a theoretical and practical challenge of contemporary project management, especially in infrastructure projects. The growing pressure from investors, regulatory bodies, and society for greater transparency and socio-environmental responsibility has increased the need to integrate biodiversity-related aspects into project risk management and governance practices. The concept of stakeholder, according to the PMBOK (2017; 2021), encompasses any individual, group, or organization that can affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project. Biodiversity, as a set of living beings and systems directly affected by the actions and decisions associated with ventures, fulfills this fundamental criterion.

Thus, by understanding biodiversity as an affected part, as foreseen in the expanded understanding of the PMBOK, the legitimacy of incorporating it as a stakeholder in analysis and decision-making is reinforced, especially in initiatives involving land use, conservation, and environmental impact. The absence of recognition of biodiversity as an indirect stakeholder reduces the potential for risk anticipation and project performance improvement. Given this context, this study aims to analyze how biodiversity is considered in stakeholder management in infrastructure projects, in light of PMBOK best practices.

2. Material and Methods

The present research was characterized as a single case study, of an applied nature and qualitative approach, with exploratory and descriptive purpose. This methodology was selected because it allows for an in-depth analysis of a contemporary phenomenon in its real context, according to the guidelines of Yin (2018), being suitable for investigating the complexity of stakeholder management in infrastructure projects and the consideration of biodiversity in this process.

The empirical object of the study consisted of a project for the implementation of electric power transmission lines in Brazil, covering the states of Espírito Santo and Minas Gerais, with approximately 85 km in length. The choice of this undertaking was justified by the relevance of the potential impacts on biodiversity and the need for a structured approach for its consideration in stakeholder management throughout the project’s lifecycle.

For data collection, a documentary analysis of public sources made available by the project proponent company was carried out. The collection instruments included the Environmental Impact Statement (RIMA), the Complementary Environmental Impact Statement (RIMA 2), and the project’s institutional page. These documents provided the socioeconomic, environmental, and institutional diagnosis of the areas of influence, as well as information on the venture’s socioeconomic and environmental guidelines and commitments.

The theoretical framework for the analysis of stakeholder management was based on the Project Management Body of Knowledge (PMBOK) Guide, using the 6th edition (PMI, 2017) and the general principles of the 7th edition (PMI, 2021). This foundation allowed the analysis to be aligned with internationally recognized best practices in project management, especially regarding the identification, analysis, engagement planning, and monitoring of stakeholders.

A framework for analysis was developed, structured in four dimensions, aligned with the PMBOK stakeholder management processes. The first dimension, “Stakeholder Identification”, assessed how biodiversity is recognized in the identification process. The second, “Stakeholder Analysis”, examined how biodiversity is considered in terms of power, interest, and impact.

The third dimension, “Engagement Planning”, investigated the existence of structured strategies to incorporate biodiversity into project management. Finally, the fourth dimension, “Monitoring and Integration into Management”, analyzed how biodiversity information is used throughout the project lifecycle, allowing for the assessment of the presence and quality of biodiversity integration into project management processes.

The classification of the identified stakeholders was carried out using the “Power x Interest” matrix, as recommended by the PMBOK. The “power” criterion was assigned based on the stakeholder’s ability to influence decisions, resources, deadlines, or the project’s continuity. The “interest” criterion reflected the degree of direct or indirect impact suffered, the dependence on the venture’s results, and the sensitivity to associated risks.

Regarding ethical considerations, it was decided not to disclose the name of the company analyzed, in accordance with the guidelines of the TCC Manual. The identification of the organization studied was kept anonymous to ensure institutional confidentiality and compliance with the research’s ethical requirements, with only the geographical location and the aspects necessary for understanding the case study being presented.

It is important to note that the study did not involve direct measurement of environmental impacts or in-depth ecological analysis, focusing on the managerial perspective of project management. No interviews, questionnaires, or external inferences were conducted at this stage, and interpretations and conclusions were limited to the information explicitly available in the analyzed documentary sources, respecting the defined methodological scope.

The documentary analysis allowed us to observe how elements related to biodiversity were highlighted in the examined documents, without asserting the non-existence of other internal actions or procedures of the organization. Thus, the research remained faithful to the available data, avoiding extrapolations or assumptions about undocumented practices.

3. Results and Discussion

This section presents and discusses the results obtained in the selected case study, based on the documentary analysis of the Environmental Impact Statement [EIS] and other public project documents. Initially, the proponent company and the undertaking are contextualized, detailing the main socio-environmental impacts identified, with a focus on the effects on the biotic environment and local communities. This contextualization is crucial for understanding the project’s complexity, its territorial insertion, and the relevance of socio-environmental aspects in the management process, establishing the scenario for stakeholder analysis in light of good project management practices. The subsequent discussion is structured from the proposed analytical framework, based on the PMBOK guidelines for stakeholder management, addressing the identification and analysis of stakeholders, engagement planning, and monitoring and integration into management.

The results show a predominantly reactive approach in considering environmental aspects, with efforts focused on meeting licensing requirements and executing monitoring and mitigation programs. Although these practices are essential for environmental management, limited integration of the generated information into the project’s strategic decision-making processes was observed. However, the management of traditionally recognized stakeholders, such as regulatory bodies, local communities, and owners of affected areas, demonstrated effectiveness, with engagement strategies compatible with PMBOK recommendations for these groups, indicating adherence to good practices in social and regulatory stakeholder management.

The discussion also highlighted the need for greater integration between stakeholder management, risk management, and project management. The analysis of biodiversity as an indirect stakeholder revealed that, despite its high interest and the direct impacts suffered by the project’s activities, its representation occurs indirectly through environmental agencies, regulatory standards, and conservation units. This mediation reduces the influence of biodiversity in decision-making processes, causing relevant information about environmental risks to often remain restricted to the technical sphere, limiting its contribution to project planning and management. The findings reinforce the need for a more strategic approach, integrating biodiversity in a more structured way into governance processes, stakeholder engagement, and risk management.

Company and project characterization

The company analyzed is part of a private group operating in Latin America, specifically in the electric power transmission sector in Brazil. It operates and develops energy infrastructure projects in various regions of the country, focusing on the expansion and reliability of the National Interconnected System (SIN). The organization is large, with over 1,600 employees and a presence in 18 Brazilian states. Its operations are conducted by concessionaires, responsible for strategic transmission assets and for the implementation of new projects regulated by the National Electric Energy Agency (ANEEL).

Due to the nature of its ventures and the demands of the environmental licensing process, the organization demonstrates maturity in socio-environmental management. This includes the existence of specialized technical structures and procedures aimed at meeting regulatory and sustainability requirements. The development of Environmental Impact Studies and Reports (EIA/RIMA) for its infrastructure projects, as well as the presence of a specialized Environment and Sustainability team, are indicators of this maturity, aligned with the high demand from the electricity sector for robust governance.

The case study project involves the implementation of a set of electric power transmission lines in the states of Espírito Santo and Minas Gerais, totaling approximately 85 km in length. This undertaking aims to strengthen the transmission system of the Southeast and Northeast regions of Brazil. The project scope covers various typical activities, such as the implementation of high-voltage transmission lines, the installation of towers and support structures, and the clearing and maintenance of servitude strips. It also includes the implementation of temporary and permanent access roads, the execution of civil works and electromechanical assembly, in addition to the operation and maintenance activities of the structures after the implementation phase.

The project activities cross rural and natural areas, including regions with remnants of native vegetation, areas of agricultural use, and proximity to environmentally sensitive areas. This territorial characteristic justifies the requirement for environmental licensing and the elaboration of the EIS, which becomes a central document for the assessment and management of impacts. Within the environmental scope, the EIS identifies impacts on the physical, biotic, and socioeconomic environments, proposing mitigating and compensatory measures and specific environmental programs. Although biodiversity is widely analyzed as a component of the biotic environment, its consideration occurs predominantly under the logic of environmental impact, and not explicitly as an indirect stakeholder in the project management process, which justifies the choice of this project for the study.

Main socio-environmental impacts identified in the EIS

Based on the project’s Environmental Impact Statement (EIS) documents, biodiversity is mainly presented through the socio-environmental impacts associated with the implementation and operation phases of the undertaking. The identified environmental impacts include the suppression of native vegetation for the implementation of structures and the opening of the servitude strip, resulting in the fragmentation of natural habitats. There was also interference with permanent preservation areas (PPAs), where applicable, and the displacement, movement, and possible mortality of wildlife.

Additionally, interferences in flight routes and bird usage areas were identified, as well as temporary alteration of the landscape. Soil compaction and exposure, with potential for erosive processes, were observed, along with the generation of solid waste and effluents during the works. Noise and dust emissions during the construction phase were also a relevant impact, as was the risk of introducing exotic or invasive species associated with the movement of machinery and people.

The social and socioeconomic impacts identified in the Environmental Impact Statement [EIS] include interference with rural properties and productive areas, which requires easement negotiation. The temporary alteration of the routine of local communities during the construction phase was observed, as well as the generation of direct and indirect jobs, mainly during the implementation phase. There was also a temporary increase in demand for local services and possible conflicts in land use, including recreational activities such as paragliding. The need for resettlement or compensation, when applicable, and the occupational and safety risks associated with construction activities were other points raised, as well as the impacts on the landscape perception by the local population.

Identification of Project Stakeholders

The identification of stakeholders was carried out based on documentary analysis, following the process of identifying interested parties described in the PMBOK. All individuals, groups, or organizations that could affect or be affected by the project, directly or indirectly, were considered. The identification included internal, external, institutional, social, and environmental stakeholders, including those representing interests associated with biodiversity. Among the internal stakeholders, the Project Entrepreneur/Proponent and the project Workers and labor force stand out.

External stakeholders include the State environmental licensing body, Federal environmental bodies, Municipalities, Local Communities, Local social and community organizations, Owners of affected properties and lands, Family farmers, ranchers, local businesses and service providers, and Recreational and sports activity users (paragliding). State and municipal Conservation Units and protected areas were identified as external environmental stakeholders, representing areas sensitive to intervention and focused on the assessment of ecological impacts, definition of mitigating measures, environmental compensations, and monitoring.

The Entrepreneur/Project Proponent was represented as the agent responsible for the technical, economic, and legal feasibility of the undertaking, as well as for the implementation of mitigation measures, environmental compensation, and socio-environmental programs provided for in the licensing. The state environmental licensing body represented the public interest in environmental protection and legal compliance, acting as the authority responsible for analyzing impacts, defining conditions, and overseeing compliance with environmental obligations. The federal environmental bodies represented national environmental interests, especially when there was interference with assets or areas under federal jurisdiction, reinforcing regulatory and environmental protection criteria.

The municipal governments represented local interests related to territorial planning, urban infrastructure, revenue collection, and socioeconomic impacts in the municipalities crossed by the undertaking. Local Communities were represented mainly through the socioeconomic diagnosis, focusing on impacts on quality of life, land use, safety, mobility, and possible interferences in social and productive routines. Local social and community organizations represented collective and community interests, being recognized in the documents as channels for dialogue, social participation, and mediation of local demands related to the project’s impacts.

The Owners of intercepted properties and lands were represented from the land and asset perspective, focusing on administrative easement processes, indemnities, negotiations, and financial compensation. The Project Workers and labor were represented as a public directly involved in the undertaking’s execution, with interests associated with employment, working conditions, health, safety, and professional training. Family Farmers, livestock farmers, local businesses, and service providers were represented based on direct and indirect economic impacts, including changes in productive activities, income generation opportunities, and possible temporary or permanent losses.

Recreational and sports activity users (free flight) were represented as specific groups affected by the restriction of area use and landscape alteration, with their interests treated punctually in impact studies. Conservation Units and state and municipal protected areas were represented as areas sensitive to intervention, focusing on the assessment of ecological impacts, definition of mitigating measures, environmental compensations, and monitoring, without characterization as active stakeholders, but as objects of environmental protection.

Stakeholder Classification – “Power × Interest Matrix”

In alignment with the stakeholder analysis dimension of the proposed framework, the identified stakeholders were classified using the “power × interest” matrix, as recommended by the PMBOK. This classification allowed for the assessment of the level of influence and interest of each stakeholder in the project. The “power” criterion was assigned based on the stakeholder’s ability to influence decisions, resources, deadlines, conditions, or the project’s continuity. The “interest” criterion reflected the degree of direct or indirect impact suffered, dependence on the venture’s outcomes, and sensitivity to associated risks.

Institutional stakeholders with legal or regulatory authority, such as the entrepreneur, the environmental licensing body, ANEEL, the MME, and state governments, were classified as having high power and high interest. This classification is justified by their formal capacity to make decisions, approve, condition, or halt the project, as well as their high responsibility for the venture’s viability, regulatory compliance, and performance. For these groups, the engagement strategy recommended by PMBOK is “Manage Closely,” which implies continuous engagement, frequent communication, and participation in key decisions, in addition to active expectation management.

Local communities and intercepted property owners were positioned as stakeholders with medium power and high interest. Although they do not have formal authority equivalent to that of regulatory bodies, they exert relevant influence through land negotiations, participatory processes, and potential socio-environmental conflicts, being directly impacted by the undertaking. For these stakeholders, the engagement strategy is also “Manage Closely”. Conservation Units, in turn, were classified with medium power and high interest, as their interests are represented indirectly through environmental regulations and by the licensing body, granting them indirect influence capacity, while also suffering relevant environmental impacts. For Conservation Units, the indicated strategy is “Keep Satisfied”, which involves strategic and objective communication, avoiding information overload and ensuring the fulfillment of critical requirements.

Stakeholders with high power and medium interest, such as CONAMA and the Ministry of Mines and Energy (MME), were classified with the “Keep satisfied” strategy. Stakeholders with medium power and medium interest, such as municipal governments and local social organizations, also fit the “Keep satisfied” strategy. Finally, stakeholders with low power and medium interest, such as project workers and local economic activities, were classified with the “Keep informed” strategy, which foresees regular communication, transparency about impacts and decisions, and feedback channels. Free flight practitioners, with low power and medium interest, were classified for the “Monitor” strategy, which involves periodic monitoring and occasional interventions when necessary.

Analysis of biodiversity as an indirect stakeholder from the PMBOK perspective

Although the PMBOK does not explicitly recognize natural elements as formal stakeholders, the guide defines a stakeholder as any party that can affect or be affected by the project. From this expanded perspective, biodiversity can be understood as an indirect stakeholder, as it is directly affected by the project’s outcomes but does not directly participate in decision-making, communication, or governance processes. Its interests are represented indirectly by other parties, such as regulatory bodies, institutions, or standards. In the context of this infrastructure project, biodiversity is represented by the environmental licensing agency, environmental regulations, and identified conservation units.

When considering biodiversity (fauna, flora, ecosystems) as an indirect stakeholder and analyzing its performance in the “power x interest” matrix, using the same methodology applied to other stakeholders, it was found that biodiversity presents low power and high interest. The low power stems from its influence occurring indirectly through other parties in decision-making, without actively and directly influencing decisions, resources, results, or the project’s continuity. The high interest, in turn, is justified by being directly impacted by the implementation of the transmission lines. Considering this assessment, the engagement strategy to be adopted for biodiversity, under good stakeholder management practices, should be “Keep informed”.

Analysis of the engagement strategy for biodiversity

The analysis of the engagement strategy for biodiversity, related to the planning dimension of engagement within the framework, revealed a divergence between current practice and the PMBOK recommendation. Although biodiversity presents high interest and low power, the engagement strategy currently practiced, according to project documents, is predominantly “monitoring”. This reactive approach focuses on meeting legal requirements and executing environmental programs, resulting in limited action to technical impact monitoring.

This practice, although essential for environmental licensing, does not translate into a structured engagement strategy as advocated by the guide for stakeholders classified with “high interest and low power”. Nor does it contemplate the explicit incorporation of biodiversity as an indirect stakeholder in the project’s stakeholder management plan. Consequently, environmental information tends to remain restricted to the technical sphere, with limited integration into the project’s managerial and decision-making processes. This approach contrasts with the PMBOK recommendations, which emphasize the importance of comprehensive and early identification of stakeholders, especially those associated with relevant project risks, and the definition of engagement strategies compatible with their power and interest profile.

In the case of biodiversity, the “keep informed” strategy, recommended by PMBOK for an indirect stakeholder, implies the institutionalization of representation and communication mechanisms that ensure the systematic consideration of environmental impacts and risks in decision-making processes. The absence of this formal recognition limits the integration between environmental management and project risk management, reducing the potential for anticipating impacts and mitigating risks throughout the project’s lifecycle. The choice to treat biodiversity not as a formal stakeholder, but as a strategic issue represented by intermediate stakeholders, such as environmental agencies, regulatory standards, and conservation units, contributes to greater analytical clarity and adherence to the PMBOK framework. However, the weakening of this representation can generate significant risks to project performance, as when environmental interests are treated exclusively as technical requirements or regulatory obligations, there is a tendency for their consideration to occur late, reactively, or in a compartmentalized manner, with limited integration into the central processes of decision-making, risk management, and project planning.

Well-known examples in the Brazilian context, such as the dam rupture in Brumadinho in 2019, highlight the potential effects of an approach where environmental and biodiversity impacts are not strategically incorporated into the governance and risk management of undertakings. Although it is a distinct sector, the case illustrates how the undervaluation of environmental interests, even if formally supported by licenses, regulations, and technical studies, can result in severe environmental, social, reputational, and economic consequences. From a project management perspective, such events reinforce the importance of recognizing the environment and biodiversity as critical interests, whose representation by intermediate stakeholders must be strengthened and systematically integrated into decision-making processes, rather than being restricted to regulatory compliance.

From the perspective of the monitoring and integration dimension to project management, information related to biodiversity is predominantly used for regulatory compliance purposes, with limited integration into decision-making and risk management processes. This finding reinforces the need for a more strategic approach, capable of integrating biodiversity in a more structured manner into governance, stakeholder management, and risk management processes. The adoption of formal mechanisms for representation and incorporation of environmental information into decision-making processes would contribute to more preventive action, to the anticipation of socio-environmental risks, and to the alignment between sustainability and good project management practices throughout the entire lifecycle of the undertaking.

Implications for project management

In light of the PMBOK Guide’s guidelines, considering biodiversity as an indirect stakeholder could strengthen the stakeholder engagement planning and risk management processes, promoting a more proactive and integrated approach. By adopting the “keep informed” strategy, information from environmental programs would cease to be merely for legal compliance, and would instead support decisions related to schedule, construction methods, resource allocation, and communication strategies with other stakeholders. Thus, the structured incorporation of biodiversity into project management would contribute to anticipating impacts, reducing uncertainties, and improving project performance throughout its lifecycle, aligning environmental practices with good project management practices.

The application of the proposed model to an infrastructure project showed that the early consideration of biodiversity as an indirect stakeholder can contribute to the reduction of conflicts, rework, and non-conformities, in addition to favoring alignment with corporate governance and sustainability practices. In this regard, it is recommended that infrastructure projects promote the explicit representation of biodiversity in the stakeholder management plan, formally linking it to institutional representatives, such as environmental agencies, socio-environmental teams, and technical specialists. Additionally, it is suggested to include biodiversity indicators in project reports, systematically discuss environmental impacts and risks in management forums, and integrate the results of environmental programs into the project’s decision-making processes.

In this way, environmental monitoring ceases to have a merely technical or regulatory character and begins to assume a managerial purpose, transforming environmental data into relevant inputs for risk management. This approach allows for the anticipation of impacts that may result in delays, additional costs, institutional conflicts, or reputational damage, in addition to supporting schedule adjustments, revision of construction methods, cost management, and redefinition of engagement strategies with other stakeholders. The proposed approach does not replace environmental licensing instruments but complements them, promoting greater coherence between the technical, environmental, and managerial dimensions of infrastructure projects. The presented model has an applied and flexible character, and can be adapted to different types of projects and organizational contexts, which expands its potential for practical use by project management professionals.

This study also raises a critical question regarding the effectiveness of biodiversity representation through institutional stakeholders. It is questioned to what extent these actors, especially regulatory bodies, actually represent ecological interests, and not primarily political, economic, or institutional interests. Although such entities play a formal role in environmental protection and in mediating between development and conservation, their actions are embedded in complex decision-making contexts, often influenced by pressures for project feasibility, regulatory deadlines, and public policy guidelines. As a result, biodiversity representation may become partial or limited, restricted to meeting minimum legal requirements, to the detriment of a broader and more strategic consideration of ecological impacts. This limitation reinforces the need for complementary mechanisms for integrating biodiversity into stakeholder management, which do not rely exclusively on its indirect representation by institutions, but incorporate it more explicitly and structurally into the project’s decision-making processes.

The results show that the project adopts consolidated environmental management practices, especially in meeting the requirements of environmental licensing and in implementing programs for mitigation, control, and compensation of socio-environmental impacts. The Environmental Impact Statement [EIS] presents a detailed diagnosis of impacts on the physical, biotic, and anthropic environments, providing relevant information for the environmental monitoring of the undertaking. However, from the perspective of project management, it is observed that these impacts are predominantly treated as legal requirements, rather than as strategic elements of the stakeholder management process. Biodiversity, although widely characterized in environmental studies, is not explicitly recognized as a stakeholder in the formal process of identifying, analyzing, and planning stakeholder engagement. The application of the assessment framework also showed that the consideration of biodiversity in the studied project is predominantly at a reactive level, characterized by compliance with legal requirements and the execution of environmental programs, with low integration into stakeholder management and risk management.

In this context, the influence of biodiversity on the project occurs indirectly, mediated by environmental agencies, regulatory standards, and legal conditions, which characterizes a predominantly reactive approach. This approach contrasts with the recommendations of the PMBOK, which highlight the importance of comprehensive and early identification of stakeholders, especially those associated with relevant project risks. The absence of biodiversity as a formally recognized indirect stakeholder limits the integration between environmental management, stakeholder management, and risk management, reducing the potential for anticipating impacts, defining more effective engagement strategies, and improving overall project performance throughout its lifecycle. The provocation proposed by this work by using the expression “invisible stakeholder” does not seek to assert that biodiversity should necessarily be framed as a formal stakeholder in the traditional PMBOK mold, but rather to highlight a recurring gap in the practice of infrastructure project management. Even though its interests are represented by intermediate stakeholders – such as environmental agencies, regulatory standards, and conservation units –, biodiversity remains absent as an explicit reference in the process of identifying, analyzing, and planning stakeholder engagement. This absence contributes to its interests being treated in a fragmented, predominantly technical, and reactive manner, hindering their strategic integration into stakeholder and risk management processes.

Thus, the concept of biodiversity as an “invisible stakeholder” serves as an analytical resource to draw attention to the fact that, although central in terms of impact and risk, the biotic environment does not hold a position equivalent to its relevance in the formal project management instruments. By making this invisibility explicit, the study reinforces the need to strengthen the mechanisms for representing and integrating environmental interests into project governance, aligning environmental management with good project management practices. In this way, biodiversity ceases to be merely a regulatory requirement to be met and begins to be recognized as a strategic interest, whose early and structured consideration can contribute to risk mitigation, improved project performance, and the sustainability of its results throughout its life cycle. The analysis also reinforces the importance of understanding sustainability as a transversal element to project management, and not just as a requirement associated with environmental licensing or regulatory compliance. From this perspective, strategic stakeholder management plays a fundamental role by enabling the identification, representation, and consideration of interests that might otherwise remain less visible in decision-making processes, such as those related to biodiversity and the long-term environmental impacts. Engagement tools, such as public consultations, social participation mechanisms, and structured communication and dialogue processes with stakeholders, contribute to a broader understanding of the risks and opportunities associated with the project, favoring more informed and balanced decisions. Thus, effective stakeholder engagement strengthens the integration between sustainability and project management, contributing to the mitigation of socio-environmental impacts and the generation of value throughout the entire life cycle of the undertaking.

As a main contribution, this study demonstrates that biodiversity, although traditionally neglected in project management, can be incorporated in a structured way as an indirect stakeholder, aligning with the best practices recommended by the PMBOK. The consideration of biodiversity as a stakeholder, integrated into the processes of identification, planning, management, and monitoring of stakeholder engagement, contributes to strengthening risk management, expanding the predictability of impacts, and supporting more informed and strategic managerial decisions. The application of the proposed model to an infrastructure project showed that the early consideration of biodiversity as an indirect stakeholder can contribute to the reduction of conflicts, rework, and non-conformities, in addition to favoring alignment with corporate governance and sustainability practices. In this regard, it is recommended that infrastructure projects promote the explicit representation of biodiversity in the stakeholder management plan, formally linking it to institutional representatives, such as environmental agencies, socio-environmental teams, and technical specialists. Additionally, it is suggested to include biodiversity indicators in project reports, systematically discuss environmental impacts and risks in management forums, and integrate the results of environmental programs into the project’s decision-making processes. This approach allows for anticipating impacts that may result in delays, additional costs, institutional conflicts, or reputational damage, in addition to supporting schedule adjustments, revision of construction methods, cost management, and redefinition of engagement strategies with other stakeholders.

In summary, the results of this case study indicate that, despite biodiversity being widely considered in the environmental studies of the analyzed infrastructure project, its integration into stakeholder management occurred in a limited and predominantly reactive manner. The absence of explicit recognition of biodiversity as an indirect stakeholder, with low power and high interest, led to a “monitoring” engagement strategy instead of the recommended “keep informed,” which restricts its influence on decision-making processes. This gap reduces the potential for risk anticipation and project performance improvement, reinforcing the need to incorporate biodiversity in a structured and strategic way into stakeholder management, through formal mechanisms for representation and integration of environmental information into managerial processes, to promote more proactive and sustainable management.

4. Conclusion

This study sought to analyze how biodiversity is considered in stakeholder management in infrastructure projects, in light of PMBOK best practices. It was found that, although biodiversity has been widely addressed in the environmental studies of electric power transmission line projects, its integration into stakeholder management occurred in a limited and predominantly reactive manner. The findings indicated that the consideration of biodiversity focused on meeting legal requirements, mediated by regulatory bodies, without explicit recognition as an indirect stakeholder. When applying the power and interest matrix, it was identified that biodiversity has low power and high interest, but the engagement strategy practiced was “monitoring”, diverging from the PMBOK recommendation of “keep informed”. This approach resulted in environmental information being restricted to the technical sphere, with limited integration into the project’s strategic decision-making and risk management processes.

The main contribution of this work lies in the proposition of an analysis framework that allows the structured incorporation of biodiversity as an indirect stakeholder in project management, aligning with PMBOK best practices. This approach demonstrated potential to strengthen risk management, broaden impact predictability, and support more informed and strategic managerial decisions, contributing to the reduction of conflicts and non-conformities. It is recommended that infrastructure projects promote the explicit representation of biodiversity in stakeholder management plans, linking it to institutional representatives and specialists, and include biodiversity indicators in reports, with systematic discussion in management forums. However, the study was limited by the analysis of a single project and the use of secondary documentary sources, which restricts the generalization of the results. Additionally, a critical reflection emerged on the effectiveness of institutional stakeholders representing ecological interests. For future studies, it is suggested to expand the application of the proposed model to other projects, explore quantitative analyses of the generated benefits, and deepen the integration of biodiversity with risk management processes.

Bibliographic References

CONVENÇÃO SOBRE A DIVERSIDADE BIOLÓGICA (CBD), 2006. Convention Text – Article 2: Use of Terms. 2006. Disponível em: https://www.cbd.int/convention/articles/?a=cbd-02. Acesso em: 14 mar. 2026. [cbd.int]

IPBES. Global Assessment Report on Biodiversity and Ecosystem Services. Bonn: Intergovernmental Science-Policy Platform on Biodiversity and Ecosystem Services, 2019. Disponível em: <https://ipbes.net/global-assessment>. Acesso em: 15 dez. 2025.

PROJECT MANAGEMENT INSTITUTE. Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK®). 6. ed. Newtown Square, PA: Project Management Institute, 2017.

PROJECT MANAGEMENT INSTITUTE. Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK®). 7. ed. Newtown Square, PA: Project Management Institute, 2021.

WEF. Nature Risk Rising: Why the Crisis Engulfing Nature Matters for Business and the Economy. Geneva: World Economic Forum, 2020. Disponível em: <https://www.weforum.org/reports/nature-risk-rising>. Acesso em: 15 dez. 2025.

WWF. 2025. WORLD WILDLIFE FUND. What is Biodiversity? 2025. Disponível em: https://www.worldwildlife.org/resources/explainers/what-is-biodiversity/. Acesso em: 14 mar 2026.

WWF. Living Planet Report 2022: Building a Nature-Positive Society. Gland: World Wide Fund for Nature, 2022. Disponível em: <https://wwf.panda.org>. Acesso em: 15 dez. 2025.

Yin, 2018 [Full reference not found in the original document]

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.