October 19, 2026
Sequencing in propulsion system calibration projects: comparison between primary and derivative projects
Sequencing in Propulsion System Calibration Projects: Comparison between Primary and Derivative Projects
Rogério Gonçalves Ribeiro Junior; Paula Regina Fortes
DOI: 10.22167/2675-6528-202601394
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
The global automotive industry is undergoing significant transformations, making the calibration of propulsion systems a strategic and critical process. The study proposed a comparative analysis of activity sequencing in primary and derivative calibration projects, aiming to identify how technical maturity influences engineering effort and schedule compression. The methodology employed a dual case study, based on documentary analysis of Work Breakdown Structures (WBS), Precedence Diagramming Methods (PDM), and risk management strategies, collecting data from an automotive organization. The results demonstrated that the reuse of technical assets allowed the conversion of calibration activities into validation tasks, reducing the scope and variability of the effort. A significant compression of the total cycle, from 22 to 12 months, was observed in derivative projects, reflecting the transition from active development to validation. However, areas such as emissions and on-board diagnostics (OBD) still required active calibration due to legal compliance and system sensitivity, remaining on the critical path. It was concluded that strategic sequencing, supported by Quality Gates, promoted a more efficient resource allocation and *lead-time* compression in the conceptual phases. The mitigation of residual risks proved essential to ensure schedule predictability and technical compliance until the start of production (SOP), offering a conceptual basis for engineering managers to adjust sequencing models according to the maturity of each project.
Keywords: Schedule Management; Risk Management; Automotive Industry; Control Milestones; Technical Maturity.
1. Introduction
The global automotive industry is undergoing a period of profound transformations, driven by increasingly stringent environmental regulations, the growing vehicle electrification, and the incessant demand for greater energy efficiency and performance (CONAMA, 2018). In this dynamic scenario, the development and calibration of propulsion systems remain one of the most strategic and complex pillars of product engineering. Calibration, which involves the optimization of thousands of parameters to ensure compliance with regulatory and functional requirements for emissions, consumption, drivability, and durability, is an indispensable step in the vehicle lifecycle (Wasserburger et al., 2021). Specialized multidisciplinary teams work on the calibration of modern propulsion systems (Schmidt et al., 2023), but the complexity of interdependencies between these disciplines, often non-sequential and with constant iterations, challenges traditional project management models (Lukas et al., 2021).
Project management literature offers a wide range of consolidated models and tools for activity sequencing, such as the Critical Path Method (CPM) and various schedule compression techniques (PMI, 2021). However, the isolated application of these generic approaches often proves insufficient to capture the complexity inherent in Research and Development (R&D) environments within the automotive industry. The dynamic is amplified by the dual nature of calibration projects: primary projects, characterized by a high degree of technical innovation and uncertainty, and derivative projects, which focus on optimizing and reusing organizational process assets. In primary projects, the absence of a prior calibration base demands greater flexibility and adaptability in the face of technical unpredictability, whereas in derivative projects, the existence of a known calibration allows for more predictive planning and the adoption of more aggressive parallelism strategies, such as “fast-tracking”. This distinction imposes specific challenges on scope and time management, where technical variability in primary projects directly impacts the accuracy of duration estimates and risk management, while in derivative projects, the challenge lies in the effective management of “carryover” and resource allocation.
Industry practice shows that the reuse of technical assets and the accumulated knowledge from previous projects allow for a significant reconfiguration of engineering effort. In many cases, active calibration activities can be converted into validation and revalidation tasks, resulting in a notable reduction in the scope and variability of the required effort. This strategic transition has demonstrated the ability to significantly compress the total development cycle, with practical examples indicating deadline reductions from 22 to 12 months in derivative projects, reflecting the shift from an active development stage to a greater focus on validation. However, this optimization does not apply uniformly to all areas. Critical sectors such as emissions calibration and onboard diagnostics (OBD) often continue to require substantial active calibration, even in derivative projects. This is due to strict legal compliance and the high sensitivity of these systems, which keep them on the project’s critical path, regardless of the overall technical maturity level of the project. Effective management of these inflection points is crucial for schedule predictability and technical compliance.
Given the complexity and criticality of activity sequencing in propulsion system calibration projects, especially in distinguishing between approaches for primary and derivative projects, it becomes imperative to deepen the understanding of how technical maturity influences engineering effort and schedule compression. The gap in the specialized literature regarding how sequencing strategies align with the degree of project uncertainty in the automotive context justifies the relevance of this study. Thus, the present article aims to comparatively analyze the sequencing of activities in primary and derivative calibration projects, seeking to identify how technical maturity impacts engineering effort and schedule compression, offering a conceptual basis for optimizing schedule management and resource allocation in the automotive sector.
2. Material and Methods
This research was characterized as a study of an applied nature, with exploratory and descriptive objectives, under a predominantly qualitative approach. The methodological design adopted consisted of documentary research, structured in the form of a comparative double case study. The choice of this method was justified by the need to investigate complex phenomena in their real context, allowing an in-depth analysis of project management strategies adopted in distinct scenarios, according to the nature of automotive calibration projects.
Data collection was carried out through documentary survey in a database of an organization in the automotive sector, located in the city of Guarulhos, in the state of São Paulo. The analysis period for completed projects covered a development cycle of up to 34 months, according to the established control milestones. The unit of analysis consisted of two propulsion system calibration projects, which were selected and anonymized for the study.
The sample was intentionally selected, comprising two completed propulsion system calibration projects. The motivation for this choice stemmed from the opportunity to compare two products from the same client that had a direct technical succession relationship. The primary project (Case A) served as the basis for the development of the derivative project (Case B), allowing for the isolation of the impact of reusing technical assets on schedule management and ensuring an effective comparison between different levels of uncertainty.
Case A was characterized as a primary project, marked by a high degree of technical uncertainty and the absence of a previous calibration base. In contrast, Case B was defined as a derivative project, with a low degree of uncertainty, as it started from an already known base calibration. This distinction was crucial for the comparative analysis of sequencing strategies and interdependence management.
For data collection, several project management instruments were used, obtained through documentary survey. The Project Charters (TAP) were analyzed to validate the initial scope, the “carryover” assumptions, and the strategic objectives established in the initiation phase. These documents served as the basis for subsequent planning decisions, differentiating the strategic guidelines between the primary and derivative projects.
The Work Breakdown Structure (WBS) was applied as a fundamental tool for Scope Management. Through it, the hierarchical decomposition of technical deliverables into comparable work packages was carried out. This structuring allowed for the identification, within the areas of Base, Emissions, Drivability, On-Board Diagnostics (OBD), and Robustness, of which fronts the scope could be simplified from “calibration” to “validation”, without compromising the integrity of the final product.
The Precedence Diagramming Method (PDM) was employed for the construction of the schedule model, establishing the logical relationships between project activities (Project Management Institute [PMI], 2021). The PDM was applied to connect the work packages defined in the WBS (Work Breakdown Structure), determining the finish-to-start (FS) dependencies between the base calibration, emissions, and diagnosis phases, and the start-to-start (SS) relationships for the anticipation of validation tasks.
The schedule and Gantt chart were used to present the activities linked with planned dates, durations, and milestones. Based on the scope defined in the WBS (Work Breakdown Structure), this tool allowed for the analysis of activity sequencing and the measurement of schedule compression. It was identified how prior technical maturity influenced the critical path in the derived projects compared to the primary ones, providing a visual representation of interdependencies.
Risk Management was employed to identify, analyze, and plan responses to project uncertainties. The tool assessed how the organization dealt with the technical variability inherent in calibration, focusing on schedule risks, specifically the risk of error in “carryover” assumptions. It was observed how mitigation strategies, such as reinforcing resources at critical milestones, were structured to ensure compliance with the “Start of Production” (SOP).
Status Reports and “Quality Gates” Meeting Minutes comprised the project’s monitoring, control, and communication system. These “Quality Gates” functioned as phase control milestones, used to compare planned progress with executed progress. They allowed for the identification of mitigation strategies for schedule risks and operational bottlenecks, especially when “carryover” assumptions were not confirmed during execution.
The data processing followed the precepts of content analysis, according to the methodology proposed by Bardin (2016). The analytical process comprised four fundamental stages. The first stage, data organization, consisted of pre-analysis with the selection and floating reading of documents. Subsequently, in the coding stage, raw data was transformed into recording units, classifying them between calibration and validation.
The third stage of the analytical process was categorization, where the data were grouped by specific themes, such as Base, Emissions, Driveability, On-Board Diagnostics (OBD), and Robustness. Finally, the fourth stage consisted of inference and interpretation, which involved a critical analysis of the results obtained and the confrontation of these findings with the previously established objectives for the work, seeking to extract meanings and patterns.
The ethical procedures included the anonymization of the two calibration projects studied, ensuring the confidentiality of the organization’s information and technical data. The validity of the research was assured by triangulating documentary sources, cross-referencing information from the Project Charters, Work Breakdown Structures, and schedules with records from the “Quality Gates” Meeting Minutes and Status Reports. This approach mitigated potential documentary gaps, ensuring convergent evidence on the sequencing strategies adopted.
3. Results and Discussion
The scope of this documentary analysis meticulously focused on the engineering activities of the software and hardware development phases, delimiting a strategic temporal cut-off between the start of calibration (CQG 0) and the start of production (“Start of Production” – SOP). This delimitation was not arbitrary; it allowed for an in-depth investigation of the project’s most critical lifecycle, where schedule management is intrinsically more sensitive to technical uncertainties and the inherent complexities of developing automotive propulsion systems. The choice of this interval reflects the understanding that decisions made and strategies implemented in these phases have a disproportionate impact on the predictability, cost, and quality of the final product, aligning with the view that R&D project management requires a sharp focus on the initial stages of conception and validation (Lukas et al., 2021).
To enable this comparative and robust analysis, the governance structure of the studied company organizes the work in a modularized and hierarchical logic, based on five main technical fronts: Base, Emissions, Steerability, On-Board Diagnostics (OBD), and Robustness. This division is not merely organizational but functions as the base Work Breakdown Structure (WBS), a fundamental artifact of scope management as advocated by the Project Management Institute (PMI, 2021). Each of these technical fronts represents a distinct work package, with specific deliverables and interdependencies that, when integrated, feed into the project’s master schedule. The decomposition of work into manageable packages is crucial for the complexity of automotive calibration, allowing multidisciplinary teams to act in a coordinated manner, but with sufficient autonomy to address the specific technical challenges of their areas, while maintaining a holistic view of project progress.
The integration between these work packages is governed by the Precedence Diagramming Method (PDM), an essential technique for building the schedule model that establishes the logical relationships between project activities (PMI, 2021). The PDM, in this context, not only defines the sequence in which tasks should be executed but also differentiates between Finish-to-Start (FS) dependencies, where a successor activity can only begin after the preceding one is completed, and Start-to-Start (SS) relationships, which enable technical parallelism and phase overlap. This latter practice, known as “fast-tracking”, is a schedule compression strategy that, although it may introduce additional risks, is frequently employed in R&D environments to accelerate development and reduce time to market. The application of PDM allows for sophisticated workflow modeling, where areas such as Emissions and Drivability can initiate their activities out of sync with Base Calibration, optimizing the engineering flow without compromising final integration on critical milestones, such as Robustness. This flexibility in sequencing is a competitive differentiator, allowing the organization to adapt its execution strategies to the nature and complexity of each project, as illustrated in Figure 1.
Source: Original research results
Figure 1. PDM diagram of technical areas
Figure 1 visually demonstrates the complex network of interdependencies between the different technical areas. The presence of Start-Start (SS) relationships between “Base” and “Emissions” or “Steerability” is a clear example of how “fast-tracking” is implemented. This overlap of activities, although requiring rigorous coordination and accurate risk management, is fundamental for schedule compression in projects with high complexity and tight deadlines, such as those in the automotive industry. Project management literature corroborates that the application of schedule compression techniques, such as “fast-tracking”, can be effective in reducing project duration, but requires careful analysis of associated risks, such as an increased probability of rework and the need for intensified communication (PMI, 2021). In the context of automotive calibration, where technical interdependencies are intrinsic and often non-sequential (Lukas et al., 2021), PDM modeling allows the organization to navigate these complexities, balancing the need for agility with the assurance of quality and technical compliance. The practical implication is that the engineering team can start calibration and validation tasks in parallel, provided that critical dependencies are monitored and the risks of incompatibility or rework are proactively mitigated.
From this network of precedences and interdependencies, the flow of activities is governed by control milestones called “Calibration Quality Gates” (CQG). These CQGs are not just checkpoints, but function as critical interfaces that ensure technical maturity and regulatory compliance at predefined stages of the project. The interfaces between these milestones and the positioning of technical areas throughout the project lifecycle are detailed in Figure 2, which offers a visual representation of the progression and control points.
Source: Original research results
Figure 2. CQG Interface
Figure 2 illustrates how the different technical fronts (Base, Emissions, Driveability, OBD, Robustness) align with the CQGs over time. For example, Base calibration tends to be one of the first to start and be completed, serving as the foundation for the others. Emissions and Driveability may have longer and overlapping activity windows, while OBD and Robustness tend to focus on the more advanced stages of the project, when system maturity is higher. This visualization is crucial for the project manager, as it allows for the identification of potential bottlenecks, optimization of resource allocation, and assurance that quality and performance requirements are met at each stage. CQG management is a robust practice that aligns with project control principles, where progress is measured against predefined milestones to ensure the project stays on track in terms of scope, time, and cost (PMI, 2021). The practical relevance lies in the ability to anticipate problems, realign strategies, and make informed decisions before deviations become critical, minimizing the impact on “time-to-market” and regulatory compliance.
The definition of the calibration schedule uses the reverse planning technique, starting from the final production start milestone (“Start of Production” [SOP]). This approach is particularly effective in projects with fixed deadlines and strict regulatory requirements, such as those in the automotive industry, where SOP is a non-negotiable milestone. Table 1 presents the systematization of these milestones (CQGs), establishing the necessary time windows to ensure software and hardware maturity.
Table 1. “Calibration Quality Gates” – CQG’s
|
CQG’s |
Description |
Conclusion |
|
CQG -2 |
Definition of the concept of hardware and its goals |
-34 Months |
|
CQG -1 |
Definition of software requirements |
-28 Months |
|
CQG 0 |
Calibration Start |
-22 Months |
|
CQG 1 |
Calibration for first durability (on bench) |
-19 Months |
|
CQG 2 |
Vehicle calibration start |
-17 Months |
|
CQG 3 |
Hardware confirmation (hardware freeze) |
-15 Months |
|
CQG 4 |
Base Calibration Finalization (bench), first emissions handover for OBD, OBD fleet start |
-12 Months |
|
CQG 5 |
Emissions calibration at 75%, climate calibration completed |
-10 Months |
|
CQG 6 |
End of calibration |
-6 Months |
|
CQG 7 |
Validation with production hardware |
-4.5 Months |
|
CQG 8 |
OBD validation with production hardware |
-3 Months |
|
SOP |
End of the OBD fleet |
0 Months |
Source: Original research results
Table 1 details the sequence and timing of the CQGs, from the definition of the hardware concept (CQG -2, -34 months before SOP) to the end of the OBD fleet (SOP, 0 months). These deadlines reflect the technical reliability and legal compliance requirements for global projects, serving as the baseline for comparing efficiency between Cases A and B. The existence of a reverse schedule, anchored in quality milestones, is a project management practice aimed at ensuring the delivery of complex products within established deadlines and quality standards. Project management literature emphasizes the importance of control milestones for monitoring progress and making corrective decisions (PMI, 2021). In the context of automotive calibration, where compliance with emissions regulations (CONAMA, 2018; Brazil, 2018) is critical, each CQG represents an opportunity to verify adherence to requirements and mitigate risks of non-compliance. The practical implication is that the project team has a clear view of the path forward, with defined control points that allow for regular progress assessments and strategic adjustments, ensuring that the necessary technical maturity is achieved in each phase before moving on to the next. For example, CQG 4, which marks the completion of Base Calibration and the first emissions “handover” to OBD, is a crucial turning point, as it consolidates the technical foundation for subsequent phases and initiates the integration of more complex systems.
For the comprehension of the presented results, it is fundamental to explain the managerial logic that integrates the project management tools applied in this study. This flow begins with the Work Breakdown Structure (WBS), which organizes the scope of work into specific technical packages. These packages, in turn, feed the schedule responsible for establishing task dependencies and defining control milestones called “Calibration Quality Gates”. Structured in this way, the milestones allow for rigorous project monitoring, culminating in the use of a progress metric that links physical advancement to the expected technical maturity at each stage. This integrated approach, which connects scope (WBS), schedule (PDM/Gantt), and control (CQGs), is a pillar of effective project management, ensuring that all project dimensions are managed cohesively and aligned with strategic objectives (PMI, 2021).
In this context, the measurement of activity progress is carried out according to the maturation levels established in Table 2. This standardization is essential for clear and consistent communication about the project status, both internally and with external stakeholders.
Table 2. Standardization of activity progress
|
Status Percent |
Description |
|
0 |
Not started |
|
25 |
Pre-calibrated |
|
50 |
Calibrated |
|
75 |
Verified |
|
90 |
In continuity (“carryover”) |
|
100 |
Complete |
Source: Original research results
Table 2 presents a status scale ranging from “Not started” (0%) to “Completed” (100%). Among the classifications presented, the 90 percent status, defined as “carryover”, plays a central role in distinguishing between the cases studied. This index characterizes activities that have a high degree of technical maturity inherited from previous projects, requiring only continuity and punctual adjustments. From a management perspective, this classification allows for the segregation of technical effort and optimization of the schedule by prioritizing the release of resources for calibration tasks that present greater complexity and a high risk of rework. The concept of “carryover” is a key element in the management of derivative projects, as it represents the capitalization of knowledge and technical assets developed in previous projects. The literature on Knowledge Management and innovation highlights the importance of asset reuse for efficiency and cost reduction in R&D (Schmidt et al., 2023; Wasserburger et al., 2021). The practical implication is that, by identifying activities with high “carryover” potential, project managers can reallocate resources more strategically, concentrating specialists in areas that require active calibration and innovation, while validation activities can be executed with less effort and in less time, accelerating the overall development cycle.
The organization of the work scope is fundamental for project governance, being structured through the Work Breakdown Structure (WBS). This tool organizes deliverables into modular technical packages, ensuring that the calibration effort is systematically decomposed and aligned with project control milestones. The visual representation of the WBS, consolidated in Figure 3, details this technical hierarchy, serving as the foundation for the integration of the Base, Emissions, Drivability, On-Board Diagnostics (OBD), and Robustness areas.
Source: Original research results
Figure 3. Work Breakdown Structure
Figure 3 illustrates the hierarchical decomposition of the calibration work into its smaller components, from the major technical areas to specific work packages, such as “Data Setup” in Base Calibration or “Lambda and O2 Sensors Control” in Emissions. This granularity allows for detailed scope management, facilitating responsibility assignment, effort estimation, and dependency identification. The WBS (Work Breakdown Structure) is a universally recognized tool in project management for its ability to provide a clear view of what needs to be delivered, preventing “scope creep” and ensuring all stakeholders have a common understanding of the work to be performed (PMI, 2021). In the automotive context, where technical complexity is high, a well-defined WBS is indispensable for demystifying the project and making it manageable. The practical implication is that the WBS serves as a roadmap for project execution, allowing engineering teams to focus on their specific deliverables, while the project manager maintains an integrated view of the whole, facilitating coordination and decision-making.
Once the scope was defined via WBS (Work Breakdown Structure), the temporal execution dynamics were established by the Precedence Diagramming Method (PDM), which guided the elaboration of comparative schedules between the Primary Project (Case A) and the Derived Project (Case B). The analysis of these schedules reveals a significant compression of the total cycle, from 22 to 12 months. This reduction is not solely due to the reconfiguration of the precedence network, but fundamentally to the alteration in the nature of the technical effort: while in Case A active calibration (developing parameters from scratch) predominates, in Case B the high incidence of “carryover” activities shifts the focus to parameter validation and revalidation, significantly reducing the cycle time. This transition from “calibration” to “validation” is a direct reflection of the inherited technical maturity and the utilization of assets from previous projects, which aligns with literature advocating for the reuse of components and knowledge to optimize product development (Schmidt et al., 2023). The practical implication is that derived projects, by capitalizing on pre-existing knowledge, can be executed with greater agility and efficiency, freeing up resources for more innovative projects or for optimizing other aspects of development.
To deepen this comparison, the detailed analysis of the technical fronts individually discusses the performance of each area. The focus is on how the reuse of calibration parameters alters the engineering effort in the areas of Base, Emissions, Driveability, OBD, and Robustness, contrasting the linearity of Case A with the resource optimization observed in Case B.
In the Base Calibration, the comparative analysis began with the Project Opening Terms (TAP), documents that establish the strategic guidelines for each venture. In Case A (Primary), the TAP defines premises of high uncertainty and the need for integral development of new functionalities, requiring a ground-up creation approach. In contrast, in Case B (Derivative), the TAP formalizes the objective of technical reuse (“carryover”), establishing cost and development time reduction as the central goal. This distinction in guidelines at the executive level justifies why, in the subsequent Project Breakdown Structure (WBS), Case B presents a scope focused almost exclusively on validation. This scope transition is evidenced in the Base Calibration package, where Case B is strictly limited to verification activities. While Case A required the complete development of air, fuel, and thermal management models, Case B demanded only the verification of these parameters in a new environment. Under the PMBOK management logic, this movement characterizes the efficient use of Organizational Process Assets (OPAs) whose physical models and consolidated databases developed during Case A become valuable assets that reduce planning and execution effort in the derivative project. As a result, there is an optimization in the use of specialized resources. From a management perspective, this transition from “Calibration” to “Validation” is what allows for the reduction of the critical path in the derivative project schedule, as it eliminates the trial-and-error changes inherent in ground-up modeling. Project management literature frequently discusses the importance of OPAs as valuable resources that can be reused to improve the efficiency and effectiveness of future projects (PMI, 2021). The application of this principle in automotive calibration demonstrates a strategic alignment between theory and practice, where knowledge and data generated in a primary project are systematically capitalized to accelerate the development of derivative projects. The practical implication is the ability to significantly reduce development time and associated costs, while maintaining quality and technical compliance, as the validation of existing parameters is inherently less risky than creating new ones.
Unlike Base Calibration, the Emissions package presents greater complexity in the derived project. The technical workload in Case B is higher in certain activities, as emissions control and driving cycle variables prevent the full reuse of data. Areas such as “Lambda Control and O2 Sensors” and “Cycle and RDE Optimization” remain in the Calibration status in both cases. This need for new technical intervention stems from the after-treatment system’s sensitivity to variations, even in derived platforms. For the project manager, this data is crucial for feeding the WBS (Work Breakdown Structure), as it indicates that the Emissions package will not undergo the same deadline compression observed in Base Calibration. Consequently, Resource Management must foresee the allocation of specialists for a prolonged period in this area, since the critical path of the derived project is dictated by the complexity of emissions standards and not by the mechanical base. The persistence of the need for active calibration in emissions areas, even in derived projects, underscores the critical influence of environmental regulations (CONAMA, 2018; Brazil, 2018) on the scope and engineering effort. The literature on automotive engineering and regulatory compliance frequently highlights the complexity and iterative nature of emissions calibration, which requires continuous optimization to meet increasingly stringent standards (Wasserburger et al., 2021). The practical implication for project management is the need for a differentiated approach to work packages sensitive to regulations. This means that, even in a “carryover” context, resource and schedule planning for emissions must be as robust as in a primary project, with safety margins and the allocation of high-level specialists to mitigate the risks of non-compliance and delays. Failure to recognize this complexity can lead to operational bottlenecks and an unexpected increase in the critical path of the derived project.
The areas of Driveability, OBD, and Robustness show similar behavior in Case B, with a significant scope reduction, albeit with important nuances. In Driveability, data interpretation reinforces that idle stability and starting strategies could be migrated for validation in Case B due to hardware similarity. This result directly feeds the subsequent schedule, allowing the engineering team to initiate field phases earlier compared to the primary project. The ability to convert calibration activities to validation in these areas demonstrates the value of “carryover” in optimizing sequencing and accelerating development. Literature on automotive product development frequently addresses the importance of modularity and platform reuse to achieve efficiency and agility (Schmidt et al., 2023). The practical implication is the freeing up of time and resources that can be directed to other more critical areas or to the optimization of other vehicle aspects, in addition to allowing an earlier start to field testing, which can provide valuable feedback for fine-tuning.
Subsequently, the On-Board Diagnostics (OBD) package reveals that technical complexity manifests itself again in specific points. Although the risk plan is not an isolated artifact, governance is implicitly revealed in the response to the technical challenges of each scenario. In Case A, uncertainty regarding homologation is mitigated by a dense sequencing of active calibration, ensuring data robustness from the base. In contrast, in Case B, the “carryover” strategy acts as a response to the risk of schedule delay, using already consolidated parameters to gain agility. However, the criticality of legal compliance in emissions prevents simplified data reuse; this technical barrier forces the manager to keep such activities on the critical path, even in projects of a derivative nature. This is particularly evident in activities such as “Emissions Monitoring” within the OBD package, which, similarly to the Emissions package, remains an active calibration activity in Case B. The need for continuous calibration for “Emissions Monitoring” in OBD, even in derivative projects, reinforces the idea that regulatory compliance is a driver of complexity that transcends the maturity of the base platform. The literature on on-board diagnostic systems emphasizes the rigor of homologation requirements and the need for extensive testing to ensure compliance (Wasserburger et al., 2021). The practical implication is that, although “carryover” can accelerate many parts of the project, the project manager must identify and protect critical legal compliance activities, ensuring they receive the necessary resources and attention, even if this means less aggressive sequencing in these areas.
Finally, Robustness activities consolidate the project’s final validation flow. The data demonstrate that, in derivative projects, the Robustness phase becomes the main focus of the schedule. The substitution of creation effort by fleet verification and production inspection highlights the product’s technical maturity, allowing for a more predictable project closure with a lower rate of technical rework. This shift in focus to final validation in derivative projects is a testament to the effectiveness of “carryover” and knowledge management. Product engineering literature highlights that the validation phase is crucial for ensuring product quality and reliability before launch (Schmidt et al., 2023). In derivative projects, where the technical base is more stable, the Robustness phase can be more focused and efficient, capitalizing on accumulated data and experience. The practical implication is that the project team can concentrate its efforts on quality assurance and last-minute risk mitigation, rather than dealing with development uncertainties. This leads to a smoother project closure process and a more robust and reliable final product, with a lower probability of post-launch issues.
The synthesis of results in the technical areas showed that technical variability is the main risk factor for the schedule. As systematized, the organization mitigates these uncertainties through governance based on “Quality Gates”. While Case A prioritizes active calibration as a response to development uncertainty, Case B uses parameter reuse as a delay risk mitigation strategy. This approach demonstrates that risk management is not just reactive, but a layer of protection integrated into the sequencing logic of each project. The failure in the “carryover” premise, for example, is mitigated by a realignment via “Quality Gates”, which demonstrates the adaptability of the project control system. The complexity in Emissions/OBD, which represents a risk of legal non-compliance, is addressed by anticipating specialized resources, indicating a proactive talent allocation strategy. Technical rework, which can increase the calibration cycle, is mitigated by virtual prototyping and bench testing, emphasizing the importance of early validations and the use of simulation tools to reduce the need for extensive and expensive physical tests. This multifaceted approach to risk management, which integrates planning, control, and mitigation tools, is an example of good practices in R&D project management (PMI, 2021). The practical implication is that the organization not only identifies risks but also incorporates response strategies directly into project planning and execution, transforming potential threats into opportunities for optimization and learning.
The results of this study confirm that the strategic differentiation between primary and derivative projects is a determining factor for technical predictability and operational efficiency in the automotive sector. It is concluded that sequencing based on pre-existing technical assets, “carryover”, acts not only as a technical facilitator but as the main vector for schedule optimization in research and development environments. Thus, the objectives of comparing sequencing strategies and managing interdependencies were achieved, demonstrating how technical uncertainty dictates schedule configuration. While the primary project requires dense sequencing of optimization tasks from the initial phases due to the absence of a technical basis, derivative projects allow for real compression of “lead-time” in the concept phases, enabling an early focus on critical certification milestones. This distinction highlights the importance of an adaptive approach in project management, where strategies are shaped by the nature and degree of innovation of the undertaking, as suggested by Lukas et al. (2021) in agile development contexts.
It was noted that the alignment between engineering needs and quality milestones (CQG) results in a significant reduction of the critical path in the derived project. The applied managerial logic demonstrates that the anticipation of compliance milestones is enabled by the simplification of technical dependencies, allowing for a more aggressive sequencing of activities. This dynamic reflects the commitment to delivering value, converting uncertainties into tangible technical assets and maximizing the return on engineering investment. In this process, the integration of management tools, particularly the WBS (Work Breakdown Structure), the PDM, and the “Quality Gates” milestones, proved essential for the organization to transition from exploratory development to high-performance execution in a structured and predictable manner. The synergy between these project management tools is a pillar for effective governance, allowing the complexity inherent in automotive calibration to be managed systematically and controlled (PMI, 2021).
Finally, this work demonstrates that, although the derivative project regime offers greater agility, the monitoring of sensitive areas such as emissions and OBD must remain rigorous. Inherited technical maturity reduces creation effort but does not eliminate the need for careful validation, reaffirming that calibration project management must be adaptive and based on residual risk analysis. This study therefore offers a conceptual basis for engineering managers to adjust their sequencing models according to the maturity of each project, avoiding the common mistake of underestimating the technical complexity of certain fronts even in derivative projects, to ensure the success of the launch at SOP. The ability to discern where “carryover” is fully applicable and where active calibration is still indispensable is a critical competence for project managers in the automotive sector, ensuring that the pursuit of efficiency does not compromise regulatory compliance and the quality of the final product.
4. Conclusion
It is concluded that the objective was achieved by comparatively analyzing the sequencing of activities in primary and derivative calibration projects, and identifying how technical maturity impacts engineering effort and schedule compression in the automotive sector. The results confirm the criticality of strategic differentiation between these projects for technical predictability and operational efficiency. “Carryover”, based on pre-existing technical assets, proved to be the main driver for optimizing R&D schedules, allowing real compression of “lead-time” in derivative projects and early focus on certification. Primary projects, in turn, demand dense optimization sequencing from the initial phases, due to the absence of a technical basis. The integration of WBS (Work Breakdown Structure), PDM, and “Quality Gates” proved essential for a structured transition between exploratory development and high-performance execution, aligning engineering and quality to reduce the critical path.
This study, however, presents limitations due to being a dual case study in a single organization, restricting the generalization of findings. The documentary analysis, although robust, did not capture nuances of real-time dynamics. Even in derivative projects, sensitive areas such as Emissions and On-Board Diagnostics (OBD) maintain high technical complexity, requiring active calibration and rigorous monitoring, which limits the full applicability of “carryover” in these areas. For future studies, it is suggested to expand the research to other organizations and contexts, deepen the quantitative analysis of the benefits of “carryover”, and investigate the long-term impact of “fast-tracking” on post-launch quality and costs. Exploring methodologies to optimize sequencing in areas of high regulatory sensitivity, such as Emissions and OBD, in derivative projects, would be of great value.
Bibliographic References
Bardin, L. 2016. Análise de Conteúdo. 1ed. Edições 70, São Paulo, SP, Brasil.
Brasil. 2018. Resolução N. 492, de 20 de Dezembro de 2018. Altera a Resolução n° 15/1995 Estabelece as Fases PROCONVE L7 e PROCONVE L8 de exigências do Programa de Controle da Poluição do Ar por Veículos Automotores PROCONVE para veículos automotores leves novos de uso rodoviário, altera a Resolução CONAMA n° 15/1995 e dá outras providências. Diário Oficial da União, Brasília, 24 dez. 2018. Seção 1, p. 141.
CONAMA, 2018 [Referência completa não encontrada no documento original]
Lukas, A.; Moerth-Teo, O.; Schwarz, L.; Schnöll, H.; Wolf, M. & Ramsauer, C. 2021. Agile powertrain development: Considerations to incorporate agile principles. MDPI Designs. 5(4): 1-19. DOI: 10.3390/designs5040060
Project Management Institute [PMI]. 2021. Padrão de Gerenciamento de Projetos e Guia do Conhecimento em Gerenciamento de Projetos (Guia PMBOK). 7ed. Project Management Institute, Inc., Newton Square, Pennsylvania, USA.
Schmidt, H.; Büttner, K.; Prokop, G. 2023. Methods for virtual Validação of automotive powertrain systems in terms of vehicle drivability – A systematic literature review. IEEE Access. 11(1): 27043-27065. DOI: 10.1109/ACCESS.2023.3257106
Wasserburger, A.; Didcock, N; Hametner, C. 2021. Efficient real driving emissions Calibração of automotive powertrains under operating uncertainties. Engineering Optimization. 55(1): 140-157. DOI: 10.1080/0305215X.2021.1989589
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq