Article

October 19, 2026

Sequencing of Macro Activities and Schedule Planning in a Credit Cooperative Construction Project

Sequencing of Macro Activities and Schedule Planning in a Credit Cooperative Construction

Roger de Souza Fajardo; Vanderléia de Souza da Silva

DOI: 10.22167/2675-6528-202601396

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The civil construction sector faces increasing demand for efficiency and reduced deadlines, while credit unions expand their physical infrastructure, requiring optimized project management. This study aimed to develop a structured model for macro-activity sequencing and deadline planning in a credit union construction project, with an area of 400m² and a total duration of 180 days. To this end, the PMBOK methodology was used, employing the Work Breakdown Structure (WBS) to decompose the scope and define activity sequencing. The schedule was developed based on precedence relationships (Finish-to-Start and Start-to-Start) and lags, applying a quantitative approach to estimate durations and deadlines. The PDCA (Plan-Do-Check-Act) cycle guided the organization and control of the stages. The results obtained demonstrated that the proposed model organized the construction flow logically, facilitated the identification of interdependencies and critical activities, such as electrical and special installations, and optimized the total execution time. The approach reduced dependence on empirical decisions and increased planning predictability. It was concluded that the application of the WBS and logical activity sequencing constituted an effective strategy for civil construction project planning, offering a solid basis for project management and demonstrating the practical applicability of management methodologies for greater precision and effectiveness in project execution.

Keywords: Civil construction; WBS (Work Breakdown Structure); Latency; Plan-Do-Check-Act; Precedence.

1. Introduction

The civil construction sector is a fundamental economic pillar in Brazil, driving Gross Domestic Product and job creation. The Brazilian Chamber of the Construction Industry (2026) projects continuous growth, stimulated by interest rate reduction and increased real estate credit. However, this expansion demands greater operational efficiency and rigor in meeting deadlines in a competitive market, requiring optimization of resources and costs. In parallel, credit cooperatives have expanded their physical presence in the country, opening new service points for greater capillarity and proximity to members, in contrast to the digitalization of traditional banks (Financial Cooperativism Portal, 2024; G1 and Campos, 2025). The growth of the National System of Credit Cooperatives (SNCC) generates continuous demand for civil works, which need to be executed quickly and economically viably to sustain the competitiveness and expansion of these institutions.

Civil construction projects are intrinsically complex, marked by a multiplicity of stages, diversity of agents, and critical interdependencies. The execution deadline is a sensitive variable, as delays in one task can generate a cascading effect, compromising costs and the final delivery. This complexity demands structured and effective planning. To mitigate these risks, construction planning is crucial, organizing activities in a logical sequence, highlighting interdependencies, and optimizing resource allocation, which increases execution predictability (Mattos, 2010). In this context, the Work Breakdown Structure (WBS), a pillar of the *Project Management Body of Knowledge* (PMBOK), becomes essential by decomposing the scope into manageable parts, facilitating the visualization of deliverables and activities (Tristancho, 2026; Fritzen, 2018). The WBS allows for responsibility assignment (Kerzner, 2017) and integration of scope with the schedule. The logical sequencing of activities, with precedence relationships (Finish-to-Start, Start-to-Start) and lags for schedule adjustments, is vital for constructive fluidity. Additionally, Deming’s (1986) PDCA (*Plan-Do-Check-Act*) cycle guides management as a continuous process of planning, execution, verification, and adjustment, ensuring the monitoring and correction of deviations (Campos, 2004).

Despite the existence of established methodologies, schedule planning in small and medium-sized construction projects, such as those of credit unions, is still often carried out empirically, lacking clear structuring of activity sequencing. This practice results in inconsistent schedules, control difficulties, recurring delays, and excessive reliance on the individual experience of managers, compromising predictability and efficiency. It is therefore crucial to develop a model that systematizes schedule planning and control, reducing subjectivity and increasing effectiveness in the management of civil construction projects. This study is justified by the need to propose a structured approach that optimizes the construction flow and supports more assertive managerial decisions. The objective of this work is to develop a structured model for sequencing macro-activities and planning the schedule for a credit union construction project, aiming to support schedule organization, identification of interdependencies, and improvement of execution time control.

2. Material and Methods

This research was characterized as descriptive, seeking to detail the sequencing of the macro-stages of a construction schedule. A quantitative approach was adopted, based on calculations of durations, latencies, and deadlines of activities, using numerical information for the elaboration of the schedule (Gil, 2019; Lakatos and Marconi, 2017). The study was framed as applied research, as it generated practical knowledge related to the planning and control of deadlines in civil construction. It also had a demonstrative character, limiting itself to the presentation of a single schedule scenario, without any claim of statistical generalization or additional comparative tests.

The study was developed in the context of a civil construction project for a credit cooperative, with an approximate built area of 400.00m². The development, located in Sertãozinho, SP, according to the context of the TCC, had a total execution period of 180 days. The planning and simulated execution period covered from March 23, 2026, to September 18, 2026, according to the elaborated schedule. The unit of analysis consisted of the construction project itself, focusing on the development of a structured model for the sequencing of its macroactivities and deadline planning.

Considering the demonstrative nature of the research, there was no definition of population or sample in the statistical sense. The study focused on a single civil construction project, serving as a case study for the practical application and illustration of methodological concepts. No selection criteria were established for participants or documents, as the focus was on the structuring and sequencing of activities for a specific undertaking. This approach aimed to demonstrate the applicability of the proposed model in a real-world scenario, without the intention of statistical generalization of the results.

For data collection and structuring, the methodology of the *Project Management Body of Knowledge* (PMBOK) was used, with emphasis on the Work Breakdown Structure (WBS) tool. The WBS was employed to organize and represent the constructive stages and their respective precedences, serving as the basis for the schedule sequencing. Initially, the level of detail for activities was defined in a macro phase control, allowing for global management of each project stage. This approach was in line with the best practices of the PMBOK Guide, which defines the WBS as the hierarchical subdivision of the work into manageable components.

The initial planning of the construction phases was structured based on civil engineering logic and integrated into the cycle of the PDCA (*Plan-Do-Check-Act*) methodology, developed by Deming (1986). This integration allowed the schedule to be organized in a way that enables continuous and systematic project control. The PDCA cycle, according to Campos (2004), is essential for transforming plans into concrete results, establishing a process of verification and adjustment. The application of PDCA allowed for planning activities, executing according to the schedule, monitoring deadline compliance, and identifying deviations, as well as implementing corrective actions to ensure delivery within the planned timeframe, as illustrated in

.

The elaboration of the Work Breakdown Structure (WBS) followed a hierarchical decomposition of the project scope. At the most comprehensive level, the project was represented as a whole, synthesizing all deliverables necessary for its completion. At a second level, the project was decomposed into six major deliverables, grouping activities of a similar nature, such as Foundation and Structure, Installations, Enclosures, Finishes, Furnishings, and Finalization. At the third level, the sub-packages and specific activities of each macro-deliverable were detailed, according to the constructive logic of civil engineering, covering tasks up to the third level of detail, as presented in

.

The duration of the activities was estimated using the analogous technique, which involved comparison with similar civil construction projects. This estimate was based on the author’s experience and a benchmarking process with engineers who had already carried out similar ventures. After defining the durations, the precedence relationships between activities were established, considering technical and operational dependencies. Two main types of precedence were adopted: Finish-to-Start (FS), where a successor activity can only begin after the predecessor has finished, and Start-to-Start (SS), which allowed simultaneous execution of tasks, provided both had been initiated.

With the WBS and precedence relationships defined, the project schedule was structured sequentially and logically, encompassing all phases of the work. Activities were organized into work packages, linked by their technical dependencies. To optimize planning, the concept of activity latency was used, which consists of the time interval between the start or end of a predecessor activity and the start of the successor. This technique, according to Mattos (2010), was applied to tasks that require technical waiting periods, such as concrete curing, allowing for partial task overlap when technically feasible and optimizing the total execution time.

The treatment and analysis of the data were intrinsic to the model construction process. A quantitative approach was employed to calculate durations, latencies, and activity deadlines, using numerical information as the basis for schedule elaboration. The analysis consisted of the logical structuring of this information, allowing for the identification of interdependencies and the sequential organization of macro-activities. This methodology enabled the objective measurement of deadlines and the evaluation of the constructive flow’s coherence, in accordance with the principles of quantitative research that seeks precision in measurement (Lakatos and Marconi, 2017).

As a methodological limitation, the study had a demonstrative character, focusing on the presentation of a single schedule scenario for a specific work. No additional simulations or comparative tests were performed, which restricts the statistical generalization of the results, according to the nature of demonstrative research (Lakatos and Marconi, 2017). Additionally, the cost-team relationship was not contemplated in the analysis, as the research addressed the contractor’s perspective, focusing primarily on schedule planning and control. This delimitation allowed for a deeper exploration of the structured model’s proposal without deviating into aspects of financial resource allocation.

3. Results and Discussion

The results of this study culminate in the proposition of a structured model for deadline planning in civil construction projects, specifically applied to the sequencing of macro-activities and the careful definition of their precedence relationships. This model unfolds into three interconnected levels, each contributing to a comprehensive and detailed view of the undertaking: the decomposition of the scope through the Work Breakdown Structure (WBS), the meticulous definition of precedence relationships between activities, and finally, the elaboration of the schedule based on consistently estimated durations. The relevance of these findings lies in the ability to transform a frequently empirical process into a systematic approach, aligned with best practices in project management.

The Work Breakdown Structure (WBS) developed for the model proved to be a fundamental tool for planning and control. Its conception allowed for a hierarchical and systematic decomposition of the scope, essential for effective understanding and management of the undertaking. At the most comprehensive level, the project was represented as a whole, synthesizing all deliverables required for its completion. This macro view, by consolidating the undertaking into a single entity, offers the client and the management team a unified perspective of the final objective, facilitating strategic alignment and communication of the project’s major milestones. The clarity provided by this initial representation is crucial, as, according to Kerzner (2017), a clear understanding of the scope is the starting point for any successful planning, minimizing ambiguities and ensuring that all stakeholders share the same vision of what needs to be delivered.

Moving to the second level, the project was decomposed into six major deliverables, each grouping activities of a similar nature: Foundation and Structure, Installations, Enclosures, Finishes, Furnishings, and Finalization. These work packages, or “Macro-deliverables,” function as logical and sequential blocks, organizing the schedule in an intuitive and manageable way. Project management literature, such as that presented by Meredith and Matel (2014), emphasizes that the hierarchical breakdown of tasks into work packages facilitates risk analysis and priority setting, making the interdependence between stages visible. In the context of this study, this decomposition allowed the manager to identify the main project phases, evaluating the complexity and resources needed for each in a more granular way than the macro view, but still without the excessive detail that could overload the initial planning. The organization into macro-deliverables also promotes better communication among the teams responsible for each phase, as their assignments and the boundaries of their work packages are clearly defined, reducing conflicts and optimizing coordination.

At the third level of the Work Breakdown Structure (WBS), as detailed in Figure 2 (mentioned in the methodology section), sub-packages and activities that compose each macro-delivery were specified. This detailing encompassed tasks such as Preliminary Services, Electrical and/or Logical, Masonry, Screeds and Floors, among others, following the constructive logic of civil engineering. The WBS, by breaking down the work into smaller and more manageable components, facilitated the visualization of deliverables and activities, as advocated by Tristancho (2026). This granularity is vital for the precise estimation of activity durations and for resource allocation, as it allows for an in-depth analysis of each task. Fritzen (2018) highlights that the WBS is a pillar of construction planning, as it connects the scope to the budget and the physical-financial schedule, providing greater predictability and control over execution. The application of the WBS at this level of detail ensured that no essential task was overlooked, providing a solid foundation for schedule construction and the identification of operational and technical dependencies. Clarity in defining the scope and structuring activities, as achieved through the WBS, is one of the critical success factors in complex projects, as argued by Pinto and Slevin (1988).

The hierarchy established by the WBS not only ensured clarity in scope definition but also facilitated the control of deadlines and resources, allowing the schedule to be built logically and consistently. By organizing the scope, the WBS played a strategic role in defining responsibilities and sequencing activities. The decomposition into work packages, as observed, allows each team to clearly understand their assignments, reducing ambiguities and favoring communication between the different sectors involved, a crucial point for efficiency in civil construction projects. Furthermore, the WBS enabled the identification of critical activities and assisted in defining activity durations, as the hierarchical organization of tasks makes the interdependence between stages visible, facilitating risk analysis and priority setting, as pointed out by Meredith and Matel (2014). The use of the WBS, therefore, reinforced the integration between theory and practice, providing a robust framework for project planning and control.

The interdependence between activities proved to be a decisive factor in establishing the total project deadline. The nature of civil construction, where each stage is intrinsically connected to the start or completion of others, makes the execution deadline particularly sensitive. Delays in a single activity can generate cascading impacts, compromising not only the schedule but also the costs and the final quality of the work. To mitigate these risks, the planning was structured logically, identifying technical and operational links that ensured the continuity of the process. Mattos (2010) emphasizes that predecessor activities constitute fundamental dependency relationships for the constructive logic, as they determine the correct order of execution and ensure the coherence of the planning. This systematic approach allowed for the anticipation of potential bottlenecks and the planning of contingencies, providing greater robustness to the schedule.

In the proposed model, two main types of precedence were adopted: Finish-to-Start (FS) and Start-to-Start (SS). The Finish-to-Start (FS) relationship, where a successor activity can only be initiated after the predecessor has finished, was the most common and fundamental to ensure the logical sequence of most construction stages. For example, the concreting of a slab must be completed before the masonry on top of it can begin. This sequential dependency is crucial for the structural integrity and quality of the construction. The consistent application of FS precedence ensures that technical prerequisites are met, avoiding rework and failures that could arise from disordered execution. Adherence to this logic is a pillar for schedule predictability and safety, aligning with the PMBOK Guide’s guidelines for activity sequencing.

The second type, the Start-Start (SS) relationship, allowed the simultaneous execution of tasks, as long as both had been initiated. This logic favored the controlled overlap of activities, optimizing the total execution time without compromising quality. Clear examples of its application were the start of the roof and the start of the parapet wall, where the execution of one does not prevent the start of the other, provided that certain initial conditions are met. The strategic use of the SS precedence is a differentiator for efficiency, as it recognizes that not all activities need to be strictly sequential. By allowing certain tasks to progress in parallel, the total project time can be significantly reduced. However, this technique requires more careful management to ensure that the conditions for overlap are maintained and that there are no interferences or resource conflicts. The flexibility introduced by SS precedence, when well managed, reflects sophisticated planning that seeks continuous optimization.

An additional resource used to optimize planning was the concept of activity latency, which consists of the time interval between the start or end of a predecessor activity and the start of the successor. This technique, according to Mattos (2010), was applied to tasks that require technical waiting periods, such as concrete curing before masonry execution. Latency allowed for partial overlap of tasks when technically feasible, optimizing the total execution time without compromising quality or safety. For example, after concreting a structure, a curing period is essential before masonry loads can be applied. Instead of waiting for the complete end of curing to start any other activity, latency allows other tasks that are not dependent on full curing, or that can be initiated in parallel after a minimum waiting period, to progress. This feature provides greater realism and flexibility to the schedule, avoiding unnecessary delays and ensuring that construction processes follow best engineering practices. Effective latency management is an indicator of mature planning, which balances temporal efficiency with technical and quality requirements.

After the elaboration of the Work Breakdown Structure (WBS) and the definition of precedence relationships, the project schedule was structured sequentially and logically, encompassing all phases of the work. Activities were organized into work packages, linked by their technical dependencies, and adjusted through the use of activity latencies. The application of this model allowed for the logical organization of the construction flow, reducing inconsistencies in the schedule and facilitating the visualization of interdependencies between activities. Furthermore, it contributed to the identification of critical activities and to the effective monitoring of the execution deadline.

Table 1. Project Schedule

Source: Original research results

The schedule analysis, as presented in Table 1 (which corresponds to Figure 3 of the original document), showed that the total deadline of 180 days for the execution of the work was compatible with the complexity of the stages involved, from the foundation to the finishes and the outfitting items. The quantitative approach used to calculate the total duration of the construction phase of the undertaking, allowing for a more precise estimation of the execution deadline for the stages, provided robustness to the planning and reduced subjectivity in deadline estimation. Lakatos and Marconi (2017) and Gil (2019) reinforce that quantitative research, by translating opinions and information into numbers, allows for greater precision in measurement and objectivity in the interpretation of results, which was fundamental for the validation of the proposed schedule. Precision in deadline estimation is a critical factor for project success, as it directly impacts resource allocation, negotiation with suppliers, and customer satisfaction.

The sequencing of activities considered the time required for the curing of reinforced concrete, an indispensable step to ensure structural stability and which cannot be accelerated without compromising quality. This is an example of a technical constraint that, if not properly planned, can lead to significant delays and compromise the safety of the work. Furthermore, some critical activities, such as electrical and logical installations, special installations, glass curtain wall closures, and internal and external visual communication, presented technical restrictions that made their parallel planning with other phases difficult, requiring chained planning. These activities, due to their temporal extent and interdependence with others, require greater attention in management, as any deviation can compromise the final deadline of the work. Kerzner (2017) emphasizes that effective management of critical activities is a determinant for project success, as delays in key tasks directly impact the delivery date. The identification and continuous monitoring of these critical activities, visible in the detailed schedule, are essential for proactivity in risk management and for corrective decision-making.

Compared to unstructured approaches, the proposed model significantly reduced the reliance on empirical decisions and contributed to greater predictability in project planning. The development of a structured schedule, with predefined stages, established start and end dates, and clear identification of dependencies between activities, represents a management practice that ensures predictability, efficiency, and control over the resources employed. This organization allows for systematic progress monitoring, deviation correction, and mitigation of risks related to delays and additional costs. The absence of detailed planning, characteristic of empirical approaches, often results in fragmented execution dependent on momentary circumstances, leading to uncertain deadlines, reactive resource mobilization, and a higher probability of rework and waste. The structured model, in contrast, offers a clear roadmap for execution, minimizing uncertainty and maximizing efficiency.

The integration of the initial planning of construction stages with the PDCA (Plan-Do-Check-Act) methodology cycle, developed by Deming (1986), was a relevant finding. This integration allowed the schedule to be organized in a way that enables continuous and systematic project control. According to Campos (2004), PDCA is essential for transforming plans into concrete results, establishing a continuous process of verification and adjustment. Applying PDCA in schedule management means that planning is not limited to the initial creation of the schedule, but also involves systematic monitoring (Do and Check) and corrective decision-making (Act) throughout project management. This allows the manager to monitor deadline compliance, identify deviations in a timely manner, and implement corrective actions to ensure delivery within the planned timeframe. This dynamic and iterative approach gives the model a capacity for adaptation and continuous improvement, which is fundamental in complex and change-prone project environments.

In general, the proposed model contributed significantly to the organization of deadline planning in construction projects, allowing for the structuring of activity sequencing, identification of interdependencies, improvement of schedule control, and support for managerial decision-making. Its application favors greater predictability in execution and reduces the occurrence of planning inconsistencies, which are common sources of delays and additional costs in civil construction projects. The systematization achieved with this model ensures that each macro-stage is duly planned and monitored, avoiding overlaps and gaps in the schedule that could compromise the efficiency and quality of the work.

As a methodological limitation, the study had a demonstrative character, focusing on the presentation of a single schedule scenario for a specific work. No additional simulations or comparative tests were performed, which restricts the statistical generalization of the results, according to the nature of demonstrative research (Lakatos and Marconi, 2017). However, this delimitation allowed for a deeper exploration of the structured model proposal, illustrating its practical applicability in a real scenario. Additionally, the cost-team relationship was not contemplated in the analysis, as the research addressed the client’s perspective, focusing primarily on schedule planning and control. Although this delimitation allowed for a focus on the structured model proposal without deviating into aspects of financial resource allocation, it is important to recognize that schedule optimization is intrinsically linked to resource and cost allocation. Setting very short deadlines for certain tasks, for example, may create the need to excessively increase the workforce, which would significantly raise costs and generate operational incompatibility problems on site. The model, however, adopted compatible durations, taking into account the necessary premises for the start of each stage, which indirectly contributes to more balanced management, even without explicit cost analysis. The model’s replicability in different contexts and project sizes, with due adjustments for durations and technical specificities, suggests a promising path for future research that could integrate the dimension of costs and resources more explicitly.

4. Conclusion

It is concluded that the objective was achieved, as this work developed a structured model for the sequencing of macro-activities and deadline planning in a credit union construction project. The proposed model proved effective in supporting schedule organization, identification of interdependencies, and improvement of execution deadline control. The application of the Work Breakdown Structure (WBS), the careful definition of precedence relationships (Finish-to-Start and Start-to-Start), and the strategic use of activity latencies allowed for the construction of a logical and consistent schedule, with a total duration of 180 days. This systematic approach reduced reliance on empirical decisions, providing greater predictability and efficiency to project management. The integration with the PDCA cycle also reinforced the capacity for continuous monitoring and adjustment, essential for the success of the work.

However, it is important to recognize the limitations of this study. Its demonstrative nature, focused on a single schedule scenario for a specific work, restricts the statistical generalization of the results, with no simulations or comparative tests. Additionally, the cost-team relationship was not explicitly contemplated in the analysis, prioritizing the contractor’s perspective and deadline control. For future studies, it is suggested to replicate the model in different contexts and project sizes, with adjustments to durations and technical specificities. It is also recommended to integrate the dimension of costs and resources, deepening the analysis on the financial impact of deadline and team optimization decisions, which would enrich the practical applicability of the model.

Bibliographic References

CAMPOS, Vicente Falconi. TQC: Controle da Qualidade Total (no estilo japonês). 8. ed. Belo Horizonte: INDG Tecnologia e Serviços Ltda., 2004.

CÂMARA BRASILEIRA DA INDÚSTRIA DA CONSTRUÇÃO. Construção civil projeta 2026 mais positivo que 2025, impulsionado por crédito e investimentos. Brasília: CBIC, 11 fev. 2026. Disponível em: <https://cbic.org.br/construcao-civil-projeta-2026-mais-positivo-que-2025-impulsionado-por-credito-e-investimentos>. Acesso em: 15 abr. 2026.

DEMING, W. Edwards. Out of the Crisis. Cambridge, MA: MIT Press, 1986.

FRITZEN, Mário. Planejamento e controle de obras: teoria e prática. Curitiba: Editora CRV, 2018.

G1. CAMPOS, João. Cooperativas de crédito ampliam presença física e desafiam bancos tradicionais. São Paulo: G1, 15 mar. 2025. Disponível em: https://g1.globo.com/economia/noticia/cooperativas-de-credito-ampliam-presenca-fisica.ghtml (g1.globo.com in Bing). Acesso em: 15 abr. 2026.

GIL, Antonio Carlos. Métodos e técnicas de pesquisa social. 7. ed. São Paulo: Atlas, 2019.

KERZNER, Harold. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 12. ed. Hoboken: John Wiley & Sons, 2017.

LAKATOS, Eva Maria; MARCONI, Marina de Andrade. Fundamentos de metodologia científica. 8. ed. São Paulo: Atlas, 2017.

MATTOS, Aldo Dórea. Planejamento e controle de obras. São Paulo: Pini, 2010.

MEREDITH, Jack R.; MANTEL, Samuel J. Project Management: A Managerial Approach. 8. ed. Hoboken: John Wiley & Sons, 2014.

PINTO, Jeffrey K.; SLEVIN, Dennis P. Critical Success Factors in Effective Project Implementation. New York: Project Management Institute, 1988.

PORTAL DO COOPERATIVISMO FINANCEIRO. Expansão das cooperativas de crédito no Brasil em 2024. Brasília: Portal do Cooperativismo Financeiro, 2024. Disponível em: https://cooperativismodecredito.coop.br/expansao-cooperativas-credito-2024 (cooperativismodecredito.coop.br in Bing). Acesso em: 15 abr. 2026.

TRISTANCHO, José. Estrutura Analítica do Projeto: fundamentos e aplicações na gestão de obras. São Paulo: Atlas, 2026.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.