PROCEDURE FOR DURATION ESTIMATES FOR IT SCHEDULES IN TECHNICAL PROPOSALS
André Luiz Lira Paes; Adriano Machado da Silva
DOI: 10.22167/2675-6528-202600554
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The complexity of Information Technology (IT) projects has frequently resulted in delays and cost overruns due to inadequate duration estimates. This work aimed to propose, apply, and evaluate a structured procedure for duration estimates in IT technical proposals, incorporating probabilistic approaches for explicit uncertainty management. The methodology was characterized as applied research, with a mixed approach, using the multiple case study method in five real and anonymized scenarios. Project Breakdown Structure (WBS), Precedence Diagramming Method (PDM), PERT technique estimates, and Monte Carlo simulation techniques were applied. The results demonstrated that the variability of deadlines was directly linked to the technological and organizational maturity of the analyzed environments: contexts with greater automation and standardized “pipelines” showed less dispersion, while legacy systems and high “bus factor” significantly increased the risks of delay. The discussion validated the use of the P80 percentile as a balanced reference for contractual commitments, by mitigating optimistic bias without compromising commercial competitiveness. It was concluded that the transition from deterministic estimates to probabilistic models expanded predictability and transparency in the client-supplier relationship. The proposed procedure proved to be replicable and effective for decision-making in solution architecture, although future studies should integrate cost dimensions and monitoring via “Earned Schedule” during execution.
Keywords: Duration Estimates; Schedule Management; P80 Percentile; Monte Carlo Simulation.
1. Introduction
Schedule management is one of the fundamental pillars of project management, translating strategic objectives into structured operational plans, defined by activities, deadlines, and timeframes. The correct definition of the time required for activity execution is essential to ensure predictability, coordination between teams, and performance control throughout the project lifecycle (PMI, 2021; Kerzner, 2022).
In the context of Information Technology (IT) projects, schedule management assumes even greater relevance due to high technical and organizational complexity. IT projects frequently deal with volatile requirements, inter-system dependencies, multiple
interested parties
and a rapid technological evolution, factors that significantly increase the degree of uncertainty associated with schedule estimates (Meredith; Mantel Jr., 2017).
Inadequate duration estimates are among the main causes of delays and cost overruns in IT projects. In technical proposals, the estimation of activity duration is a critical element for contractual viability and the credibility of the proposing organization. Overly optimistic deadlines can compromise project execution, while overly conservative estimates can reduce the competitiveness of the proposal, reflecting the optimistic bias frequently identified in studies on deadline estimation failures (Flyvbjerg, 2014).
It is observed that, in many corporate environments, schedule estimates are developed in a simplified manner, based on individual judgments or poorly structured past experiences (Kerzner, 2022). This approach tends to disregard relevant factors such as technical risks, team maturity, external dependencies, and the inherent variability of development activities. Structural imprecision is described by McConnell (2006) in the concept of the “cone of uncertainty”, where variability is maximum at the beginning of the project and decreases as the scope becomes defined.
The growing adoption of practices like DevOps and DevSecOps adds new layers of complexity to the temporal planning of IT projects. Continuous delivery, the automation of
conduits
, infrastructure as code, and frequent integration of changes require more flexible schedules capable of absorbing variations without compromising the delivery cadence.
In this scenario, the need for more structured methods to estimate the duration of activities and the project as a whole becomes evident. Techniques that explicitly incorporate uncertainty, such as probabilistic estimates and analyses based on probability distributions, are more suitable for supporting decision-making during the technical proposal development phase (Vargas, 2018; PMI, 2019).
Techniques such as PERT and Monte Carlo simulation address this need by allowing duration to be analyzed as a probabilistic distribution, with percentiles and confidence levels, rather than a fixed value that ignores the variability present in real work (Vargas, 2018; PMI, 2019). By running thousands of scenarios, the simulation produces complete probability distributions for the total project duration, offering the manager an objective basis for negotiating deadlines with the contractor and anchoring the commercial commitment in a percentile appropriate to the risk profile (Hulett, 2009; Valerdi, 2011).
This study is limited to the context of IT projects developed within the scope of technical proposals, focusing on initiatives related to the adoption of DevOps, DevSecOps practices, system modernization, standardization of
conduits
of Continuous Integration and Continuous Delivery (CI/CD), infrastructure as code, and observability. The analysis focuses on the temporal dimension of project management, with an emphasis on estimating activity durations and building more realistic schedules in IT technical proposals, considering that, in practice, these schedules are often developed from poorly founded deterministic estimates, influenced by commercial pressures and the absence of structured historical data.
The transition from deterministic estimates to probabilistic models enhances predictability and transparency in the client-supplier relationship, justifying the need for a structured procedure. Thus, the objective of this work is to propose, apply, and evaluate a structured procedure for estimating the duration of schedules in IT technical proposals, incorporating probabilistic techniques — such as PERT and Monte Carlo simulation — in order to produce more realistic, transparent, and aligned deadline estimates with the inherent uncertainties in IT projects.
2. Material and Methods
The present study was characterized as an applied research, with a mixed methodological approach, combining qualitative and quantitative elements. The applied nature aimed at the proposition, application, and evaluation of a structured procedure to estimate the duration of schedules in technical proposals for Information Technology (IT). A multiple case study strategy was adopted, exploring five real and anonymized scenarios for data collection and analysis.
The unit of analysis consisted of IT technical proposals elaborated in a real corporate environment, focusing on DevOps, DevSecOps, systems modernization, standardization of
conduits
of Continuous Integration and Continuous Delivery (CI/CD), infrastructure as code, and observability. The selection of the five cases followed an intentional sampling criterion for typicality and variety (Yin, 2015), seeking to cover different project profiles regarding the technological environment, degree of complexity, and predominant sources of uncertainty. The cases were identified as Client 1, Client 2, Client 3, Client 4, and Client 5, ensuring data anonymization and confidentiality.
The secondary data collection involved the analysis of technical documents and real artifacts from corporate IT proposals. Among the materials examined were Gantt charts, scope statements, planning assumptions, risk registers, governance rules, testing strategies, information about technological environments, and models of
conduits
of CI/CD. These documents provided the basis for understanding the contexts and structuring the estimates.
In addition to secondary data, primary data were generated by applying the proposed probabilistic estimation procedure. For each project phase, the author produced duration estimate trios — optimistic, most likely, and pessimistic — as recommended by the PERT technique. The estimates were developed based on structured expert judgment, anchored in available documentary artifacts, and calibrated by comparison between cases.
The methodological procedure integrated consolidated project management practices with quantitative methods for dealing with uncertainty. Initially, the scope of the proposals was decomposed using the Work Breakdown Structure (WBS), organizing the deliverables into phases representative of the flow of DevOps and system modernization initiatives. Subsequently, activities were sequenced using the Precedence Diagramming Method (PDM), to map precedence relationships and identify logical dependencies (PMI, 2021; Kerzner, 2022).
The PERT technique was applied to translate uncertainty into measurable duration variations, using the formulation proposed by Vargas (2018). Duration estimates were validated through expert judgment, considering factors such as technical maturity, degree of automation, external dependencies, and availability of
interested parties
. To reduce subjectivity, the procedure adopted anchoring in documentary artifacts, comparison between cases, and systematic evaluation of five risk dimensions.
As an analytical complement, Monte Carlo simulation was used as the main mechanism for quantifying uncertainty. The simulation was structured based on the Beta-PERT distribution, which concentrates probability around the most likely value, maintaining asymmetric tails, suitable for scenarios with less likely extreme events (Hulett, 2009). For each case study, at least 25,000 iterations per scenario were performed, ensuring the statistical stability of the generated distributions.
The critical path was identified based on the sequencing defined by the PDM, considering the dependency relationships between phases. Duration variations in phases outside the critical path were considered to capture the effect of near-critical paths (PMI, 2019). The simulation produced complete probability distributions for the total project duration, allowing the extraction of relevant percentiles, such as P50, P80, and P90. The simulations were processed in spreadsheets.
All data were anonymized, and the cases were identified only as Client 1 to Client 5, ensuring compliance with the ethical principles of scientific research. Data organization was carried out using standardized spreadsheets for recording estimates, version control, simulation parameters, and the history of adopted premises. Gantt chart schedule models, grouped by phase, were also used to structure the information.
3. Results and Discussion
The application of the proposed methodological procedure to the five case studies allowed for the obtainment of probabilistic duration estimates, based on the documentary analysis of technical proposals and schedules, combined with the use of the PERT technique and Monte Carlo simulation. This approach replaced point estimates with probability distributions, offering a more realistic view of the expected behavior of deadlines and aligned with the uncertainties inherent in IT projects, as per the study’s objective. The methodology employed ensured statistical stability of the generated distributions, with a minimum of 25,000 iterations per scenario.
The consolidated analysis of probabilistic estimates revealed consistent patterns of variation among projects, indicating that factors such as technical maturity, degree of automation in delivery pipelines, standardization level of CI/CD “pipelines”, quality of existing documentation, and complexity of integrations directly influence the dispersion of deadlines. Projects with higher operational maturity tended to exhibit more concentrated distributions, while projects with external dependencies or legacy environments showed more pronounced upper tails, reflecting a higher risk of delay. These findings corroborate the literature that emphasizes the importance of organizational maturity in project management (Kerzner, 2022).
The simulations allowed for the derivation of complete distributions for the total duration of each project, highlighting relevant percentiles for decision-making: P50 (median), P80 (recommended percentile for commitments), and P90 (conservative scenario). These percentiles not only show the most probable deadline but also the degree of risk associated with activity variability, providing objective support for defining deadline commitments in technical proposals. The adoption of P80 as the primary commitment reference results from a deliberate balance between commercial competitiveness and risk mitigation.
The P50 percentile, although it represents the median deadline, implies a 50% probability of delay, an unacceptable margin for a contractual commitment. The P90 and higher percentiles, while technically safer, tend to compromise the commercial competitiveness of the proposal, as they produce excessively conservative deadlines compared to the competition. The P80 balances these two vectors: it offers an 80% probability of completion within the committed deadline, reducing exposure to optimistic bias without making the proposal unfeasible, and remains consistent with benchmark practices in project risk analysis (Hulett, 2009).
The results obtained corroborate classical and contemporary literature on schedule management, especially regarding the superiority of probabilistic approaches over traditional deterministic estimates. According to PMI (2021), the explicit consideration of uncertainty is a critical factor for the reliability of time planning, especially in complex projects with a high degree of variability. Additionally, the results reinforce the analyses of Flyvbjerg (2014), who points to optimistic bias as one of the main causes of failures in schedule estimates.
The dispersion identified in the simulations reflects not only technical characteristics of the projects but also organizational factors frequently underestimated in traditional estimates. The availability of *stakeholders*, the speed of approval in governance structures, the level of team engagement, and the quality of available artifacts are variables that directly affect the actual deadline. By parameterizing these factors in the estimation intervals, the proposed procedure incorporates them indirectly, but systematically, into the final result, enhancing the robustness of the estimates.
Another relevant aspect is the relationship between DevOps practices and schedule predictability. Environments with well-established CI/CD *pipelines*, test automation, and observability practices tend to show greater stability in estimates, which is consistent with what the literature on DevOps Research and Assessment (DORA, 2025) points out regarding the impact of continuous delivery practices on predictability and *deploy* frequency. This correlation demonstrates the importance of considering the maturity level of software engineering practices in the estimation process.
Client 1 – DevSecOps in AWS environment
In Client 1, whose objective was to elevate DevSecOps maturity in a pre-existing AWS environment, the application of the PERT technique and Monte Carlo simulation identified a deadline distribution with relatively stable behavior and a moderate upper tail. The obtained percentiles were: P50 of approximately 14.3 weeks, P80 around 15.0 weeks, and P90 close to 15.4 weeks, representing the lowest dispersion among the five cases analyzed. This stability is associated with the standardization of CI/CD *pipelines* and the partial availability of reusable infrastructure as code (IaC) modules.
Initial maturity was also observed in the use of automation practices, which contributed to reducing uncertainty in the implementation and validation phases. Even in this more favorable scenario, relevant risks were identified, especially related to the enablement and segregation of AWS accounts, dependencies on corporate security policies, and the need for formal approvals to execute changes in production environments. These factors influenced the asymmetry of the deadline distribution, albeit in a controlled manner, which supports the adoption of P80 as a commitment reference in this case. The range between P50 and P90 was only 1.1 weeks, indicating an environment with well-defined risks, as described by Hulett (2009) for standardized environments.
Client 2 – Sales application with “offline” operation
For Client 2, with the scope of modernizing a sales application with robust “offline” mode operation and reliable synchronization, a significantly greater variability was observed compared to Client 1. The Monte Carlo simulation resulted in a P50 of approximately 18.7 weeks, a P80 around 19.7 weeks, and a P90 close to 20.2 weeks, showing a much more pronounced upper tail. This greater dispersion is linked to the complexity of integrations with legacy systems, the heterogeneity of connectivity scenarios, and the high volume of functional and end-to-end tests required to validate critical use cases.
Aspects such as synchronization conflict resolution, consistency policies, data reconciliation strategies, and testing under adverse conditions, such as high latency or prolonged connection loss, were determinants for the increase in uncertainty. This result directly dialogues with Flyvbjerg’s (2014) discussion on optimistic bias, as projects with high technical complexity and non-trivial integrations are susceptible to underestimated estimates. The difference between P50 and P90, approximately 8% in deadline, can mean weeks of contractual delay, validating P80 as a balance between prudence and competitiveness.
Client 3 – Evolution of ALM, DevOps and quality with multiple “squads”
In Client 3, whose objective was to elevate the maturity of ALM, DevOps, and Quality (QA) in an environment composed of four *squads* with distinct paces and maturity levels, the results revealed intermediate variability. Estimates produced by the PERT technique and Monte Carlo simulations resulted in an approximate P50 of 17.5 weeks, P80 of about 18.6 weeks, and P90 around 19.2 weeks, configuring a relatively stable distribution, but still sensitive to information availability and the quality of existing artifacts.
An expressive portion of the uncertainty focused on the *assessment* phase, particularly in collecting and validating technical evidence, historical documentation, and standards adopted by the teams. This stage was impacted by the unavailability of *stakeholders*, the absence of formal records, and the differences in maturity among the *squads*. Another relevant factor was the heterogeneity in automated test coverage, which directly influenced the time needed to stabilize the *pipelines* and implement the defined quality practices, such as the test pyramid and integrated *quality gates*.
The observed dispersion suggests that advances in standardization, test automation, and clarity of responsibilities via RACI tend to reduce variability in future estimation iterations. This framework converges with what Kerzner (2022) describes regarding the relationship between team heterogeneity and planning difficulty. When multiple teams operate with distinct practices, rhythms, and quality criteria, schedule variability tends to be higher not only due to differences in execution speed but also from the need to align standards and resolve inconsistencies, factors that widen pessimistic intervals. The P80 remained the most appropriate deadline reference.
Client 4 – “Assessment” of legacy system with fragile integrations
In Client 4, whose scope involved conducting an in-depth *assessment* of a legacy system characterized by low documentation, high coupling, and unstable critical integrations, the results showed uncertain behavior primarily influenced by the availability of *stakeholders* and the progressive discovery of hidden technical components. The Monte Carlo simulation produced a P50 of approximately 15.4 weeks, a P80 of 16.2 weeks, and a P90 of around 16.7 weeks, revealing a moderate upper tail.
A large part of the variability stems from the investigative nature of the project, which depends heavily on the participation of internal teams for reconstructing workflows, understanding business rules, and mapping undocumented integrations. In legacy environments, additional technical dependencies are usually identified only during interviews, log analysis, and historical surveys, which directly affects the accuracy of initial estimates. Despite the uncertainties, the observed pattern indicates that, once the information gathering and validation stage is completed, the subsequent phases of analysis, risk consolidation, and roadmap development tend to exhibit less variability.
The adoption of P80 as a commitment reference remained adequate, serving as a sufficient buffer to absorb oscillations in the initial phases without compromising the overall schedule. This characteristic of Client 4 well illustrates what Kerzner (2022) describes when discussing the relationship between organizational maturity and planning quality. In organizations with low maturity, project artifacts tend to be scarce, assumptions are rarely documented, and knowledge is concentrated in key individuals, a scenario that produces initially unstable estimates that only stabilize after a period of immersion and discovery.
Client 5 – Modernization of claims system with high “bus factor”
In Client 5, whose project involved the modernization of a highly critical claims system historically maintained by a single developer, characterizing a *bus factor* of 1, one of the largest deadline dispersions among the analyzed cases was recorded. The application of the PERT technique, followed by Monte Carlo simulation, resulted in a P50 of approximately 18.6 weeks, a P80 around 19.8 weeks, and a P90 around 20.4 weeks, configuring a quite pronounced upper tail. The main source of uncertainty is associated with the critical dependence on tacit knowledge, concentrated in a single individual who masters the system’s operation.
This characteristic directly affects activities such as technical assessment, business rule mapping, internal flow reconstruction, technical debt identification, and prioritization of the modernization *backlog*. Furthermore, the absence of automated tests and the fragility of versioning and code review practices intensify the risk of regressions, increasing the variability of estimates. Another relevant factor concerns the need to implement, at least initially, a set of minimum *hardening* actions, including security improvements, *pipeline* integration, *build* and test automation, and observability reinforcement, before deeper refactoring steps could be initiated.
This set of preliminary activities contributed to the expansion of the range projected by the simulations. This situation precisely illustrates what McConnell (2006) describes with the concept of “cone of uncertainty”: at the beginning of a project, especially when the technical scope depends on knowledge not yet mapped, the amplitude of uncertainty is maximum and only reduces as the survey progresses. In the case of Client 5, the concentration of knowledge in a single developer kept the perceived cone artificially narrow, but the simulations revealed that the real variability was substantially greater than intuitive estimates suggested. The choice of P80 as a deadline reference thus becomes even more essential in this case.
Consolidated Analysis of the Five Cases
The preliminary analysis of the five case studies revealed consistent patterns regarding the behavior of duration estimates in IT technical proposals involving DevOps, DevSecOps, system modernization, and pipeline evolution practices. In all scenarios, applying the PERT technique combined with Monte Carlo simulation allowed for the identification of not only a single estimated deadline but also the complete distribution of uncertainties, reflected in the P50, P80, and P90 percentiles, offering a comprehensive view of project predictability.
It was observed that projects with greater maturity in automation, standardization of *pipelines*, availability of reusable infrastructure as code (IaC) modules, and security governance exhibit less variability and narrower upper tails, as occurred in the cases of Clients 1 and 3. In contrast, initiatives dependent on legacy integrations, variable connectivity, absence of formal evidence, or concentration of technical knowledge, as in Clients 2, 4, and 5, demonstrated longer upper tails, indicating the need for broader margins and greater caution in formulating initial commitments.
The comparison between percentiles shows that, despite the differences between projects, P80 remains a coherent parameter for defining realistic deadlines, balancing commercial competitiveness and risk mitigation. This pattern suggests that the use of probabilistic distributions is more suitable than deterministic estimates in the proposal phase, especially in environments subject to structural uncertainties, which validates the central proposal of this study.
The external validity of this study should be understood in its appropriate terms. Multiple case studies do not produce statistical generalization; it is not intended to claim that the percentiles obtained are valid for any IT project. What is offered is analytical generalization (Yin, 2015): the identified patterns — relationship between operational maturity and distribution concentration of deadlines, effectiveness of P80 as a commitment reference, role of organizational factors in variability — are theoretical propositions that can be transferred to contexts with similar characteristics, such as other modernization initiatives, DevOps adoption, or development of technical proposals in environments of high uncertainty.
Adherence tends to be higher when the following coexist: relevant technical uncertainty, need for contractual term negotiation, minimum availability of documentary artifacts, and a delivery-oriented project profile. The estimated schedule dispersion, calculated as the difference between P90 and P50, highlighted contexts with greater variability and higher exposure to delay risk, reinforcing the need for a probabilistic approach. The recommended interpretation of each percentile emphasizes P80 as the preferred reference for contractual commitments in technical proposals, with P50 serving as an internal planning reference and P90 for contingency planning in more conservative scenarios.
In summary, the results demonstrated that the proposed structured procedure, by incorporating probabilistic techniques such as PERT and Monte Carlo simulation, allowed for the generation of more realistic and transparent duration estimates for IT technical proposals. The variability of deadlines revealed a direct correlation with the technological and organizational maturity of the environments, and the validation of the P80 percentile as a balanced contractual reference proved effective in mitigating optimistic bias without compromising competitiveness, thus responding to the objective of proposing, applying, and evaluating a procedure that aligns estimates with the uncertainties inherent in IT projects.
4. Conclusion
This work aimed to propose, apply, and evaluate a structured procedure for duration estimates in Information Technology technical proposals, incorporating probabilistic approaches for explicit uncertainty management. The application of the procedure, which integrated the PERT technique and Monte Carlo simulation in five case studies, allowed for the obtainment of probabilistic duration estimates, replacing point values with probability distributions. It was found that the variability of deadlines was directly linked to the technological and organizational maturity of the analyzed environments; contexts with greater automation and standardized “pipelines” showed less dispersion, while legacy systems and high “bus factor” significantly increased the risks of delay. The discussion validated the use of the P80 percentile as a balanced reference for contractual commitments, by mitigating optimistic bias without compromising commercial competitiveness. The transition from deterministic estimates to probabilistic models expanded predictability and transparency in the client-supplier relationship, and the proposed procedure proved to be replicable and effective for decision-making in solution architecture.
As limitations, this study focused strictly on the temporal dimension and the proposal elaboration phase, without monitoring the actual execution of projects or comparing the estimated percentiles with subsequent performance in all cases. It is recognized that PERT input values depend on qualified technical judgment, which requires rigorous documentation of assumptions. As it involves five cases within a specific universe of IT technical proposals, the findings should be read as analytical evidence transferable by contextual similarity, rather than as a universal rule. For future work, it is recommended to apply “Earned Schedule” metrics during project execution to verify the practical adherence of planned durations based on P80. It is suggested to systematically compare estimated percentiles with actual completion deadlines, expand the procedure to integrate cost and effort dimensions, enabling a multidimensional risk analysis, and investigate how increasing maturity in DevOps practices and the adoption of artificial intelligence in project management can refine the input parameters for simulations.
Bibliographic References
DORA (DEVOPS RESEARCH AND ASSESSMENT). The Four Keys of DevOps Performance. [S.I.]: DORA, 2025. Disponível em: https://dora.dev/guides/dora-metrics-four-keys/. Acesso em: 19 set. 2025.
FLYVBJERG, Bent. What you should know about megaprojects and why: an overview. PM World Journal, [S.I.], v. 3, n. 2, p. 1–18, 2014.
HULETT, David T. Practical schedule risk analysis. Burlington: Gower Publishing, 2009.
KERZNER, Harold. Project management: a systems approach to planning, scheduling, and controlling. 13. ed. Hoboken: John Wiley & Sons, 2022.
MCCONNELL, Steve. Software estimation: demystifying the black art. Redmond: Microsoft Press, 2006.
MEREDITH, Jack R.; MANTEL JR., Samuel J. Project management: a managerial approach. 9. ed. Hoboken: John Wiley & Sons, 2017.
PMI (PROJECT MANAGEMENT INSTITUTE). A guide to the project management body of knowledge (PMBOK® Guide). 7. ed. Newtown Square, PA: PMI, 2021.
PMI (PROJECT MANAGEMENT INSTITUTE). Practice standard for scheduling. 3. ed. Newtown Square, PA: PMI, 2019. Disponível em: https://www.pmi.org/standards/scheduling-third-edition. Acesso em: 19 set. 2025.
VALERDI, Ricardo. Heuristics for systems engineering cost and schedule estimation. IEEE Systems Journal, v. 5, n. 1, p. 91–98, mar. 2011.
VARGAS, Ricardo Viana. Gerenciamento de projetos: estabelecendo diferenciais competitivos. 9. ed. Rio de Janeiro: Brasport, 2018.
YIN, Robert K. Estudo de caso: planejamento e métodos. 5. ed. Porto Alegre: Bookman, 2015.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq
To learn more about the course, click here and access the MBX Academy platform