Technical risk management practices in software development and integration projects

Andrew Martins Dos Santos; Beatriz Cristina de Freitas

DOI: 10.22167/2675-6528-202600570

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

The management of technical risks in software projects is crucial for mitigating uncertainties and supporting decision-making in highly complex environments. This study analyzed the influence of technical risk management on the decision-making process in system development, integration, and update projects, proposing a structured management model applicable to similar contexts. A quali-quantitative approach was adopted, employing surveys, Ishikawa diagrams, Probability × Impact matrices, and 5W2H to collect and analyze professionals’ perceptions. The results revealed high agreement in structured risk identification (64.7%) and in the relevance of managerial experience (94.1%). Incompatibility issues between modules were widely recognized (88.3%), and the analysis phase demonstrated consolidated maturity (100%) in assessing risks by cost, deadline, and quality. Risks strongly influenced technical decisions (94.1%) and managerial security (100%), with continuous monitoring (88.2%) and the use of historical data (100%) indicating institutionalization. Integration failures between modules were identified as the most critical risk. The proposed model integrates these dimensions into a continuous flow, consolidating technical risk management as a strategic process that enhances predictability and decision quality in software projects.

Keywords: Software development; Project governance; Systems integration; Organizational maturity; Decision making.

1. Introduction

Projects involving software development and integration are inherently complex, characterized by multiple interdependencies and constant exposure to uncertainties. Unlike predominantly physical or linear initiatives, digital technology-based ventures face challenges such as requirement variability, rapid architectural evolution, frequent version changes, and complex dependencies between teams and suppliers. This dynamic environment increases the likelihood of unforeseen failures, making project performance highly sensitive to technical risks and requiring managerial practices capable of anticipating problems and sustaining decisions under conditions of uncertainty.

In this challenging scenario, project management has consolidated itself as an essential discipline for organizing temporary efforts aimed at delivering value. Formal planning, monitoring, and control structures are adopted to ensure predictability of schedule, cost, and quality (PMI, 2021). The standardization of processes and the clear definition of responsibilities contribute to reducing improvisation and promoting greater consistency in conducting activities. However, as projects become more technological and interconnected, it becomes evident that the mere formalization of planning is not sufficient to deal with uncertain events that emerge during execution (Khatun et al., 2022). In such contexts, risk management plays a strategic role in anticipating uncertainties and supporting decision-making at critical project milestones.

Specialized literature emphasizes that the prior analysis of threats and opportunities should be treated as an integral part of the project lifecycle, enabling the identification of factors capable of compromising strategic objectives. The practice of anticipating adverse scenarios, estimating impacts, and preparing responses contributes to reducing dependence on reactive decisions, promoting greater operational stability and alignment with organizational objectives (Miranda et al., 2019). In the specific context of software, risk management takes on particular characteristics. Integration failures between modules, technical incompatibilities, testing limitations, external dependencies, and frequent requirement changes are among the most recurring events (Springer et al., 2022). Such risks not only impact isolated tasks but tend to produce systemic effects, propagating delays and rework across different work fronts, which reinforces the need for prevention mechanisms even in the initial phases of the project.

The presence of technical risks also alters the dynamics of the decision-making process. Managers constantly need to choose between alternatives under time and resource constraints, evaluating trade-offs between delivery speed, solution stability, and correction effort. Decisions made without due consideration of uncertainties tend to generate cumulative consequences, such as increased defects, customer dissatisfaction, and loss of schedule control. On the other hand, when risk exposure is explicitly integrated into analyses, choices become more informed, favoring priorities more consistent with strategic objectives (Estublier et al., 2005). Another relevant aspect refers to the role of professional experience in conducting these decisions. In technological environments, a large part of the knowledge about potential failures is tacit, built from previous experiences. Experienced professionals develop a greater ability to recognize patterns, anticipate recurring problems, and interpret early signs of deviation (Meng et al., 2022). Software integration projects frequently involve multiple actors with distinct responsibilities, which requires continuous information exchange to align priorities and coordinate activities. The absence of formal communication channels tends to reduce problem visibility and delay responses, while transparent information flows enable faster and more consistent decisions (Mahdi et al., 2021).

Despite conceptual advances and the recognized importance of risk management, it is observed that many initiatives still conduct risk management informally or fragmented, especially in software teams operating under pressure for rapid deliveries. Prioritizing immediate solutions can reduce the time dedicated to preventive analysis, increasing exposure to recurring failures. This mismatch between the strategic importance of the topic and its practical application highlights a gap, indicating the need for clear, simple, and replicable models capable of guiding managers in the systematic incorporation of risk management practices into the project’s daily routine (Mossa et al., 2025). Thus, a structured model is fundamental to increase predictability, reduce rework, and strengthen governance in software projects, contributing to safer decisions and more consistent results.

Given this panorama, the central question of this work is: how are technical risk management practices structured and used to support decision-making in software development and integration projects? Thus, the present study aims to analyze how technical software risk management influences the decision-making process in systems development, integration, and update projects, proposing a structured management model applicable to similar contexts.

2. Material and Methods

This research was characterized as an applied study, seeking to generate practical knowledge to improve the management of technical risks in software projects. An exploratory-descriptive nature was adopted, investigating a little-systematized phenomenon in the context of software integration and updating and characterizing the perceptions of professionals. The methodological approach was quali-quantitative, combining objective measurement of structured data with qualitative interpretation of open-ended responses, allowing for a comprehensive understanding of the phenomenon (Krauss, 2024).

The methodological design was based on a survey, suitable for collecting data directly from respondents with similar professional characteristics, working in various organizational contexts (Mineiro, 2020). The sample, non-probabilistic by convenience, included Project Managers and Project Leaders directly involved in conducting software projects. The inclusion criteria covered practical experience in system implementation, integration, or upgrade projects and active participation in technical or managerial decisions. Individuals without direct involvement in project management were excluded.

For data collection, a structured questionnaire was used, developed based on the risk management guidelines of the Project Management Institute (PMI) and systematized in A Guide to the Project Management Body of Knowledge (PMBOK). The instrument consisted of 22 questions: four for profile characterization, sixteen closed statements in thematic blocks, and two open-ended for qualitative deepening. The closed statements were evaluated using a five-point Likert scale. A pre-test with two professionals in the field verified the clarity and adherence of the instrument.

The questionnaire was made available in digital format via the Google Forms platform, remaining active for 15 days during January 2026. The access link was sent individually, via the WhatsApp application, to 20 previously selected professionals. At the end of the period, 17 valid responses were obtained, resulting in an adherence rate of 85%. This return rate was considered satisfactory for research applied to professionals with intense operational routines.

After consolidating the responses, the data from the closed-ended questions were organized and treated using descriptive statistics, presenting absolute numbers and percentages. The quantitative analysis was conducted with the aid of GraphPad Prism software version 10.2. The responses to the open-ended questions were subjected to qualitative analysis by thematic categorization, grouping reports by semantic similarity to identify recurring themes. Subsequently, the frequency of occurrence of each category was quantified, converting the qualitative data into comparable indicators.

For the prioritization and planning of responses to risks, the Probability × Impact Matrix was employed as a structured analysis technique (A. Kassem et al., 2019). This matrix classified the criticality of the identified risks, supporting the definition of managerial priorities. The method evaluated each risk bidimensionally, considering the probability of occurrence (P) and the potential impact (I) on project performance, using a five-level ordinal scale (1 to 5) for both dimensions. The criticality level was determined by the product P × I, with values from 1 to 25, and classified into ranges: Low, Medium, High, and Critical.

The 5W2H technique was adopted as a methodological procedure to structure the responses to the previously prioritized technical risks. It consisted of a method for planning and detailing managerial actions, transforming diagnoses into executable operational plans (Cioffi et al., 2022). From the consolidation of the identified risk events classified by criticality, each item was broken down into specific actions organized according to the seven dimensions of the method: What, Why, Where, When, Who, How, and How Much. The information was recorded in tabular format.

The structured process model, the central proposal of this study, was conceived based on the results and analyses, following a sequential and cyclical flow to organize the technical risk treatment steps. This structure was adopted as a methodological reference to systematize the findings and propose a mechanism to support managerial decision-making. The study was exempted from review by the CEP/CONEP system, with the support of the ESALQ/USP Ethics Waiver Form (FDE). All participants expressed their agreement through the Informed Consent Form (TCLE).

3. Results and Discussion

The analysis of the research results allowed us to understand the dynamics of technical risk management in software development and integration projects, as well as the influence of these practices on the decision-making process. Initially, the characterization of the respondents’ profile revealed a sample composed mainly of professionals in leadership and management roles, with 58.8% being Project Managers, 29.4% Project Leaders, and 11.8% Technical Leaders. This distribution indicates that the perceptions collected reflect the vision of individuals with direct responsibility for the strategic coordination and direction of the projects, which lends greater adherence and reliability to the study’s findings.

Regarding experience time, the sample demonstrated a highly qualified profile, with 52.9% of respondents having more than 10 years of experience in software projects. Additionally, 23.5% had experience between 6 and 10 years, and another 23.5% between 3 and 5 years, with no records of participants with less than two years of experience. This high level of experience is crucial in highly complex environments, where tacit knowledge and the ability to anticipate problems are developed over time. Technical specialization also proved prominent, with 76.5% classifying their experience in system development, integration, or updating as high, and 23.5% as moderate, with no occurrences of low experience.

The main role of participants in the projects revealed a balance between operational and managerial vision. It was observed that 41.2% of professionals predominantly act in technical coordination, 35.3% exercise both strategic management and technical coordination, and 23.5% focus exclusively on strategic management. This diversity of roles indicates that the respondents actively participate in different decision-making levels, from purely technical aspects to planning and prioritization, which enriches the analysis of the influence of technical risks on the decision-making process. The combination of experience and direct responsibility strengthens the basis for interpretations of the maturity of risk management practices.

Identification of technical risks in software development and integration

The investigation into the identification of technical risks revealed that 64.7% of respondents agree or fully agree that technical risks in software implementation are identified in a structured manner at the beginning of the project. However, the presence of 35.3% disagreement suggests that, although formal practices exist, their application is not yet homogeneous across all projects or teams. Early and systematic risk identification is fundamental to mitigate uncertainties and avoid the need for reactive decisions, which frequently result in defects, rework, and delays, compromising the project’s timeline and cost (Gong et al., 2024).

An almost absolute consensus was observed regarding the role of managerial experience in risk identification. Sixteen respondents, equivalent to 94.1%, fully agreed that the Project Manager or Leader’s prior experience contributes significantly to the identification of technical risks, with only 5.9% remaining neutral. This data reinforces the importance of tacit knowledge, accumulated from previous projects, for recognizing failure patterns and anticipating problems in software environments, where architectural dependencies and systemic constraints are not always explicitly documented (Bulmer et al., 2025).

Compatibility issues between modules or versions were widely recognized as relevant risks since the initial phases of the project, with 88.3% of participants agreeing or strongly agreeing with this statement. Only 5.9% disagreed and 5.9% remained neutral. This result underscores the criticality of these problems in software projects, which often involve high coupling between components. Early identification of these vulnerabilities is essential to avoid extensive corrective testing cycles and to ensure safer decisions at schedule milestones, reducing rework and improving delivery predictability (A. Kassem et al., 2019).

Regarding the risks arising from dependencies between teams or suppliers, the perception was more dispersed. Only 41.2% of respondents agreed or fully agreed that these risks are formally recorded, while an equivalent percentage (41.2%) disagreed, and 17.6% remained neutral. This lack of consensus indicates that organizational and inter-team coordination factors may be treated more informally compared to purely technical risks. The non-formalization of these risks can reduce their visibility in the decision-making process, limiting the capacity for preventive planning and increasing the impact on schedule and cost, which contradicts good management practices that recommend the rigorous recording of these elements (Abreu et al., 2025).

Analysis and prioritization of technical risks

The stage of analysis and prioritization of technical risks demonstrated a high degree of managerial maturity. All respondents (100%) agreed or fully agreed that the identified technical risks are evaluated considering their impact on schedule, cost, and quality. This unanimity suggests that technical decisions are not made solely from an operational perspective, but incorporate strategic reflections on the project’s value, performance, and outcomes. The joint evaluation of these criteria expands prioritization capacity and prevents isolated decisions that could optimize one criterion to the detriment of another (Buganová et al., 2019).

The probability of occurrence of technical risks also proved to be a central factor in prioritization, with 94.1% of participants agreeing or fully agreeing that it directly influences risk ranking. This pattern highlights the practical application of probabilistic reasoning in the decision-making process, bringing risk management closer to structured assessment methods. By considering probability, managers can anticipate more likely events, reducing exposure to recurring failures and improving project predictability (Chen et al., 2025).

The clarity in the criteria used to classify technical risks as critical was confirmed by 94.1% of respondents, who agreed or strongly agreed with this statement. This result indicates a positive perception regarding the existence of defined parameters for criticality classification, suggesting that decisions do not depend exclusively on subjective judgment. The presence of clear criteria contributes to greater consistency among managers and reduces conflicts in prioritizing corrective actions, promoting a more objective decision-making environment (Chaabouni et al., 2024).

However, the differentiated attention to software development-related risks, compared to other types of risk, showed less consensus. Although 64.7% of respondents expressed agreement, there was 23.5% neutrality and 11.8% disagreement. This lower percentage of agreement, accompanied by a relevant presence of neutrality, suggests that a lack of specific focus on technical risks can lead to reactive decisions, especially when defects emerge in advanced stages of the project. The absence of a more targeted approach may compromise the effectiveness of risk management in software contexts (Clemente et al., 2023).

Technical risks and managerial decision-making

The influence of identified risks on technical decisions was strongly recognized, with 94.1% of respondents agreeing or strongly agreeing that technical decisions within the project framework are influenced by mapped risks. This finding demonstrates that risks play a relevant role in defining the technical actions adopted at the project’s control points. Explicit consideration of risk exposure increases the likelihood of preventive rather than reactive choices, which tends to reduce late failures, rework, and accumulated impacts in the final phases of the schedule (Koszykowski et al., 2025).

The contribution of technical risk management to safer and more informed decisions was unanimously recognized, with 100% of participants agreeing or fully agreeing. In software integration environments, which are characterized by high complexity and multiple dependencies, decisions based solely on individual perceptions can increase the probability of systemic failures. The incorporation of structured risk data favors greater predictability, planning stability, and better resource allocation, consolidating managerial safety (Lima et al., 2019).

The prioritization of technical fixes based on the project’s risk impact also achieved 100% agreement. This impact-driven approach is essential for reducing the tendency to address demands merely reactively or based on perceived urgency. Instead, it promotes strategic decisions that maximize the overall benefit for the project, ensuring that correction efforts are directed towards the problems with the greatest potential for harm.

Finally, the influence of technical risks that have already materialized on scope or schedule adjustments was recognized by 76.5% of respondents. However, the presence of 5.9% neutrality and 5.9% disagreement suggests that this practice may not occur entirely systematically in all projects. Structured scope and schedule adjustments after risk materialization characterize an adaptive stance, essential in project management. When changes are not formally incorporated into planning, the probability of hidden delays, team overload, and loss of performance control increases (Aljadhai et al., 2024).

Monitoring and communication of risks

The continuous monitoring of technical risks throughout the project was affirmed by 88.2% of participants, who agreed or strongly agreed. Only 5.9% disagreed and 5.9% remained neutral. This predominance of full agreement suggests that risk tracking is a recurring practice and is not restricted to specific milestones, being incorporated into the management routine. Continuous monitoring is fundamental for the early detection of deviations and for a greater capacity for preventive response, as the probability and impact of risks can change over time (Mirza et al., 2013).

Clear communication about critical technical risks between Project Managers and Project Leaders was acknowledged by 76.5% of respondents, who agreed or strongly agreed. However, 11.8% disagreed and 11.8% remained neutral, indicating a predominantly positive, but less homogeneous perception compared to other items. The integration between technical and managerial leadership is a determining factor for project success, as it allows critical information to circulate rapidly and be converted into coordinated actions, preventing problems from remaining invisible until advanced stages (de Vries et al., 2010).

The use of technical risk information in follow-up and decision-making meetings achieved 100% agreement. This result demonstrates that follow-up meetings incorporate risk indicators, favoring evidence-based decisions, increasing transparency, and reducing the probability of intuitive or late choices. In software projects, where technical evolution is rapid, this dynamic contributes to greater performance control and more informed decision-making (Chaabouni et al., 2024).

Finally, the risk history of previous projects is considered in current decisions, with 100% agreement. This pattern indicates that teams use past experiences as a source of learning, incorporating previous lessons into risk planning and prioritization. The use of historical data contributes to anticipating recurring problems and reducing the repetition of already known failures. Knowledge Management, in this context, assumes a strategic role, allowing organizations to progressively evolve their processes and increase the predictability and reliability of decisions (Meng et al., 2022).

Main technical risks influencing managerial decisions

The thematic analysis of the open-ended responses allowed for the identification of the most influential technical risks in managerial decisions. The most recurrent category was external integration and dependencies, cited by 10 participants (58.8%). This finding highlights the complexity of interconnected systems and vulnerability to external factors. Subsequently, problems related to software quality, testing, and stabilization were mentioned by 9 respondents (52.9%), indicating concern about the robustness and reliability of deliverables.

Unstable requirements or poorly defined scope, along with the need for greater formalization of risk management, were cited by 8 participants (47.1%). This points to the difficulty in maintaining clarity and stability of project objectives, as well as the importance of well-defined processes for managing uncertainties. Communication and technical governance were mentioned by 41.2% of respondents, while system performance and schedule synchronization were cited by 35.3% each. This pattern of results highlights that the most critical factors are concentrated in structural aspects of software development, especially those involving technical and organizational interdependencies.

Integration problems between modules, suppliers, or teams tend to generate systemic impacts, simultaneously affecting multiple work fronts and requiring immediate corrective decisions. Similarly, weaknesses in testing and validation increase the probability of rework in advanced phases, compromising deadlines and costs. This behavior is consistent with the recommendations of the Project Management Institute (PMI, 2021), which emphasize interface, requirements, and quality risks as determinants for performance variability in complex projects. Thus, the results indicate that managerial decisions are strongly conditioned by technical elements capable of compromising the stability of the solution as a whole, reinforcing the need for early identification and continuous monitoring of these uncertainties.

Risk management practices that can be improved

Regarding risk management practices that can be improved, communication and early escalation of risks were the main opportunity for improvement, mentioned by 11 participants (64.7%). This suggests that, although technical risks are recognized and discussed, there are still gaps related to the standardization and formalization of governance processes. The effectiveness of risk management depends not only on technical analyses but also on the appropriate circulation of information between leaders and teams.

Other areas for improvement highlighted include continuous risk monitoring (52.9%), formal documentation and record-keeping (47.1%), and the definition of structured mitigation and contingency plans (47.1%). Greater integration with technical teams (41.2%), systematic use of lessons learned and project history (35.3%), and more rigorous qualification/quantification of risks (29.4%) were also pointed out. Without clear escalation mechanisms, critical issues can remain invisible until advanced project phases, reducing the capacity for preventive response. The absence of formal records and structured plans hinders the traceability of decisions and the reuse of organizational knowledge. Strengthening these practices tends to increase predictability, reduce rework, and support more informed decisions, consolidating risk management as a strategic rather than merely operational tool.

Probability x Impact Matrix

Based on the findings, the Probability × Impact Matrix was applied to classify and prioritize the most critical technical risks. Integration failures between modules (R1) were identified as the most severe risk, with maximum probability (5) and maximum impact (5), resulting in a Score of 25, classified as critical. This finding demonstrates that technical incompatibilities between components have high recurrence and the potential to directly compromise schedule milestones, possibly making complete deliveries unfeasible. In software integration projects, problems of this nature tend to generate systemic effects, demanding extensive rework, replanning, and cost increases, which justifies the recommendation for immediate mitigation, with preventive actions even in the initial development phases.

At a similar level of criticality, the dependence on external suppliers (R2) and the insufficiency of tests or automation (R3) stood out, both with high probability (4) and high impact (4), resulting in a Score of 16, also classified as critical. Dependence on third parties can generate delays outside the team’s direct control, reducing delivery predictability and increasing exposure to external factors. Weaknesses in the testing process, on the other hand, increase the probability of defects escaping to advanced phases or production, intensifying correction costs. For these cases, contingency plans and strengthening of quality assurance practices are recommended, ensuring greater technical control over the delivered product.

Subsequently, frequent requirement changes (R4), with probability 4 and impact 3, and performance issues (R5), with probability 3 and impact 4, both with a Score of 12, were classified as high risks. Although they present a relevant impact, their probability is moderately lower when compared to critical risks. Constant changes in scope tend to generate instability in planning, rework, and misalignment between teams, reinforcing the need for change control mechanisms and clear definition of requirements. In turn, performance failures can compromise the user experience and demand late adjustments in the system architecture, justifying the adoption of early testing and continuous monitoring of technical metrics.

Finally, poor communication between teams (R6) presented a Score of 9, with a probability of 3 and an impact of 3, being classified as medium risk. Although its individual impact is lower than the others, this factor acts as a cross-cutting element that can enhance other risks, hindering activity coordination and delaying responses to technical problems. In this sense, the implementation of systematic routines for alignment and information sharing is essential to reduce organizational noise and improve the effectiveness of management.

5W2H Analysis

Based on the prioritization of technical risks by the Probability × Impact Matrix, a Risk Response Plan was developed using the 5W2H technique, which structures practical mitigation, prevention, and control actions. Risks classified as critical concentrate predominantly preventive and technical actions. For integration failures between modules, the proposed action is to implement continuous integration tests, aiming to reduce rework and systemic failures, to be carried out in the CI/CD pipeline and testing environment, from the beginning of each sprint/release, with responsibility of the Technical Leader, QA, and Developers, through automated tests, smoke tests, and continuous integration, demanding reallocation of technical effort.

For external vendor dependency, the action is to create a contingency plan to minimize delays beyond control, applied at the interfaces with vendors, from the project’s inception with bi-weekly reviews, under the responsibility of the Project Manager, using SLAs, formal follow-ups, and technical alternatives, with a management time cost. Regarding insufficient testing/automation, the proposal is to expand test coverage to detect defects early, throughout the entire development and homologation cycle, with the involvement of QA and Developers, through unit tests, automated regression, and coverage metrics, demanding additional QA hours.

Risks classified as high are handled by managerial control mechanisms. For frequent requirement changes, the action is to implement formal scope control to reduce instability, using the backlog and requirements management, before approving changes, with responsibility of the PM and Product Owner, through a change committee and impact analysis, at no direct cost. For performance issues, the action is to perform performance tests to avoid late architecture adjustments, in the staging environment, with each partial release, involving the technical team and QA, through stress tests and metrics monitoring, using already available tools.

The risk of poor communication between teams, classified as medium, is addressed by implementing periodic alignment and information sharing routines. The action is to establish alignment routines to improve coordination and rapid response, in project meetings, weekly, with responsibility of the PM and Technical Leaders, through short meetings and a risk dashboard, at no additional cost. These measures aim to reduce scope instabilities and technical rework, promoting greater predictability of deliveries and planning stability, in addition to reinforcing integration between technical and managerial leadership.

Structured process model

Based on the results obtained, a conceptual-propositive model was proposed for the management of technical risks in software development, integration, and update projects. This model aims to support the managerial decision-making process in environments of high technological complexity, integrating technical and managerial practices in a continuous cycle. The model’s structure is composed of five interdependent stages: identification, analysis and prioritization, decision-making, monitoring and communication, and organizational learning, reflecting a systemic management logic.

In the identification stage, the model emphasizes early recognition of technical risks, using formal records, managers’ experience, and historical data from previous projects. The analysis and prioritization phase assesses risks based on probability and impact on schedule, cost, and quality, being operationalized by the Probability × Impact Matrix, which objectively classifies and prioritizes risks. The managerial decision-making phase is central, using prioritized risks as direct input to define technical and strategic actions, including mitigation plans, contingency, and planning adjustments.

The model incorporates continuous monitoring and structured communication of risks, ensuring that information remains updated and accessible to different management levels throughout the project cycle. Finally, the organizational learning stage promotes the recording of lessons learned and process feedback, contributing to the continuous evolution of risk management maturity. This structure favors the standardization of managerial practices, the traceability of decisions, and the integration of risk management into regular project activities, enhancing the predictability and quality of decisions.

In summary, the research findings demonstrate that technical risk management, although recognized as crucial, still presents challenges in its formalization and standardization in software projects. Managerial experience and risk assessment by impact, cost, and quality are consolidated practices, but the communication and formal recording of external dependencies and organizational risks need improvement. The proposed model integrates these dimensions into a continuous and structured flow, consolidating technical risk management as a strategic process that enhances the predictability and quality of decisions in systems development, integration, and update projects, responding to the objective of analyzing how this management influences decision-making.

4. Conclusion

This study analyzed the influence of technical risk management on the decision-making process in system development, integration, and upgrade projects, seeking to propose a structured management model applicable to similar contexts. It was found that technical risk identification occurs in a structured manner in many projects, with managerial experience being a crucial factor for this stage. It was observed that compatibility failures between modules are widely recognized as relevant risks from the initial phases. Risk analysis and prioritization demonstrated consolidated maturity, with the assessment of impact on schedule, cost, and quality being unanimously considered, and the probability of occurrence directly influencing prioritization. Identified risks strongly influenced technical decisions and contributed to greater managerial security, with continuous monitoring and the use of historical data indicating the institutionalization of practices. Integration failures between modules were identified as the most critical risk. The main contribution of this work lies in proposing a structured management model that integrates these dimensions into a continuous flow, consolidating technical risk management as a strategic process that enhances the predictability and quality of decisions in software projects.

However, the study presented some limitations arising from the methodological design. Data collection, carried out through a questionnaire applied to professionals from different organizations, made it impossible to conduct an in-depth case study or the practical implementation of the proposed actions in a single organizational context. The analyses were predominantly based on the respondents’ perception, which may reflect individual biases and a reduced sample, characteristic of exploratory research. The focus limited to the technical risks of software integration also restricted the model’s scope, not detailing strategic, contractual, or cultural factors. As a suggestion for future work, it is recommended to apply the model in specific case studies, monitoring the implementation of risk management practices over time, comparing performance indicators, and expanding the sample to different types of projects and sectors, in order to empirically validate the effectiveness and generalization of the developed framework.

Bibliographic References

A. Kassem, M., Khoiry, M. A., e Hamzah, N. 2019. Using probability impact matrix (PIM) in analyzing risk factors affecting the success of oil and gas construction projects in Yemen. International Journal of Energy Sector Management, 14(3), 527–546.

Abreu, A., Ribeiro, P., e Lima, A. 2025. Analysis of maturity in Project Management of an Information Technology company using the Prado-PMMM methodology. Procedia Computer Science, 256, 1558–1566.

Aljadhai, S., Alqahtani, F. K., Aldakhel, A., Alharbi, M., e Yamany, M. S. 2024. Assessment of scope definition for building projects in Saudi Arabia. Journal of Asian Architecture and Building Engineering, 24(5), 3863–3878.

Buganová, K., e Šimíčková, J. 2019. Risk management in traditional and agile project management. Transportation Research Procedia, 40, 986–993.

Bulmer, E., Matutano, C., e Zamarrón, I. 2025. Leadership for a Sustainable Future: Insights from Civil Engineering and Architectural Professionals. Administrative Sciences, 15(8).

Chaabouni, M., Jarrar, Q., Medini, K., e Bissardon, F. 2024. A framework for project management software tool selection. Procedia Computer Science, 239, 291-298.

Chen, M., Martins, T. S., Zhang, L., e Dong, H. 2025. Digital Transformation in Project Management: A Systematic Review and Research Agenda. Systems, 13(8).

Cioffi, L. g., e Okada, R. H. 2022. ImplementaÇÃo Da Ferramenta 5w2h No Processo De Produção Para a Obtenção De Resultados E Melhorias No Processo. Revista Interface Tecnológica, 19(2), 974–984.

Clemente, M., e Domingues, L. 2023. Analysis of Project Management Tools to support Knowledge Management. Procedia Computer Science, 219, 1769–1776.

de Vries, R. E., Bakker-Pieper, A., e Oostenveld, W. 2010. Leadership = Communication? The Relations of Leaders’ Communication Styles with Leadership Styles, Knowledge Sharing and Leadership Outcomes. J Bus Psychol, 25(3), 367–380.

Estublier, J., Leblang, D., Hoek, A. v. d., Conradi, R., Clemm, G., Tichy, W., e Wiborg-Weber, D. 2005. Impact of software engineering research on the practice of software configuration management. ACM Transactions on Software Engineering and Methodology, 14(4), 383-430.

Gong, J., Sun, Y., Du, H., e Jiang, X. 2024. Research on safety risk control of prepared foods from the perspective of supply chain. Heliyon, 10(3), e25012.

Khatun, M. T., Hiekata, K., Takahashi, Y., e Okada, I. 2022. Design and management of software development projects under rework uncertainty: a study using system dynamics. Journal of Decision Systems, 32(2), 265–288.

Koszykowski, M., e Orzeszko, W. 2025. Machine learning in project schedule creation: a systematic literature review. Journal of Scheduling.

Krauss, A. 2024. Redefining the scientific method: as the use of sophisticated scientific methods that extend our mind. PNAS Nexus, 3(4), pgae112.

Lima, R., Tereso, A., e Faria, J. 2019. Project management under uncertainty: resource flexibility visualization in the schedule. Procedia Computer Science, 164, 381–388.

Mahdi, M. N., Mohamed Zabil, M. H., Ahmad, A. R., Ismail, R., Yusoff, Y., Cheng, L. K., Azmi, M. S. B. M., Natiq, H., e Happala Naidu, H. 2021. Software Project Management Using Machine Learning Technique—A Review. Applied Sciences, 11(11).

Meng, F., Yu, S., e Xue, J. 2022. Construction Schedule Management System for Large-Scale Construction Projects Based on Multisensor Network. Comput Intell Neurosci, 2022, 3003552.

Mineiro, M. 2020. Pesquisa De Survey E Amostragem: Aportes Teóricos Elementares. Revista de Estudos em Educação e Diversidade – REED, 1(2), 284–306.

Miranda, S., e Sugarindra, M. 2019. Utilizing project management software in project scheduling: a case study. IOP Conference Series: Materials Science and Engineering, 528(1).

Mirza, M. N., Pourzolfaghar, Z., e Shahnazari, M. 2013. Significance of Scope in Project Success. Procedia Technology, 9, 722–729.

Mossa, Y., Smith, P., e Bland, K. 2025. Reconceptualizing Enterprise Resource Planning (ERP) Systems from a Software Architecture Perspective Using a Framework Based on ERP System Characteristics. Procedia Computer Science, 256, 174–189.

PMI – Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 7. ed. Newtown Square: PMI, 2021.

Springer, O., e Miler, J. 2022. A comprehensive overview of software product management challenges. Empirical Software Engineering, 27(5).

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.