Planning and schedule proposal for accountability in a higher education institution
Planning and Schedule Proposal for Accountability in a Higher Education Institution
Vitória Aline Lira Sanches; Daniel René Tasé Velázquez
DOI: 10.22167/2675-6528-202602429
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The growing supply of distance specializations demands efficient management of processes in higher education institutions. The objective of this work was to develop a schedule for the accountability process of these courses in a higher education institution, based on the “Project Management Body of Knowledge” guide. An exploratory and descriptive case study was conducted, with a mixed approach, using internal secondary data, observation, and consultation with specialists. The methodology involved structuring and defining activities, their logical sequencing, and estimating duration, culminating in the development of a Gantt chart. The proposed schedule, composed of 30 activities, was planned to be executed in 136 days. This estimate represented a reduction of 27 days (16.6%) compared to the period estimated without structured scheduling (163 days), although it exceeded the institutional deadline of 120 days by 16 days (13.3%). The proposal was validated by practical comparison and the opinion of those involved, but it was not implemented in a real accountability cycle. It is expected that, when implemented, the schedule will contribute to reducing delays, improving stage control, and increasing process efficiency, formalizing the workflow and clarifying responsibilities.
Keywords: Academic support; Specialization; Schedule management; Project management; Gantt chart.
1. Introduction
Project management has been recognized as fundamental to organizational success, enabling ideas to transform into effective actions. The Project Management Institute (PMI, 2018) emphasizes that project management empowers organizations to operate efficiently, integrating knowledge, skills, tools, and techniques. This strategic approach is crucial for creating value and benefits, aligning projects with strategic objectives and responding to diverse needs, whether regulatory, stakeholder, or product and service development (PMI, 2017).
Within the scope of project management, schedule management is an essential knowledge area, as defined by the PMI’s PMBOK Guide (2017). It encompasses the processes necessary to ensure the timely completion of projects, serving as a vital tool for communication, stakeholder expectation management, and support in performance reporting. The effectiveness of schedule management is intrinsically linked to cost and scope management, forming what is known as the project’s iron triangle. Any change in one of these elements impacts the others, compromising overall results (Carvalho and Rabechini Jr., 2019). The processes involved in this area include planning schedule management, defining and sequencing activities, estimating their durations, developing and controlling the schedule (PMI, 2017).
In the Brazilian context, distance higher education, especially specializations, has experienced significant growth in enrollment numbers. Recent data indicate a 5.6% increase in total higher education enrollment between 2022 and 2023, with an even more expressive growth of 12.2% in graduate courses during the same period. In 2023, 61% of specialization students opted for the distance learning modality (Instituto Semesp, 2025). In this scenario, educational institutions play a crucial role in fostering and offering teaching, research, and extension, contributing to local and regional development and strengthening their image as transformative agents in society (Pacheco, 2010; Fraga et al., 2018).
The multiplicity of activities present in an organization can be conceived as projects, which justifies the adaptation of project management methodologies for a wide range of operations, including educational ones (Kerzner, 2020). Educational projects, by their nature, have clear and well-defined objectives, aiming to improve processes and solve challenges (Brito and Sabariz, 2011). However, the application of these practices in higher education institutions, such as the institute object of this study, specialized in distance postgraduate courses in São Paulo, still faces challenges. Specifically in the Academic Assistance Department, the accountability process for these courses is complex, demanding articulation between different sectors. This complexity has led to operational failures and delays, resulting in a lack of efficient monitoring, failure to meet deadlines for certificate delivery, imposition of sanctions on coordinators, and dissatisfaction among graduates.
Faced with these challenges and the need to optimize the accountability process, the implementation of a formal structure to manage the execution schedule is fundamental to ensure greater efficiency, transparency, and compliance with established deadlines. Therefore, the objective of this work is to structure a schedule management model for the execution of the accountability process for the specialization courses operated by the aforementioned educational institution, taking as a foundation the practices of the PMBOK Guide from PMI (2017).
2. Material and Methods
This study was characterized as an applied research, of an exploratory and descriptive nature, with a mixed methodological approach, combining qualitative and quantitative elements. The case study strategy was adopted, as recommended by Gil (2008), Turrioni and Mello (2012), and Prodanov and Freitas (2013), aiming to deepen the understanding of a specific phenomenon in its real context and enable the immediate application of the generated knowledge.
The unit of analysis focused on the accountability process of distance postgraduate courses. The study was conducted at a higher education institution, located in the interior of São Paulo, specialized in the operationalization of these courses. The empirical object was the accountability process of the Academic Assistance Department, a mandatory procedure for the formalization of course completion and certificate issuance.
For data collection, internal secondary sources from the institution were used, covering the period from 2023 to 2025. Operational documents were consulted, such as a pre-existing template in checklist format, and accountability reports delivered within this interval. This time window was selected because it represents the most recent deliveries and reflects the current routine of Academic Assistance, allowing for the identification of bottlenecks and opportunities for improvement.
Complementarily, participant observation was employed, in which the researcher directly participated in the proposition of the schedule and subsequent steps. Additionally, the opinions of four specialists from the Academic Assistance Department were consulted. These professionals, with experience in managing similar projects and a high level of seniority, were selected for their familiarity with the process and for having been part of the team for at least four years.
The planning and schedule proposal were structured in sequential steps, based on the practices of the PMBOK Guide (PMI, 2017). Initially, schedule management planning was carried out, which involved consulting the team’s database of similar projects, undertaken between 2023 and 2025. This survey allowed for the documentation of the procedures and tools necessary for schedule development.
The second stage consisted of defining the activities, which was done by elaborating and converting the Project Breakdown Structure (WBS) into a detailed task list. The activities were defined and described based on the team’s prior knowledge parameters and the *know-how* of the four consulted specialists, ensuring that all deliverables necessary for accountability were contemplated.
In the third stage, activities were sequenced using the Precedence Diagramming Method (PDM). This method allowed for the identification of the logical sequence of tasks and the establishment of dependency relationships between them, according to the PMBOK guidelines (PMI, 2017). The diagram was designed on the Miro platform, starting from the activity blocks of the work packages (1.1 to 3.4), which facilitated a comprehensive analysis.
The fourth stage involved estimating the duration of activities, measured in days, considering the institutional deadline of 120 days for accountability. The three-point estimation technique (optimistic, most likely, and pessimistic) was employed, using the triangular distribution, according to the equation tE = (tO + tM + tP) / 3 (PMI, 2017). Projects of a similar nature were also consulted to refine these estimates.
Finally, the project schedule was developed, aiming to create a practicable model for the team. For this, the ProjectLibre software was used to model the Gantt chart, which allowed visualizing the activities in a temporal perspective and their planned durations. The proposed schedule was validated in an in-person meeting with the team members, considering their experience and the coherence between activities and duration estimates.
The ethical aspects of the research were observed in accordance with Resolution No. 510, of April 07, 2016 (Brazil, 2016), article 1, sole paragraph, items I and VII. It was understood that the study did not require registration or evaluation by the CNS’s CEP/CONEP system. For the conduct of the research, the Free and Informed Consent Term (TCLE) and the Term of Agreement (TA) were presented and signed.
3. Results and Discussion
The structuring of a schedule management model for the accountability process of specialization courses, as per the objective of this study, proved to be a multifaceted undertaking, anchored in the practices of the PMBOK Guide (PMI, 2017). Initially, the work focused on formalizing the procedures and guidelines that, until then, lacked explicit documentation, a point of recurring dissatisfaction among team members. This formalization represented a significant advance, consolidating an objective work plan for accountability, establishing the foundations for subsequent stages, and conferring greater clarity to the workflow.
The project schedule management plan outlined the essential criteria and activities for schedule development and monitoring. This plan was constructed in five sequential steps: management planning, activity definition, sequencing, duration estimating, and schedule development. Tools and techniques employed included data analysis, work breakdown structure (WBS), expert judgment, precedence diagramming, three-point estimating, and the Gantt chart. The expected outputs of each step, such as the management plan, activity list, and project schedule, were clearly defined, assigning responsibilities to the project manager and team, as per PMI (2017) guidelines.
The structuring and definition phase of activities was crucial for breaking down the accountability process into manageable components. The Work Breakdown Structure (WBS) was developed based on the accountability phases, identifying three main deliverables: the Accountability Report, the Academic Report, and the Performance Report. Each of these reports was detailed into specific work packages and activities, totaling a comprehensive list of tasks. This decomposition allowed for a deeper understanding of the project, which is executed repeatedly, depending on the number of courses under management, as emphasized by Carvalho and Rabechini Jr. (2019) regarding the clarity needed for the team.
The analysis of activities revealed significant differences in their complexity and time demand. Activities related to the Accountability Report, especially the consolidation of expenses and revenues, were identified as the most time-consuming, due to the vast amount of financial data accumulated over 18 months. In contrast, the Academic Report and Performance Report activities presented lower complexity, partly because some were already performed by other work fronts or facilitated by a report generation system developed by the Information Technology team. The contribution of the team’s specialists’ expertise was fundamental to exhaust the survey of necessary activities.
In the sequencing of activities, the Precedence Diagramming Method (PDM) was employed to establish the logic and dependencies between tasks. This method allowed for the visualization of activities as interconnected nodes, where each activity, except the first and the last, has a predecessor and a successor, ensuring a feasible schedule (PMI, 2017). It was observed that the activities for the Accountability Reports (consolidation of expenses and revenues) and the Academic Report (student results, course results, and coordinator’s perceptions) did not have direct preceding dependencies, and could be initiated at the project’s zero milestone.
On the other hand, the activities of the Performance Report (student, financial, evaluative indicators, and advisor qualification) showed a Finish-to-Start (FS) dependency in relation to academic consolidation (M2). This means that performance tasks could only begin after the completion of academic data consolidation. This identification of dependencies was crucial for optimizing the workflow and avoiding unnecessary bottlenecks, allowing some tasks to be executed in parallel and contributing to the reduction of the total schedule duration, one of the benefits of schedule management (Carvalho and Rabechini Jr., 2019).
The duration estimate for the activities was performed using the three-point technique (optimistic, most likely, and pessimistic), with the expected duration (tE) calculated by the triangular distribution, according to the equation tE = (tO + tM + tP) / 3 (PMI, 2017). This approach, combined with the analysis of previous similar projects, sought a more realistic estimate for each of the activities. The institutional maximum deadline of 120 days for accountability served as a reference for the unit of measure in days. Short-duration activities, which could be completed in a few hours, were rounded up to one day, considering the need for organization, validation, and potential rework.
The initial estimation of activities resulted in a total time of approximately 163 days for the complete execution of the process without a structured schedule. Critical points were identified in activities such as the verification of the financial document and the validation of enrolled students, which depend heavily on the completion of tasks by other teams (financial, accounting, and academic management) before the Academic Assistance Department can begin its work. These external dependencies, often not formally mapped, were a key factor in the pessimistic overestimation of some durations in previous projects, highlighting a significant bottleneck in the process.
The development of the schedule, using ProjectLibre software and the Gantt chart, allowed for the visualization of the 30 main activities in a temporal perspective. This practical schedule model made it possible to identify the most flexible activities, represented by blue bars, which can be executed in parallel or finished before others, and the points of attention, illustrated in red, which indicate the critical path for monitoring the approval of accountability by the competent bodies. The construction of the Gantt also led to a reassessment and consolidation of activities that, although listed separately in distinct work packages, are, in practice, executed in an integrated manner, such as sending reports for the coordinator’s awareness and evaluation.
With the final schedule proposal, the estimated deadline for the execution of the accountability process was 136 days. This result, when compared to the institutional deadline of 120 days, represents an increase of 16 days, or 13.3% higher than the established limit. However, the structuring of the schedule and the clear definition of the dependency relationships between activities resulted in a reduction of 27 days (16.6%) compared to the estimate of 163 days for the process without formal programming. This efficiency gain is attributed to the possibility of developing tasks in parallel and the formalization of the workflow, which previously depended on tacit knowledge.
The lessons learned during the study highlighted the importance of documenting deadlines and procedures, which were often based on the team’s tacit knowledge. The absence of structured data and the reliance on informal information were significant challenges, especially in estimating activity duration. The need for an adequate level of detail in the WBS and precedence diagram was observed, leading to the consolidation of activities to avoid repetitions and optimize the schedule. The existence of pre-existing templates and the team’s expertise were facilitators, contributing to assertiveness in defining activities and identifying parallel tasks.
Despite advances in schedule structuring and optimization, the study identified important limitations. The main one is that the schedule was not implemented in a real accountability cycle, which made it impossible to practically validate its effectiveness through monitoring and control in a real context. This gap prevents the verification of expected results, such as the reduction of delays and better stage control. The strong dependence on external factors, such as the completion of tasks by other teams, remains a significant bottleneck, requiring continuous monitoring and effective communication to ensure deadlines are met.
In summary, the work managed to structure a schedule management model for the accountability process, formalizing activities and dependencies based on the PMBOK Guide. Although the proposed 136-day schedule exceeds the institutional deadline of 120 days, it represents a reduction of 27 days compared to the unstructured process, demonstrating the efficiency potential of schedule management. The research highlighted the need for documentation and the importance of managing external dependencies, pointing to the relevance of future practical implementations and validations to consolidate the benefits and mitigate the challenges identified in the accountability process.
4. Conclusion
The present study sought to structure a schedule management model for the accountability process of specialization courses in a higher education institution, based on the practices of the PMBOK Guide. The development of a detailed schedule was verified, comprising 30 activities, with an estimated duration of 136 days. This planning represented a reduction of 27 days, or 16.6%, compared to the 163 days estimated for the process without structured scheduling. The formalization of procedures and the clear definition of dependencies between activities, using the Precedence Diagramming Method, were crucial for this optimization. The main contribution lies in offering a formalized workflow and clarifying responsibilities, elements that enhance the reduction of delays and more effective control of the accountability process stages.
However, the non-implementation of the schedule in a real accountability cycle was identified as a limitation, which prevented the practical validation of its effectiveness and the measurement of expected results in an operational context. It was observed that the proposed schedule of 136 days exceeds the institutional deadline of 120 days by 16 days, or 13.3%, indicating the persistence of challenges related to external factors and interdepartmental dependencies. For future studies, it is suggested to implement and monitor this schedule in a real accountability cycle in order to validate its effectiveness and allow for adjustments. It is also recommended to improve communication and monitoring of tasks performed by other teams, aiming to mitigate bottlenecks arising from external dependencies and ensure compliance with established deadlines.
Bibliographic References
Brasil. 2016. Resolução nº 510, de 7 de abril de 2016. Dispõe sobre as normas aplicáveis a pesquisas em Ciências Humanas e Sociais. Diário Oficial da União, Brasília, 24 maio 2016. Seção 1, p. 44-46.
Brito e Sabariz, 2011 [Referência completa não encontrada no documento original]
Carvalho, M. M.; Rabechini Jr., R. 2019. Fundamentos em Gestão de Projetos: construindo competências para gerenciar projetos. 5ed. Atlas, São Paulo, SP, Brasil.
Fraga, B. S.; Barros, M. J. F.; Fialho, S. H. 2018. Grau de efetividade na gestão de projetos em extensão universitária e as estratégias para seu alcance. In: Encontro Nacional dos Cursos de Graduação em Administração, 29, 2018, São Paulo. Disponível em: <https://www.researchgate.net/profile/Manoel-Joaquim-Barros/publication/326095828_Degree_of_Effectiveness_in_Project_Management_in_University_Extension_and_Strategies_to_its_Scope/links/5bb7b845299bf1049b70022b/Degree-of-Effectiveness-in-Project-Management-in-University-Extension-and-Strategies-to-its-Scope.pdf>. Acesso em: 03 out. 2025.
Gil, 2008 [Referência completa não encontrada no documento original]
Instituto do Sindicato das Entidades Mantenedoras de Estabelecimentos de Ensino Superior no Estado de São Paulo [Instituto Semesp]. 2025. Mapa do ensino superior no Brasil. Disponível em: <https://www.semesp.org.br/wp-content/uploads/2025/02/mapa-do-ensino-superior-no-brasil-2025.pdf>. Acesso em: 03 out. 2025.
Kerzner, 2020 [Referência completa não encontrada no documento original]
Pacheco, 2010 [Referência completa não encontrada no documento original]
Prodanov, C. C.; Freitas, E. C. 2013. Metodologia do Trabalho Científico: métodos e técnicas da pesquisa e do trabalho acadêmico. 2ed. Feevale, Novo Hamburgo, RS, Brasil. Disponível em: <https://www.feevale.br/Comum/midias/0163c988-1f5d-496f-b118-a6e009a7a2f9/E-book%20Metodologia%20do%20Trabalho%20Cientifico.pdf>. Acesso em: 04 out. 2025.
Project Management Institute [PMI]. 2017. Guia do Conhecimento em Gerenciamento de Projetos. 6ed. Project Management Institute, Newtown Square, PA, EUA.
Project Management Institute [PMI]. 2018. Pulse of the Profession 2018: Success in Disruptive Times. Disponível em: <https://www.pmi.org/-/media/pmi/documents/public/pdf/learning/thought-leadership/pulse/pulse-of-the-profession-2018.pdf?utm_source=chatgpt.com>. Acesso em: 27 set. 2025.
Turrioni and Mello, 2012 [Full reference not found in the original document]
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq
To learn more about the course, click here and access the MBX Academy platform