The Impact of Strategic Stakeholder Management on the Efficiency and Perceived Success of the Design to Value (DTV) Consulting Room Project.
Leonardo Judice Francé; Samira Sestari do Nascimento
DOI: 10.22167/2675-6528-202601060
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
Effective stakeholder management is crucial for the success of complex projects. This study analyzed the application of strategic stakeholder management in the Design to Value (DTV) Consultório S200 project of a company, aiming to evaluate its influence on efficiency and perceived success. A case study methodology was adopted, complemented by documentary research, which involved the identification, analysis, prioritization, engagement, and monitoring of stakeholders throughout the project lifecycle. Operationalization included monthly indicator meetings and weekly or bi-weekly interdepartmental alignments, in addition to individual meetings, in a company located in Ribeirão Preto, São Paulo. An improvement in communication and alignment between areas was observed, with increased engagement and sense of responsibility. The implementation of activities resulted in significant financial gains, with a projected annual cost reduction of R$ 3,323,440.00 in the Bill of Materials (BOM). The engagement strategy achieved 84.6% effectiveness, despite occasional challenges in areas with high operational load. It was concluded that the application of strategic stakeholder management was effective in improving the efficiency and perceived success of the DTV Consultório S200 project, corroborating the positive impact of this approach on factory implementations and contributing to the literature of Project Management and Strategic Innovation Management.
Keywords: Organizational communication; Case study; Project management; Cost optimization.
1. Introduction
Project management, in its essence, transcends the mere execution of tasks and adherence to schedules, configuring itself as a complex field that demands the orchestration of multiple resources in a dynamic environment (PROJECT MANAGEMENT INSTITUTE, 2021). In this scenario, effective stakeholder management emerges as a fundamental pillar for the success of any undertaking. The ability to adequately identify, analyze, plan, and engage individuals, groups, or organizations that impact or are impacted by a project is crucial for mitigating risks, resolving conflicts, and ensuring alignment of expectations (FREEMAN, 1984). Ignoring the influence and interests of these actors can result in significant delays, increased costs, and, ultimately, project failure. Recent studies indicate that failure in communication and stakeholder engagement is one of the main causes of failure in complex projects, with estimates of up to fifty percent failure (MASCARENHAS, 2025). The relevance of this discipline is amplified in organizational contexts that seek continuous optimization and innovation.
Within the spectrum of project management, the Design to Value (DTV) methodology represents a strategic approach that aims to optimize products and processes, ensuring that their features, quality, and cost are aligned with the customer’s perceived value, while minimizing production costs (PERIDES, 2025). This methodology is particularly relevant in sectors with high competitiveness and constant technological evolution, where the ability to deliver superior value at an efficient cost is a market differentiator. The implementation of DTV projects, due to their multifunctional and transversal nature, demands even more refined stakeholder management, as it involves redefining processes, renegotiating with suppliers, and adapting internal teams, impacting various areas of the organization and its external partners. The complexity of these projects lies not only in the technical and economic challenges but also in managing the expectations and resistances of different interest groups. The integration of strategic stakeholder management into the lifecycle of a DTV project is, therefore, indispensable to ensure that the proposed changes are accepted and implemented.
This study analyzes the application of strategic stakeholder management in the Design to Value (DTV) Consultório S200 project, developed by a company located in Ribeirão Preto, São Paulo. This product is of utmost strategic importance for the company, representing its largest sales volume and impacting revenue and market position. The central problem lies in the complexity of the challenges imposed by stakeholder management, aggravated by a complex organizational context. The company is the result of a recent merger (less than ten years) between two corporations with distinct cultures, generating challenges in cohesion, communication, and expectation alignment. Additionally, the project occurs under intense competitive pressure, with the advancement of international companies in the national market and the company’s own international expansion. The DTV project demanded the engagement of a broad and diverse range of stakeholders, both internal (including CEO, directors, and development teams) and external (clients, suppliers, and regulatory bodies). Effective management required the application of analysis techniques, such as attitude classification and the Power and Influence Matrix, essential for segmenting and planning communication and engagement.
The complexity of the scenario and the strategic relevance of the DTV Consultório S200 project justify this investigation, which seeks to provide valuable insights into how best practices in stakeholder management can be adapted to overcome frictions and achieve cost reduction and value delivery. By analyzing this high-risk, strategically impactful project, the research contributes to the applied literature of Project Management and Strategic Innovation Management, filling gaps regarding the operationalization of these approaches in challenging corporate environments. Given the above, the general objective of this study is to improve the perceived success and efficiency of the Design to Value Consultório project, using stakeholder management to identify the strategic and operational challenges imposed by the organizational and market context, and to evaluate the effectiveness of the engagement approach used.
2. Material and Methods
The present study adopted a research methodology characterized as a case study, with a predominantly practical approach, aiming to deepen the understanding of the application of strategic stakeholder management in a specific organizational context. This methodological choice allowed for a detailed and contextualized analysis of the phenomenon in question, aligning with the applied nature of the Course Conclusion Work. The theoretical foundation for stakeholder management was based on the principles of Stakeholder Theory, as proposed by R. Edward Freeman (1984), which emphasizes the importance of identifying and managing these actors for project success.
The research was developed in a company in the dental sector, located in the city of Ribeirão Preto, in the state of São Paulo. The data collection and analysis period covered the execution phase of the Design to Value (DTV) Consultório S200 project, extending from September 2025 to June 2026, according to the record of activities and indicators. The central unit of analysis was the DTV Consultório S200 project, an undertaking of high strategic relevance for the company, which demanded complex stakeholder management due to its impact on revenue and market position.
The scope of analysis for this case study comprised all stakeholders involved in the DTV Consultório S200 project. The sample consisted of stakeholders identified and categorized as core, internal, and external, whose participation was crucial for the project’s development and success. The selection of these participants was based on the author’s prior experience with the areas involved, considering organizational dynamics, decision-making flows, and the degree of involvement of each party in the specific project context, ensuring the relevance of the analyzed actors.
Data collection was carried out through a combination of instruments and procedures, with emphasis on formal meetings. Project indicator presentation meetings were conducted monthly, allowing for systematic monitoring of progress and challenges. Additionally, interdepartmental alignment meetings occurred weekly or bi-weekly, promoting integration and coordination among the various areas involved in the project. These meetings were essential for obtaining updated information and for collaborative decision-making.
Complementary to the formal meetings, individual meetings were held with specific stakeholders to deepen the understanding of their perspectives, expectations, and potential resistances. Document research also constituted a fundamental tool, encompassing the analysis of documents related to internal and external stakeholders, which allowed for the initial identification and categorization of these groups. The organization’s routine activities, inherent to the project’s day-to-day operations, also supported the continuous collection of relevant information for stakeholder management.
The stakeholder management methodology was structured in six sequential steps, based on Freeman’s Stakeholder Theory (1984). The first step consisted of identifying stakeholders, considering their typology and weight. Next, the expectations and objectives of each stakeholder were sought to be understood. The third step involved planning and prioritizing stakeholders, based on their typology, weight, and influence. Subsequently, engagement and execution of communication strategies were carried out. The final steps were continuous monitoring and control of relationships and the closing of the relationship or transition of responsibilities.
The treatment and analysis of the data began with the classification of stakeholders. To assess the degree of power and interest of the stakeholders, a classification table was used with scores assigned on a scale of one to five for each dimension. Five evaluation criteria were established for both dimensions. Based on these scores, stakeholders were categorized into low (scores one and two), intermediate (score three), and high (scores four and five) levels. This classification supported the development of the Power and Interest Matrix, a visual tool for engagement planning.
Additionally, the level of stakeholder support for the project was assessed. To this end, a rating table was developed with score assignments, using three evaluation criteria, also on a scale of one to five. Based on the sum of these scores, stakeholders were categorized into three groups: supporters, when the sum was equal to or greater than seventeen; neutral, when the values were between fourteen and sixteen; and opponents, when the sum was less than fourteen. This categorization was crucial for defining specific communication and management strategies for each group.
The monitoring and control of engagement actions were carried out through Meeting Minutes (ATAs), managed in spreadsheets. These minutes allowed for systematic tracking of mapped activities, recording their status, responsible parties, and deadlines. Furthermore, the impacts associated with the implemented actions were monitored, focusing on quality improvement and cost reduction. Continuous analysis of these records enabled the evaluation of the effectiveness of engagement strategies and the evolution of stakeholder positioning throughout the project lifecycle, adjusting approaches as needed.
It is important to emphasize that the present study, being a single case study, does not allow for the generalization of its findings to other organizational contexts or projects. The classification of stakeholders, as well as the assessment of their levels of power, interest, and support, was based on the author’s prior experience and knowledge of the company’s specific organizational dynamics. Although this approach was adequate for the objectives of this work, it introduces a subjective perspective that should be considered when interpreting the results.
3. Results and Discussion
The application of strategic stakeholder management in the Design to Value (DTV) S200 Clinic project proved to be a critical factor for improving efficiency and the perceived success of the venture, according to the principles of Freeman’s Stakeholder Theory (1984) and the guidelines of the Project Management Institute (2021). The structured approach, which encompassed the identification, analysis, prioritization, engagement, and continuous monitoring of stakeholders, allowed for more effective alignment between the various areas involved and a strategic direction of actions throughout the entire project lifecycle. This case study, although not generalizable, offers valuable insights into the practical implementation of these methodologies in a complex organizational environment, marked by mergers and intense competitive pressure.
The initial phase of identifying and categorizing stakeholders, as detailed in the methodology section, was crucial for establishing a solid foundation for management. Classification into groups (core, internal, and external) allowed for a granular understanding of each party’s roles and influence, echoing the importance of segmentation proposed by Mascarenhas (2025). The core group, represented by Research and Development (R&D), was recognized as central due to its role in product innovation and optimization. Internal stakeholders, such as CEO, Industrial Engineering, Process Engineering, Procurement, Regulatory/Certification, Technical Support, and Sales, demonstrated the complexity of the organizational structure and the multiplicity of interests that needed to be reconciled. External stakeholders, including Customers, Resellers, Certification Bodies, Financial Institutions supporting research, and Suppliers of materials and inputs, underscored the need for a holistic view that transcends company boundaries. The author’s prior experience within the organization was fundamental to this initial classification, providing a contextualized perspective, but also introducing an element of subjectivity that, while appropriate for the case study’s objectives, should be considered in the interpretation.
The in-depth understanding of each stakeholder’s expectations and objectives, as mapped, was a pillar for the project’s strategic alignment. For R&D, the pursuit of solutions with rapid implementation, quality, and cost reduction was in line with DTV’s overall objective. The CEO, in turn, expected a significant reduction in the Bill of Materials (BOM) cost, an increase in revenue, and an expansion of market share, reflecting the project’s high strategic relevance for the company. These expectations from senior leadership are typical in high-impact projects, where financial return and market position are paramount metrics (Perides, 2025). Industrial Engineering aimed at improving workflow and productivity with minimal layout changes, while Process Engineering sought to optimize production processes and reduce labor costs. Procurement focused on cost renegotiation and the development of new channels, with the adoption of *dual sourcing*, a strategy aimed at mitigating risks of dependence on single suppliers and optimizing costs, as discussed by several authors in supply chain management literature.
External stakeholders also presented distinct, but equally crucial, expectations. Customers expected a high-quality product at a lower price, while Resellers sought a competitive product and stock availability. Certification bodies required continuous compliance with technical standards, and Financial institutions supporting research demanded the demonstration of market potential and economic-financial viability. Suppliers, in turn, sought financial security and long-term commercial relationships. The diversity of these expectations highlights the complexity inherent in stakeholder management in innovation projects, where the ability to balance conflicting demands is a competitive differentiator (Freeman, 1984). Detailed mapping of these expectations allowed the project team to anticipate potential conflicts and develop more targeted communication and engagement strategies, minimizing resistance and maximizing support.
The planning and prioritization of stakeholders were crucial steps, based on criteria of power, interest, and support, in line with classic models such as the Power and Interest Matrix (Mendelow, 1991, cited in Project Management Institute, 2021). The assessment of the degree of power and interest of stakeholders was carried out through a rating table, assigning scores from one to five for each dimension, based on five evaluation criteria. This methodology allowed stakeholders to be categorized into low, intermediate, and high levels, providing a quantitative basis for prioritization.
Table 1. Classification of stakeholder power and interest levels
|
Dimension |
Criterion |
Description |
CEO |
Research and Development (R&D). |
Process Engineering |
Supplies |
Regulatory/ Certification |
Technical Assistance |
Customers |
Sales |
Resales |
Industrial Engineering Teams |
Certifying bodies |
Financial institutions supporting research |
Suppliers of materials and inputs |
|
Power |
Formal authority |
Hierarchical level or institutional position of the stakeholder |
5 |
4 |
2 |
4 |
3 |
1 |
1 |
4 |
1 |
3 |
1 |
1 |
1 |
|
Resource control |
Degree of control over budget, team, technology, or information |
5 |
4 |
2 |
4 |
4 |
1 |
1 |
5 |
1 |
3 |
1 |
5 |
1 |
|
|
Decision-making capacity |
Autonomy to approve, veto, or alter project decisions |
5 |
3 |
3 |
3 |
3 |
1 |
1 |
4 |
1 |
3 |
5 |
2 |
1 |
|
|
Informal influence |
Capacity to influence other stakeholders |
5 |
3 |
3 |
3 |
2 |
2 |
3 |
4 |
2 |
2 |
4 |
3 |
1 |
|
|
Project dependency |
Degree to which the project depends on this stakeholder |
5 |
5 |
4 |
5 |
4 |
3 |
5 |
3 |
3 |
4 |
5 |
5 |
1 |
|
|
Summation |
25 |
19 |
14 |
19 |
16 |
8 |
11 |
20 |
8 |
15 |
16 |
16 |
5 |
||
|
Interest |
Project Impact |
Intensity of the project’s effects on the stakeholder |
5 |
5 |
4 |
4 |
3 |
3 |
5 |
5 |
5 |
4 |
3 |
3 |
5 |
|
Expected benefits |
Perceived earning potential |
5 |
5 |
3 |
4 |
3 |
3 |
5 |
5 |
4 |
4 |
3 |
5 |
3 |
|
|
Perceived risks |
Potential losses or negative impacts |
5 |
5 |
3 |
4 |
4 |
3 |
5 |
5 |
4 |
4 |
3 |
5 |
3 |
|
|
Current engagement |
Level of participation in project activities |
5 |
5 |
3 |
5 |
3 |
3 |
5 |
3 |
3 |
5 |
3 |
4 |
3 |
|
|
Strategic Alignment |
Degree of alignment with project objectives |
5 |
5 |
3 |
5 |
4 |
3 |
4 |
5 |
5 |
5 |
2 |
4 |
3 |
|
|
Summation |
25 |
25 |
16 |
22 |
17 |
15 |
24 |
23 |
21 |
22 |
14 |
21 |
17 |
Source: Elaborated by the author.
As presented in Table 1, the classification of stakeholders by power and interest revealed the distribution of influence and involvement. For example, the CEO and R&D were identified with high power and interest, which positioned them as key actors requiring continuous attention and engagement. In contrast, Suppliers of materials and inputs showed lower power and interest, indicating the need for a more transactional management approach, focused on maintaining the business relationship. The analysis of these scores allowed for the construction of the Power and Interest Matrix, an indispensable visual tool for strategic engagement planning.
Source: Elaborated by the author.
Figure 1. Matrix – Power x Interest
Figure 1, the Power and Interest Matrix, graphically illustrates the position of each stakeholder, allowing for a clear visualization of who should be “managed closely” (high power, high interest), “kept satisfied” (high power, low interest), “kept informed” (low power, high interest), or “monitored” (low power, low interest). This categorization is fundamental for efficient allocation of resources and communication efforts, as emphasized by Mascarenhas (2025). Stakeholders such as the CEO and the financial institutions supporting research, located in the high power and interest quadrant, required proactive and continuous engagement strategies, focusing on decision-making and strategic alignment. Groups such as Technical Assistance and Suppliers of materials and inputs, with lower power and interest, demanded more punctual and informative communication.
Additionally, the assessment of stakeholder support for the project was carried out through another classification table, using three evaluation criteria on a scale of one to five. This classification allowed stakeholders to be categorized as supporters, neutral, and opponents, based on the sum of the scores. This distinction is vital for developing personalized engagement strategies, aiming to strengthen support, convert neutrality, and mitigate opposition. Project management literature frequently highlights the importance of identifying and managing stakeholder attitudes, as resistance can jeopardize the project, even with high power and interest (Project Management Institute, 2021).
Table 2. Classification of stakeholder support level.
|
Dimension |
Criterion |
Description |
CEO |
Research and Development (R&D). |
Process Engineering |
Supplies |
Regulatory/Certification |
Technical Assistance |
Customers |
Sales |
Resales |
Industrial Engineering Teams |
Certifying bodies |
Financial institutions supporting research |
Suppliers of materials and inputs |
|
Support |
Declared positioning |
Explicit opinions on the project |
5 |
5 |
2 |
5 |
3 |
4 |
5 |
5 |
4 |
3 |
1 |
3 |
3 |
|
Support |
Observed behavior |
Practical actions (collaboration or resistance) |
5 |
5 |
2 |
5 |
3 |
4 |
4 |
4 |
4 |
3 |
5 |
4 |
4 |
|
Support |
Interaction history |
Previous experiences with similar projects |
5 |
4 |
1 |
4 |
3 |
3 |
4 |
4 |
4 |
4 |
5 |
5 |
4 |
|
Support |
Confidence Level |
Confidence in the team or project proposal |
5 |
5 |
4 |
5 |
4 |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
|
Summation |
20 |
19 |
9 |
19 |
13 |
16 |
18 |
18 |
17 |
15 |
16 |
17 |
16 |
Source: Elaborated by the author.
As shown in Table 2, the initial classification of stakeholders by level of support revealed that most key players, such as CEO, R&D, Procurement, Customers, Sales, Resellers, and research-supporting financial institutions, were supporters. This favorable initial scenario indicated a good starting point for the project, but also highlighted the need to maintain and nurture this support. Neutral stakeholders, such as Industrial Engineering Teams, Technical Assistance, Certifying Bodies, and Suppliers of materials and inputs, represented an opportunity for proactive engagement, aiming to convert them into supporters. On the other hand, opponents, such as Regulatory/Certification and Process Engineering, required special attention and risk mitigation strategies, as their resistance, often based on technical or regulatory requirements, could generate delays and additional costs. The identification of these groups allowed the project team to develop specific action plans for each category, optimizing engagement efforts.
The engagement and execution phase was where the defined strategies were put into practice, based on the power, interest, and support classifications. Table 3, which details the engagement strategies, served as a guide for interacting with each stakeholder group.
Table 3. Definition of the engagement and execution strategy.
|
Interested party |
Opponent |
Neutral |
Supportive |
Power |
Interest |
Engagement actions |
|
CEO |
C, D |
High |
High |
Monthly meetings throughout the project duration, for monitoring the project’s cost, schedule, and investment indicators. Also included in the project’s technical and design decisions. |
||
|
Research and Development (R&D) |
C, D |
High |
High |
Weekly meetings with the project team throughout the project lifecycle, with the aim of micro-managing activities and reporting statuses. |
||
|
Sales |
C, D |
High |
High |
Monthly meetings throughout the project duration, for monitoring the project’s cost, schedule, and investment indicators. Also included in the project’s technical and design decisions. |
||
|
Industrial Engineering Teams; |
C |
D |
High |
High |
Monthly meetings throughout the project duration, for monitoring the project’s cost, schedule, and investment indicators. Also included in the project’s technical and design decisions. |
|
|
Certifying bodies; |
C, D |
High |
Low |
Sporadic meetings, most of the time for record updates, documentation, support for prototype testing, etc. |
||
|
Regulatory/Certification |
C |
D |
High |
Low |
Sporadic meetings, most of the time for record updates, documentation, support for prototype testing, etc. |
|
|
Process Engineering |
C |
D |
D |
High |
Low |
Sporadic meetings, most of the time for updates on assembly and manufacturing processes of some project negotiations. In some cases, meetings needed to be weekly due to the complexity and size of the implemented activities. Alignments intensify from the middle to the end of the activities. |
|
Supplies |
C, D |
Low |
High |
Meetings held throughout the project, initially bi-weekly, but which became weekly due to the volume of ongoing information/negotiations. This stakeholder’s engagement increased after the implementation of common goals for the DTV project. |
||
|
Resales |
C, D |
Low |
High |
Sporadic meetings, generally quarterly, guiding decisions and the directions the market is taking. |
||
|
Financial institutions supporting research. |
C, D |
Low |
High |
Semiannual meetings to monitor technology development indicators, as a way to verify project progress and adequate allocation of funds. |
||
|
Customers |
C, D |
Low |
High |
Sporadic meetings, with strategic and influential clients in the dental market, with the aim of collecting valuable feedback. More common in scope definitions. |
||
|
Suppliers of materials and inputs. |
C, D |
Low |
Low |
Sporadic meetings, generally together with the supply team solely for technical grounding in proposed cost reduction solutions. |
||
|
Technical Assistance |
C |
D |
Low |
Low |
Sporadic meetings, only for updates and training on implementations that influence customer technical support (whether installation scripts, manuals, training for internal or third-party technicians) |
Source: Elaborated by the author.
Table 3 highlights the diversity of approaches adopted, ranging from monthly meetings with high-power and high-interest stakeholders (such as CEO and R&D) to sporadic meetings with those of lesser influence. For stakeholders classified as supporters, the main objective was to maintain engagement and continuously communicate project progress and benefits. Monthly meetings with senior leadership and R&D, for example, focused on monitoring cost, schedule, and investment indicators, as well as technical and design decisions. This proactive approach is fundamental to ensuring that key decision-makers remain aligned and committed to the project’s success, as advocated by the PMBOK Guide (Project Management Institute, 2021).
For initially neutral or opposing stakeholders, the strategies were more focused on changing positioning. The Industrial Engineering area, initially neutral, was the target of monthly meetings to monitor indicators and decisions, aiming for its evolution to a supportive condition. The importance of transforming neutral stakeholders into supporters is widely recognized in the literature, as they can become project advocates and actively contribute to its success (Mascarenhas, 2025). The Regulatory/Certification and Process Engineering areas, initially classified as opposing due to technical and regulatory requirements, were engaged through sporadic meetings for updates on records, documentation, and support for trials. The complexity and volume of activities implemented, especially in Process Engineering, required meetings to become weekly at times, demonstrating the flexibility of the engagement approach.
Communication and transparency were key elements in the execution of the strategies. Monthly presentations, as illustrated in Figure 2, were an effective mechanism to highlight the relevance of the proposed actions and the benefits generated for the organization.
Source: Elaborated by the author.
Figure 2. Monthly presentations model.
Figure 2 demonstrates the structure of the monthly presentations, which included ongoing themes, next steps, and indicators. This practice of regular and formal communication is vital for keeping all stakeholders informed and engaged, especially in complex projects like DTV Consultório S200, where clarity on progress and challenges can mitigate resistance and build trust. The presentation of concrete data on cost reduction (e.g., pallet and cardboard reduction) and the status of upcoming steps reinforces the project team’s credibility and demonstrates the value generated, aligning with the DTV methodology of “design for value”.
In addition to the monthly high-level meetings, bi-weekly meetings with the Industrial Engineering and Supply Chain areas were implemented, with a more technical character. The objective was to maintain these stakeholders as supporters, given their relevance for the execution of activities. The monitoring and controlling of these actions were carried out through Meeting Minutes (ATAs), managed in electronic spreadsheets, as illustrated in Figure 3.
Source: Elaborated by the author.
Figure 3. ATA model used in weekly follow-ups.
Figure 3 shows an ATA model that recorded activities, responsible parties, status, and completion date. This management tool is fundamental for the systematic monitoring of activities, ensuring accountability and transparency. The use of ATAs to record progress and associated impacts, especially in improving quality and reducing costs, allowed for the evaluation of the effectiveness of engagement strategies and the adjustment of approaches as needed. The intensification of meeting frequency, changing from bi-weekly to weekly as the project advanced, demonstrates the team’s adaptability in response to the increasing volume of topics and the need to improve alignment. This flexibility is a distinctive feature of effective project management in dynamic environments (Perides, 2025).
Continuous monitoring and control revealed a significant improvement in communication and alignment level among the involved areas. Meetings and forums became more fluid and effective, demonstrating greater integration among stakeholders. This result corroborates the literature that points to effective communication as one of the pillars of project success, especially in business merger contexts, where cultural and operational differences can generate friction (Mascarenhas, 2025). The increased sense of belonging and responsibility (“ownership mentality”) among project participants was another positive indicator. The decentralization of the initiative for rapid alignments, which shifted from being centralized with the project leader to being shared among the various stakeholders, suggests a maturation of the team and greater autonomous engagement, a sign of a more collaborative organizational culture.
From the perspective of practical results, the DTV Consultório S200 project demonstrated a notable increase in the number of activities implemented and mapped. Table 4 illustrates the evolution of financial gains (savings) derived from these activities.
Table 4. Savings in reais from activities implemented per month.
|
Date |
Activities |
Monthly Savings (BRL) |
|
09/2025 |
||
|
10/2025 |
||
|
11/2025 |
||
|
12/2025 |
||
|
01/2026 |
Linear actuators cost renegotiation |
BRL 1.809.760,0 |
|
02/2026 |
New Transformer |
BRL 547,200.0 |
|
03/2026 |
New external packaging |
BRL 470,760.0 |
|
04/2026 |
||
|
05/2026 |
New injected Basin |
BRL 437,520.0 |
|
06/2026 |
New seat upholstery |
BRL 58,200.0 |
Source: Elaborated by the author.
Table 4 reveals that, in the first four months (September to December 2025), there was no implementation of activities, which is attributed to the initial phase of applying the stakeholder management methodology. This initial period is crucial for identification, analysis, and planning, and the absence of tangible implementations can be expected as the foundation for engagement is being built. From January 2026 onwards, however, the implementation of planned activities began, generating significant financial gains. The renegotiation of the cost of linear actuators in January 2026, for example, resulted in a saving of R$ 1,809,760.00, demonstrating the direct impact of stakeholder management on reducing BOM costs. Other activities, such as the new transformer and the new external packaging, also generated substantial savings. The projected annual saving, totaling R$ 3,323,440.00, is a testament to the direct contribution of the adopted approach to the project’s financial performance, validating the premise that strategic stakeholder management can lead to tangible and measurable results.
The evaluation of the effectiveness of the execution of stakeholder engagement strategies, after the application of the methodology, was consolidated in Table 5.
Table 5. Result of the engagement and execution strategy.
|
Dimension |
Criterion |
Description |
CEO |
Research and Development (R&D). |
Process Engineering |
Supplies |
Regulatory/Certification |
Technical Assistance |
Customers |
Sales |
Resales |
Industrial Engineering Teams |
Certifying bodies |
Financial institutions supporting research |
Suppliers of materials and inputs |
|
Support |
Declared positioning |
Explicit opinions on the project |
5 |
5 |
2 |
5 |
3 |
4 |
5 |
5 |
4 |
3 |
1 |
3 |
3 |
|
Support |
Observed behavior |
Practical actions (collaboration or resistance) |
5 |
5 |
2 |
5 |
3 |
4 |
4 |
4 |
4 |
3 |
5 |
4 |
4 |
|
Support |
Interaction history |
Previous experiences with similar projects |
5 |
4 |
1 |
4 |
3 |
3 |
4 |
4 |
4 |
4 |
5 |
5 |
4 |
|
Support |
Confidence Level |
Confidence in the team or project proposal |
5 |
5 |
4 |
5 |
4 |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
5 |
|
Summation |
20 |
19 |
9 |
19 |
13 |
16 |
18 |
18 |
17 |
15 |
16 |
17 |
16 |
Source: Elaborated by the author.
According to Table 5, most stakeholders met the established engagement goal, resulting in a success rate of 84.6% compared to the plan. This high effectiveness rate reinforces the validity of the stakeholder management approach used. However, two stakeholders did not reach the desired level: Process Engineering and Technical Assistance. Process Engineering, which was expected to evolve to the supporter level, remained neutral. The explanation for this lies in the small size of the team and its strong focus on maintaining already implemented projects and factory productivity. This pre-existing operational burden limited its capacity for full engagement in the DTV Consultório S200 project. Although it did not become a supporter, the evolution to a neutral position, from an initial classification as an opponent, represents a partial advance and demonstrates that the engagement strategies had some effect, even in the face of operational constraints.
The case of Technical Assistance is similar. Also classified as neutral, it did not reach the goal of becoming a supporter. The team has a priority focus on customer service and support for already implemented projects, which impacted its participation in alignments related to ongoing activities. Maintaining neutral status, despite engagement efforts, underscores the importance of considering stakeholder capacity and availability when planning strategies. In both cases, resource limitations and focus on routine or maintenance activities represented significant barriers to full engagement. This suggests that, in future projects, a more in-depth analysis of stakeholders’ involvement capacity, especially those with a high operational workload, should be conducted to define more realistic engagement goals or to allocate additional resources to facilitate their participation. Literature on project management frequently discusses the tension between new projects and ongoing operations, and how resource allocation and prioritization can impact engagement (Project Management Institute, 2021).
In summary, the results demonstrate that strategic stakeholder management was effective in most cases, promoting robust organizational alignment and generating substantial financial benefits. The 84.6% effectiveness rate in engagement is a strong indicator of the methodology’s success. The limitations observed with Process Engineering and Technical Assistance offer important learnings about the need to adapt engagement strategies to the operational and resource realities of each stakeholder. The ability to identify, analyze, and respond to stakeholder dynamics, even in a complex environment of merger and competitive pressure, was crucial for the perceived success and efficiency of the DTV Consultório S200 project.
4. Conclusion
It is concluded that the objective was achieved, demonstrating that the application of strategic stakeholder management in the Design to Value (DTV) Design Studio S200 project was effective in improving the perceived success and efficiency of the venture. The structured approach to identifying, analyzing, prioritizing, engaging, and monitoring stakeholders promoted robust organizational alignment, optimizing communication and streamlining decision-making processes. The practical results corroborate this effectiveness, showing a significant increase in the number of activities implemented and the generation of substantial financial gains, totaling R$ 3,323,440.00 in projected annual savings. The 84.6% effectiveness rate in stakeholder engagement reinforces the validity of the adopted strategies, even in a complex organizational context with intense competitive pressure.
However, the study presented important limitations, notably the difficulty in achieving the desired level of engagement with the Process Engineering and Technical Assistance areas. These teams, due to their reduced size and priority focus on maintenance activities and support for already implemented projects, could not fully engage, remaining neutral. Furthermore, the initial classification of stakeholders, based on the author’s prior experience, introduced an element of subjectivity inherent in case studies. For future studies, it is suggested to investigate specific strategies for engaging stakeholders with high operational load and limited resources. It is also recommended to conduct quantitative research in different organizational contexts to generalize the findings, as well as longitudinal studies to evaluate the sustainability of engagement and long-term benefits, and to deepen the analysis of the influence of post-merger organizational culture on DTV project management.
Bibliographic References
FREEMAN, R. Edward. Strategic management: a stakeholder approach. Boston: Pitman, 1984.
MASCARENHAS, Janaina. Gerenciamento de stakeholders. Apresentação de slides. São Carlos: Universidade de São Paulo, Escola de Engenharia de São Carlos, 2025.
Mendelow, 1991 [Referência completa não encontrada no documento original]
PERIDES, Maria Paula N. Planejamento do projeto: outros domínios de desempenho. Piracicaba: Universidade de São Paulo, Escola Superior de Agricultura “Luiz de Queiroz” (ESALQ), 2025. Material de aula (apresentação em slides).
PROJECT MANAGEMENT INSTITUTE. A guide to the project management body of knowledge (PMBOK® Guide). 7th ed. Newtown Square, PA: Project Management Institute, 2021.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq