Hybrid Methodology in Public Contracts Schedule Management

Allan Soares Torres; Adriano Machado

DOI: 10.22167/2675-6528-202600555

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

A study investigated the application of hybrid methodologies in the management of schedules in public infrastructure contracts, a sector traditionally marked by the rigidity of the waterfall model. The research was motivated by the inefficiency of purely predictive approaches, which frequently result in delays and lack of transparency in Brazilian public administration. The central objective was to verify the impacts of inserting elements of the agile Scrum framework into the routine of a railway contract inspection team in the southeast region of Brazil, seeking to identify how the hybridization between the predictive and agile model contributed to the mitigation of delays and transparency in decision-making. The adopted methodology was characterized as a qualitative case study, which employed participant observation, documentary analysis, and semi-structured interviews with members of the technical team. The hybridization consisted of integrating agile rituals, such as daily meetings (Daily Scrum), into existing inspection tasks, aiming for greater fluidity in identifying impediments. The results indicated that the fragmentation of macro-tasks into short inspection cycles made contract progress more visible, promoting greater information transparency and agility in problem-solving. The team perceived an improvement in the ability to respond to scope changes and a potentialization of collaboration. It was concluded that the hybridization of schedule management in public contracts is viable and necessary to increase efficiency in the inspection of complex works, demonstrating potential to mitigate delays arising from fragmented communication and excessive bureaucracy, and validating the effectiveness of the proposed framework for the case study.

Keywords: Public Administration; Agility; Works Inspection; Railway Infrastructure; Scrum.

1. Introduction

Project management, traditionally associated with the waterfall model, is characterized by a strictly sequential and linear approach to activities. In this paradigm, progression to a new phase depends on the complete conclusion of the previous stage, which favors detailed planning in contexts of low uncertainty. However, this system faces considerable challenges when project requirements do not remain stable from their initial conception.

One of the main problems with the predictive model lies in the late validation of solutions, which generally occurs only after the completion of actual production. This characteristic frequently results in substantial delays and execution difficulties, as any errors are detected only in the final stages, as pointed out by Pietrzak et al. (2022). The inherent rigidity of these models, which attempts to anticipate all future needs, becomes an obstacle in dynamic environments subject to constant and unpredictable changes (Lalić et al., 2019).

In the Brazilian public administration scenario, contract management faces critical obstacles, with the traditional oversight model often being slow in promoting results that ensure the proper use of resources (Godoi, 2020). Reactive management has proven inefficient in guaranteeing the necessary effectiveness for public services (Cunha et al., 2016). Excessive emphasis on bureaucratic processes and strict formal compliance, to the detriment of practical results, hinders resource optimization and the achievement of advantageous acquisitions.

In contractual environments demanding continuous adaptation, prioritizing rigorous control generates exhaustive documentation, resulting in slow responsiveness to changes and compromising institutional agility (Pinton & Torres, 2020). This hierarchical structure prevents teams from promptly adjusting to new requirements that arise during execution, which is particularly serious in civil works schedules, such as railway ventures, where the inflexible nature of the traditional model makes accommodating scope changes complex and costly, leading to non-compliance with deadlines and budgets (Valadares et al., 2024).

In response to these limitations, agile methodologies emerge as a viable alternative, due to their adaptability to dynamic scenarios (Pinton & Torres, 2020). The application of an agile framework, such as Scrum, in the routine of public contract inspection teams characterizes a hybrid methodology approach. This integration allows for the combination of agile principles with predictive elements to manage complex projects in public agencies, as highlighted by Ali and Sameh (2024).

Hybridization offers a path to achieve greater efficiency in the management of contractual deadlines and schedules, allowing for greater flexibility in scope. This approach is crucial for public administration, which deals with fixed cost constraints while needing to adapt to changing requirements. The present study focuses on the application of this model in a railway infrastructure project in the southeastern region of Brazil (Mergel et al., 2018).

The central problem lies in the inability of traditional models to handle the inherent volatility in large public civil engineering projects. The reliance on linear flows prevents critical impediments from being identified and resolved in a timely manner, leading to contractual delays. This inefficiency compromises the transparency of processes and the correct application of funds allocated to national infrastructure, directly affecting delivery deadlines. It is therefore questioned to what extent the transition to a hybrid routine can mitigate communication and planning failures in construction supervision, impacting the efficiency in meeting project schedules, also considering the perception of collaborators regarding the effectiveness of the new routines implemented in the face of real field challenges.

The justification for this study is based on the need to modernize public management to ensure the delivery of infrastructure works according to their respective contractual schedules. The use of agile artifacts can contribute to greater visibility of the progress of activities and better team allocation, directly reflecting in cost reduction and the effectiveness of technical supervision. This work thus seeks to generate practical recommendations for other managers facing similar challenges in the public sector, offering insights on how to overcome cultural barriers during the transition to more adaptable management models. The central objective of this investigation is to analyze the impacts of implementing Scrum framework rituals on the supervision routine of a public railway contract, aiming to identify, from the team’s perspective, how the hybridization between the predictive model (waterfall) and the agile model contributes to the mitigation of schedule delays and to transparency in decision-making.

2. Material and Methods

The present study adopted a qualitative methodological approach, aimed at a deep understanding of complex phenomena in their natural context, as advocated by Marconi and Lakatos (2017). The nature of the research was characterized as a case study, a suitable method for investigating the application of agile management practices in a large-scale railway infrastructure enterprise, embedded in a real context of public works.

The unit of analysis consisted of the inspection routine of a public railway contract, located in the Southeast region of Brazil. To preserve anonymity and confidentiality, the names of the contracting public organization, the executing company, and the specific cities or states were not disclosed. The inspection team, the empirical object of the study, was composed of a Coordinator (Responsible Inspector), an engineer, and three specialist technicians, totaling five participants.

The methodological intervention consisted of hybridizing management, integrating elements of the Scrum framework into the traditional inspection routine, which was based on the predictive (waterfall) model. This approach did not aim at the integral substitution of existing methods, but rather at the incorporation of agile rites to confer greater dynamism and responsiveness to project demands, adapting to the contractual and normative rigidity inherent in public works (Jocham et al., 2025).

The team structure was organized into three functional pillars, adapted from Scrum: the Product Owner, responsible for prioritizing the activity Backlog according to critical schedule milestones; the Scrum Master, who acted as a facilitator and impediment remover; and the Development Team, composed of engineers and technicians who executed field inspections, documentary analyses, and factory inspections.

For the application of agile rituals, the official physical-financial schedule of the work was used as the project’s Macro-Backlog. The monthly macro-tasks were broken down into smaller items, forming the Sprint Backlog, which was recorded in the minutes of the Contractual Production Meetings, adapted to function as the Sprint planning. Additionally, weekly internal meetings for Sprint Review and Sprint Retrospective, and daily informal Daily Scrums, lasting about 10 minutes, were implemented for activity alignment.

Data collection was carried out through triangulation, combining participant observation, documentary analysis, and semi-structured interviews. The researcher was embedded in the inspection team, which allowed for the recording of the dynamics and interaction of the members in the real context. Documentary analysis included the administrative contract, physical-financial schedules, and meeting minutes, providing an objective basis for the research.

Semi-structured interviews were conducted with members of the inspection team approximately three months after the implementation of the new routine. The interview script was structured into four thematic blocks: Information Transparency; Efficiency and Decision-Making; Communication and Team Dynamics; and Challenges and Cultural Adaptation, based on the pillars of the Scrum framework (Sutherland, 2025) and agile governance guidelines (Mergel et al., 2018).

For the analysis of the collected data, the Content Analysis technique was employed, which involved the systematic coding and categorization of information. The process was divided into three phases: pre-analysis, for organizing and reading the material; material exploration, for coding and identifying units of meaning; and results treatment, for grouping into thematic categories, according to the thematic blocks of the interviews.

Ethical care was rigorously observed, in accordance with CNS Resolutions nº 466/2012 and nº 510/2016. The Ethical Guidance Form [FDE] was completed, and the Institutional Responsible’s Statement of Agreement was obtained. All participants signed the Free and Informed Consent Form [TCLE], ensuring the voluntariness of participation, the confidentiality of their identities, and the anonymity of their responses.

3. Results and Discussion

The implementation of a hybrid methodology in the schedule management of public infrastructure contracts, specifically in a railway undertaking in the southeast region of Brazil, revealed significant impacts on the routine of the inspection team. The transition from a purely predictive model, characterized by rigidity and sequentiality, to an approach that integrates elements of the agile Scrum framework, demonstrated potential to optimize processes and mitigate challenges inherent to the sector. The results obtained, based on participant observation, documentary analysis, and semi-structured interviews, allowed for an understanding of the hybridization dynamics and its repercussions on the dimensions of transparency, efficiency, communication, and cultural adaptation.

The hybridization of the management model was conceived as a strategic junction between the traditional cascade model and the artifacts and rituals of Scrum, recognizing the need for flexibility in a public contractual environment. The official physical-financial schedule of the work, which represents the traditional planning tool, was adapted to function as the project’s Macro-Backlog, establishing legal milestones and deadlines. This integration allowed the predictive structure to define the project’s “destination,” while the agile elements provided the “reaction speed” for the journey, according to the metaphor used by the interviewees.

For the planning of activities, the monthly macro-tasks of the schedule were broken down into smaller items, which began to be recorded in the minutes of the Contractual Production Meetings, functioning as the Sprint Planning and the Sprint Backlog. This adaptation allowed for a more granular view of the activities, facilitating monitoring and management. The inspection team was organized into agile roles, with the engineer acting as Product Owner, prioritizing the backlog, and the specialist technicians forming the Development Team, responsible for executing inspections and issuing reports.

The execution and control rites were marked by the implementation of Daily Scrums, informal daily meetings of approximately ten minutes, aimed at aligning the day’s activities and reviewing previous events. Additionally, weekly internal meetings were established to function as Sprint Review, where “increments” (inspection and commissioning reports) were presented, and Sprint Retrospective, for discussing process improvements. This routine aimed to ensure that the inspection kept pace with the construction execution, avoiding bureaucratic bottlenecks and promoting continuous task prioritization.

Transparency and Information Visibility

One of the most prominent findings of the research was the substantial improvement in the transparency and visibility of contract progress. The fragmentation of macrotasks into short inspection cycles, characteristic of the agile approach, made the progress of activities “visible to everyone,” as reported by team members. This operational clarity is fundamental to the integrity of public procurement, aligning with Godoi’s (2019) thesis on transparency as an essential ethical and practical prerequisite.

The adoption of the Sprint Backlog, adapted from meeting minutes, materialized the concept of active transparency, as proposed by Mergel et al. (2018), by making available information about what was being done and what the next steps would be. The team perceived the elimination of the “feeling that information was lost” throughout the process, which strengthened internal trust and everyone’s ability to see the broader project horizon. Weekly review meetings, in particular, were seen as crucial opportunities to realign routes and correct deviations, ensuring that objectives were understood and achieved.

However, the research also identified an important limitation: maintaining this visibility intrinsically depends on the team’s continuous discipline in keeping artifacts updated. If the executive rigor of agile rites diminishes, transparency risks becoming merely pro forma, reverting to traditional documentary inertia. This highlights the need for a constant commitment to new practices so that the benefits of visibility are not lost in an environment that still values formality.

Agility in Impediment Resolution and Schedule Management

The research revealed a notable shift in decision-making speed and problem-solving ability. Respondents indicated that impediments were now resolved “at their core,” ensuring the continuous evolution of the physical-financial schedule. The “gear” metaphor was frequently used to describe how the waterfall model established the destination (contractual milestones), while Scrum provided the necessary agility for the journey, allowing for a quick response to deviations.

This dynamic directly addressed the risk of late validation, a chronic bottleneck pointed out by Pietrzak et al. (2022), where execution errors are detected only in the final stages of long production cycles. The hybrid methodology allowed the team to overcome bureaucratic rigidity without, however, breaking the legal and normative foundation of the public contract, which is essential in public administration. The ability to identify and address specific problems in the field immediately prevented them from becoming complex issues that would impact the original scope, preventing recurring stoppages.

Despite the gains in agility, a relevant external limitation was identified: the effectiveness of this agility is conditioned by the interface with the contracting company. For problem resolution to be fully efficient, the contracted company also needs to align its response pace with the new rituals implemented by the inspection team. This suggests that hybridization, to be fully effective, may require an extension of the agile approach beyond the limits of the inspection team.

Collaboration and Information Flow in the Team

The introduction of agile rites enhanced the multifunctional capacity of the inspection team, fostering a breakdown of hierarchical barriers and a more pronounced sense of collaboration. Engineers and technicians began to feel that they “play together,” which contrasts with the tendency of excessive bureaucracy in public administration to stifle spontaneous collaboration, as argued by Cunha et al. (2016). The study’s data interpret the hybrid model as an antidote to this inertia, promoting the horizontality essential for managing complex engineering projects.

The structuring of conversation moments, such as daily and weekly meetings, significantly improved communication between team members and with the coordinator. Collaborators reported that this integration allowed for greater knowledge of each other’s work and an enhanced ability to solve problems that, before, might have been outside their direct scope. The flow of technical information became more fluid and less dense, facilitating understanding and decision-making by all involved.

The strengthening of the technical-operational bond was a highlight, with freedom and flexibility in decision-making improving interaction. However, the informality of rituals such as the Daily Scrum may be viewed with skepticism by external control instances or traditional audits, which still prioritize formal records over communication agility. This perception highlights the tension between the need for agility and adherence to bureaucratic protocols, a common challenge in public administration.

Cultural Barriers and Adaptation Challenges

The main difficulty encountered during the transition to the hybrid routine resided in the “bootstrapping” of the method and the acceptance of new concepts by collaborators accustomed to decades of purely predictive models. The resistance detected was not technical in nature, but cultural, requiring increased attention to the human aspects of agile transition, as described by Pinton and Torres (2020). The paradigm shift in established institutions is inherently slow, as warned by Marconi and Lakatos (2017), and the “initial start” was the most delicate moment for the team.

The initial perception of reluctance to accept the new was overcome as collaborators realized the benefits of the new routines as facilitators of work. However, a critical negative point was the difficulty in “selling” the effectiveness of the methodology to senior management, who often remain tied to rigid administrative rituals. This leadership resistance can cause hybridization to remain an isolated “island of efficiency,” vulnerable to changes in contract coordination, without clear institutional sponsorship.

Another cultural and adaptation challenge pointed out was the need to integrate more digital technologies to optimize the recording and retrieval of information. The team suggested the implementation of an integrating software that would allow linking the activity log to cloud platforms, generating reports and facilitating progress monitoring. This technological improvement could complement agile rituals, ensuring that relevant data would not be lost and that transparency would be even more robust, overcoming the dependence on informal records that can be viewed with skepticism by control bodies.

In summary, the implementation of rites from the Scrum framework in the oversight of a public railway contract proved to be a viable and effective approach to mitigate delays and increase transparency. The fragmentation of tasks, agility in resolving impediments, and improved team communication and collaboration were the main positive impacts. Although cultural challenges and the need for alignment with external and superior instances persist, the results indicate that hybridization offers a promising path for modernizing the management of complex projects in Brazilian public administration, validating the potential of the proposed framework for the case study.

4. Conclusion

This study sought to analyze the impacts of implementing rites from the Scrum framework on the routine inspection of a public railway contract, with the aim of identifying how the hybridization between the predictive and agile model contributed to the mitigation of schedule delays and to transparency in decision-making. It was found that the insertion of agile elements, such as the fragmentation of macro-tasks into short inspection cycles and the adoption of rites like daily meetings, promoted a substantial improvement in the transparency and visibility of the contract’s progress. It was observed that information became more accessible to all team members, strengthening internal trust and the ability to respond to changes. The agility in resolving impediments was also enhanced, allowing problems to be addressed “at their core” and avoiding the late validation of errors, a common bottleneck in purely predictive models. Additionally, a significant improvement was identified in collaboration and information flow among team members, who began to act in a more multifunctional and integrated manner, overcoming hierarchical and bureaucratic barriers.

The main contribution of this work lies in demonstrating the viability and effectiveness of hybridizing schedule management in public infrastructure contracts, offering a promising model for modernizing the oversight of complex works in Brazilian public administration. However, the research revealed important limitations, such as the dependence on the team’s continuous discipline to keep agile artifacts updated and the need for alignment with the executing company for the full effectiveness of agility. Cultural barriers were also noted, especially in the initial acceptance of the method and the difficulty in obtaining sponsorship from senior management, which tends to prioritize rigid administrative rituals. For future studies, it is suggested to investigate the integration of digital technologies, such as integrating software, to optimize the recording and retrieval of information, complementing agile rites and ensuring even more robust transparency, which can mitigate the skepticism of external control bodies.

Bibliographic References

Ali, A.; Sameh, H. 2024. Developing a theoretical framework for enhancing green project approaches via Agile methodology. Scientific Reports 14 (1): 1-22.

Cunha, F.A.; Dutra, A.; Binotto, M. 2016. Avaliação dos serviços de licitação para apoiar a gestão administrativa de orgão público municipal. Revista Brasileira de Gestão e Inovação 4 (1): 90-111.

Godoi, C.E.G. 2019. La transparencia como presupuesto de la lucha contra la corrupción en la contratación pública en Brasil. Boletín Mexicano de Derecho Comparado 51 (155): 841-896.

Jocham, R.; Coleman, J.; Sutherland, J. 2025. Scrum Guide Expansion Pack. Disponível em: < https://scrumexpansion.org/scrum-guide-expansion-pack/2025.6/pdf/scrum-guide-expansion-pack.en-us.pdf>. Acesso em: 15 out. 2025.

Lalić, D.C.; Lalic, B.; Gracanin, D.; Tasic, N.; Delic, M.; Medic, N. 2019. Agile vs. Traditional Approach in Project Management: Strategies, Challenges and Reasons to Introduce Agile. Procedia Manufacturing 39 (1): 1407-1414.

Marconi, M.A.; Lakatos, E.M. 2017. Fundamentos de Metodologia Científica. 8ed. Atlas, São Paulo, SP, Brasil.

Mergel, I.; Gong, Y.; Bertot, J. 2018. Agile government: Systematic literature review and future research. Government Information Quarterly 35 (2): 291-298.

Pietrzak, P.; Cieciora, M.; Klimaszewski, K. 2022. The use of traditional and agile PM methodologies in ICT. Journal of Modern Science 49 (2): 509-528.

Pinton, M.; Torres Junior, A.S. 2020. Human Aspects of Agile Transition in Traditional Organizations. Journal of Technology Management & Innovation 15 (3): 62-73.

Valadares, F.S.; Moura, N.C.S.; Pereira, T.N.F.; Arantes, M.O. 2024. Identification of the Main Traditional Project Management Methods Through a Systematic Literature Review. International Journal of Advanced Computer Science and Applications 15 (6): 952-960.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.