Schedule management maturity in Enterprise Resource Planning systems implementation projects

Schedule Management Maturity in Enterprise Resource Planning Systems Implementation Projects

Rodrigo de Almeida Dias; Fabricio Martins Lacerda

DOI: 10.22167/2675-6528-202601403

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The schedule management in Enterprise Resource Planning (ERP) system implementation projects is crucial for operational efficiency and decision-making in complex environments. The maturity of schedule management in ERP system implementation projects was assessed from the perception of involved managers, and improvements were proposed to strengthen monitoring, deadline control, and decision-making during implementation. An applied case study with a qualitative approach was conducted, based on semi-structured interviews with project managers. The data were analyzed by categorical content analysis, using the OPM3 model, radar charts, and management tools such as a prioritization matrix and 5W2H. It was found that the organization presented intermediate maturity (level 3) in schedule management, with formalized but reactive practices, and poorly integrated with predictive analyses. The Work Breakdown Structure (WBS) stood out with advanced maturity (level 4), while planning, sequencing, milestones, and estimates remained at an intermediate level. Monitoring and control showed progress, with identification of delays and formalization of reviews at an advanced level (level 4). The main weakness lay in the management tool, classified at an initial level (level 2), due to limitations in flexibility, integrated view, and indicator generation. The proposed improvements indicated an evolution to the advanced level (level 4), with the adoption of dashboards, comparative reports, and preventive alerts, aiming for more analytical and proactive management. The research contributed by demonstrating the potential for evolution towards a more predictive and data-driven model through technological and managerial enhancements.

Keywords: Management dashboards; Management tool; Management improvements; OPM3; Decision making.

1. Introduction

In the contemporary information technology landscape, Enterprise Resource Planning (ERP) systems are consolidated as strategic pillars for organizational efficiency and competitiveness. The implementation of these systems, however, transcends the mere installation of software, configuring itself as complex projects that demand rigorous management to align processes, integrate teams, and satisfy the client (Hustad et al., 2023). In business environments characterized by the simultaneous execution of multiple projects and frequently negotiated deadlines, schedule management emerges as a determining factor for success. Delivering projects on time directly impacts value generation and company reputation. Empirical studies indicate that IT projects, including ERP implementations, frequently face delays and deadline overruns, resulting in additional costs and dissatisfaction, reinforcing the criticality of robust schedule management.

Schedule management, in this context, goes far beyond the simple allocation of dates. It comprises structured processes of planning, duration estimation, task sequencing, and continuous monitoring and control throughout the project lifecycle (Koszykowski et al., 2025). Understood as a dynamic instrument, an effective schedule must provide robust support for decision-making, enabling risk anticipation and proactive implementation of corrective actions (Abreu et al., 2025). However, practice reveals that many ERP system implementation projects still face significant limitations in continuous progress monitoring, information integration, and agile decision-making support capacity. Such weaknesses frequently culminate in delays, rework, and difficulties in meeting deadlines, compromising efficiency and value delivery.

To understand and improve these practices, the concept of project management maturity emerges as a fundamental analytical lens. Maturity reflects an organization’s degree of development and its capacity to consistently apply project management practices, processes, and methods in a structured and effective manner (Domingues et al., 2023). Lower maturity levels are characterized by reactive and informal approaches, while higher levels denote standardized, integrated processes oriented towards continuous improvement and predictive analysis. The Organizational Project Management Maturity Model (OPM3) is a framework that describes the evolution of organizational capability to align projects with strategy and execute practices in a measurable and improved way (Domingues et al., 2023). Within the scope of schedule management, maturity implies clear planning processes, the use of historical data-based estimates, systematic progress monitoring, and the ability to proactively analyze the impacts of schedule deviations.

Decision-making is intrinsic to schedule management, complicated by the multiplicity of *stakeholders*, conflicting interests, and external constraints in ERP implementation projects. In organizations with lower maturity, decisions tend to be reactive and centralized. In contrast, more advanced levels promote collaborative decisions, based on detailed impact analyses and oriented towards deviation prevention (Suresh et al., 2024). The use of performance indicators and monitoring metrics is crucial. Although recommended, their effectiveness depends on the organizational capacity to interpret and convert information into strategic decisions. In contexts of lower maturity, indicators may be merely descriptive, while at higher levels, they support predictive and preventive analyses, allowing for more proactive management (Kim et al., 2022; Meng et al., 2022). The absence of an integrated view and the limitation in generating comparative reports hinder data-driven decision-making, characterizing low levels of maturity in project management support systems (Li et al., 2017).

Given the complexity of ERP system implementation projects and the fragilities in schedule management, which impact operational efficiency and decision-making, it becomes imperative to understand the maturity level of organizational practices in this domain. The gap in information integration, the reactivity in deviation management, and the limitations of support tools highlight the need for an in-depth diagnosis to identify improvement opportunities. Thus, this work is justified by the relevance of providing subsidies for organizations to evolve towards a more predictive and data-driven schedule management model, strengthening deadline control and strategic decision-making. The objective of this article is to assess the maturity of schedule management in Enterprise Resource Planning system implementation projects, based on the perception of involved managers, and to propose improvements to strengthen monitoring, deadline control, and decision-making during implementation.

2. Material and Methods

This research was characterized as a case study of an applied nature, with a predominantly qualitative approach. The case study was employed to investigate in-depth the phenomenon of maturity in schedule management in ERP system implementation projects, inserted in its real context, as advocated by Cheong et al. (2023). The applied nature of the research aimed to generate practical knowledge, contributing to the improvement of organizational processes and support for managerial decision-making. The qualitative approach, in turn, allowed for the interpretation of managers’ perceptions, seeking to understand the meanings, practices, and limitations of schedule management, valuing the depth of analysis over statistical generalization (Lestyánszka Škůrková et al., 2023).

The study was developed in an organization in the information technology sector, specialized in the development and supply of enterprise resource planning (ERP) systems, as well as in conducting implementation projects for these solutions for clients in different segments. This company operates with integrated management platforms, responsible for centralizing and automating organizational processes, such as finance, operations, logistics, and human resources, promoting greater control and support for decision-making. The organization is responsible for the execution of implementation projects, which involve system configuration, adaptation to client processes, and monitoring of stages until go-live. The interviews were conducted between January 12 and 16, 2026.

The unit of analysis for the research was the schedule management practices in ERP system implementation projects, as perceived by the managers. Managers directly involved in the conduct of these projects, responsible for planning, monitoring, and controlling schedules, were considered respondents. The target population of the study comprised five project managers directly linked to the analyzed organization. Of these, four effectively participated in the research, resulting in a response rate of 80%, a percentage considered adequate for qualitative organizational studies, where the depth of information is more relevant than statistical representativeness.

As exclusion criteria, professionals who did not directly manage projects or participate in decisions related to deadline control were disregarded, ensuring the coherence of the collected information with the study’s objective. The sample, therefore, was by convenience, selected based on the participants’ experience and direct involvement with the research topic. This approach ensured that the perceptions collected were from individuals with in-depth knowledge and practical experience in the analyzed dimensions, contributing to the richness and internal validity of the qualitative data obtained.

For data collection, a semi-structured interview script was used, developed based on the theoretical dimensions of schedule management in projects. The instrument was structured to explore the practices adopted by managers throughout the project lifecycle, allowing for an understanding of formal and operational aspects of time management. The script was organized into thematic blocks, corresponding to the main analytical dimensions of the study, ensuring alignment between the collected data and the analytical concepts used in the research.

The dimensions addressed in the roadmap included schedule planning, which encompassed initial structuring, activity definition, work breakdown structure, and the establishment of control milestones. The second dimension focused on estimates and deadlines, exploring the criteria for defining activity durations, the use of historical data, and the method for defining project deadlines. Subsequently, schedule monitoring and control practices were investigated, including update frequency, mechanisms for identifying delays, and impact analysis on project deadlines.

The fourth dimension addressed the schedule management tool, seeking to identify operational limitations, the level of support for data analysis, and the managers’ capacity for information visualization. The fifth dimension dealt with decision-making, analyzing how managers act in the face of schedule deviations, the level of decision anticipation, and the degree of stakeholder participation in the decision-making process. Finally, the sixth dimension encompassed the proposition of improvements, allowing for the identification of enhancement opportunities in the processes and tools used, based on the managers’ perception.

The theoretical basis that supported the development of the interview script is presented below, detailing the dimensions analyzed and the reference authors who grounded each one. This structure ensured that the questions were pertinent and aligned with consolidated concepts in project management, providing a robust framework for collecting relevant information and the subsequent analysis of the schedule management maturity in the studied organization.

Table 1. Theoretical basis of the interview script

Analyzed dimension

Theoretical description

Main authors base

Schedule planning

Schedule structuring, activity definition, WBS, and milestones

(Suresh et al., 2024)

Estimates and deadlines

Estimation techniques, use of historical data, and duration definition

(Kim et al., 2022)

Monitoring and controlling

Progress tracking, deadline control, and deviation analysis

(PMI, 2021)

Management tool

Technological support, data integration, and information visualization

(Chaabouni et al., 2024)

Decision making

Decision-making process in projects, impact analysis, and stakeholder engagement

(Dasović et al., 2020)

Improvement proposal

Continuous improvement and organizational adaptation

(Abreu et al., 2025)

Source: Original survey data

Before the definitive application, the interview script was submitted to a pre-test with a project manager active in the analyzed organizational context, selected for their direct experience in conducting ERP system implementation projects. The objective of this stage was to assess the clarity of the questions, the adequacy of the language to the organization’s practical context, and the interview application time. From this procedure, punctual adjustments were identified, mainly related to the reformulation of technical terms, simplification of the wording of some questions, and reorganization of the sequence of thematic blocks, aiming to improve the interview flow and ensure greater quality and consistency in the responses.

The five interviews were conducted individually, in a virtual environment, between January 12 and 16, 2026, respecting the participants’ availability. Each interview lasted an average of approximately 40 to 50 minutes, allowing for an objective yet sufficient exploration of the proposed themes to capture the managers’ perceptions of schedule management practices. The responses were recorded in writing during the interviews, ensuring fidelity to the information provided by the participants. Subsequently, the collected data were organized and systematized into a textual *corpus*, structured according to the thematic blocks of the interview script, which enabled the qualitative analysis by categories.

Considering the nature of the research, the absence of sensitive data collection, and the exclusive participation of adults in an organizational context, the study was exempted from review by the CEP/CONEP system, being supported by the Ethics Exemption Form [FDE] issued by ESALQ/USP. All participants were informed about the research objectives and agreed to participate through the Consent agreement [TCLE]. This ethical procedure ensured the voluntariness and protection of the participants, in accordance with the guidelines for research involving human beings in organizational contexts.

The data analysis was conducted through a qualitative approach by categories, defined *a priori* based on the theoretical dimensions of schedule management in projects. The categorical analysis consisted of organizing and interpreting the data from units of meaning grouped into analytical categories, allowing the identification of patterns, convergences, and divergences in the participants’ perceptions (Bardin, 2011). The categories adopted in this study corresponded to the structural blocks of the interview script, enabling the systematization of responses and comparative analysis among managers.

The interpretation of the data was guided by the concept of maturity in project management, understood as the degree of organizational development and capability in the consistent application of project management practices, processes, and methods (Kerzner, 2017). Complementarily, the conceptual reference used was the organizational maturity model proposed by the Project Management Institute, through the *Organizational Project Management Maturity Model* [OPM3], which defines maturity as the organization’s ability to align projects with strategy and execute practices in a standardized, measurable, and continuously improved manner (Domingues et al., 2023).

For the purposes of this study, an ordinal maturity scale ranging from one to five was adopted, representing the evolution of practices from informal and poorly structured levels to more integrated, standardized, and continuous improvement-oriented levels. It should be noted that the application of the maturity concept in this study did not fully follow the OPM3 model in its formal structure, being adopted in an adapted and qualitative manner, with the objective of evaluating the level of development of schedule management practices in the analyzed organizational context.

After consolidating the interviews, an exploratory reading of the collected material was carried out, the initial stage of qualitative analysis that aimed to provide familiarity with the data and identify preliminary patterns (Cheong et al., 2023). This stage allowed for the recognition of key terms, recurring expressions, and operational descriptions related to process maturity, such as schedule update frequency, use of project history, formalization of reviews, tool limitations, impact analysis, and stakeholder participation in decisions.

Next, the content was coded according to the technique of categorical content analysis, which consists of decomposing the material into units of meaning and subsequently regrouping them into analytical categories (Cheong et al., 2023). Initially, units of record were identified in the managers’ statements, which were later grouped into broader categories corresponding to the dimensions of schedule management. This procedure allowed for the systematic organization of information and the identification of patterns, convergences, and divergences among respondents.

The analytical dimensions adopted were defined based on project management best practices, as established by the Project Management Institute [PMI], covering essential aspects of schedule management. Among these dimensions, schedule planning, estimates and deadlines, monitoring and control, the management tool used, and decision-making stand out. Each of these dimensions was analyzed independently, yet considering their interrelationship, since schedule management maturity is understood as a systemic and integrated construct.

The assignment of maturity levels followed a systematic and rigorous procedure. Initially, empirical evidence was extracted from managers’ statements for each dimension analyzed, prioritizing operational descriptions of what actually occurs in schedule management, rather than normative or idealized declarations. Subsequently, this evidence was compared with the maturity scale descriptors, seeking to identify the level that best represented the predominant practice. In cases of divergence between reports, a conservative criterion was adopted, assigning the level corresponding to the most recurrent and representative pattern of the organizational reality, rather than isolated punctual exceptions or individual perceptions.

Furthermore, an internal consistency validation was performed among the evaluated dimensions to avoid inconsistent maturity assignments. For example, dimensions related to monitoring and decision-making were not classified at high levels when the management tool presented significant limitations in flexibility, reporting, or integration, as such restrictions compromise the analytical use of the schedule. This procedure contributed to reducing interpretive biases and ensuring greater robustness to the qualitative analysis. To enable the visual representation of the results, radar charts were used, which allow the simultaneous visualization of multiple dimensions in the same graphical structure, facilitating comparison between variables and the identification of performance gaps.

The prioritization matrix for schedule management improvement actions was developed with the objective of ranking the proposed interventions based on the results obtained in the interviews and the maturity analysis performed. Given the identification of multiple weaknesses and opportunities for improvement, it became necessary to adopt a systematic procedure that would allow the selection of actions with the greatest potential to contribute to the improvement of deadline control and decision-making. The improvement actions were defined from the consolidation of the suggestions presented by the managers in the interviews, especially those related to the limitations of the current tool and the perceived needs for the evolution of schedule management.

After grouping the proposals by conceptual similarity, each action was evaluated according to two criteria: expected impact and implementation effort. To support the analysis, these qualitative criteria were converted into an ordinal scale from one to five, where higher values indicate greater impact or greater effort. For each action, a score for impact and effort was assigned based on the convergence of managers’ perceptions, and the simple arithmetic mean of these evaluations was subsequently calculated when applicable. This procedure was descriptive and analytical in nature, and was used exclusively to support the relative positioning of actions in the matrix.

The 5W2H analysis was applied with the objective of structuring and operationalizing the improvement actions classified as high priority in the impact * effort prioritization matrix. The 5W2H tool consists of a method for planning and organizing actions based on the definition of seven fundamental elements: *What* (what will be done), *Why* (why it will be done), *Where* (where it will be carried out), *When* (when it will be carried out), *Who* (who will be responsible), *How* (how it will be executed), and *How much* (how much it will cost), being widely used to detail and enable the implementation of improvements in organizational contexts (Cioffi et al., 2022).

Finally, a comparative radar chart was developed with the objective of confronting the current situation of schedule management maturity with the proposed situation after the implementation of prioritized improvement actions. The construction of this comparative radar was based on the use of averages of the maturity levels attributed to the analyzed dimensions, allowing for an integrated synthesis of the expected effects of the proposed improvements on the set of evaluated practices. The use of the average as a synthesis procedure was adopted to facilitate visual comparison between the two scenarios and allow for clear identification of the overall evolution of schedule management maturity. This procedure is analytical and illustrative in nature, being suitable for the qualitative context of the study.

3. Results and Discussion

The analyzed organization operates in an environment characterized by the simultaneous execution of multiple ERP system implementation projects, with different levels of complexity and deadlines negotiated directly with clients. This scenario, as highlighted by Hustad et al. (2023), imposes a strong dependence on the performance of project managers to ensure the fulfillment of agreed-upon schedules. Effective schedule management, in this context, transcends the mere definition of dates, becoming a critical element for the overall performance of projects, client satisfaction, and the sustainability of the company’s business model. The inherent complexity of ERP implementation projects, which involve system configuration, process integration, and alignment between technical teams and end-users, elevates the criticality of time management, requiring activity synchronization and timely decision-making to mitigate risks such as delays and rework (Mossa et al., 2025).

The assessment of schedule management maturity, consolidated through interviews with managers, revealed different levels of development in the analyzed dimensions. The maturity scale used, ranging from 1 (non-existent) to 5 (optimized), was guided by classic project management maturity models, which advocate for an incremental progression of organizational processes and practices (Abreu et al., 2025). This qualitative approach allowed for an in-depth understanding of managers’ perceptions, valuing data richness over statistical generalization, aligning with the applied case study methodology (Lestyánszka Škůrková et al., 2023).

Regarding the schedule development, maturity level 3, characterized as intermediate, was assigned. The interviewed managers reported that the schedule is built based on the contracted scope and the client’s go-live expectations, being complemented by technical feasibility studies for adjustments. These findings suggest that, although formal planning practices exist, they remain relatively reactive to external demands and lack deeper integration with organizational strategies and analytical tools for performance forecasting, as pointed out by Al-Marri et al. (2025). The literature on project management maturity, such as PMI’s Organizational Project Management Maturity Model (OPM3), emphasizes that at intermediate levels, organizations formalize basic processes but do not yet integrate them systemically to support predictive and proactive analyses (Domingues et al., 2023). The transition to more advanced levels would require schedule development to be less a response to immediate requirements and more a strategic component, capable of anticipating scenarios and optimizing resource allocation according to business objectives. The implementation of practices that allow for more robust scenario analysis and the integration of the schedule with the organization’s strategic planning would be crucial steps to elevate this maturity level.

Source: Original research results

Figure 1. Representation of the maturity levels of schedule planning practices based on managers’ perceptions.

Regarding the use of the Work Breakdown Structure (WBS), the dimension reached level 4 (advanced maturity), standing out as the most mature among the dimensions analyzed in planning, as illustrated in Figure 1. The WBS is recognized in the literature as one of the key practices in project management maturity models, being essential for decomposing the scope into manageable parts, facilitating detailed planning, and improving communication among stakeholders (Chagas et al., 2021). Models such as the *Project Management Maturity Model* (PMMM) associate the formalization of the WBS and schedule structuring techniques with more advanced maturity levels, reflecting a greater capacity for repeatability and structured control (Abreu et al., 2025). This finding suggests that the organization has a solid foundation in scope definition and work organization, which is an important differentiator. The practical implication is that this strength can be leveraged to improve other dimensions, such as duration estimation and sequencing, by providing a more granular and understandable structure for these activities. The standardization and clarity provided by the WBS can serve as a pillar for the introduction of more agile and iterative methodologies, which, although flexible, still depend on a well-defined scope structure to avoid significant deviations.

Regarding the sequencing of activities, level 3 (intermediate) was assigned. Respondents indicated that sequencing is documented and presented in the *kickoff* phase, with defined dependencies and milestones. However, flexibility during project execution is limited, suggesting a more rigid approach than advocated in the literature. Advanced maturity models emphasize that organizations should treat sequencing as an iterative process, capable of supporting priority adjustments and change management as new information emerges during the project (Domingues et al., 2023). The observed rigidity can lead to rework and delays when unexpected deviations occur, as adaptation to new realities becomes a bureaucratic and time-consuming process. To move forward, the organization could explore the implementation of more flexible approaches, such as *rolling wave* planning or agile methodologies, which allow for continuous reviews and adaptations of sequencing, integrating *feedback* and new information more dynamically. This would require not only changes in tools but also an organizational culture that values adaptability and continuous collaboration among teams and *stakeholders*.

For the definition and control of milestones, level 3 (intermediate) was also observed. Although milestones have clear dates and are supported by formal closing documentation, they are predominantly used as documentary checkpoints, rather than dynamic performance control mechanisms. Project management literature, especially in maturity models, recommends that milestones be used not only to validate completed stages but also as critical analysis points and anticipation of delay risks and impact on the overall schedule (Hartono et al., 2019). Organizational maturity in project management, including planning, control, and integrated use of management tools, tends to develop incrementally, moving from a focus on process formalization to an analytical and continuous improvement-oriented practice (Hartono et al., 2019). The implication is that the organization could transform milestones into triggers for more in-depth reviews, risk analyses, and strategic discussions with stakeholders, using them as opportunities to proactively reassess progress and adjust the project’s course. This would involve creating metrics associated with each milestone that allow for the evaluation not only of deadline compliance but also of delivery quality and residual risks.

The analysis of the dimension “Duration and Schedule Estimates” revealed a level 3 (intermediate) of maturity. Managers indicated the existence of structured mechanisms for estimating activity duration, based on task detailing, complexity of the packages to be deployed, dependencies, and resources involved. The use of historical data from previous projects, consulting documents and lessons learned, corroborates recommended practices for more realistic estimates (Wernicke et al., 2021). The combination of *top-down* and *bottom-up* approaches is frequently recommended to produce more accurate estimates (PMI, 2017).

Source: Original research results

Figure 2. Representation of the maturity levels of estimation practices and deadline definition based on managers’ perceptions.

However, according to Figure 2, the reports also show that durations still depend significantly on averages based on the manager’s individual experience, which, despite being a legitimate practice in intermediate maturity scenarios, can introduce variability and subjectivity into estimates. The organization uses pre-defined clusters in the ERP to establish general delivery dates, configuring a formalized level of temporal restriction (de Vries et al., 2010). Despite this, the internal deadlines for each stage can be negotiated with stakeholders, considering the project’s reality, business demands, and resource availability. This negotiation practice, which goes beyond the mere adherence to rigid dates, demonstrates a trait of intermediate maturity in estimates and deadline negotiations (Balsarini et al., 2021). In more advanced maturity stages, deadlines and estimates are integrated into forecasting and simulation models, such as Monte Carlo analysis and probabilistic modeling techniques, allowing for more accurate completion scenario projections (PMI, 2017). The consistent absence of such practices in the analyzed context, where deadline definition relies mostly on negotiations or pre-defined ERP rules, indicates that the organization is still in an intermediate stage, with clear opportunities for evolution in the use of quantitative methods to reduce subjectivity and increase the reliability of estimates. The practical implication is the need to invest in training for managers on more advanced estimation techniques and in customizing the tool to incorporate functionalities that support probabilistic analyses and the more systematic use of historical data, transforming individual experience into explicit and replicable organizational knowledge.

The monitoring and control dimension of the schedule was analyzed based on the update frequency, delay identification mechanisms, and critical path impact analysis. Regarding the schedule update frequency, level 3 (intermediate maturity) was assigned. The initial schedule is developed at the beginning of the project and updated whenever delays, unforeseen changes, or adjustments are necessary. There are typically few formal revisions throughout the project lifecycle, with updates occurring weekly or bi-weekly, and the expectation that the schedule will undergo minimal changes. This behavior is characteristic of organizations at an intermediate maturity level, where the schedule is monitored but still treated as an artifact that is sought to be kept stable, rather than a dynamic tool for continuous support of decision-making (Kim et al., 2022). The implication is that the organization needs to adopt a more proactive mindset, where the schedule is viewed as a living instrument that must be continuously adjusted and communicated to reflect the project reality and support real-time decisions. This would require the automation of update processes and integration with other project data sources.

Source: Original research results

Figure 3. Maturity levels of schedule monitoring and controlling practices based on managers’ perceptions.

Regarding delay identification, maturity was classified as level 4 (advanced), according to Figure 3. The interviews show that delays are identified through various integrated mechanisms, such as daily activity monitoring, service orders, weekly or bi-weekly status reports, and comparison between planned and actual progress. The non-completion of activities or the inability to proceed to subsequent stages makes delays visible both in the system and on the schedule. The existence of systematic monitoring routines and formal mechanisms for comparing planned and actual progress is a strong indicator of advanced maturity in schedule control, as it allows for timely detection of deviations (Koszykowski et al., 2025). This is a significant strength of the organization, which can be leveraged to enhance other dimensions, such as impact analysis and the preventive nature of decisions. The ability to efficiently identify delays, however, needs to be complemented by an equally efficient ability to analyze their causes and impacts, and to take corrective and preventive actions in a timely manner.

Regarding the critical path impact analysis, level 3 (intermediate) was assigned. Managers reported that, in the face of deviations, delays, or new requests, an analysis of possible impacts on the project schedule and, in some cases, on the project cost is performed. However, these analyses seem to occur in a predominantly qualitative manner, based on the project manager’s experience and visual criticality indicators, such as the “project thermometer,” without the systematic use of more robust quantitative techniques. The literature indicates that critical path analysis tends to be integrated with formal performance analysis methods, such as Earned Value Management (EVM), allowing for more precise assessments of the impacts of deviations throughout the schedule (Li et al., 2017). The practical implication is the need to train managers in the use of quantitative tools and techniques for impact analysis, as well as to integrate these functionalities into the management tool, allowing for scenario simulations and more objective assessments of risks and opportunities.

Finally, regarding the formalization of schedule revisions, maturity was assessed as level 4 (advanced). The results indicate that every schedule update must be justified and recorded in the ERP, requiring agreement from both the company and the client for the revision to be accepted. This process ensures traceability of changes, transparency of decisions, and alignment among the involved parties. The formalization of revisions and control of schedule changes are typical practices of organizations with higher project management maturity, as they reduce conflicts, increase information reliability, and strengthen project governance (Suresh et al., 2024). This is another strength of the organization, demonstrating a commitment to governance and formal communication. However, the effectiveness of this formalization can be compromised if the management tool is not flexible enough to support revisions agilely, or if the impact analysis preceding the revision is predominantly qualitative, introducing subjectivity into the process.

The evaluation of the tool currently used for schedule management revealed significant limitations in supporting project monitoring, control, and analysis, which was identified as the main weakness in the study. Regarding the tool’s flexibility, level 2 (initial maturity) was assigned. Interviews indicate that the tool presents several operational restrictions, such as locks that prevent direct adjustments by the project manager, requiring the opening of formal “*flows*” with service level agreements (*SLAs*) that frequently negatively impact schedule management, as shown in Figure 4. Furthermore, projects with greater complexity or a high degree of customization cannot be tracked in a structured and centralized manner. Low-flexibility management tools limit the project manager’s ability to respond quickly to deviations and changes, a typical characteristic of organizations in the initial stages of maturity in the use of decision support systems (Forcael et al., 2025). The implication is that the current tool acts as a bottleneck, hindering maturity evolution in other dimensions, even where formalized processes exist. The need to open *flows* and wait for *SLAs* for simple adjustments introduces latency into the management process, transforming what should be a support tool into an operational obstacle. The organization needs to consider adopting a more flexible tool that allows managers greater autonomy to make operational adjustments without compromising governance.

Source: Original research results

Figure 4. Schedule management tool maturity levels based on managers’ perceptions.

Regarding the visualization of delays, maturity was classified as level 3 (intermediate). Managers recognize that the tool allows identifying delays by highlighting differences between planned and actual progress, especially when projects are analyzed individually. However, there is a consensus that delay identification could be more agile, particularly due to restrictions in updating the schedule. Concerning the integrated (macro) view of projects, level 2 (initial maturity) was assigned. Responses indicate that, although the tool allows for good visualization of delays in individual projects, it does not offer a consolidated view of the project portfolio, hindering the simultaneous analysis of multiple schedules. This limitation is particularly relevant for managers responsible for several projects, who miss a macro view that allows for prioritization, resource balancing, and identification of systemic risks. The absence of an integrated view is one of the main obstacles to evolving to more advanced maturity levels, especially in organizations that do not yet have consolidated portfolio management practices (Li et al., 2017). The implication is that the organization is operating with a fragmented view of its projects, which hinders strategic decision-making regarding resource allocation and risk mitigation at the portfolio level. The introduction of managerial *dashboards* and macro visualization tools would be essential to overcome this limitation.

Regarding the availability of reports and indicators, maturity was also classified as level 2 (initial). Managers reported the absence of reports or graphs that allow for quick and intuitive analysis of project performance, making it necessary to check each project individually. Furthermore, the tool’s limitation was pointed out regarding the recording of informal information or negotiations carried out during the sales phase, which directly impact deliveries but are not documented in the system. It is known that schedule management tools with low indicator generation capacity hinder data-driven decision-making, restricting the managerial use of information and characterizing low levels of project management support systems maturity (Meng et al., 2022). The implication is that the organization relies excessively on manual analyses and individual manager experience, which introduces subjectivity and inefficiency. The lack of informal information recording also represents a loss of organizational knowledge. Improvement would involve customizing the tool to generate automated reports and dashboards, as well as creating mechanisms to record and integrate negotiation information and other decisions that impact the schedule.

The decision-making dimension was analyzed considering the actions taken when delays are identified, the preventive or reactive nature of decisions, and the actors involved in the decision-making process. Regarding the analysis of impacts resulting from delays, level 4 (advanced maturity) was assigned, according to Figure 5. The interviews indicate that, when a delay is perceived, managers perform structured analyses of the impacts on the schedule and, in some cases, on the project cost, evaluating alternatives that minimize negative effects on implementation. These analyses are generally presented to the client for validation of corrective actions. The ability to assess impacts before decision-making is characteristic of organizations with high maturity, as it allows for more informed decisions aligned with project objectives (PMI, 2021). This is an important strength of the organization, demonstrating a systematic approach to dealing with deviations. The implication is that this analytical capability can be further enhanced by integrating more robust data and using tools that allow for more complex scenario simulations, transforming structured analysis into predictive and optimized analysis.

Source: Original research results

Figure 5. Radar map of decision-making maturity in schedule management

Regarding the preventive nature of decisions, maturity was classified as level 3 (intermediate). Managers reported that they seek to act preventively, maintaining frequent contact with the client and monitoring the project’s evolution to anticipate possible problems. However, they acknowledge that reactive decisions still occur in situations not previously identified or arising from unforeseen events. This behavior highlights that, at intermediate maturity levels, organizations already have continuous monitoring practices but are not yet able to systematically anticipate all risks and deviations, resorting, in part, to corrective actions (Hustad et al., 2023). The implication is that, although there is preventive intention and effort, the lack of predictive tools and an integrated portfolio view prevents consistent proactivity. The organization could benefit from implementing early warning systems and trend analysis, which would allow potential deviations to be identified before they become critical problems, moving from a reactive to a proactive stance.

Regarding the project manager’s autonomy, level 3 (intermediate) was assigned. The responses indicate that the project manager has autonomy to decide in less complex situations; however, decisions with greater impact are frequently escalated to coordination, management, or submitted for client validation. This hybrid model of autonomy and escalation is typical of organizations in an intermediate stage of maturity, where there is still a strong dependence on higher instances for strategic decisions, but there is already room for managerial action at the operational level (Sadovnikova et al., 2023). The implication is that the organization can empower project managers with more data and analytical tools so that they can make more complex decisions autonomously, reducing the need for escalation and accelerating the decision-making process. This would require not only improving the tool but also reviewing policies and training managers.

Finally, regarding decision-making governance, level 4 (advanced maturity) was assigned. The results show that decisions related to delays and schedule adjustments are mostly made jointly, involving the project manager, internal *stakeholders*, and the client. This collaborative decision-making process, based on alignment and shared responsibilities, is associated with higher levels of project management maturity, as it reduces conflicts, increases stakeholder commitment, and strengthens the legitimacy of the decisions made (Sutherland et al., 2022). This is a notable strength of the organization, promoting an environment of collaboration and shared responsibility. The implication is that, with the improvement of tools and the availability of more accurate and integrated data, this collaborative process would become even more efficient and effective, allowing joint decisions to be based on more complete and real-time information.

Based on the results obtained from the analyses of planning, estimates, monitoring, current tool, and decision-making, the need for evolution in schedule management through the adoption of a more flexible, analytical, and deviation-prevention-oriented tool becomes evident. The improvement proposals presented below directly reflect the gaps identified in the maturity maps and the perceptions of the interviewed managers, being aligned with good practices in project management.

Regarding the implementation of *dashboards* and a macro view of projects, maximum relevance (level 5) was assigned, as shown in Figure 6. Managers highlighted the need for a consolidated view of all projects under their responsibility, allowing simultaneous monitoring of schedules, resources, and key milestones. This functionality would enable the early identification of bottlenecks, resource conflicts, and systemic risks, favoring more strategic decisions. The integrated visualization of the project portfolio is a critical factor for increasing organizational maturity, especially in environments with multiple projects running simultaneously (Forcael et al., 2025). The implication is that the implementation of *dashboards* would not only address the macro view gap but also transform how managers interact with data, enabling more proactive and strategic portfolio management.

Source: Original research results

Figure 6. Level of proposed functionalities for schedule management improvement

Regarding the use of automatic preventive alerts, high relevance (level 4) was assigned. Managers indicated that a tool capable of sending daily or periodic alerts to the project manager, indicating deviations between the planned and the actual, or imminent risks to the critical path, would function as a continuous schedule audit. This mechanism would contribute to the transition from a predominantly reactive management to a more preventive approach. Proactive monitoring and alert systems are central characteristics of organizations with higher maturity in project management, as they expand the capacity for anticipation and risk mitigation (Li et al., 2017). The implication is that the automation of alerts would free managers from repetitive monitoring tasks, allowing them to focus on analysis and decision-making, in addition to ensuring that no deviation goes unnoticed, strengthening the preventive nature of management.

Regarding the integrated resource analysis within the schedule, the functionality was assessed with high relevance (level 4). Managers reported the need to associate the Gantt Chart with the resources required for each project, enabling team balancing, overload analysis, and activity prioritization. The integration between schedule and resource management is fundamental to increase deadline reliability and reduce delays arising from operational conflicts, being a typical practice of more advanced levels of project management maturity (Koszykowski et al., 2025). The implication is that optimizing resource allocation, made possible by this integration, would not only improve operational efficiency but also reduce the risks of delays caused by resource bottlenecks, contributing to predictability and deadline adherence.

Finally, regarding the generation of comparative reports and graphs, maximum relevance (level 5) was assigned. Managers highlighted the importance of reports that allow comparing planned versus actual, as well as comparative analyses between different projects, using real-time filters and performance indicators. This functionality would facilitate project progress tracking and support data-driven decisions, reducing reliance on individual and manual analyses (Li et al., 2017). The implication is that the availability of intuitive reports and graphs would transform decision-making, making it more objective, faster, and evidence-based, which is a fundamental pillar for project management maturity.

The prioritization matrix for improvement actions for schedule management was developed from the consolidation of interviews with managers, considering the frequency and recurrence of reported needs, as well as the potential impact of each proposal on improving schedule control, monitoring, and decision-making. The implementation effort was estimated qualitatively, taking into account technical complexity, integration dependency with existing systems, and the need for organizational changes.

Table 2. Prioritization matrix of improvement actions for schedule management

Improvement proposal

Evidence in interviews

Expected Impact

Deployment effort

priority

Dashboards with a macro view of projects

Strong demand for consolidated vision, simultaneous monitoring, and analysis of multiple projects

High

Average

High

Comparative reports and charts (planned × actual / between projects)

Recurring lack of quick and intuitive reports

High

Low

High

Automatic preventive deviation alerts

Desire for daily auditing and preventive action

High

Average

High

Schedule × resource integration

Need for resource balancing and bottleneck analysis

Medium-High

High

Mean

Real-time critical path visualization

Difficulty in advanced analysis and dynamic impacts

Average

Medium-High

Mean

Record of informal information (sale negotiations)

Lack of complete history in the system

Average

Low

Mean

Source: Original research results

Table 2 presents the prioritization of improvement actions. It is observed that actions classified as high priority focus on functionalities related to the macro visualization of projects, comparative reports, and automatic preventive alerts, which present a high expected impact on schedule management and a low to medium implementation effort. These results indicate that the main bottlenecks identified are not associated with the absence of formal planning, but rather with the limitation of analytical and visualization tools, which compromises the capacity for continuous monitoring and preventive decision-making. The implementation of managerial *dashboards* and comparative reports would allow managers to simultaneously track multiple projects, identify deviations more quickly, and reduce dependence on individual and manual analyses. This prioritization approach, which considers multiple criteria such as impact and effort, is widely used in managerial prioritization studies and aligns with PMI best practices (PMI, 2021). Actions classified as medium priority, such as the integration between schedule and resources and the expansion of critical path analyses, although presenting a high potential for improvement, require greater technical and organizational effort for their implementation. Therefore, it is recommended that these initiatives be implemented in a second stage, after the consolidation of improvements with the greatest impact and least effort.

Based on the prioritization matrix (Impact × Effort), actions with high potential for improving schedule management and low to medium implementation effort were selected as high-priority actions, as evidenced in the interviews with managers. The application of the 5W2H tool to high-priority actions shows that the main improvements proposed for schedule management are feasible from an organizational perspective and can be implemented incrementally. The selected actions focus on expanding the analytical and preventive capacity of management, through managerial *dashboards*, comparative reports, and automatic alerts, elements that directly address the gaps identified in the interviews with managers. The 5W2H tool, as a method for planning and organizing actions, is widely used to detail and enable the implementation of improvements in organizational contexts (Cioffi et al., 2022).

Table 3. Action plan (5W2H) for priority improvements in schedule management

Source: Original research results

Table 3 details the 5W2H action plan for priority improvements. The adoption of these improvements in the short term tends to generate significant gains in project performance visibility, deviation anticipation, and decision-making quality, without demanding complex structural changes. Thus, the proposed action plan contributes to the evolution of schedule management maturity, aligning the organization with project management best practices and creating the foundation for the future implementation of more complex initiatives. Structuring these actions through 5W2H ensures clarity regarding objectives, responsibilities, deadlines, and execution methods, facilitating implementation and progress monitoring.

Finally, a comparison was made between the current level of schedule management maturity and the projected level after the implementation of the improvements proposed in the 5W2H analysis. In the current situation, the organization presents predominantly intermediate maturity (level 3) in the dimensions of planning, estimates, monitoring, and decision-making, and initial maturity (level 2) with regard to the schedule management tool, as shown in Figure 7.

Source: Original research results

Figure 7. Comparison of schedule management maturity (current situation × proposed situation)

In the proposed situation, consistent evolution is observed across all analyzed dimensions, with emphasis on the management tool, which shows the greatest relative gain in maturity, moving from level 2 to level 4. This advancement stems from the adoption of managerial *dashboards*, comparative reports, and preventive alerts, functionalities that directly address the gaps identified in the interviews with managers. The dimensions of schedule planning, estimates and deadlines, monitoring and control, and decision-making show an evolution from the intermediate level (3) to the advanced level (4). This progression indicates a transition from predominantly operational and reactive management to a more analytical, integrated, and preventive approach, aligned with project management best practices. The comparative radar highlights that the proposed improvements aim not only at replacing or enhancing the tool used but at systematically elevating the maturity of schedule management, strengthening the use of information to support decision-making, anticipate risks, and effectively control project deadlines. The use of the average as a synthesis procedure, although descriptive, is adequate for the qualitative context of the study, reflecting the convergence of managers’ perceptions and expressing a plausible and incremental maturity target (Abreu et al., 2025).

4. Conclusion

It is concluded that the objective was achieved, evaluating the maturity of schedule management in Enterprise Resource Planning system implementation projects, based on the perception of managers, and proposing improvements to strengthen monitoring, deadline control, and decision-making during implementation. The study revealed that the analyzed organization operates with predominantly intermediate maturity (level 3) in schedule management. Although formalized practices of planning, estimation, monitoring, and decision-making exist, they still prove reactive and lack robust analytical integration. The main identified weakness lies in the management tool used, classified at an initial level (level 2), which imposes significant restrictions on operational flexibility, obtaining an integrated view of the project portfolio, and generating essential performance indicators. The proposed improvements, focused on implementing management dashboards, comparative reports, and automatic preventive alerts, outline a clear path towards more analytical, proactive, and deviation-prevention-oriented management, projecting an evolution to an advanced maturity level (level 4).

This work, however, presents limitations inherent to its qualitative approach and single case study, relying on managers’ perception as the primary data source. Although this approach is suitable for in-depth analysis, it may introduce subjectivity and restricts the statistical generalization of results to other organizations. For future studies, it is recommended to incorporate quantitative performance indicators, such as *Earned Value Management* (EVM), to more objectively assess the impacts of proposed improvements on reducing delays and meeting deadlines. Furthermore, replicating this study in different contexts and sectors, with larger samples, could validate and broaden the findings, contributing to a more comprehensive understanding of schedule management maturity in ERP implementation projects.

Bibliographic References

Abreu, A., Ribeiro, P., e Lima, A. 2025. Analysis of maturity in Project Management of an Information Technology company using the Prado-PMMM methodology. Procedia Computer Science, 256, 1558–1566.

Al-Marri, R., Abdalla, G., e Mahdi, E. 2025. Project management maturity in project-based organizations: frameworks, drivers, and the role of sustainability. Future Business Journal, 11(1).

Balsarini, P., Lambert, C., Ryan, M. M., e MacCarthy, M. 2021. Subjective Knowledge, Perceived Risk, and Information Search when Purchasing a Franchise: A Comparative Exploration from Australia. Journal of Risk and Financial Management, 14(8).

Bardin, 2011 [Referência completa não encontrada no documento original]

Bui, T. T. H., Jambulingam, M., e Amin, M. 2022. A literature review of franchisee performance: Insights for further research. Cogent Business & Management, 9(1).

Chaabouni, M., Jarrar, Q., Medini, K., e Bissardon, F. 2024. A framework for project management software tool selection. Procedia Computer Science, 239, 291-298.

Chagas, F., Passos, F. U., e Figueiredo, P. 2021. Maturity of project teams and the accuracy of the delivered projects in achieving goals. Gestão & Produção, 28(4).

Cheong, H.-i., Lyons, A., Houghton, R., e Majumdar, A. 2023. Secondary Qualitative Research Methodology Using Online Data within the Context of Social Sciences. International Journal of Qualitative Methods, 22.

Cioffi, L. g., e Okada, R. H. 2022. ImplementaÇÃo Da Ferramenta 5w2h No Processo De ProduÇÃo Para a ObtenÇÃo De Resultados E Melhorias No Processo. Revista Interface Tecnológica, 19(2), 974–984.

Dasović, B., Galić, M., e Klanšek, U. 2020. A Survey on Integration of Optimization and Project Management Tools for Sustainable Construction Scheduling. Sustainability, 12(8).

de Vries, R. E., Bakker-Pieper, A., e Oostenveld, W. 2010. Leadership = Communication? The Relations of Leaders’ Communication Styles with Leadership Styles, Knowledge Sharing and Leadership Outcomes. J Bus Psychol, 25(3), 367–380.

Domingues, L., e Ribeiro, P. 2023. Project Management Maturity Models: Proposal of a Framework for Models Comparison. Procedia Computer Science, 219, 2011–2018.

Forcael, E., Cifuentes, L., Nope, A., Garces, G., Casanello, F., e Diaz-Lantada, A. 2025. Implementation of extreme collaboration methodology in a Capstone project course. Sci Rep, 15(1), 39750.

Hartono, B., Wijaya, D. F., e Arini, H. M. 2019. The impact of project risk management maturity on performance: Complexity as a moderating variable. International Journal of Engineering Business Management, 11.

Hustad, E., e Stensholt, J. 2023. Customizing ERP-systems: A framework to support the decision-making process. Procedia Computer Science, 219, 789–796.

Kerzner, 2017 [Referência completa não encontrada no documento original]

Kim, J., Lim, J., Lim, H.-C., e Kim, D. Y. 2022. Improving Sustainable Project Success Strategies Focused on Cost and Schedule for Electrical Construction Project Management. Sustainability, 14(5).

Koszykowski, M., e Orzeszko, W. 2025. Machine learning in project schedule creation: a systematic literature review. Journal of Scheduling.

Lestyánszka Škůrková, K., Fidlerová, H., Niciejewska, M., e Idzikowski, A. 2023. Quality Improvement of the Forging Process Using Pareto Analysis and 8D Methodology in Automotive Manufacturing: A Case Study. Standards, 3(1), 84-94.

Li, X., Xu, J., e Zhang, Q. 2017. Research on Construction Schedule Management Based on BIM Technology. Procedia Engineering, 174, 657–667.

Meng, F., Yu, S., e Xue, J. 2022. Construction Schedule Management System for Large-Scale Construction Projects Based on Multisensor Network. Comput Intell Neurosci, 2022, 3003552.

PMI, 2017 [Referência completa não encontrada no documento original]

PMI, 2021 [Referência completa não encontrada no documento original]

Sadovnikova, A., Kacker, M., e Mishra, S. 2023. Franchising structure changes and shareholder value: Evidence from store buybacks and refranchising. J Acad Mark Sci, 51(5), 1098-1117.

Suresh, D., e Annamalai, S. 2024. Effect of schedule management plan in project management worth using structural equation modelling. An Acad Bras Cienc, 96(2), e20230117.

Sutherland, H., Recchia, G., Dryhurst, S., e Freeman, A. L. J. 2022. How People Understand Risk Matrices, and How Matrix Design Can Improve their Use: Findings from Randomized Controlled Studies. Risk Anal, 42(5), 1023-1041.

Wernicke, B., Stehn, L., Sezer, A. A., e Thunberg, M. 2021. Introduction of a digital maturity assessment framework for construction site operations. International Journal of Construction Management, 23(5), 898–908.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.