Article

October 26, 2026

Lean Construction aiming for alignment between support areas for the delivery of high-standard developments

Ana Laura Cordellini da Silva; Renata Maria Marè Gogliano

DOI: 10.22167/2675-6528-202600552

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

Civil construction frequently faces inefficiencies arising from process fragmentation and lack of integration between sectors. In this context, the application of Lean Construction principles was analyzed as a strategy for alignment between support areas in the delivery of high-standard developments in the city of Curitiba (PR). The study aimed to evaluate how the adoption of lean practices can contribute to improving communication, defining responsibilities, and the overall performance of the development. To this end, a qualitative case study was employed in a large construction company, with an analysis of the planning, costs, projects, budgeting, and construction areas. The results indicated that the application of Lean Construction promoted greater integration between areas, increased information transparency, reduced rework, and greater predictability of activities. Furthermore, improvements were observed in schedule and cost control, as well as greater alignment between the design and execution stages, demonstrating the methodology’s effectiveness in optimizing processes and results.

Keywords: Lean Construction; Project Management; Process Integration; Planning; Productivity.

1. Introduction

The civil construction industry, a sector of great economic and social relevance, is undergoing a continuous process of evolution, encompassing everything from the growth of its various areas of operation to the modernization of its controls, deliverables, and execution methods. However, in the Brazilian context, the quality and efficiency of constructions still fall short of expectations, with managerial problems being pointed out as the main cause of these deficiencies (Isatto et al., 2000). Furthermore, the sector is characterized by high consumption of natural resources and significant generation of waste, often without adequate environmental disposal.

The pursuit of productivity and efficiency in industries and construction dates back to the mid-1950s in Japan, with the emergence of Toyotism. This management model, focused on jobs with defined roles and salaries for each delivery, prioritizes the Just-in-time system, which demands correct production at the right time, with an emphasis on total quality and teamwork. Factors such as union representation and inter-company relations are also crucial elements of this form of organization (Ribeiro, 2015). Since then, business management strategies have constantly adapted to economic dynamics and labor availability, but teamwork remains a fundamental pillar for excellence in delivery.

In civil construction, the implementation of lean principles has proven to be a persistent challenge. The lack of integration between the project conception stages and the production of materials necessary for their execution results in inconsistencies and negative impacts on the performance of ventures. A practical example of this problem can be observed in the conception of facades with irregular fins, where the technical requirements for fire resistance between floors are not always adequately considered in the design phase. This can lead to the need for rework during execution, such as the inclusion of firewalls, generating increased costs, extended construction time, and the need for revision of executive projects and technical manuals.

In this scenario, Lean Construction, also known as Construção Enxuta, emerges as a promising approach to optimize the delivery of high-standard projects. Based on the principles of Lean Manufacturing or the Toyota Production System (TPS), its primary objective is the elimination of waste and the maximization of value with minimal resources. The TPS principles, such as specifying value for the end customer, identifying the value stream, ensuring flow, pull production, and the pursuit of perfection, are adapted in civil construction to encompass suppliers, products, and processes more broadly (Piccirillo et al., 2016).

The application of Lean Construction focuses on eleven essential criteria, including the reduction of non-value-adding activities, the increase of product value according to customer needs, the decrease of variabilities and activity cycle times, the simplification of steps, the increase of process flexibility and transparency, global control through evaluations and indicators, continuous improvement, flow balancing, and benchmarking (Piccirillo et al., 2016). Techniques such as simultaneous engineering, responsible evaluations, daily meetings, Kanban system, and visual inspections are employed to add value to this method. The relevance of Lean Construction is emphasized by the contemporary context, which demands agility, efficiency, and excellence for business competitiveness and sustainability, requiring more assertive and in-depth planning at all stages of the project (Correia, 2018).

The integrated performance of support areas is fundamental to the success of the venture, including in the stages preceding the start of the work. Any disconnects between these areas negatively impact the process as a whole, resulting in rework, information misalignments, schedule delays, inconsistencies between projects and execution, and increased unforeseen costs. The conventional civil construction model, by focusing on subprocesses and considering only the requirements of end customers, neglects the optimization of the system as a whole and the relationship with internal clients (Isatto et al., 2000). The author’s professional experience, as a collaborator of the analyzed company, allowed access to data and the application of the method, reinforcing the practical relevance of this study.

Given this scenario, the present study aimed to analyze the application of Lean Construction principles as a strategy for aligning support areas in the delivery of high-standard developments, evaluating how the adoption of lean practices can contribute to improving communication, defining responsibilities, and the overall performance of the development.

2. Material and Methods

This work was developed based on a case study, adopting a qualitative methodological approach. This choice allowed for the investigation of a contemporary phenomenon within its real context, considering the variables that influence it. The qualitative approach sought to understand the processes and aspects involved in depth, prioritizing descriptive and interpretive analysis over numerical representativeness (Gerhardt et al., 2009). The central objective was to analyze the application of Lean Construction principles as a strategy for alignment between support areas in the delivery of high-standard projects.

The research was applied in a high-standard development, located in the city of Curitiba, Paraná. This development, built by a large construction company, has 26,000 m² of built area, distributed across three independent towers, each with ten floors and one apartment per floor. The units of analysis were the main support areas of the construction company: Planning, Costs, Projects, Budgets, and Construction (execution site). The author’s professional experience as a collaborator of the analyzed company facilitated access to data and the application of the study method.

To structure the scope and organize the development stages of the work, the Work Breakdown Structure (WBS) tool was used. According to the Project Management Institute (PMI, 2021), the WBS consists of a hierarchical decomposition of the total project scope to achieve the project objectives. The WBS developed for the implementation of the Lean Construction methodology in the construction company’s support areas was organized into five macro-phases: Project Management; Diagnosis and Mapping; Process Redesign; Lean Tools Implementation; and Monitoring and Continuous Improvement.

Data collection involved several stages. Initially, a survey of the structuring of support areas was carried out before the implementation of lean construction, including the description of flowcharts, functions, and obligations of each sector. Then, the main “pain points” of each area were identified, aiming to identify disconnections that could cause rework or unforeseen resource expenses. An external consultancy was hired by the company to carry out a detailed mapping between the areas, lasting approximately four months, to understand the deliverables and roles of each sector. This mapping included conversations with the teams to understand routines, task times, and responsibilities.

To assist in the analysis and organization of responsibilities, the PDCA (Plan, Do, Check, Act) methodology was employed, focused on continuous improvement, especially in the Redesign of Processes macro-phase. Additionally, the RACI (Responsible, Accountable, Consulted, and Informed) matrix was used, a management tool to specify roles and responsibilities within organizational processes (PMI, 2021). The application of the RACI matrix allowed for the comparison of the responsibility structure before and after the implementation of Lean Construction. Process flowcharts were developed and compared to visualize the changes and the alignment between support areas.

The Lean Construction tools and practices implemented by the construction company, which were the subject of analysis, included the use of the Prevision platform. This online tool operates with the logic of the balance line or Gantt chart, allowing visual control and the link between work packages. A weekly management tool, organized in a spreadsheet, was also implemented for alignment with contractors and the recording of activity progress. Additionally, visual management boards were developed with the aim of presenting information on ongoing services and performance indicators. Phase planning, divided into ten stages, was established to integrate the previous definitions of the work among all involved areas.

The analysis of the collected data focused on comparing the scenarios before and after the implementation of Lean Construction practices. The main performance indicators of the work were analyzed, covering quality, planning, safety, physical progress, and contingency. The performance records considered refer to the last six months of the work, specifically from September 2025 to February 2026. This period was selected because it corresponded to the time when the company had already completed the diagnosis of the areas and was applying the Lean methodology daily. The analysis of these indicators aimed to understand the evolution of performance and the effectiveness of the implemented changes.

3. Results and Discussion

The integrated performance of support areas in civil construction has proven to be a critical factor for the success of ventures, although the clear definition of their responsibilities and the alignment of objectives throughout the production process still represent significant challenges. The research, conducted at a high-end construction company in Curitiba, aimed to analyze the application of Lean Construction principles to optimize this integration. Information was collected from the author’s professional experience at the company, allowing direct access to data and the application of the methodology, which provided an internal and in-depth perspective on the processes.

Initially, the analysis of the support areas revealed the existing structure and interactions before the implementation of lean practices. The planning department was responsible for monitoring the physical progress of the construction, conducting weekly, monthly, and annual analyses, and developing action plans to achieve the goals. For this, it used the Prevision tool, which operates with the balance line or Gantt chart, assisting in the control of activities on site. However, monthly reprogramming and the dissemination of information, such as service listings and points of attention, were frequently carried out without detailed daily and weekly mapping, which limited the accuracy of the monitoring.

The cost area’s main objective was to map and control construction expenses, using the base budget as a reference. Its routines included monthly meetings for expense closing and projection adjustments, allowing for deviation analysis and the creation of a historical record. The validation of contracts and purchase orders was also an assignment of this department, which monitored cost updates by the National Civil Construction Index (INCC), resulting in a floating budget. This dynamic, although essential, presented challenges in predictability and variation management.

The project sector, one of the first to act in the undertaking, was responsible for the in-depth development of the design elements, in collaboration with specialized designers. The process, which lasted about eighteen months before the start of construction, was divided into preliminary design (AP), executive (EX), and ready for construction (LO), with the objective of ensuring the availability of the LO for the field team at each stage. Despite continuous support for the construction, the monthly analysis of potential incompatibilities between disciplines after the completion of the construction was a point of attention, indicating the need for greater integration in the initial phases.

The budgeting area played a crucial role at the beginning of each venture, working together with the projects department to perform cost analyses and surveys. The budgeting process was structured in three stages – preliminary, launch, and executive – consolidating data for a detailed view of overall costs. After the completion of the executive budget, the department assumed a consultative role, assisting the planning and construction team in clarifying doubts. Budgets served as the basis for planning in Prevision and for monthly cost control, but the lack of involvement from other areas in the initial phases generated inconsistencies.

The construction site, considered the core of the undertaking, was where all information consolidated by support areas materialized into actions. With released projects, defined budget, and ongoing planning, the construction absorbed this data and transformed it into execution, functioning like an industrial production line. Its controls included concrete traceability, structural dates, contractor measurements, cladding surveys, and client inspection control. However, the integrated performance of these areas, especially in the stages preceding the start of construction, was a critical point, as any disconnections negatively impacted the process as a whole.

The initial flowchart of project development in the company revealed critical points, such as the start of the conception with little information and the involvement of the planning area only two months prior for consideration. The release of executive budgets frequently occurred without complete executive projects, and involvement with the project’s peculiarities only happened after the start of construction. This sequence of activities, characterized by fragmentation, contributed to rework and misalignments, as identified in the preliminary process analysis.

The application of the RACI matrix (Responsible, Accountable, Consulted, and Informed) before the implementation of Lean Construction showed a reduced number of agents classified as “consulted” and “informed” in the project sequencing. This observation indicated a low level of alignment between areas, which favored communication failures and late identification of problems. The lack of clarity in responsibilities and the little interaction between sectors were factors that compromised the efficiency and predictability of processes, resulting in performance below expectations for high-standard projects.

Faced with this scenario, the company, which was facing outdated deadlines and costs, in addition to a higher-than-expected technical assistance rate, hired a consultancy to implement the Lean Construction system. The process began with a detailed mapping of the routines and scopes of each area, which lasted about four months. During this phase, the consultancy spoke with the teams to understand the tasks, execution times, those responsible, and the results, seeking to identify the disconnections that most impacted the company’s daily operations and final product.

The identified disconnects were the main points for improvement, leading to alignment meetings. In these meetings, the disconnects were presented, and action plans were developed for each sector, with a three-month deadline for the completion and implementation of adjustments. The objective was to optimize the process as a whole, ensuring that all areas were aligned at every stage of project development, from conception to the final delivery of the work, minimizing incompatibilities and rework.

To guide the improvements, the PDCA (Plan-Do-Check-Act) tool was used in each area. In the planning phase, the problem was the creation of superficial schedules, without weekly control and concrete indicators. The proposed action was the redesign of the process, with the revision of the service flowchart and alignment meetings with the construction team, and its implementation in a model project for control verification. This approach aimed to improve the precision and monitoring capability of activities, making the planning more robust and responsive to the site’s needs.

In the cost area, the challenge was the superficial control of monthly variations and the stipulation of unfounded values for projections. The implemented solution was alignment through the base spreadsheet, with the monthly closing of the indicator and its submission to the board. This change allowed for a more precise validation of funds, based on more reliable projections, and reduced the need to fill in projections with inconsistent data, contributing to more assertive and transparent financial management, aligned with the principles of waste elimination.

For the project sector, the various divergences between the preliminary design (AP) and the executive design (EX) were a recurring problem. The strategy adopted was to subdivide the deliverables, aiming for more reliable releases for the construction site as execution progressed, and the development of a standard for other works. This standardization and the division of projects into a model work, following the phase planning schedule, contributed to the reduction of errors and incompatibilities, ensuring that the field team had access to more consistent projects aligned with the progress of the work.

In the budgeting area, the release of executive budgets without all project definitions was a weakness. The improvement consisted of seeking prior alignment between areas before closing the numbers, involving the project and planning sectors for more refined work. This early integration allowed for deeper project developments, resulting in gains in time and costs, and ensuring greater efficiency from the initial phases of the undertaking, avoiding late adjustments and costly rework.

Finally, in the construction area, the various weekly restrictions, low productivity, and missed targets were the main challenges. The implemented solution was assistance in visualizing below-standard indicators and the creation of action plans based on these indicators, provoking constant monitoring and analysis of discrepancies. This approach allowed for more proactive management of activities, focusing on identifying and resolving problems in real-time, contributing to the continuous improvement of productivity and deadline adherence.

After the implementation of the changes, the planning area began to perform weekly monitoring and more detailed opening of services and deliverables. One of the main previous disconnections, the lack of daily and weekly mapping, was overcome. The work packages, previously generic, such as “Structure”, were subdivided into sub-services such as formwork, rebar assembly for columns, shoring, SPDA (lightning protection system), beam bottom, and concreting, allowing for daily mapping. This granularity in planning, using the Prevision tool as a Gantt chart, provided more detailed and visual control of activities on the construction site.

Additionally, a management tool was implemented that, with each monthly reprogramming, systematically updates the project information, including the medium-term plan (three months) and its constraints. The practice of identifying constraints for each service, such as material purchase or labor, became fundamental for those responsible to develop preventive action plans. The objective was to reduce constraints, ensuring a continuous and uninterrupted production flow, which reflects one of the central principles of Lean Construction of eliminating waste and variability.

With the new management tool, the project managed to consolidate all important information in a single spreadsheet, used for weekly alignment with contractors. This allowed for setting goals and adjusting points of attention, as well as analyzing the assertiveness of the planning on a weekly basis. All projects became standardized and evaluated with the same parameters and information, promoting greater transparency and control. This standardization contributed to the reduction of variability and the increase of operational reliability, essential elements for efficiency in civil construction (Isatto et al., 2000).

Still in the planning phase, a visual management board was developed with the objective of making the information from the last month of the construction project accessible and visual for all stakeholders. This board consisted of two sections: one for the ongoing services from the previous and current week, with productivity indicators and completion percentages, organized by companies based on the ABC curve (groups A and B, representing 95% of the total construction cost); and another for the main indicators of the construction project for the last month, such as quality, safety, planning, cost closing, and inspection release evaluations.

These visual management boards began to be used as a scoring parameter in planning and quality evaluations, with the aim of recognizing outstanding works of the month. The results obtained were linked to the Prêmio Nota 10 (Grade 10 Award), a financial incentive for the field team, associating responsibility for meeting partial goals, such as cost and deadline, not only with the administrative team but also with production. The constant updating of these boards became a vital internal control for the work and support areas, reinforcing the culture of continuous improvement.

One of the most significant changes in the planning area was the implementation of phased planning, which encompassed all areas in the previous definitions of the work. This planning, divided into ten phases (from the site setup to the delivery of the units), involved not only the planning sector, but also projects, product, and site engineers. This approach allowed incompatibilities to be raised beforehand, with ample time for effective resolution, without impacting the project’s deadline or cost, promoting a more robust alignment from the initial stages.

In the cost area, the main change focused on the method of controlling financial projections. Previously, the entire budget was readjusted by the National Construction Cost Index (INCC); with the change, the update occurs only on the packages of the Project Breakdown Structure (EAP) that have not yet been contracted. This modification allowed for more precise control of variations, preventing amounts already delivered from being automatically characterized as positive variation, which made it difficult to measure cost reduction targets and manage urgencies.

With the implementation of the new methodology, the project began to have a variable contingency throughout the months. Every quarter, the company’s board evaluates the possibility of reducing this contingency, withdrawing amounts to be incorporated into the results, based on the analysis of opportunities and risks identified by the project team. This approach provided greater control over financial projections and support for decision-making, contributing to savings of approximately two million from the base budget, a result of reengineering and leveraging opportunities identified by Lean.

In the projects sector, the main change was the improvement in the delivery times of the different phases, which previously presented recurring delays and divergences. With phase planning, developed jointly with the planning and construction teams, the projects area gained greater clarity on priority work fronts. This enabled the organization of the release schedule according to the execution logic, ensuring that the construction site was not left without projects when starting specific services, as in the example of developments with multiple towers, where the execution of the structure of Tower 2 guided the other disciplines.

Other implemented improvements included project compatibility through the BIM (Building Information Modeling) methodology. This approach aims for more precise quantity extraction, optimization of team time, and reduction of errors in surveys, integrating the main characteristics and disciplines of the undertaking on a single platform (Jalali, 2009). A practical example of the positive impact was the customization of units, for which the adjustment survey began to be carried out about a year before the final delivery, allowing the development of action plans for discrepancies and resulting in the unit’s delivery even before the certificate of completion of the work, increasing customer reliability.

The budgeting area, aligned with the logic of phased planning, has undergone significant changes in its process, especially in the involvement of other sectors in budget preparation. Since the preliminary phase, the planning and construction areas have actively participated, seeking optimization solutions from the beginning, such as defining attack fronts, surveying equipment, developing histograms, and opening packages according to the degree of design complexity. This early integration allowed for the identification of unharmonized items in the initial phases, enabling adjustments before the start of construction.

Furthermore, the surveys from the budgeting area were reorganized to serve both the planning area, in the process of weighting weights in the Prevision tool, and the construction site, in the elaboration of hiring frameworks. This change contributed to the reduction of time dedicated to *on-site* surveys by the field team, optimizing work and ensuring greater coherence between budget, planning, and execution. The early participation of other areas in the budgeting process reduced the need for adjustments during construction, assisting in the monthly justifications for closing service packages.

The construction sector consolidated the changes implemented in the other sectors, assuming the role of information centralization and systematic activity monitoring. Its responsibilities now include the elaboration of phase planning together with the other areas, the presentation of this planning to the board with the justification of the action plan, the presentation of monthly cost variations, the weekly update of the activity management tool, the maintenance of visual management boards, and the weekly or daily update of restrictions. These actions aimed to engage the support chain (management and board) whenever necessary, ensuring the continuous flow of information.

The revised project development flowchart, after applying Lean Construction principles, demonstrated a significant alteration in how areas interact. Constant alignment was observed during project conceptions, a project schedule meeting budget and planning priorities, and the development of considerations and action plans before construction began. The organization of the Work Breakdown Structure (WBS) for variation control and the technical development of the project, seeking efficiency, were centralized in phase planning, evidencing a more robust and continuous integration.

The RACI matrix post-Lean Construction revealed a significant increase in interactions between sectors, especially in the “consulted” and “informed” categories. This expansion of participation and information sharing reflected greater integration in the decision-making flow, providing the company with much greater predictability. This predictability was not limited to the current month’s scenario but extended to the annual project outlook, facilitating strategic and operational decision-making. The increased clarity in defining responsibilities and the visibility of information between areas were direct results of applying lean practices.

The performance evaluation through indicators, referring to the last six months (September 2025 to February 2026), the period of daily application of the methodology, showed a gradual evolution. In quality indicators, the assessed score consistently remained above the target of 85, reaching 100 in January 2026 and 95.7 in February 2026, with positive deviations. This indicates greater process control and adherence to established routines, reflecting the standardization of activities and the expansion of visual management, fundamental principles of lean construction that reduce variability and increase operational reliability.

In the planning, the calculated score showed fluctuations, with negative deviations of -8.8 in November 2025 and -12.7 in February 2026, compared to the target of 85. These deviations in February 2026, along with a deviation of -0.92% in physical execution, were attributed to the annual replanning of the works, which occurs in the second half of January. The reprogramming for January and February was not carried out at the beginning of the period, but only in March, compromising the evaluation parameters and generating greater fragility in control, as the January deviations could not be properly incorporated into the planning.

The safety indicator, with a target of 85, generally showed scores above expectations, such as 91.1 in October 2025 and 91.3 in February 2026. However, in January 2026, there was a negative deviation of -0.2 points, resulting from four workplace accidents on the construction site, a criterion with significant weight in the evaluation. Furthermore, the item “High-Risk Area or Services” performed only regularly, which may be related to the finishing and handover phase of the work, characterized by an accumulation of activities and tighter deadlines, which may have reduced the rigor of controls in higher-risk services.

The analysis of the monthly physical progress of the work revealed greater consistency in its evolution, both in the planned and the actual progress, demonstrating a more continuous and predictable production flow, even with negative deviations. Although physical execution was the most challenging indicator to meet the target, with deviations of -0.03% in September 2025 and -0.92% in February 2026, the general trend pointed towards an improvement in predictability. This difficulty in achieving the target is often linked to the dependence on third parties, such as contractors and material suppliers, and to the inherent productivity of the construction process.

The contingency indicators demonstrated greater control over financial variations throughout the analyzed period, with contingency values that fluctuated but indicated an evolution in the capacity for risk anticipation and decision-making. For example, the contingency of 1,542,784 in September 2025 rose to 1,661,567 in February 2026, with a withdrawal of value in November 2025 for the company’s internal results. This improvement can be associated with greater integration between the cost, planning, and construction areas, and the use of continuous monitoring mechanisms, in line with the Lean principle of global process control.

In summary, the implementation of Lean Construction principles at the analyzed construction company promoted direct and positive impacts on process performance, especially regarding the integration between sectors, the predictability of activities, and the control of results. An increase was observed in the level of detail of work packages and in the incorporation of constraint control in planning, resulting in greater predictability and better adherence to the schedule. In the cost area, the review of the budget update method and the introduction of contingency mechanisms allowed for more precise control of financial projections, generating significant savings.

The project sector benefited from integration with phase planning, which resulted in greater alignment between project deliverables and construction needs, reducing delays and incompatibilities. The adoption of compatibility practices, such as BIM, improved the quality of information and the predictability of planning. In the budgeting area, the early participation of other areas in the elaboration process allowed for the early identification of inconsistencies, reducing the need for adjustments during construction and promoting greater coherence between budget, planning, and execution. The construction, in turn, consolidated these changes, assuming a central role in information management and systematic activity monitoring, with the use of visual management tools and constraint control, which favored the monitoring of execution conditions and communication among those involved. The effectiveness of these changes, however, is conditioned by the continuity of the adopted practices and the constant alignment among all agents involved.

4. Conclusion

This study analyzed the application of Lean Construction principles as a strategy for aligning support areas in the delivery of high-standard developments in Curitiba (PR). It was found that the implementation of lean practices promoted a significant transformation in the construction company’s internal processes. Before the intervention, fragmentation, communication failures, and inconsistencies were identified, resulting in rework, delays, and unforeseen costs. With the adoption of Lean Construction, greater integration was observed between the planning, costs, projects, budgeting, and construction departments. This integration manifested in increased information transparency, clear definition of responsibilities, and improved interdepartmental communication. The use of tools such as the PDCA cycle, the RACI matrix, and detailed phase planning enabled the reduction of rework and increased activity predictability, positively impacting the overall performance of the development. Furthermore, more precise control of deadlines and costs was noted, with early identification of inconsistencies and significant cost savings, such as a reduction of approximately two million from the base budget. The main contribution of this work lies in the practical demonstration of Lean Construction’s effectiveness in optimizing project management in high-standard civil construction, providing an integration model that enhances the efficiency and quality of deliverables.

Despite the advances, the study identified some limitations and challenges. Fluctuations were observed in planning and safety indicators during certain periods, such as in February 2026, due to annual replanning and occasional occurrences of workplace accidents. Physical execution, although more consistent, still faced difficulties in achieving targets, often associated with dependence on third parties and the inherent productivity of the construction process. For future studies, it is suggested to deepen the Lean philosophy in the organization, with the structuring of a continuous improvement program that includes the clear definition of responsible parties, goals, and the systematic recording of lessons learned. It is also recommended to improve the planning system through the Last Planner System, focusing on the analysis and removal of constraints and on increasing the reliability of short-term plans, using indicators such as the Percent Plan Complete (PPC). Strengthening the Lean culture at all levels of the organization, through continuous training and encouragement of active team participation in identifying improvements, and the evolution of production control with the standardization of productivity indicators and rework rates, are essential for more efficient management oriented towards data-driven decision-making.

Bibliographic References

Correia, 2018 [Referência completa não encontrada no documento original]

Gerhardt et al., 2009 [Referência completa não encontrada no documento original]

ISATTO, Eduardo Luis et al. Lean Construction: diretrizes e ferramentas para o controle de perdas na construção civil. Porto Alegre, 2000.

JALALI, Said. Metodologia BIM: Building Information Modeling na direcção técnica de obras. Braga, 2009.

Piccirillo et al., 2016 [Referência completa não encontrada no documento original]

PROJECT MANAGEMENT INSTITUTE (PMI). A guide to the project management body of knowledge (PMBOK guide). 7. ed. Newtown Square, PA: PMI, 2021.

RIBEIRO, Andressa. Taylorismo, fordismo e toyotismo. Bahia, 2015.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.