October 27, 2026
Inclusion of definitive energy connection processes in the management of construction project schedules in civil construction
Lucas Samofalov Diniz; Daniel Spinoso Prado
DOI: 10.22167/2675-6528-202601115
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
The construction sector faces challenges that directly impact project costs, making schedule management an essential strategic tool for planning and monitoring activities. The study analyzed and proposed improvements in schedules for social housing construction projects, with an emphasis on incorporating the necessary steps for the definitive connection of electrical energy, including the execution and inspection of the metering center. The research, descriptive in nature, was based on documentary analysis and observation of the processes of a construction company in São Paulo. Historical records of electrical connections and project schedules were examined, applying best practices from the Project Management Body of Knowledge (PMBOK) Guide. Activities were identified, sequenced by the Precedence Diagramming Method (PDM), and their durations were estimated by expert opinion. The schedule was developed in Microsoft Project. As a result, an updated schedule was developed that incorporated the definitive energization steps, detailing activities, dependencies, and regulatory deadlines. A significant reduction was observed in the estimated time for the completion of the steps under the responsibility of the construction company, decreasing from historically higher scenarios of over 400 to approximately 250 days. It was concluded that the systematic inclusion of these steps in the schedule increased predictability, reduced risks, and strengthened time management, contributing to the technical, financial, and contractual success of the projects, especially in Social Housing projects.
Keywords: Dealership; Buildings; Time management; Social housing; Predictability.
1. Introduction
The construction sector plays a fundamental role in the global economy (Al Hashid et al., 2020). However, it is intrinsically complex and subject to challenges that directly impact the viability and success of ventures. The dynamism and volatility of the current economic context, characterized by market fluctuations and competitive pressures, demand from organizations a continuous capacity for adaptation and improvement of their processes (Cavalcanti and Silveira, 2016). In this scenario, project management emerges as an essential strategic discipline, enabling companies to respond with agility and efficiency to demands (Carvalho and Rabechini Jr., 2018). The adoption of robust management models and investment in project management practices, methods, and tools become imperative for achieving organizational goals in highly competitive environments (Kaufmann and Kock, 2022). The absence of effective management often results in delays, budget overruns, and compromised quality, affecting the sustainability of construction companies.
Schedule control takes a prominent position as a strategic tool for planning, organizing, and monitoring activities. The project schedule is one of the central artifacts of Time Management, translating the overall strategy into a structured temporal plan (PMI, 2017). Its function involves defining logical sequencing, estimating durations, and identifying critical milestones, essential for delivery within the established scope and deadline. Beyond its operational function, the schedule plays a strategic role in communication and aligning stakeholder expectations, acting as a temporal contract (Kerzner, 2017). The accuracy and reliability of a schedule are directly linked to the methodology employed in its development, requiring rigorous ordering of activities, mapping of interdependencies, and application of consistent duration estimation techniques (Cavalcanti and Silveira, 2016). Failures in this process, such as inaccurate estimates or optimistic assumptions, can lead to unfeasible schedules, compromising overall project performance and causing cascading effects on resource allocation, costs, and quality (Kerzner, 2017).
Despite the recognized importance of schedule management, it is observed that in many civil construction ventures, critical stages are frequently underestimated or treated generically. A notorious example is the definitive electrical power connection process, which, although fundamental for the asset’s delivery and operation, is often not adequately detailed in conventional schedules. Activities such as technical feasibility requests, electrical project approvals, external infrastructure execution, connection point installation, and utility inspections are frequently omitted or implicitly treated, hindering precise deadline planning and critical path identification. This gap is particularly problematic in Social Interest Housing (HIS) projects, which are intended for low-income populations and are intrinsically linked to public policies and subsidies, with strict contractual and financial restrictions (Brasil, 2001; Bonduki, 1998; São Paulo, 2014). In these ventures, resource disbursements by financial institutions, such as Caixa Econômica Federal (2020), are rigidly tied to physical-financial progress, making any delay in energization a critical risk factor that can suspend disbursements, generate contractual penalties, and compromise the project’s economic feasibility (Kerzner, 2017). Historical data from similar ventures reveal that the effective time for the definitive power connection, from the budget request to energization, can exceed 400 days, highlighting the unpredictability and inefficiency of existing planning models.
The lack of detail and inadequate management of the final electricity connection stages in the schedules, evidenced by historical delays exceeding 400 days, represents a significant risk to the success of developments, particularly in Social Housing, where the financial and contractual consequences are severe. Dependence on individual experience and the lack of a structured process generate unpredictability. Thus, the analysis and proposal of improvements in construction schedules for social interest buildings are justified. The objective is to explicitly incorporate the final electricity connection stages, including the execution and inspection of the metering center, aiming to improve predictability, reduce risks, and strengthen time management, contributing to the technical, financial, and contractual success of the projects.
2. Material and Methods
The research was characterized as descriptive, according to Gil (2017), having as its primary purpose the study and description of the characteristics of a given phenomenon or group, without, however, manipulating variables or attributing cause-and-effect relationships. Complementarily, Vergara (2020) emphasizes that studies of this nature seek to expose specific characteristics of a population or fact, contributing to the expansion of understanding about the investigated topic. This approach was fundamental to detailing existing practices and identifying opportunities for improvement in construction schedules.
The study was conducted at a construction and development company based in the Vila Olímpia region, in São Paulo, Brazil. This company has a diversified portfolio, including high, medium, and low-standard residential developments. The unit of analysis focused on Social Interest Housing (HIS) and Popular Market Housing (HMP) developments undertaken by the company. The analysis period covered records from the last three years, providing a historical basis for understanding the timelines and processes involved in the electricity connection.
The selection of HIS and HMP developments for analysis was justified by their greater sensitivity to schedule variations, especially due to the strict contractual restrictions imposed by the financing agents. Unlike high-standard projects, these developments operate with reduced profit margins and critically depend on the release of funds tied to physical-financial progress. The sample consisted of historical records of projects with similar electrical and civil characteristics, including plots with two to four towers, an implantation floor, ground floor, and typical floors varying between nine and twenty stories, with approximately ten apartments per floor.
For data collection, several instruments and procedures were used. Initially, a comprehensive documentary analysis was carried out, which included the examination of the internal document called “escadinha” and Excel spreadsheets containing the record of energy connection dates for previous projects. Additionally, institutional records related to similar projects were consulted, and current processes related to the elaboration of construction schedules were analyzed, in collaboration with the construction company’s planning department. This approach allowed for the understanding of current practices and the identification of gaps in the schedule’s detail.
Complementary to the documentary analysis, the expert judgment technique was employed to estimate activity durations. This technique, according to Kerzner (2017) and Vargas (2019), is valuable for incorporating lessons learned and institutional knowledge, increasing the reliability and feasibility of the schedule. The study was also based on project management best practices, according to the Project Management Body of Knowledge (PMBOK) Guide (PMI, 2017), which served as a theoretical and practical framework for structuring and improving the schedule.
The research execution followed a structured sequence of steps. The initial phase consisted of planning the schedule management, where the “escadinha” document and the Excel spreadsheet with the call history were analyzed. Institutional records and schedule development processes were consulted with the planning department. Subsequently, the definition of the indispensable activities for the definitive energy connection was carried out, structured through a Work Breakdown Structure (WBS), ensuring that the scope was detailed and all essential tasks were identified.
After defining the activities, the next step was sequencing, which involved the logical organization of tasks. For this, the Precedence Diagramming Method (PDM) was used, a technique that graphically represents the logical dependencies between activities, including the four types of relationships (Finish to Start, Finish to Finish, Start to Start, and Start to Finish), as well as leads and lags (Vargas, 2019). The estimation of activity durations was carried out through the expert opinion of the construction planning team, based on their tacit knowledge and practical experience.
The development of the schedule was the subsequent step, integrating sequencing, duration, resource, and constraint information to build the project timeline. For the preparation and presentation of the schedule, the “Microsoft Project” (MS Project) platform was used, which allowed for the systematic organization, visualization, and monitoring of the planned stages through a Gantt Chart. The multidisciplinary integration process, from the Preliminary Study (EP) to the Executive Project (PE), was fundamental to reconcile the disciplines and ensure constructive coherence (Kerzner, 2017).
Within the integration process, the electrical team requested a preliminary consultation from the ENEL utility company to validate technical concepts and confirm the feasibility of the energy supply. This stage was crucial for identifying specific requirements and necessary notes for the development of the executive project. Subsequently, in the Executive Project phase, the electrical designer submitted the request for preliminary project analysis to the utility company, aiming for authorization to construct the metering center and compliance with current standards, culminating in the issuance of a project release letter.
The collected data, including historical records of electricity connection deadlines and schedule development processes, were treated through comparative analysis. The granularity of the construction company’s traditional schedules was examined, contrasting them with PMBOK best practices and the detailing needs of the final energy connection stages. This analysis allowed for the identification of gaps in conventional models and supported the proposal of a revised schedule, which explicitly incorporated activities and their deadlines, aiming for greater predictability and risk reduction.
Table 1. Activity duration
|
ID |
Task Name |
Duration (days) |
Predecessors |
|
1 |
AIR CONNECTION – POST |
||
|
2 |
Concrete casting of the pole + installation of insulators and eyelet support |
5 |
|
|
3 |
Concrete curing |
28 |
|
|
4 |
Post painting following the building’s facade |
2 |
|
|
5 |
BUDGET REQUEST FOR NEW CONNECTION |
||
|
6 |
Entry with the necessary documents for budget preparation |
2 |
|
|
7 |
Request for quotation for new connection |
30 |
|
|
8 |
Submission of the budget letter |
4 |
|
|
9 |
Boleto payment |
15 |
8 |
|
10 |
Photo submission proving the execution of the post |
2 |
3 |
|
11 |
Execution of the external network service for which the concessionaire is responsible |
60 |
10 |
|
12 |
MEASUREMENT CENTER, ELECTRICAL “SHAFT” AND LOCAL READING BOX |
||
|
13 |
Hiring of measurement center equipment and shielded busbar |
45 |
|
|
14 |
Hiring of “shaft” doors |
45 |
|
|
15 |
Hiring of visual communication for technical areas |
45 |
|
|
16 |
Hiring of the “stop fire” |
45 |
|
|
17 |
Masonry elevation of the measurement center |
2 |
|
|
18 |
Installation of hollow elements for permanent ventilation |
1 |
|
|
19 |
Execution of the bases of the measurement boxes |
2 |
|
|
20 |
Measurement center painting |
1 |
|
|
21 |
Positioning of the electrical panels in the metering center |
1 |
13, 19 |
|
22 |
Purchase of feeder cables for the metering center |
15 |
21 |
|
23 |
Passage and installation of feeder cables inside the metering center |
1 |
|
|
24 |
Passage of cables from the power entry post to the compact distribution board |
1 |
3 |
|
25 |
Vertical and horizontal infrastructure bus |
3 |
|
|
26 |
Positioning and connection of measurement frames inside the electrical “shaft” interconnecting to the busbar |
3 |
|
|
27 |
Execution of the vertical infrastructure for remote communication |
2 |
|
|
28 |
Installation of “shaft” doors |
5 |
14 |
|
29 |
Passage of the feeder cables from the metering box to the apartments |
5 |
|
|
30 |
Positioning of the “stop fire” in the “shaft” of electric |
1 |
16 |
|
31 |
Masonry execution for a sheltered local reading box near the gatehouse |
1 |
|
|
32 |
Local reading box positioning |
1 |
13 |
|
33 |
Passage and installation of vertical + horizontal remote communication cables |
3 |
|
|
34 |
Installation of visual communication for technical areas |
1 |
15 |
|
35 |
Request for inspection of the measurement center |
2 |
|
|
36 |
Document analysis of the inspection request |
3 |
|
|
37 |
Request for meter connection |
2 |
11 |
|
38 |
Meter installation |
5 |
|
|
39 |
Request for provisional cut-off of works |
2 |
38 |
|
40 |
Temporary construction cut-off |
7 |
Source: Original research results
The study acknowledged some important methodological limitations. The proposed schedule was not submitted to a robust empirical field validation process, nor was systematic testing conducted across multiple projects. The main contribution of the schedule lies in increased transparency and the adequate incorporation of final energy connection steps, filling a gap in conventional models. Specific ethical procedures, such as ethics committee approval, were not detailed, as the research was based on documentary analysis and observation of the construction company’s internal processes.
3. Results and Discussion
The structuring of the schedule, as outlined in the present research, was meticulously conducted using MS Project software, a platform widely recognized and employed in project management for its ability to systematically organize, visualize, and monitor activities (PMI, 2017). The choice of this tool not only reflects the best practices of the PMBOK Guide but also offers the robustness necessary to handle the complexity inherent in civil construction projects, especially those for Social Interest Housing (HIS) and Popular Market Housing (HMP), which have more pronounced budgetary and time constraints. Activities were temporally dimensioned in days, a level of granularity that allows for more precise control and more efficient resource allocation, contrasting with more generic approaches that frequently result in delays and deviations.
The basis for defining activity durations was multifaceted, combining historical records from previous projects with the technical expertise of the professionals involved in planning. This hybrid approach is crucial because, as Kerzner (2017) and Vargas (2019) highlight, expert opinion is a valuable resource that incorporates lessons learned and the tacit knowledge of the team, complementing empirical data and increasing the reliability of estimates. The integration of historical data allows for the identification of patterns and trends, while expert judgment adjusts these estimates to the particularities of each new undertaking, considering contextual variables that may not be explicit in the records. The practice of weekly schedule updates, with the recording of actual completion dates and the incorporation of readjustments, is a fundamental pillar for proactive time management. This periodicity ensures that deviations are identified and addressed early, minimizing negative impacts and keeping the project aligned with its objectives. The project coordinator’s responsibility for maintaining and adhering to established deadlines reinforces the need for active and engaged leadership, capable of mobilizing the team and resources to mitigate risks and resolve problems in real-time, as advocated by Carvalho and Rabechini Jr. (2018) regarding the importance of schedule control.
The Work Breakdown Structure (WBS), presented in Figure 1, plays a central role in organizing the execution scope for HIS ventures. The activities detailed in the WBS correspond to the essential deliverables of the project execution phase, being indispensable for ensuring the venture’s feasibility, its coherence, and internal consistency. The WBS, by breaking down the project work into smaller, more manageable components, facilitates the understanding of the total scope and the identification of all necessary tasks for the definitive connection of electrical energy (PMI, 2017). This structured approach is particularly critical in HIS projects, where compliance with current legislation and regulations, as well as adherence to the project approved by the concessionaire, are strict requirements. The absence of a detailed WBS, as often occurs in traditional schedules, can lead to omissions and inconsistencies that compromise the quality and deadline of deliverables, as warned by Kerzner (2017).
Source: Original research results
Figure 1. WBS of the analyzed project of a social housing building
The proposed WBS not only ensures that all essential tasks are identified, but also that their interdependencies are understood, resulting in the definitive connection of electrical power and meeting the construction company’s needs and expectations. The clarity provided by the WBS improves communication among teams, suppliers, and the utility company, establishing clear responsibilities and delivery milestones. This mitigates the risk of critical stages being overlooked or treated superficially, a common problem in projects with less detailed schedules. The hierarchical visualization of activities in the WBS allows all stakeholders to have a unified understanding of the work to be done, from initial planning to final delivery, promoting strategic alignment that is fundamental to project success.
The sequencing of activities, a crucial process for project efficiency, was performed using the Precedence Diagramming Method (PDM), a well-established technique aligned with the premises established by PMI (2017). The PDM, as illustrated in Figure 2, allows for the graphical representation of logical dependencies between activities, through nodes and arrows, clearly and systematically visualizing the mandatory sequence of task execution. This methodology is fundamental for identifying the project’s critical path, which represents the sequence of activities that, if delayed, will delay the entire project. The ability to model the four types of dependency relationships – Finish to Start (FS), Finish to Finish (FF), Start to Start (SS), and Start to Finish (SF) – as well as incorporate leads and lags, confers superior precision and robustness to the schedule (Vargas, 2019).
Source: Original research results
Figure 2. PDM of the analyzed project of a social housing building
The application of the PDM is particularly relevant for final energy connection activities, which involve multiple interfaces and complex dependencies, both internal and external (with the utility company). For example, the “Request for inspection” activity (ID 35) cannot start before the “Installation of visual communication in technical areas” (ID 34) and other civil and electrical activities have been completed. Similarly, “Meter connection” (ID 38) depends on “Request for meter connection order” (ID 37), which in turn has “External network service execution” (ID 11) as its predecessor. The precise identification of these dependencies allows for optimizing resource allocation, avoiding rework, and anticipating potential bottlenecks, contributing to schedule predictability and control. Visualizing these logical relationships in the PDM facilitates communication among teams and stakeholders, ensuring everyone understands the critical sequence of activities and the implications of any delay.
The definition of activity durations, although not explicitly presented with a table tag in the body of this section due to its prior inclusion in Materials and Methods, is one of the most tangible research outcomes. Table 1, which details the duration of each task, was constructed based on the experience and tacit knowledge of the construction company’s designers and installers, complemented by historical data from similar projects. This method, known as expert opinion, is validated by Kerzner (2017) and Vargas (2019) as an effective technique for incorporating lessons learned and institutional knowledge, increasing the reliability and feasibility of the schedule. The granularity presented in Table 1, which breaks down activities into categories such as “Aerial Connection – Pole”, “Budget Request for New Connection”, and “Metering Center, Electrical Shaft, and Local Reading Box”, is a significant differentiator compared to traditional schedules.
For example, the activity “Pole concreting + installation of insulators and clevis support” (ID 2) has an estimated duration of 5 days, followed by 28 days for “Concrete curing” (ID 3). The “Request for quotation for new connection” (ID 5) phase is particularly long, with 30 days for the “Request for quotation for new connection order” (ID 7) and 60 days for the “Execution of external network service by the concessionaire” (ID 11). These durations, especially those involving the concessionaire, highlight the importance of early planning and effective communication with external agents. The clarification of these deadlines allows the construction company to prepare for interfaces with the concessionaire, allocating resources and planning contingencies to mitigate delays. In contrast, less detailed schedules often underestimate or ignore these durations, leading to unexpected delays and financial impacts.
The comparative analysis between the construction company’s traditional work schedules and the proposed revised schedule reveals a critical gap in conventional models. Traditional schedules, although well-structured from the perspective of the main construction stages (foundation, structure, enclosure, and finishing), tend to present a macro approach, neglecting the detailing of activities necessary for the definitive connection of electrical power. This low granularity, especially concerning interfaces with energy concessionaires like Enel, results in an incomplete view of the project lifecycle. Crucial activities such as the technical feasibility request, electrical project approval, external infrastructure execution, entrance standard installation, inspections, and the actual connection are not individually specified, which hinders adequate deadline planning and the identification of critical paths. This deficiency causes these stages to be treated relatively, often initiated late and without proper follow-up, generating unpredictability and significant delays.
The absence of detailed energization steps in traditional schedules severely compromises risk management. Without the explicit mention of these activities, it becomes extremely difficult to predict approval timelines with the utility company, which can vary significantly depending on the project’s complexity and design compliance. This lack of clarity prevents the inclusion of adequate “buffers” and mitigation strategies, misaligning the planning with good project management practices (Cavalcanti and Silveira, 2016). The research by Al Hashid et al. (2020) and Kaufmann and Kock (2022) corroborates that a lack of detail and inadequate risk management are persistent challenges in the construction industry, impacting project profitability and efficiency. The proposed schedule, by clearly and objectively incorporating the final energy connection steps, offers greater robustness in planning and control, breaking down activities into more detailed levels and allowing for the correct identification of dependencies, regulatory deadlines, and institutional interfaces. This approach makes it possible, for example, to anticipate analyses and inspections by the utility company, reducing uncertainties and mitigating risks of delay.
The relevance of this improvement is even more accentuated in Social Housing (HIS) and Popular Market Housing (HMP) ventures. In these projects, profit margins are reduced and schedules are rigidly linked to the stages of resource release by financing agents, such as Caixa Econômica Federal (Caixa Econômica Federal, 2020). Energization delays can directly impact cash flow, resource release, and, consequently, the economic-financial viability of the venture. The literature on HIS (Bonduki, 1998; Rolnik, 2015; São Paulo, 2014) emphasizes the sensitivity of these projects to schedule variations due to contractual restrictions and dependence on subsidies. Therefore, the adoption of the proposed schedule, with its explicit detailing of the final electricity connection stages, contributes significantly to the predictability, control, and success of these ventures, ensuring compliance with the requirements of financing agents and the delivery of the asset within the planned time and cost.
The gains promoted by the schedule update are significant and multifaceted. A significant reduction was observed in the estimated timeframe for the completion of the stages under the responsibility of the construction company, moving from historically higher scenarios of over 400 days to approximately 250 days. This 37.5% reduction in the total time for the definitive connection of electrical energy represents a substantial advance in terms of planning and predictability. The greater transparency, traceability, and integration of activities, enabled by the new schedule, allow for clear identification of dependencies, regulatory deadlines, and responsibilities involved in the energization process. This mitigates operational misalignments between the construction company and the utility, a common problem that frequently causes delays.
The visualization of the revised schedule, as exemplified in the Gantt Chart (Figure 3), offers a clear and concise representation of activities, their durations, and interdependencies. This graphical tool is essential for monitoring and controlling project progress, allowing the coordinator to quickly identify any deviations and take corrective actions. The Gantt Diagram, built in MS Project, integrates all information on sequencing, duration, resources, and constraints, providing a comprehensive project timeline (PMI, 2017). The ability to visualize the critical path and activity floats aids in optimizing resource utilization and prioritizing tasks, ensuring that the focus remains on activities that directly impact the project’s final deadline.
Source: Original research results
Figure 3. Gantt chart: schedule of electrical and civil installations (part A)
The improvement in predictability and the reduction of deadlines have direct financial implications, especially for HIS/HMP ventures, where resource release is tied to physical-financial progress. The ability to anticipate and manage energy connection stages more effectively means fewer contractual penalties, better cash flow, and greater project economic viability. Furthermore, schedule clarity enhances communication with all stakeholders, including investors, regulatory bodies, and clients, increasing trust and satisfaction. Kerzner (2017) emphasizes that a well-managed schedule serves as an agreed-upon temporal contract, aligning the expectations of all interested parties and strengthening project governance.
Despite the significant advances provided by this research, it is essential to acknowledge some methodological limitations. The main one lies in the absence of the proposed schedule submission to a robust empirical validation process in the field, as well as the lack of systematic testing throughout multiple ventures. Although the schedule was developed based on historical data and expert opinion, validation in a real project environment would be crucial to confirm its effectiveness and identify additional adjustments. Future research could address this gap through case studies in pilot projects, comparing the performance of the proposed schedule with the performance of traditional schedules under real construction conditions.
Although the study focused on the aerial connection, the original text mentions that the underground connection, while not contemplated, follows a similar logic, with the addition of specific steps, such as partial inspection of the metering center’s electrical system and the civil execution of the transformer chamber. This suggests that the proposed methodology can be adapted for other types of connections, reinforcing the model’s generalizability. The revised schedule, due to its comprehensive and detailed nature, can be generically adopted by construction companies operating in the city of São Paulo, Enel’s concession area, provided that the constructive particularities of each project are considered and the due adaptations are made to the civil and electrical execution deadlines. This adaptability is a strong point, as it allows the tool to be adjusted for different contexts, maintaining its essence of greater control, predictability, and alignment with project management best practices. The integration of these activities into the schedule planning not only contributes to risk mitigation and delay reduction but also constitutes an essential element for the technical, financial, and contractual success of the ventures, promoting a more robust and results-oriented planning culture in civil construction.
4. Conclusion
It is concluded that the objective was achieved, as the research analyzed and proposed significant improvements in construction schedules for social housing buildings, explicitly incorporating the stages of definitive electricity connection, including the execution and inspection of the metering center. This approach enhanced predictability, reduced risks, and strengthened time management, contributing to the technical, financial, and contractual success of the projects. The detailed structuring of the schedule, using MS Project software and based on historical data and expert opinion, demonstrated a significant reduction in the estimated timeframe for the completion of stages under the responsibility of the construction company, decreasing from historically higher scenarios of over 400 days to approximately 250 days. Such a 37.5% gain is crucial, especially in Social Housing developments, where the rigidity of deadlines directly impacts resource release and economic viability.
Despite the advances, the study presents important limitations, mainly the absence of submission of the proposed schedule to a robust process of empirical validation in the field and the lack of systematic testing in multiple ventures. For future studies, it is suggested to conduct case studies in pilot projects, comparing the performance of the revised schedule with traditional models under real construction conditions. Additionally, the methodology can be adapted for other connection typologies, such as underground, incorporating its specific stages, which would reinforce the generalizability of the model and broaden its impact on civil construction project management.
Bibliographic References
Al Hashid, M.A.; Al-Kaabi, J.H.; Abdullah, R. 2020. Project management challenges in construction industry. International Journal of Advanced Research 8(5): 123-135.
Bonduki, N. 1998. Origens da habitação social no Brasil. Estação Liberdade, São Paulo, SP, Brasil.
Brasil, 2001 [Referência completa não encontrada no documento original]
Caixa Econômica Federal. 2020. Manual de instruções para contratação e execução de obras habitacionais. Disponível em: <https://www.caixa.gov.br/Downloads/habitacao-minha-casa-minha-vida/Cartilha-PMCMV-FAR.pdf>. Acesso em: 18 abril 2026.
Carvalho, M.M.; Rabechini Jr., R. 2018. Fundamentos em gestão de projetos. 5ed. Atas, São Paulo, SP, Brasil.
Cavalcanti, F.R.P.; Silveira, J.A.N. 2016. Fundamentos de gestão de projeto: gestão de riscos. 1ed. Atlas, São Paulo, SP, Brasil.
Gil, A.C. 2017. Como elaborar projetos de pesquisa. 6ed. Atlas, São Paulo, SP, Brasil.
Kaufmann, C.; Kock, A. 2022. Does project management matter? The relationship between project management effort, complexity, and profitability. International Journal of Project Management 40(6): 624-633.
Kerzner, H. 2017. Project management: a systems approach to planning, scheduling, and controlling. 12ed. Wiley, Hoboken, NJ, EUA.
Project Management Institute [PMI]. 2017. Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK®). 6ed. Project Management Institute, Newtown Square, PA, EUA.
Rolnik, R. 2015. Guerra dos lugares: a colonização da terra e da moradia na era das finanças. Boitempo, São Paulo, SP, Brasil.
São Paulo. 2014. Lei nº 16.050, de 31 de julho de 2014. Plano Diretor Estratégico do Município de São Paulo. Diário Oficial do Município de São Paulo, São Paulo, 31 jul. 2014.
Vargas, R.V. 2019. Análise de valor agregado em projetos: método simplificado para gerenciamento de prazos e custos. 4ed. Brasport, Rio de Janeiro, RJ, Brasil.
Vergara, S.C. 2020. Projetos e relatórios de pesquisa em administração. 16ed. Atlas, São Paulo, SP, Brasil.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq