Impact of CAPEX investments on the operational reliability indicators of a chemical industry
Allan David Santos Milanez; João Carlos Boyadjian
DOI: 10.22167/2675-6528-202600501
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
CAPEX investments are relevant projects that demand effective management and monitoring through operational reliability indicators. This case study aimed to present the results of an analysis applied to a multinational chemical industry, comparing the mean time between failures (MTBF) and mean time to repair (MTTR) indicators in the pre- and post-CAPEX periods. The research, of an applied nature and quantitative approach, used a multiple-case design, with secondary data from corporate maintenance and project control systems from 2024 to September 2025. MTBF and MTTR were analyzed, organized into pre-CAPEX, CAPEX, and post-CAPEX periods, and the Operational Variation Index (IVO) was applied to synthesize the operational effect. The sample included Plants A, E, H, and I, selected based on objective criteria. The results indicated measurable variations in reliability indicators after the execution of the projects, with distinct behaviors among the plants, and a trend of increasing MTBF and decreasing MTTR in some of the units, suggesting improvements. It was concluded that the methodological approach allowed for the evaluation of operational reliability associated with investments, contributing as a support tool for project management and operational performance analysis in complex industrial environments.
Keywords: Chemical industry; Maintenance indicators; FEL methodology; Industrial projects.
1. Introduction
The chemical industry, characterized by continuous and capital-intensive production processes, operates in an environment where asset reliability plays a crucial role. Operational stability, process safety, and the very competitiveness of the business depend directly on the ability of equipment and systems to function as expected, without unexpected failures (ABNT, 2014; Moubray, 1997). In this scenario, investments in capital projects, known as CAPEX (Capital Expenditure), are strategic. They encompass maintenance, replacement, and modernization actions for critical equipment, being fundamental to sustain adequate levels of operational performance over time (Tsang, 2002; Wireman, 2004). Such investments aim not only to expand production capacity but also to preserve the integrity and efficiency of existing assets, ensuring the continuity and safety of operations.
Traditionally, the assessment of the effectiveness of these capital investments has been predominantly guided by financial analyses, using metrics such as Net Present Value (NPV), Internal Rate of Return (IRR), and Payback. Although these tools are indispensable in the initial phases of feasibility and decision-making, they have an essentially predictive character. This means that such analyses project future benefits based on assumptions, but do not directly and empirically capture the actual behavior of assets and the operational performance effectively achieved after project implementation (Batavia, 1999; PMI, 2017). The gap therefore lies in the need to complement these financial assessments with indicators that reflect technical and operational performance.
To fill this gap, the incorporation of operational reliability indicators becomes imperative, allowing verification of whether the technical benefits foreseen during project planning materialize in operation. Among the most used metrics to monitor failure frequency and maintenance intervention efficiency, the mean time between failures (MTBF) and mean time to repair (MTTR) stand out (Chin et al., 2020; Moubray, 1997). In parallel, in the corporate environment, the structuring of CAPEX projects is often supported by formal management methodologies, such as Front-End Loading (FEL). This approach organizes project development into progressive phases, aiming to reduce uncertainties and increase the predictability of results in terms of cost, schedule, and operational performance (Batavia, 1999). FEL seeks to ensure that the operational benefits estimated in the feasibility phases are effectively achieved after the implementation of investments, focusing on project maturity before its execution.
Despite the consolidation of the FEL methodology in industrial projects, there is a scarcity of studies that systematically confront the operational reliability indicators observed before and after project execution, using real historical data from industrial plants. This gap limits organizations’ ability to empirically validate whether the gains predicted during project planning translate into measurable improvements in operational performance over time. This challenge is even more evident when the analysis is performed at an aggregate industrial plant level. Although consolidating data from different equipment into a single average value can mask specific behaviors and hinder the direct causal attribution between a CAPEX project and the observed variation in indicators (Tsang, 2002), MTBF and MTTR remain widely used as synthetic metrics for evaluating operational performance at the plant level, especially in comparative and trend analyses (Moubray, 1997; Wireman, 2004). The absence of robust post-implementation empirical validation prevents a complete understanding of the operational return on investment.
Given this scenario, the present research is justified by the need to deepen the understanding of the real impact of CAPEX investments on the operational reliability of chemical industries. By analyzing historical performance data, the study seeks to provide empirical evidence that complements predictive and financial assessments, contributing as a support tool for project management and operational performance analysis in complex industrial environments. This work aims to present the results of an analysis applied to a multinational chemical industry, based on the comparison of Mean Time Between Failures (MTBF) and Mean Time To Repair (MTTR) indicators in the pre-CAPEX and post-CAPEX periods.
2. Material and Methods
This research was characterized as a study of an applied nature, with a quantitative approach and a methodological design based on a multiple case study. The choice of a quantitative approach was justified by the use of numerical operational reliability indicators, such as mean time between failures (MTBF) and mean time to repair (MTTR), which were extracted from corporate systems. This approach allowed for objective measurement of performance variations and enabled greater standardization and reproducibility of results.
The design as a multiple-case study was adopted to allow comparative analysis between different industrial plants, all belonging to the same business group. This strategy made it possible to evaluate how CAPEX investments impacted reliability indicators in distinct operational contexts, but under a common corporate project management framework (Yin, 2015). The aim was to understand performance variations between similar units of analysis, preserving their particularities.
The research was conducted in a large-scale chemical industry, located in the state of São Paulo, Brazil. This industry is characterized by continuous and capital-intensive production processes, possessing multiple industrial plants and an organizational structure dedicated to the management of maintenance and projects. The study was observational in nature, with no direct intervention in the company’s production processes.
The data used were obtained through indirect field research, by accessing the company’s corporate investment maintenance and control systems. Data collection occurred in a standardized manner for all analyzed industrial plants, using consolidated reports made available by the responsible corporate areas. These systems centralize operational and investment information from all production units, ensuring the acquisition of homogeneous and comparable data.
The database covered the period from 2024 to September 2025 and included monthly operational reliability indicators, specifically Mean Time Between Failures (MTBF) and Mean Time To Repair (MTTR), consolidated by industrial plant. Additionally, information regarding the execution of CAPEX projects was collected, such as project activity periods and the occurrence of associated financial disbursements. Data extraction occurred retrospectively, based on historical records.
The MTBF indicator, which expresses the average operating time of a system or asset between two consecutive failures (Moubray, 1997; Chin et al., 2020), was calculated by the ratio between the total available operating time of the plant and the number of failures recorded in the considered period. The MTTR indicator, which represents the average time required to restore equipment to an operational state after a failure (Moubray, 1997; Chin et al., 2020), was calculated by the ratio between the total time spent on corrective interventions and the number of failures that occurred in the same period.
Both indicators were calculated monthly by the corporate maintenance systems, based on failure records and completed service orders at each plant, following standardized measurement criteria adopted by the company. A limitation of the database consisted of the indicators being aggregated at the industrial plant level, not allowing for individualized analysis per equipment (Tsang, 2002; Wireman, 2004).
For analytical purposes, the data were temporally classified into three categories, according to their relationship with the execution of CAPEX projects. The pre-CAPEX period corresponded to the months prior to the project’s start at each plant. The CAPEX period comprised the months during which there was an active project, with records of financial disbursements. The post-CAPEX period included the months subsequent to the project’s completion, used to evaluate the behavior of indicators after the implementation of investments.
The sample of plants for in-depth analysis followed objective criteria to ensure analytical consistency and comparability between cases. Only plants that presented clearly defined pre- and post-CAPEX periods, CAPEX projects with a minimum duration of three months, and measurable variations in MTBF or MTTR indicators were considered. Additionally, plants that presented mathematically invalid or inconsistent values in the analyzed indicators were excluded.
Based on these criteria, Plants A, E, H, and I were selected for analysis, as they presented complete data, structured CAPEX execution, and indicator behavior compatible with the study’s objectives. For comparative purposes, the averages of MTBF and MTTR were calculated in the pre-CAPEX and post-CAPEX periods for each selected plant.
Additionally, the Operational Variation Index (IVO) was applied as a synthetic indicator to jointly measure the relative variation of reliability indicators between the pre and post-CAPEX periods. The IVO was defined to reflect operational improvements both by increasing reliability and by reducing repair time. Positive IVO values indicated relative improvement in operational performance after the execution of CAPEX projects, either by increasing MTBF, by reducing MTTR, or by a combination of both.
The analysis procedures consisted of the monthly consolidation of MTBF and MTTR data by plant. Subsequently, the averages of MTBF and MTTR were calculated for the pre and post-CAPEX periods, and the IVO calculation was applied. Finally, the results obtained were compared between the selected plants, allowing for a relative evaluation of the operational impact associated with CAPEX investments.
3. Results and Discussion
The results obtained in the research indicated that CAPEX investments were associated with measurable variations in the operational reliability indicators of the industrial plants evaluated. In general, an increase in the mean time between failures (MTBF) and a reduction in the mean time to repair (MTTR) were observed in some of the analyzed units, suggesting improvements in operational reliability after the implementation of the projects. However, the magnitude and direction of these variations were not uniform across the plants, evidencing distinct behaviors among the evaluated production systems and the complexity of attributing direct and homogeneous impacts to all investments.
This heterogeneity in results can be attributed to several factors, including the initial operational conditions of each plant, the specific type of intervention performed, and the criticality level of the equipment involved in CAPEX projects. Plants that presented lower initial reliability levels tended to exhibit more significant variations in indicators after the interventions, a behavior that aligns with literature suggesting more expressive gains in systems with a higher frequency of failures or lower initial operational maturity (Moubray, 1997; Wireman, 2005). A detailed analysis of each case allowed for an understanding of the nuances of these interactions.
Overview of the Operational Variation Index (OVI)
The analysis of the Operational Variation Index (IVO) revealed a wide range of responses in the operational performance of the plants after the execution of capital projects. IVO values ranged from positive to negative, reflecting different impacts on reliability indicators. For example, Plant H showed the highest IVO, at 248%, while Plant C registered an IVO of -70%, indicating a significant deterioration. This synthetic metric, which combines the increase in MTBF and the reduction in MTTR, was fundamental for comparing operational behavior between different industrial units and identifying the cases of greatest and least success.
Among the evaluated plants, units A, E, H, and I were selected for a more in-depth analysis, due to the clarity in defining the pre- and post-CAPEX periods, the minimum project duration of three months, and the presence of measurable variations in MTBF or MTTR indicators. These units represent a diverse spectrum of responses to investments, allowing for a richer discussion on the factors influencing operational reliability. The careful selection of cases strengthened the robustness of the comparative analysis.
Individual analysis of selected plants
Plant A
In Plant A, CAPEX projects were executed between March and June 2025, involving investments in asset maintenance and replacement. A reduction was observed in the average MTBF from 36.0 days in the pre-CAPEX period to 19.1 days in the post-CAPEX period, representing a decrease of 47%. However, the average MTTR showed a more pronounced drop, going from 22.5 hours to 9.5 hours, a reduction of 58%. Despite the decrease in MTBF, the significant improvement in repair efficiency resulted in a positive IVO of 11%, indicating an overall operational gain, even with the increased frequency of failures.
The monthly evolution of MTBF in Plant A showed fluctuations, with peaks of 40.0 days in January and April 2025, and drops to 17.1 days in September 2025. The 2024 average for MTBF was 36.7 days. MTTR, in turn, exhibited a more consistent downward trend, starting from 22.5 hours in January 2025 and reaching 9.2 hours in September 2025, with a 2024 average of 25.1 hours. The reduction in MTTR during and after the CAPEX period suggests that the investments may have focused on optimizing maintenance response capacity, minimizing equipment downtime.
Plant E
CAPEX projects at Plant E occurred between April and June 2025, and the results indicated a substantial improvement in operational reliability. The average MTBF increased from 20.5 days in the pre-CAPEX period to 41.1 days in the post-CAPEX period, a growth of 101%. The average MTTR remained relatively stable, with 7.7 hours in the pre-CAPEX and 7.8 hours in the post-CAPEX, showing a slight variation of -2%. Plant E’s IVO was 99%, demonstrating a significant improvement in reliability, mainly driven by the increase in mean time between failures.
The MTBF time series at Plant E revealed a progressive increase, starting from 18.9 days in January 2025 and reaching 51.4 days in September 2025, surpassing the 2024 average of 18.3 days. The monthly MTTR, despite minor fluctuations, remained close to the 2024 average of 7.6 hours, with values ranging between 6.4 hours and 8.0 hours throughout the period. The MTBF behavior at Plant E suggests that CAPEX investments were effective in extending the continuous operation time of the assets, aligning with the objective of increasing availability and reducing failure frequency (Chin et al., 2020).
Plant H
Plant H presented the most significant results in terms of operational reliability improvement after the execution of CAPEX projects, which occurred between March and June 2025. The average MTBF recorded a notable increase from 120.0 days in the pre-CAPEX period to 330.0 days in the post-CAPEX period, representing a growth of 175%. Simultaneously, the average MTTR drastically decreased from 28.5 hours to 7.7 hours, a reduction of 73%. This combination of a significant increase in MTBF and a sharp reduction in MTTR resulted in the highest IVO among all plants analyzed, reaching 248%.
The monthly evolution of MTBF at Plant H illustrates a clear shift in level, with stable values of 120.0 days in the early months of 2025, followed by a jump to 330.0 days from July 2025 onwards, largely surpassing the 2024 average of 110.0 days. The monthly MTTR also showed a downward trend, starting from 28.6 hours in January 2025 and stabilizing around 24.7 hours in the post-CAPEX months, with the 2024 average at 22.7 hours. These results indicate that the investments in Plant H were highly effective in optimizing reliability and maintainability.
Plant I
In Plant I, CAPEX projects were carried out between March and April 2025. The results, however, indicated a deterioration in operational reliability. The average MTBF decreased from 66.0 days in the pre-CAPEX period to 22.2 days in the post-CAPEX period, a reduction of 66%. The average MTTR, in turn, showed a slight reduction from 30.1 hours to 26.5 hours, a variation of 12%. Plant I’s IVO was -55%, reflecting the predominance of the MTBF drop over the small improvement in MTTR, resulting in lower overall operational performance after the investments.
The time series analysis of MTBF at Plant I showed a sharp decline, from 72.0 days in January 2025 to 17.1 days in September 2025, falling below the 2024 average of 41.3 days. Monthly MTTR, despite variations, remained at high levels, with values between 24.4 hours and 34.3 hours, compared to the 2024 average of 22.7 hours. Plant I’s performance suggests that CAPEX investments may not have been directed towards the most critical reliability bottlenecks, or that other external operational factors may have negatively impacted the indicators.
Discussion of results
The results obtained indicate that the CAPEX investments analyzed were associated with measurable variations in the operational reliability indicators of the industrial plants evaluated. In general, an increasing trend in mean time between failures (MTBF) and a reduction in mean time to repair (MTTR) were observed in some of the analyzed units, suggesting improvements in operational reliability after project implementation. However, the magnitude of these variations was not uniform across the plants, evidencing distinct behaviors among the production systems evaluated.
This heterogeneity may be related to the initial operational conditions of each plant, the type of intervention performed, and the degree of criticality of the equipment involved in CAPEX projects. Plants that presented lower initial reliability levels tended to show more significant variations in indicators after the interventions. This behavior is consistent with studies in the area of industrial reliability and maintenance, which indicate that technical interventions usually generate more expressive gains in systems with a higher frequency of failures or lower initial operational maturity (Moubray, 1997; Wireman, 2005).
Among the analyzed units, Plant H presented the highest value for the Operational Variation Index (IVO), indicating an expressive improvement in the combination between MTBF increase and MTTR reduction after the investments were executed. This result suggests that CAPEX interventions directed at critical assets can generate significant impacts on operational reliability when they act on components that represent relevant bottlenecks for the productive system’s performance. On the other hand, some plants presented more moderate variations or close to stability, which may indicate that part of the investments were aimed at different objectives, such as asset replacement due to obsolescence, safety improvements, or operational adjustments that are not necessarily directly reflected in the analyzed reliability indicators.
The use of the Operational Variation Index (IVO) allowed for the synthesis of simultaneous changes in the MTBF and MTTR indicators, offering an aggregated metric for comparison between the analyzed plants. This approach enabled an integrated evaluation of two relevant dimensions of operational performance: the frequency of failure occurrences and the efficiency in executing corrective maintenance activities. Although simplified, this metric proved useful for identifying general trends of improvement or stability in the indicators after project execution.
The results also reinforce the importance of post-implementation analysis of capital projects. In project management literature, feasibility assessments are usually carried out predominantly based on economic and financial indicators during the initial phases of project development. However, such analyses are essentially predictive and do not necessarily reflect the operational performance actually observed after the implementation of investments. Thus, the use of operational indicators such as MTBF and MTTR can contribute to complementing traditional analyses, allowing for an evaluation of whether the technical benefits expected during project planning materialize during the operation of industrial plants.
Despite the contributions presented, some methodological limitations should be considered in the interpretation of the results. The analysis was conducted using historical data consolidated by industrial plant, which limits the identification of direct causal relationships between specific projects and observed variations in reliability indicators. Furthermore, external operational factors, such as changes in operating regimes, variations in production load, modifications in maintenance practices, or specific equipment replacements, can also influence the MTBF and MTTR values over time.
Another relevant limitation concerns the level of data aggregation used. As the indicators were analyzed at the plant level, it was not possible to assess the impact of investments at the level of specific equipment or subsystem. Future studies could deepen this analysis using more detailed reliability data, allowing for more direct relationships to be established between technical interventions and changes in the operational behavior of assets. This more granular approach would allow for a more precise understanding of the effects of each CAPEX project.
In general, the results obtained suggest that CAPEX investments may be associated with improvements in operational reliability indicators, although the magnitude of these improvements depends on the specific characteristics of each plant, the initial operating conditions, and the technical scope of the interventions carried out. The comparative analysis between the pre- and post-CAPEX periods, using MTBF, MTTR, and IVO, proved to be a valuable tool for evaluating the operational impact of investments, complementing financial analyses and offering a more complete view of the return on capital projects in the industrial environment.
4. Conclusion
The present study aimed to present the results of an analysis applied to a multinational chemical industry, comparing the mean time between failures (MTBF) and mean time to repair (MTTR) indicators in the pre and post-CAPEX periods. It was verified that CAPEX investments were associated with measurable variations in the operational reliability indicators of the evaluated plants. An increasing trend in MTBF and a reduction in MTTR were observed in some of the units, suggesting improvements in operational reliability after the implementation of the projects. However, the magnitude and direction of these variations were not uniform across the plants, evidencing distinct behaviors influenced by initial operational conditions, the type of intervention, and equipment criticality. Plant H, for example, showed the most significant improvement, while Plant I registered a deterioration. The use of the Operational Variation Index (IVO) proved to be a useful tool for synthesizing the observed changes, contributing to the evaluation of post-investment operational performance and complementing predictive financial analyses.
Despite the contributions, some methodological limitations were identified. The analysis was conducted using historical data consolidated by industrial plant, which restricted the identification of direct causal relationships between specific projects and variations in reliability indicators. External operational factors, such as changes in operating regimes or maintenance practices, may also have influenced the results. Furthermore, the level of data aggregation prevented the evaluation of the impact of investments at the level of specific equipment or subsystem. For future studies, it is suggested to deepen the analysis using more detailed reliability data, allowing for more direct relationships to be established between technical interventions and changes in the operational behavior of assets. The results obtained demonstrate that the joint analysis of reliability indicators can significantly contribute to the evaluation of operational performance associated with CAPEX investments, offering a valuable complement to the analyses traditionally performed during the project planning phases.
Bibliographic References
Associação Brasileira de Normas Técnicas [ABNT]. 2014. NBR ISO 55000: Gestão de ativos – Visão geral, princípios e terminologia. Rio de Janeiro, RJ, Brasil.
Batavia, R. 1999. Front-End Loading – A Path to a Successful Project. In: Project Management Institute Annual Seminar & Symposium. 1999, Philadelphia, Pennsylvania, USA. Disponível em: <https://www.wcu.edu/pmi/1999/OG02.PDF>. Acesso em: 10 jan. 2026.
Chin, H. H.; Varbanov, P. S.; Klemeš, J. J.; Benjamin, M. F. D.; Tan, R. R. 2020. Asset maintenance optimisation approaches in the chemical and process industries – A review. Chemical Engineering Research and Design 164 162-194. Disponível em: <https://doi.org/10.1016/j.cherd.2020.09.034>. Acesso em: 10 jan. 2025.
Moubray, J. 1997. Reliability-centered maintenance. 2ed. Industrial Press Inc., Woodbine, New Jersey, EUA.
Project Management Institute (PMI). 2017. Um Guia do Conhecimento em Gerenciamento de Projetos (Guia PMBOK). 6ed. Project Management Institute, Newtown Square, Pennsylvania, EUA.
Tsang, A. H. 2002. Strategic dimensions of maintenance management. Journal of Quality in Maintenance Engineering 8(1): 7-39. Disponível em: <https://doi.org/10.1108/13552510210420577>. Acesso em 12 jan. 2026.
Wireman, T. 2005. Developing performance indicators for managing maintenance. 2ed. Industrial Press Inc., New York, NY, EUA.
Yin, R. K. 2015. Estudo de caso: planejamento e métodos. 6ed. Bookman, Porto Alegre, RS, Brasil.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq