Haiti as a “graveyard of projects”: humanity’s greatest memorial as a paradigm shift
Haiti as the “Cemetery of Projects”: Humanity’s Greatest Memorial as a Paradigm Shift
Wendy Ledix; Daniel Luis Garrido Monaro
DOI: 10.22167/2675-6528-202602447
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
Haiti has historically been characterized as a “graveyard of projects” due to the chronic failure of international interventions that, despite substantial investments and the involvement of global experts, have not generated tangible improvements for the population. The study aimed to propose an epistemic and managerial shift, replacing traditional models focused on deadlines and costs with management oriented towards value delivery and the ethical engagement of the local community and the Haitian diaspora. To this end, the research adopted a qualitative and action-research approach, using the principles of stakeholder and resource management from the PMBOK Guide as a technical framework. The earthquake of January 12, 2010, was analyzed as a reference point that exposed structural management failures and the absence of Haitian protagonism in decision-making processes. As a main result, the implementation of the “greatest memorial in humanity” was proposed as a pilot project. This project aims to transform the memory of the 300,000 earthquake victims into concrete actions for infrastructure and sustainability, such as the construction of 300,000 meters of roads to combat road insecurity and facilitate circulation, and the planting of 300,000 trees to promote reforestation and combat erosion. The strategy was based on the potential of the Haitian diaspora and the recovery of peasant protagonism, integrating agricultural ethno-techniques and social engineering, with the use of technologies for resource mobilization and monitoring. It was concluded that Haiti’s development depends on projects that make sense to its people and that are managed based on solidarity and national autonomy, overcoming the logic of ineffective external interventions.
Keywords: International cooperation; Haitian diaspora; Project management; Social innovation; Local protagonism.
1. Introduction
Haiti, a Central American nation with 27,750 square kilometers and an estimated population of 11,867,032 inhabitants (IHSI, 2024), holds a unique and paradoxical position in the history of the Americas. Recognized as the first country to abolish slavery through a revolution carried out by enslaved Black people, Haiti symbolizes anti-colonial resistance and self-determination of peoples. However, despite its geopolitical and symbolic importance, the country has been the target of interventions and humanitarian aid programs that, paradoxically, have resulted in accumulated failures. This reality has led part of the critical literature to label Haiti as a “graveyard of projects” (Seitenfus, 2014).
The term “project graveyard” describes the chronic failure of international interventions that, even with contributions exceeding 30 billion dollars and the involvement of thousands of global specialists, have not generated tangible improvements for the Haitian population. The earthquake of January 12, 2010, served as a benchmark that revealed structural management flaws and the absence of Haitian leadership in decision-making processes (Seitenfus, 2014).
In this context, a fundamental question arises about the effectiveness of traditional project management models. Approaches frequently focused only on scope, deadline, and cost have proven insufficient to deal with the social, political, and institutional complexity of the post-earthquake Haitian environment. The absence of local stakeholder engagement and the fragmentation of initiatives contributed to the low sustainability and limited results of the projects.
The problem lies not only in the lack of management techniques, such as resource and stakeholder management, but in the way these are implemented. Frequently, there is no proper adaptation to the institutional, cultural, and socioeconomic specificities of the environment in which they are inserted. Factors such as the multiplicity of actors, dependence on external funding, and pressure for short-term results exacerbate the mismatch between planning and execution, preventing the generation of lasting value for the population (PMI, 2013).
The need to rethink project management in highly complex environments, such as the Haitian one, justifies this study. The post-2010 scenario shows that the mere multiplication of projects does not guarantee the generation of sustainable value. Valuing the potential of the Haitian diaspora, whose financial remittances represented 37.1% of GDP in 2019 (WB, 2021), and rescuing peasant protagonism, integrating agricultural ethno-techniques and social engineering, are crucial for development.
As a practical example of a paradigm shift, this work proposes the implementation of the “largest memorial in humanity” as a pilot project. Unlike a static monument to suffering, the project aims to transform the memory of the 300,000 victims of the earthquake into concrete actions for infrastructure and sustainability. This includes the construction of 300,000 meters of roads, combating road insecurity (pointed out as the main cause of death in the country, according to Boyard, 2021), and the planting of 300,000 trees, promoting reforestation to combat desertification and severe erosion of Haitian soil (HAITI, 2015).
Given the persistence of project management failures and the underutilization of endogenous potential, the search for an approach that prioritizes value delivery and the ethical engagement of the local community and the Haitian diaspora is justified, with the objective of proposing an epistemic and managerial shift that replaces traditional models focused solely on deadlines and costs with management oriented towards value delivery and the ethical engagement of the local community and the Haitian diaspora.
2. Material and Methods
The present research adopted an explanatory nature and qualitative approach, according to Gil’s (2002) classification of objectives. This methodological choice aimed to deepen the understanding of the cause-and-effect relationships of social events, focusing on the dynamics of international interventions in Haiti, rather than the mere quantification of variables.
The research design was based on action research, following Tripp’s (2005) principles. This methodology was selected for its characteristic of seeking practical interventions during the research process, and not just as final recommendations. It was understood as an action research cycle that involved continuous planning, implementation, monitoring, and evaluation, aiming to improve practice and learning.
For data and information collection, two main techniques were employed. Firstly, a survey of secondary data was conducted. This survey focused on technical terms of resource management and stakeholders, using the PMBOK Guide (PMI, 2013) as a basis, which served as a reference for the analysis of project management approaches.
Secondly, participant observation and fact-finding were used with the Haitian Community in São Paulo. This stage was crucial for collecting direct perceptions and experiences from those involved, complementing secondary data and offering a local perspective on the challenges and opportunities in project management in highly complex contexts.
The research structure was organized into three distinct and complementary parts. The first part investigated the structural, political, historical, and epistemological reasons that contributed to Haiti being characterized as a “graveyard of projects,” an emblematic case of chronic international failure. Projects that failed after the earthquake of January 12, 2010, which became a benchmark for understanding management failures, were analyzed.
The second part of the research was dedicated to proposing an epistemic turn in project management in Haiti. To this end, the integration of the local community as a strategic ally in the execution of projects was sought, adapting management approaches to the social and cultural specificities of the country. Successful experiences were considered, such as those of the “Alliance Gonaïvienne d’Outre-Mer” (AGO-M) in Gonaïves, which demonstrated the potential of financial support from the Haitian diaspora.
Finally, the third part consisted of proposing a pilot project, named “the greatest memorial of humanity”. This project was conceived with a strong symbolic value for the collective memory of the Haitian people, in homage to the 300,000 lives lost in the 2010 earthquake, aiming to transform mourning into concrete actions of infrastructure and sustainability, aligned with the proposed epistemic shift.
The proposed pilot project included the construction of 300,000 meters of highways and the initial planting of 300,000 native and fruit trees along these roads and in their surroundings. These actions were outlined to combat road insecurity, identified as the main cause of death in the country, and to promote reforestation, mitigating desertification and severe soil erosion in Haiti.
The analysis of the data, both that collected secondarily and that obtained by observation, was conducted under a critical and de(s)colonial approach. This method allowed for the identification of recurring flaws in project management and the absence of Haitian protagonism in decision-making processes, focusing on the inadequacy of traditional management approaches to the local context.
The technical framework that underpinned the analysis and the proposition of solutions was based on the principles of stakeholder and resource management from the PMBOK Guide (PMI, 2013). This guide provided the guidelines for identifying, planning, managing, and controlling stakeholder engagement, as well as for mobilizing and managing human, financial, and technological resources.
Human resource management, according to the 5th edition of the PMBOK Guide (PMI, 2013), was considered a fundamental point for the project’s success. The need to plan, mobilize, develop, and manage the project team was emphasized, integrating the centrality of local stakeholders and social participation to ensure ownership and sustainability of the initiatives.
For the fundraising for the pilot project, the use of technologies such as virtual applications and platforms, inspired by transparency models, was foreseen. The technological resources would be employed by the management team for activities such as soil analysis, toll collection system operation, and water resource search, in addition to supporting environmental education.
The financial sustainability of the pilot project was planned to be ensured by toll fees and revenues generated by the bus stations. These collection mechanisms were designed to cover the costs of infrastructure maintenance and expansion, as well as the remuneration of collaborators, aligning with value delivery and the ethical engagement of the community.
3. Results and Discussion
The analysis of the research results revealed that the earthquake of January 12, 2010, forcefully exposed the pre-existing structural, economic, and social fragilities in Haiti, in addition to causing unprecedented devastation in terms of human lives and infrastructure. It is estimated that hundreds of thousands of people were directly affected, with the destruction of urban infrastructure, public services, and the administrative capacity of the Haitian state. Seitenfus (2014) highlighted that the catastrophe struck the country’s economic heart, concentrated in Port-au-Prince, resulting in a loss equivalent to 120% of the Gross Domestic Product and approximately one-third of state employees in a matter of seconds.
In response to this calamity, a massive international and national mobilization was observed, with multilateral agencies, foreign governments, non-governmental organizations, and institutions implementing thousands of humanitarian and development projects. Haiti thus became one of the largest recipients of projects in the post-disaster period, characterizing an environment of high complexity management, with multiple “stakeholders”, divergent interests, and a significant volume of financial resources. However, despite the investment of over 30 billion dollars and the involvement of global experts, the interventions did not result in tangible or sustainable improvements for the population, leading to Haiti being characterized as a “project graveyard” (Seitenfus, 2014).
Haiti as a “graveyard of post-disaster projects”
The destruction caused by the 2010 earthquake generated an immediate demand for reconstruction in several areas, including education, health, and urban mobility. Brazil, for example, was the only Latin American country to join the Interim Haiti Reconstruction Commission (CIRH), pledging US$ 340 million in aid out of a total of US$ 11 billion promised at the 2010 Donors Conference for Haiti (Seitenfus, 2014). Despite this unprecedented effort and inspiration from the successful Aceh tsunami model, the CIRH did not manage financial resources nor plan their application, acting more as a forum for dialogue than an executive body. This resulted in stagnant reconstruction, with the country facing an inflation rate of 47.2% in October 2022 and negative economic growth of -1.7% between 2020 and 2021 (IHSI, 2023), evidencing the persistence of vulnerability.
The analysis of the Action Plan for the Recovery and Development of Haiti (PARDH), which was supposed to guide the actions of the CIRH, revealed a paradox: despite the volume of projects and resources, sustainable impacts were non-existent. The failures were attributed to the fragmentation of “stakeholders”, governance deficiencies, lack of sustainability, and absence of maintenance plans. Many projects failed to generate lasting value or integrate with local capacities, leading to criticisms and popular demonstrations that questioned the destination of the “CIRH money”. The CIRH, co-chaired by Bill Clinton and the Haitian government, operated as a “parallel State”, marginalizing local institutions and preventing Haitian ownership of development.
The main failures of the CIRH included poor management and the exclusion of Haitian stakeholders, with local commission members complaining of being excluded from decisions. Aid was fragmented by numerous NGOs, compromising the effectiveness of fund management. The “Build Back Better” strategy also failed, with inadequate resettlement of victims, slow debris removal, and unfinished housing projects due to land tenure issues. The security response was unsustainable, leaving the national police weakened and contributing to the increase in insecurity and the action of armed gangs years later (Seitenfus, 2014).
Furthermore, essential social needs, such as psychosocial support and mental health, were neglected despite widespread trauma. A decade after the earthquake, reconstruction failed to eradicate poverty and even exacerbated inequalities, making Haiti more vulnerable to future disasters. The inadequate approach was evident in the imbalance of funds, with a large portion of humanitarian aid allocated to the operational costs of international organizations rather than sustainable reconstruction. The plan’s neoliberal orientation favored foreign private investment and public-private partnerships, characterizing a “disaster capitalism” that did not meet the population’s immediate needs.
The export model prioritized the construction of industrial parks, such as Caracol, at the expense of agriculture and local infrastructure. The lack of decentralization was another critical point, with the concentration of economic activities in Port-au-Prince, exacerbating population density and vulnerability in the capital. Instead of reducing pressure on Port-au-Prince, the reconstruction replicated the same risks and vulnerabilities, leading to the proliferation of irregular constructions and slums. In summary, the CIRH was perceived as a bureaucratic, inefficient, and unaccountable structure, incapable of transforming the billions of dollars promised into sustainable and inclusive reconstruction.
Paradigm shift in Project Management in the country
From the perspective of Project Management, the Haitian post-earthquake context raises fundamental questions about the adopted models, success criteria, and the conception of value. Traditional approaches, focused on scope, schedule, and cost, proved insufficient given the social, political, and institutional complexity of Haiti. The observed failure is not limited to specific execution flaws but reflects the need for a paradigm shift in how projects are conceived and managed in humanitarian and post-disaster contexts, according to the premise of this work.
The absence of the Haitian State, as pointed out by Trouillot (2012), generates a “discursive authority” that prevents the people from self-defining, resulting in more attention being paid to Westerners than to Haitians themselves. This dynamic is reflected in the management of stakeholders and resources, creating fertile ground for project failure. The need to rethink Project Management in environments of high complexity, multiple stakeholders, and diffuse objectives, such as the Haitian post-2010 context, justifies the search for a new approach that recognizes that the mere multiplication of projects does not guarantee the generation of sustainable value.
In the context of the PMBOK Guide, especially in its 7th edition, Project Management is understood as a means to deliver value, and not just as a set of execution processes. For the success of a project, it is fundamental to establish and maintain appropriate communication and engagement with stakeholders (PMI, 2013). The Haitian experience demonstrated a significant misalignment between the implemented projects and the fundamental principles of good management, such as effective stakeholder engagement, adaptation to the local – cultural – context, responsible leadership, and integrated governance.
The management of stakeholders in Haiti’s reconstruction projects has been absent, either due to the non-existence of a formal process or the lack of transparency and communication. This process includes identifying all individuals, organizations, and groups that can impact or be impacted by the project, analyzing their expectations and impact, and developing appropriate management strategies for effective engagement in project decisions and execution. The four main steps are: identify stakeholders, plan management, manage engagement, and control engagement (PMI, 2013).
The fragmentation of initiatives, the absence of strategic coordination, and, above all, the exclusion of local actors from the decision-making process are factors that contribute to the “premature death” of projects in Haiti. It is common to find development projects in localities without the knowledge of the inhabitants, who could be key resources for development and maintenance. The PMBOK Guide, in its 5th edition, highlights human resource management as fundamental to project success, including planning, mobilization, development, and team management. The RACI Matrix (Responsible, Accountable, Consulted, Informed) suggests that the inhabitants of project development areas should, at a minimum, be consulted and/or informed, connecting stakeholder management with social participation.
The proposed analysis allows for the identification of recurring failures that can be avoided in future projects, expanding the decision-making capacity of project managers, sponsors, and executing organizations. By proposing a paradigm shift guided by PMBOK principles, this work seeks to contribute to more ethical, sustainable, and effective management, aligned with contemporary demands for value creation and social responsibility. This epistemic and managerial shift aims to replace traditional models focused solely on deadlines and costs with management oriented towards value delivery and the ethical engagement of the local community and the Haitian diaspora.
The implementation of humanity’s largest memorial as a pilot project
The attempts to reconstruct Haiti post-earthquake, especially those coordinated by the CIRH, revealed a management deficiency that paralyzed the delivery of concrete values. However, the active engagement of the Haitian diaspora in building sustainable infrastructures in the country has been observed, as in the case of the opening of the canal over the Massacre River, an endogenous initiative that demonstrated success when the diaspora’s strength united with the complicity of the local population. Although rigorous management, with detailed financial reports, may not have been a constant due to the diversification of funding sources, satisfactory stakeholder management resulted in a visible delivery of value.
Based on this diasporic commitment, the implementation of the “largest memorial of humanity” is proposed as a pilot project. This project aims to honor the 300,000 lives lost in the 2010 earthquake, transforming numbers of calamity into numbers of hope. In 2019, remittances from Haitian migrants reached 37.1% of the country’s GDP, surpassing most nations that receive the most money from abroad (BM, 2021). The good catalysis of this financial resource from the Haitian diaspora, allied with “social remittances” – transfer of skills and attitudes that support development (IOM, 2008) –, can boost the country’s development (Ledix, 2021).
The pilot project seeks to address urgent needs through three main components: (1) reconstruction of 300,000 meters of roads; (2) initial reforestation with 300,000 native and fruit trees, focusing on sustainability and environmental protection; and (3) a maintenance plan for both items. Road reconstruction is crucial, as road insecurity is the leading cause of death in Haiti (Boyard, 2021), and the lack of adequate roads hinders access to basic services and the circulation of food, with 45% of the population facing hunger (UN, 2022). The deterioration of transport infrastructure is a chronic problem, with only 5% of the road network in good condition in 2004 (IDB, 2009), and governments have never prioritized this sector in economic, social, and health development (Prochette et al., 2012).
Poor road conditions have serious economic and social consequences, increasing transportation costs and hindering access to work, markets, schools, and hospitals (IDB, 2009). In addition to hindering safe transportation, the road problem is a matter of public health and social exclusion, primarily affecting the most vulnerable. Road insecurity is the main factor of insecurity and cause of death in Haiti, surpassing criminal violence (Boyard, 2021). Transport services represent 12% of GDP and 8% of household spending, with roads being the main means of transport (MTPTC, 2020). More than half of the inhabitants do not have access to transportation, and more than a third depend on difficult-to-access roads, limiting access to basic services and economic development opportunities (Sauveur, 2022).
Reforestation, in turn, aims to combat desertification and severe erosion of Haitian soil (HAITI, 2015). The Caribbean region is particularly vulnerable to climate change, and Haiti faces a pronounced desertification process, linked to historical, natural, anthropogenic, and institutional factors. Land degradation, soil erosion, salinization, loss of fertility, and forests are serious problems (HAITI, 2015). In 2005, Haiti ranked 141st out of 146 nations in the Environmental Sustainability Index, and approximately 46,000 m³ of wood are cut annually in an anarchic and irresponsible manner (Daniel, 2016).
Social discrimination against peasants, who are often blamed for deforestation, ignores historical, economic, and political factors that abandon them and limit them to an existence “outside the world” (Barthélémy, 1989; Hurbon, 1987). Reforestation policies, often restricted to numbers, do not address the violence inflicted on human and non-human communities (Malcom, 2022). It is therefore crucial that reforestation be accompanied by social policies that ensure the well-being and active participation of the population, prioritizing peasant leadership, the implementation of agricultural ethno-techniques, and social engineering that acts on social variables such as income, housing, culture, and education.
The pilot project’s Work Breakdown Structure (WBS), as outlined, integrates road construction (300 km of highways), the creation of toll plazas (5 units) and bus stations (5 units), and sustainability and environmental actions. Project management encompasses planning and studies (topographical, environmental, engineering), plaza and architectural design, civil construction, environmental planning, scope management, and scheduling. Highway construction includes earthworks, drainage, paving, and road signage. The toll systems (automation, manual, technological integration) and the implementation of user services are planned for the toll plazas and bus stations.
In the sustainability component, the project foresees the production and acquisition of seedlings, the planting of 300,000 trees, and environmental monitoring. The support infrastructure includes containment works, environmental remediation, and road safety. Tests and initial operation are crucial stages. The management of human, financial, and technological resources is fundamental. Human resources involve people management as a critical success factor, promoting the protagonism of local actors. The reconstruction of the highways would be put out to tender, but the management group would ensure control and oversight. In reforestation, local communities would act as co-creators and co-executors, with technological support for soil analysis and definition of suitable species.
Financial resources, originating from the diaspora, require a transparent collection mechanism, such as virtual applications and platforms, inspired by models like Ukraine’s United24. Technological resources would be used by the management team for soil studies, operation of toll collection systems, and search for water resources, in addition to lightweight technologies such as the application of the equity principle, creation of an environmental brigade, and environmental education. Toll and bus station fees would be allocated to the maintenance and expansion of infrastructure, as well as to the payment of collaborators, covering costs of road maintenance, signage, security, and works, and financing the operation and remuneration of workers.
In summary, the research demonstrated that the history of project failures in Haiti, which labeled it as a “project graveyard,” stems from the inadequacy of traditional management models and the exclusion of local protagonism. The proposal of the “largest memorial of humanity” as a pilot project, by integrating the reconstruction of roads and reforestation with the engagement of the diaspora and the peasant community, represents an epistemic and managerial turning point. This project, by transforming grief into concrete actions of infrastructure and sustainability, aligns with the principles of the PMBOK Guide for stakeholder and resource management, seeking to generate lasting value and respond directly to sustainable development objectives, promoting autonomy and national solidarity.
4. Conclusion
The study aimed to propose an epistemic and managerial shift in project management in Haiti, replacing traditional models focused on deadlines and costs with an approach oriented towards value delivery and the ethical engagement of the local community and the Haitian diaspora. It was observed that Haiti, historically labeled as a “project graveyard,” has accumulated decades of failures in international interventions, despite substantial investments. The 2010 earthquake revealed structural management flaws and the absence of Haitian leadership in decision-making processes. The analysis by the Interim Commission for the Reconstruction of Haiti (CIRH) highlighted that the fragmentation of stakeholders, governance deficiencies, and the exclusion of local actors hindered the generation of sustainable value, demonstrating the inadequacy of traditional project management approaches in the face of the country’s social, political, and institutional complexity.
In this context, the research proposed the implementation of the “largest memorial of humanity” as a pilot project, aiming to transform the memory of the 300,000 earthquake victims into concrete actions for infrastructure and sustainability. This project includes the construction of 300,000 meters of roads to combat road insecurity and facilitate circulation, and the planting of 300,000 trees to promote reforestation and combat erosion. The strategy was based on the potential of the Haitian diaspora, whose financial and social remittances represent a vital resource, and on the recovery of peasant protagonism, integrating agricultural ethno-techniques and social engineering, with the use of technologies for resource mobilization and transparent monitoring. The study’s contribution lies in demonstrating that Haiti’s development depends on projects that make sense to its people, managed with solidarity and national autonomy, and that future ventures should adopt the principles of the PMBOK Guide, focusing on ethical stakeholder engagement and transparency.
Bibliographic References
BANQUE MONDIALE (BM). 2021. Repatriments des fonds. Migration Data Portal. Disponível em: https://www.migrationdataportal.org/?i=remit_re_gdp&t=2019. Acesso em: 06/02/2026.
Boyard, J. 2021. De l’insécurité routière en Haïti: un grave problème de segurança pública trop longtemps négligé. Haïti: Le Nouvelliste.
Gil, A. C.
HAITI. 2015. Programme Aligné d’Action National de Lutte contre la Désertification. Ministère de l’Environnement: avril, p.104.
HAITI. 2024. Estimations de la population. Institut Haïtien de Statistique et d’Informatique (IHSI). Disponible sur: https://ihsi.gouv.ht/.
Project Management Institute (PMI). 2013. Um Guia do Conhecimento em Gerenciamento de Projetos (Guia PMBOK®). Quinta edição. Project Management Institute, Inc., Newtown Square, PA, USA.
Seitenfus, R. 2014. Haiti: Dilemas e Fracassos Internacionais. Ijuí: Ed. Unijuí, RS. – 464 р. ISBN 978-85-419-0108-6
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq