Risk management in educational connectivity projects in public education networks through the Risk Breakdown Structure and the Probability and Impact Matrix
Risk Management in Educational Connectivity Projects in Public Education Networks Through the Risk Breakdown Structure and the Probability and Impact Matrix
Vinícius Lima da Silva Maciel; Thais de Marchi Soares
DOI: 10.22167/2675-6528-202602406
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The non-execution of public resources for school connectivity represents a significant risk to students’ access to quality internet and to the reputation of the organizations involved. This study aimed to manage the risks of MegaEdu’s strategic planning for 2026, an organization that supports state education secretariats in implementing school connectivity policies funded by Law No. 14.172/2021. The research was characterized as applied, descriptive, with a qualitative approach and conducted through action research. Risk identification occurred through Brainwriting Pool and a validation workshop. Risks were categorized by an adapted Risk Breakdown Structure and evaluated by a Probability and Impact Matrix. The Value at Risk of Non-Execution (VRNE) was proposed as an adapted indicator, replacing the Expected Monetary Value. Eleven risks and three opportunities were identified, with two risks reaching a high level (P×I of 0.81 and 0.63). The total VRNE for the ten partner networks reached R$ 329,443,112 out of an available balance of R$ 802,575,458. Strategic responses prioritized strengthening the technical teams of the secretariats, anticipating formal agreements, and coordinating with the Ministry of Education. It was concluded that support projects for public educational connectivity policies are highly vulnerable to political-institutional risks, especially in election years. The VRNE proved to be an adequate methodological adaptation for prioritizing efforts in technical support organizations for public policies, offering a replicable contribution.
Keywords: Qualitative risk analysis; Law 14.172/2021; Strategic planning; Educational policies.
1. Introduction
The implementation of public policies, especially in contexts of high complexity, requires the adoption of robust managerial instruments to deal with uncertainties. Risk management, in this scenario, emerges as a fundamental practice, recognized by international references in project management.
The Project Management Institute (PMI), in its 7th edition of the PMBOK Guide (PMI, 2021), defines risk as an uncertain event or condition that can generate positive or negative effects on a project’s objectives. This perspective encompasses both threats and opportunities, guiding a structured management process that extends throughout the project’s lifecycle. The centrality of this practice in environments of high uncertainty is emphasized by Gray and Larson (2009), who consider risk management to be the essence of project management.
In Brazil, the school connectivity agenda gained institutional relevance with the publication of Law No. 14.172, of June 10, 2021 (Brazil, 2021). This legislation allocated resources to state education secretariats with the objective of guaranteeing access to the internet and technological devices for students and teachers of public basic education.
The execution of these resources, distributed over subsequent exercises, has 2026 as the last available year for the use of remaining balances. Failure to execute within the legal deadline implies compulsory return to the National Treasury. Such a scenario represents a direct loss to the beneficiary schools and a risk to the legitimacy of the connectivity agenda as a public policy priority.
In this context, MegaEdu, a non-profit organization, works to strengthen educational secretariats institutionally. Its work consists of supporting bidding processes, technical diagnostics, and strategic planning for the digital agenda, aiming at the implementation of school connectivity policies with quality and within legal deadlines.
MegaEdu’s main strategic goal for 2026 is to support the full execution of the resources from Law No. 14.172/2021 by partner networks. The non-execution of these resources would result in a concrete loss for students and a reputational risk for the organization. Given the complexity and political-institutional uncertainties, especially in an election year, this work is justified by the need for proactive and structured risk management. Thus, the present study aimed to manage the risks of MegaEdu’s strategic planning for 2026, through the stages of planning, identification, qualitative analysis, quantitative analysis adapted by Value at Risk of Non-Execution [VRNE], planning and implementation of responses, and monitoring, as recommended by the PMBOK Guide 7th edition (PMI, 2021).
2. Material and Methods
The research was characterized by its nature as applied, its objective as descriptive, its methodology as action-research, and its approach as qualitative. Action-research was justified by the researcher’s direct participation in the organization’s risk management process, with knowledge production from practice and feedback on strategic decisions (Thiollent, 2011). The qualitative approach was suitable for the context of risk assessment in public policy projects, where uncertainty events are not fully quantifiable in financial terms for the technical support organization (Carvalho and Rabechini Jr., 2019).
The work followed the seven steps of risk management as recommended by the PMBOK Guide 7th edition (PMI, 2021). These steps included planning, identification, qualitative analysis, adapted quantitative analysis, response planning, response implementation, and monitoring. Each of these phases was executed sequentially and integrated, aiming for proactive risk management.
The risk management planning was developed in January 2026 by a multidisciplinary squad. This squad was composed of the author, the manager of the connectivity policy implementation and monitoring area, and the institutional articulation team, which works with the Ministry of Education. The plan defined the qualitative analysis methodology with a Probability and Impact Matrix, using a scale from 0.1 to 0.9, complemented by a quantitative analysis adapted through the Value at Risk of Non-Execution (VRNE).
The responsibilities assigned to the risk squad were established, with defined roles for each stage of the process. The monthly review frequency of the Risk Register was determined, with the VRNE updated as balances were executed. The tolerance criterion for risks was defined as PxI equal to or greater than 0.18, demanding a formal response plan, according to Rabechini Jr. et al. (2019), and a monthly risk status report for the organization’s executive leadership.
The identification of risks followed the definition of the PMI (2021), which determines which risks can affect the project and documents their characteristics. For this, two sequential steps were used: a Brainwriting Pool session and a validation workshop. The Brainwriting Pool session was conducted remotely on January 28, 2026, lasting two hours, using the Miro visual collaboration platform.
Five members of the organization participated: the manager of the connectivity policy implementation and monitoring area, the coordinator of the same area, two analysts, and the operations director. Each participant individually registered the identified risks on cards on the platform, organized by thematic category. At the end of the session, the author systematized the records, grouping events by affinity, eliminating duplicates, and consolidating a preliminary list of eleven threats and three opportunities.
The validation workshop took place in person in February 2026, with the participation of the five members of the Brainwriting Pool session and the organization’s executive director, totaling six participants. The workshop’s objectives were to review and validate the systematized risk list, check if any relevant event had been omitted, and approve the fourteen identified risks for the qualitative analysis stage. The final list was confirmed by consensus at the end of the meeting.
The identified risks were categorized using the Work Breakdown Structure (WBS), a hierarchical tool that organizes risks into categories and subcategories (PMI, 2021). For this work, the WBS was adapted to the specific context of educational connectivity public policy projects. The standard technical category was suppressed, as MegaEdu does not carry out works or install equipment, acting only in support of planning and contracting.
The context of an election year introduced specific subcategories, such as incompatibility for candidacy and the replacement of a secretary due to political decision, which were incorporated into the external-political subcategory. The financing model of Law No. 14.172/2021, with refundable resources, led to the incorporation of the residual-financial category. Additionally, the prior-execution strategic subcategory was created to record the risk of networks that have already implemented connectivity policies with their own resources, and the commitment-informational subcategory to record the risk of balances already committed in current contracts.
The qualitative risk analysis consisted of prioritizing the identified risks by subjectively assessing the probability of occurrence and potential impact, using ordinal scales (PMI, 2021). For each risk, the probability of occurrence and the impact on the schedule and cost dimensions were assessed on a scale from 0.1 (very low) to 0.9 (very high). The consolidated impact was determined by the highest value between the two dimensions.
The individual risk index for each event was calculated by the product of probability and consolidated impact (PxI). The risks were positioned in three tolerability zones: red, for PxI equal to or greater than 0.36; yellow, for PxI between 0.18 and 0.35; and green, for PxI less than 0.18 (Rabechini Jr. et al., 2019). Probabilities were estimated by the risk squad based on the organization’s performance history with partner networks and information available on the political-electoral context of each state.
Quantitative risk analysis, according to PMI (2021), consists of the numerical analysis of the effect of identified risks on project objectives. The Expected Monetary Value (EMV) method did not find direct application to MegaEdu’s operating model, as the organization does not execute the public resources of partner networks and the gradation of financial impact per individual risk was not methodologically applicable.
To circumvent this limitation, the Non-Execution Value at Risk (NEVaR) was proposed as an adapted indicator. The NEVaR represents the public resource at risk of being returned to the National Treasury and was calculated by the equation: NEVaR = Available balance × Probability of non-execution. The available balance of each network was obtained from the Fundo a Fundo Portal (Fundo a Fundo Portal, 2026), and the probability of non-execution was qualitatively estimated by the risk squad based on the consolidated profile of each network, considering political-institutional, technical-administrative, low residual, and prior execution with own resources factors. Data on the networks’ action plans were obtained from the Transferegov system (Transferegov, 2026).
The response planning consisted of defining the most appropriate actions to reduce threats and enhance opportunities identified, for all risks with a PxI index equal to or greater than 0.18 and for all opportunities. For negative risks, the strategies of avoid, mitigate, transfer, and accept were adopted, as recommended by the PMI (2021). For positive risks, the strategies of exploit and enhance were adopted. For each critical risk, the responsible party for the response, the concrete action, and the monitoring indicators were defined.
The implementation of the responses began in February 2026, under the coordination of the risk squad. The monitoring was structured in a monthly cycle of reviewing the Risk Register, with the VRNE being updated as balances were executed or the probabilities of non-execution were revised. Risk control consisted of executing the management plan throughout the project cycle, responding to events as they materialized. The communication system permanently integrated the risk squad with the different actors in the project environment, according to Rabechini Jr. et al. (2019).
3. Results and Discussion
MegaEdu’s strategic planning risk management for 2026 revealed a complex scenario, marked by the imminence of federal and state elections and the deadline for the execution of resources from Law No. 14.172/2021. The Risk Management Plan, developed in January 2026, established robust governance, with a multidisciplinary squad responsible for technical implementation, policy monitoring, and institutional articulation. This structure was fundamental to addressing the multidimensional nature of the risks, which included political, technical, and administrative aspects, all with the potential for significant impact on the execution of connectivity projects. The total balance available for MegaEdu’s ten partner networks, according to data from the Fundo a Fundo Portal (2026), was R$ 802,575,458.
The identification of risks was conducted in two stages, starting with a remote Brainwriting Pool session in January 2026, with the participation of five team members. This technique, which minimizes the bias of group influence in teams with a defined hierarchy (Rabechini Jr. et al., 2019), generated 23 preliminary risk events. Subsequently, an in-person validation workshop in February 2026, with six participants, consolidated the final list into eleven threats and three opportunities. The categorization of these risks used an adapted Risk Breakdown Structure (RBS), recognizing the specificity of educational connectivity public policy projects.
The WBS adaptation was crucial, as the standard PMBOK (PMI, 2021) structure did not adequately address the particularities of the context. The technical category was suppressed, since MegaEdu does not carry out works or install equipment, focusing on supporting planning and contracting. Furthermore, subcategories such as “external-political” were created to capture electoral risks, such as the incompatibility of managers and the change of secretaries due to political decisions. The inclusion of “financial-residual” and “strategic-execution prior” also proved essential to address the risk of unexecuted balances and the situation of networks that had already implemented connectivity policies with their own resources, respectively, ensuring a complete view of the sources of uncertainty.
The qualitative risk analysis, performed using the Probability and Impact Matrix, revealed an overall negative risk of 51%, calculated by the sum of individual indices (3.73) normalized by the theoretical maximum of 7.29 (9 × 0.81). This high percentage underscored the need for proactive and structured management. Two risks were classified as high-level: the incompatibility of governor and/or secretary for electoral candidacy (R1), with PxI of 0.81, and the change of secretary that reduces the priority of connectivity (R2), with PxI of 0.63. The high probability of R1 (0.9) was justified by the identification of at least six partner governors with declared electoral interest, which would imply the appointment of interim replacements with limited mandates, hindering the continuity of long-term projects.
Risk R1, arising from the incompatibility of managers, differs from R2, which involves a change motivated by political dissatisfaction, as R1 represents an inevitable departure due to the electoral process, generating an interim substitute. In this scenario, the technical team of the secretariats emerges as the main asset for institutional continuity. Another medium-level risk, but with significant impact, was the bidding process blocked due to inconsistencies in the Terms of Reference or the public notice (R6), with a PxI of 0.45. MegaEdu’s experience in previous years demonstrated that challenges and suspensions of public notices due to technical failures resulted in average delays of three to four months, which is critical in a fiscal year with a non-negotiable deadline for resource execution.
The analysis of opportunities, in turn, indicated a positive overall risk of 62%, surpassing the negative risk. This suggests that the 2026 environment, despite challenges, presented relevant positive potential for the organization. Two opportunities were classified as high-level, both with PxI of 0.63: the possibility of a new manager unlocking paralyzed processes, using the execution of resources as a political showcase (O1), and the urgency of the deadline for Law No. 14.172/2021, which creates a window of political prioritization for the connectivity agenda in the secretariats (O2). Opportunity O1 is the positive counterpart to risk R1, as interim secretaries may seek visible short-term achievements, such as the execution of federal resources for connectivity, to generate political visibility.
The urgency of the deadline, identified as opportunity O2, reinforces the need for MegaEdu to position itself as a strategic technical partner, capable of enabling fast and impactful deliveries. This two-dimensional perspective of risk, which encompasses both threats and opportunities, aligns with the PMI (2021) definition and emphasizes that effective risk management goes beyond mere threat prevention, actively seeking to explore emerging opportunities. The articulation with the Ministry of Education and other technical partners (O3), classified as medium level, was also considered an opportunity to expand delivery capacity and the pressure for resource execution.
For quantitative analysis, the study proposed Non-Execution Value at Risk (NEVaR) as an adapted indicator, replacing the traditional Expected Monetary Value (EMV). The EMV did not directly apply to the MegaEdu model, as the organization does not execute public resources nor incur direct financial losses. The NEVaR, calculated as the product of the available balance and the probability of non-execution, quantifies the public resource at risk of being returned to the National Treasury, guiding the prioritization of MegaEdu’s technical support efforts among partner networks. The probability of non-execution was qualitatively estimated by the risk squad, considering political-institutional, technical-administrative, residual balance, and prior execution with own resources factors.
The total VRNE of the portfolio of ten partner networks reached R$ 329,443,112, which corresponds to approximately 44% of the available balance of R$ 802,575,458. The state of Mato Grosso presented the highest VRNE percentage (85%), although with an available balance of only R$ 596,906. In this case, opening a new bidding process would be economically unfeasible due to administrative and legal costs, leading to the recommendation of planned balance return and redirection of efforts to other networks. Pará (R$ 62,205,960), Amazonas (R$ 64,388,104), and Pernambuco (R$ 58,120,986) concentrated the largest absolute VRNEs, totaling approximately 52% of the total, justifying the priority allocation of MegaEdu’s technical resources in these three networks during the first semester.
In response to risk R10, which dealt with the inconsistency of the available balance due to commitments in active contracts, MegaEdu proactively mapped the amount already committed in each network. This survey revealed that Rio Grande do Norte had already committed all of its resources, eliminating the need for technical support for new processes. In Pará, it was identified that part of the resources was committed to the payment of satellite internet service, which reduced the balance effectively available for new contracts and, consequently, the necessary technical support effort from the organization. This mapping action allowed for more precise management of balances and support efforts.
The planning and implementation of responses to risks and opportunities were organized into three main strategic axes. The first axis consisted of proactively mapping the application intentions of partner secretaries, carried out through bilateral meetings between February and March 2026. For secretaries who confirmed their departure, MegaEdu accelerated the pactuation of projects and supported the technical teams in preparing documents on history and pending issues, serving as inputs for systematic presentation to new managers. Ongoing projects were registered on a collaborative management platform, ensuring traceability and continuity, regardless of personnel changes.
The second strategic axis focused on strengthening the technical capacity of the secretariat teams, recognizing them as a central asset for institutional continuity. This approach aligns with the recommendation of Rabechini Jr. et al. (2019) that the manager should influence those responsible to take the necessary measures, even outside the direct scope of the project. Actions included training technical teams in connectivity bidding processes and the systematized documentation of ongoing processes to reduce dependence on specific individuals, mitigating the risks of low technical capacity and team turnover (R4 and R5).
The third main axis was the articulation with the Ministry of Education (MEC) to increase institutional pressure for the execution of resources. Actions were agreed upon with the MEC for sending official communications to the new secretaries, reinforcing the deadline and the consequences of non-execution. This collaboration gave institutional weight to MegaEdu’s technical recommendations and corresponded to the strategy of sharing opportunity O3, involving the MEC without incurring additional costs for the organization, as recommended by PMI (2021). This articulation also aimed to mitigate the risk of a change in secretary that reduces the priority of connectivity (R2), by creating a narrative of impact and mobilizing strategic stakeholders.
In summary, the results demonstrated that MegaEdu’s strategic planning for 2026 was significantly exposed to political-institutional risks, especially in an election year, with the disqualification of managers and the replacement of secretaries representing the most critical threats. However, the context also generated relevant opportunities, such as the urgency of the deadline for Law No. 14.172/2021 and the search for political visibility by new managers. The adaptation of the Analytical Risk Structure and the proposition of Value at Risk of Non-Execution (VRNE) were crucial for identifying, categorizing, and prioritizing these risks and opportunities, guiding strategic responses focused on the institutional strengthening of the secretariats, the anticipation of agreements, and the articulation with the Ministry of Education to ensure the execution of resources and the fulfillment of the study’s objective.
4. Conclusion
The present study aimed to manage the risks of MegaEdu’s strategic planning for 2026, focusing on the execution of resources from Law No. 14.172/2021 intended for school connectivity. It was found that the planning was significantly exposed to political-institutional risks, especially in an election year, with the disqualification of managers and the replacement of secretaries due to political decisions identified as the most critical threats. The qualitative analysis revealed an overall negative risk of 51%, while opportunities presented an overall positive risk of 62%, indicating a scenario of uncertainty with potential for progress. The adaptation of the Risk Analysis Framework (EAR) was crucial for categorizing specific public policy context events, such as electoral and residual balance risks, which would not be adequately covered by standard frameworks. Additionally, the Value at Risk of Non-Execution (VRNE) was proposed as an adapted quantitative indicator, which quantified R$ 329,443,112 as the amount of public resources at risk of non-execution, out of an available balance of R$ 802,575,458. This indicator allowed for the prioritization of the organization’s technical support efforts, concentrating them on networks with the highest absolute VRNE, such as Pará, Amazonas, and Pernambuco, and guiding the recommendation of planned return for cases of very high percentage VRNE and low balance, such as Mato Grosso.
The strategic responses implemented were organized into three main axes: proactive mapping of partner secretaries’ candidacy intentions, strengthening the technical capacity of the secretariats’ teams as an asset for institutional continuity, and articulation with the Ministry of Education to increase institutional pressure for resource execution. These actions aimed to mitigate identified threats and explore opportunities generated by the electoral context and the urgency of the deadline for Law No. 14.172/2021. The study’s main contribution lies in the methodological adaptation of Value at Risk of Non-Execution (VRNE), which proved to be an adequate indicator for organizations providing technical support to public policies, offering a replicable tool for prioritizing efforts and managing public resources in contexts of high uncertainty. It is concluded that projects supporting educational connectivity public policies are highly vulnerable to political-institutional risks, especially in electoral years, and that proactive and adapted risk management is essential to ensure the effectiveness of resource execution and the achievement of public policy objectives.
Bibliographic References
Brasil. 2021. Lei nº 14.172, de 10 de junho de 2021. Dispõe sobre a garantia de acesso à internet, com fins educacionais, a alunos e a professores da educação básica pública. Diário Oficial da União, Brasília, 11 jun. 2021. Seção 1, p. 1.
Carvalho, M.M.; Rabechini Jr., R. 2019. Fundamentos em gestão de projetos: construindo competências para gerenciar projetos. 5ed. Atlas, São Paulo, SP, Brasil.
Gray, C.F.; Larson, E.W. 2009. Gerenciamento de projetos: o processo gerencial. 4ed. McGraw-Hill, São Paulo, SP, Brasil.
PMI Project Management Institute. 2021. A guide to the project management body of knowledge (PMBOK Guide). 7ed. PMI, Newtown Square, PA, USA.
Portal Fundo a Fundo. 2026. Consulta de saldos disponíveis. Serpro, Brasília, DF, Brasil. Disponível em: https://dd-publico.serpro.gov.br/extensions/fundo-a-fundo/fundo-a-fundo.html. Consultado em 20/03/2026.
Rabechini Jr., R.; Franciss, F.O.; Assis, A.P. 2019. Gestão de riscos em empreendimentos complexos. Editora CRV, São Paulo, SP, Brasil.
Thiollent, M. 2011. Metodologia da pesquisa-ação. 18ed. Cortez, São Paulo, SP, Brasil.
Transferegov. 2026. Plano de ação consulta pública. Ministério da Fazenda, Brasília, DF, Brasil. Disponível em: https://fundos.transferegov.sistema.gov.br/transferencia/plano-acao/consulta. Consultado em 20/03/2026.